WORK CLEARENCE MANGEMENT (PM-WCM) 1.0 INTRODUCTION Maintenance and Inspection work for the technical object may only be carried out when work safety measures have been implemented. These safety measures include lockout/tagout, fire protection, radiation protection etc. In lockout/tagout, for example, technical objects are isolated electrically or separated mechanically from other parts of the technical system while maintenance work or special tests are performed. Work on these technical objects can then be performed safely. Work Clearance Management (PM-WCM) component can be used to control and monitor the safety measures to ensure work safety of the employees. WCM component can replace the “Permit to Work” (PTW) system employed by almost all petrochemical and utilities industry.
2.0 WCM ARCHITECTURE PM-WCM architecture defines relationship between WCM Objects and can be selected from following models:
2.1.
Standard Model Standard Model is used when Lockout/Tagout is of primary importance.
2.2.
Enhanced Model Enhanced Model is used when Safety Measures (radiation protection, safety in the workplace, and fire protection) are also required in addition to Lockout/Tagout.
Additional Applications
3.0 WCM OBJECTS Objects that supports in Work Clearance Management process for assignment of administrative data, status, approvals, technical objects etc. and good for communication between departments.
1
PM-WCM
Following are the objects used for WCM with the responsible departments. WCM Object Work Approval Work Clearance Application Work Clearance Document
Area of Responsibility Plant Maintenance, Production Plant Maintenance, Production Production
4.0 WCM ACTIVATION IN ORDER The Maintenance Orders for which WCM is activated are marked as WCM-relevant orders. Activation of WCM for Maintenance Order can be performed by two ways: i. ii.
Assigning Permits to the Order. Assigning control key ‘WCM’ to operations in an order.
5.0 ORDER PROCESSING WITH WCM Process flows for the WCM Orders defined in PM-WCM are classified as follows: i. ii. iii.
5.1.
Order Processing without Valuation Order Processing with Valuation Order Processing with WCM-Relevant Operations
Order Processing without Valuation Standard Model
Following diagram shows the schematic of this process with status of Order and WCM Objects.
STATUS WOCO CLSD EXEC ETG EUG UNT TECO PREP VAL
DESCRIPTION Work Completed WCM object is Closed Order is Released for Execution The Operational WCD is Tagged The Operational WCD is Untagged The Operational WCD is Untaggable The order is Technically Completed The WCM object is Prepared The WCM-relevant order is Valuated
2
PM-WCM
5.2.
Order Processing with Valuation Enhanced Model
Following diagram shows the schematic of this process with status of Order and WCM Objects.
5.3.
Order Processing with WCM-Relevant Operations
Following diagram shows the schematic of this process with status of Order and WCM Objects.
6.0 EXAMPLE - ORDER PROCESSING WITHOUT VALUATION STANDARD MODEL 6.1. Scenario For the WCM Order creation we have created equipment for which maintenance is required to be performed and child equipment for the parent equipment is created which is required to be locked-out and tagged-out for performance of maintenance activity safely. Note that it is not necessary to have a parent child relationship for the equipment(s) to be tagged out.
3
PM-WCM
6.2.
Procedure
Here MP denotes Maintenance Planner (i.e. Maintenance Engineer) and WP denotes Work Clearance Planner (i.e. Safety Engineer) who will perform the respective steps as follows. MP Order Creation
Order creation is not necessary if you just want to use WCM for documentation of safety measures on the assets without planning or cost collection. 1.
Type transaction code IW31 in Command Field on SAP Easy Access Screen.
4
PM-WCM
2.
Create Maintenance Order: Initial Screen
Field
Description
Order Type
PM01
Equipment
Example: 10000089
3.
Create Maintenance Order: Header
5
PM-WCM
Field
Description
Order
Example: Maintenance of Compressor
Mn.wk.ctr
Example: Test0003
4.
Click Goto Assignments Funds management
Field
Description
Commitment Item
Example: 1110103001
Funds Center
Example: F51431
6
PM-WCM
MP Work Clearance Application (Requisition for lockout/tagout)
Here Maintenance Planner will create requisition for lock-out/tag-out and will mark the order as WCM-relevant order. Activation of WC Application for an order can be accomplished by two methods as discussed in article 4. Here we will use second method i.e. by providing control key as WCM in operation. 5.
Click Operations tab control
.
Field
Description
Control key
Example: WCM
Operation short text
Example: Electrical isolation of Compressor Motor
6.
Click WC Application button
.
7
PM-WCM
7.
Click button
.
8.
Click button
.
8
PM-WCM
9.
Create WC Application Screen
Field
Description
Application
Example: Electrical Isolation of Compressor Motor
Use of WCD
Example: YU1 (Electric Work Ticket)
(marked in red box)
Cond.Tech.Syst.
