PMP Formulas PMBOK5

August 4, 2017 | Author: Sijee Sadasivan | Category: Business, Mathematics
Share Embed Donate


Short Description

PMP Formulas PMBOK5...

Description

by Edward Chung, PMP (http://edward-designer.com/web/pmp/)

PMP Formulas mentioned in the PMBOK Guide 5th Edition Name (Abbreviation)

No. of Communication Channels

Schedule Performance Index (SPI)

Cost Performance Index (CPI)

Formula

Interpretation n should include the project manager

n (n-1)/2 n = number of members in the team

SPI = EV/PV EV = Earned Value

(SV)

1

behind schedule on schedule ahead of schedule

1

Over budget On budget Under budget

PV = Planned Value

CPI = EV/AC EV = Earned Value AC = Actual Cost

Schedule Variance

e.g. if the no. of team members increase from 4 to 5, the increase in communication channels: 5(5-1)/2 – 4(4-1)/2 = 4

SV = EV – PV EV = Earned Value

sometimes the term ‘cumulative CPI’ would be shown, which actually is the CPI up to that moment 0

Behind schedule On schedule Ahead of schedule

0

Over budget On budget Within budget

PV = Planned Value

CV = EV – AC Cost Variance (CV)

EV = Earned Value AC = Actual Cost

Estimate at Completion (EAC) if original is flawed

Estimate at Completion (EAC) if BAC remains the same

EAC = AC + New ETC AC = Actual Cost New ETC = New Estimate to Completion

if the original estimate is based on wrong data/assumptions or circumstances have changed

EAC = AC + BAC – EV AC = Actual Cost BAC = Budget at completion EV = Earned Value

the variance is caused by a onetime event and is not likely to happen again

by Edward Chung, PMP (http://edward-designer.com/web/pmp/)

Name (Abbreviation) Estimate at Completion (EAC) if CPI remains the same

Estimate at Completion (EAC) if

Formula

Interpretation

EAC = BAC/CPI BAC = Budget at completion CPI = Cost performance index

EAC = AC + (BAC EV)/(CPI*SPI) AC = Actual Cost

substandard

BAC = Budget at completion

performance

EV = Earned Value

continues

if the CPI would remain the same till end of project, i.e. the original estimation is not accurate

use when the question gives all the values (AC, BAC, EV, CPI and SPI), otherwise, this formula is not likely to be used

CPI = Cost Performance Index SPI = Schedule Performance Index

TCPI = (BAC – EV) / (BAC – AC) BAC = Budget at completion EV = Earned value To-Complete Performance Index (TCPI)

AC = Actual Cost

TCPI = Remaining Work /Remaining Funds BAC = Budget at completion EV = Earned value CPI = Cost performance index

Estimate to Completion

ETC = EAC -AC EAC = Estimate at Completion AC = Actual Cost

1

Under budget On budget Over budget

by Edward Chung, PMP (http://edward-designer.com/web/pmp/)

Name (Abbreviation)

Variance at

Formula

Interpretation

VAC = BAC – EAC

Completion

BAC = Budget at completion

0

Under budget On budget Over budget

EAC = Estimate at Completion

(O + 4M + P)/6 PERT Estimation

O= Optimistic estimate M= Most Likely estimate P= Pessimistic estimate

(P – O)/6 Standard Deviation

O= Optimistic estimate

this is a rough estimate for the standard deviation

P= Pessimistic estimate

LS – ES LS = Late start ES = Early start Float/Slack

LF – EF

=0
View more...

Comments

Copyright ©2017 KUPDF Inc.
SUPPORT KUPDF