10.
Click button
Example: X
.
9
PM-WCM
11.
Approvals - WC Application
Field
Description
Permit
Example: YU_X11 (Electric permit)
12.
Click button
.
13.
Click button
on WC Application Screen
10
PM-WCM
14.
Click Yes button on Confirmation Prompt
15.
Click button
on Assignments - Display WC Applications
11
PM-WCM
16.
Click button screen
and then
on Create Maintenance order: Operation Overview
12
PM-WCM
WP Work Clearance Document (Specify objects to be lockout/tagout) In this step Work Clearance Planner will specify the objects required to be locked-out/tagged-out.
17.
Using transaction code IW32 initiate the Change Maintenance order for order created previously in this case 4000000929
18.
Click WC Application button
19.
Click on
on Change Maintenance order: Header
in Assignments - Change WC Applications window
13
PM-WCM
20.
Click Operational WCDs button
21.
Click button
on Change WC Application screen
on Assignments - Change Operational WCDs screen
14
PM-WCM
22.
Click button
on Data Transfer screen
23.
Create Operational WCD: Header
Field
Description
WCD Usage
Example: YU1 (Isolation permit for Electric Motor)
(marked in red box)
24. 25.
Click button . Approvals - Operational WCD
15
PM-WCM
Field
Description
Permit
Example: YU_X11 (Electric permit)
26.
Click button
.
27.
Click button
28.
Create Operational WCD: Maintenance Screen
on Create Operational WCD: Header screen
16
PM-WCM
At this level we will provide the details of equipment(s) to be tagged out. In the present case we will provide the equipment 10000090 (Electric Motor of Centrifugal Compressor) which required to be tagged “OFF” for carrying out the maintenance of equipment 10000089 safely.
Field
Description
Item Category
Example: E (Equipment)
(marked in red box)
Equipment
Example: 10000090
29. 30.
Press "Return". Press F4 key after selecting Tagging Condition field
31.
Select First item in Tagging Condition window and press
.
Specifying the Tag condition “OFF” for the equipment with tagging type RBT (Red Danger Tag)
17
PM-WCM
32.
Select PF (Print Format) “XXXX” in present case for the Tag
33.
Click button
34.
Click Task button
. on Create Operational WCD: Header
18
PM-WCM
35.
Task - Operational WCD
Field
Description
Code group
Example: YU8101 (Electric Motor Isolation)
Code
Example: YU01 (Rackout for Electric Motor Switch Gear) YU02 (Close manual switch at site)
36.
Click button
.
19
PM-WCM
37.
Click button
on Create Operational WCD: Header screen
38.
Click Yes button on Confirmation Prompt
20
PM-WCM
WP Work Clearance Document (Approval for lockout/tagout) In this step Work Clearance Approver gives the approval for Lockout/tagout of the equipment defined in Operational WCD previously.
39.
Click
40.
Click button
on Assignments - Change Operational WCDs
on Change Operational WCD: Header screen
21
PM-WCM
41.
Approvals - Operational WCD
42.
Select the Permit YU_X11 row.
43.
Click Issue button
44.
Click button
.
.
22
PM-WCM
WP Work Clearance Document (Perform lockout/tagout) Here tags for the equipment(s) to be tagged are printed and are tagged physically on the location.
45.
Click button
on Change Operational WCD: Header screen
46.
Change Operational WCD: Switching Screen
47.
Click check box
48.
Click Tag button
49.
Click Tag button
. . .
23
PM-WCM
50.
Click Print button
on the Print window
51.
Change Operational WCD: Switching Screen
52.
Click Tagged button
53.
Click button
.
54.
Click button
.
.
24
PM-WCM
55.
Click button
on Assignments - Change Operational WCDs screen
25
PM-WCM
WP Work Clearance Application (Approval for lockout/tagout requisition) Work Clearance Approver now approves the WC Application for Order Execution.
56.
Change WC Application
57. 58.
Click button . Approvals - WC Application
26
PM-WCM
59.
Select the Permit YU_X11 row.
60.
Click Issue button
61.
Click button
62.
Click button
on Change WC Application
63.
Click button
on Assignments - Change WC Applications window
.
.
27
PM-WCM
MP Order (Releasing for execution) Maintenance planner now releases the order for execution.
64.
Change Maintenance order: Header
65.
Click Released for execution button
.
28
PM-WCM
MP Order (Conformance of Work Completion)
66.
Change Maintenance order: Header
67.
Click Work completed button
.
29
PM-WCM
WP Work Clearance Application (Approval for un-tagging) Here Work Clearance Planner closes the WC Application and consequently gives approval for un-tagging.