PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT NO

NAME OF STUDENT AND HAND-PHONE NO

UITM NO

1

MD ABDULHADI MOHAMMED SOPAFI

2009249132

SIGNATURE

0122090493

2

ILYAS MUSTAPHA MOHAMMAD

2009647962

0176671030

3

RIDUAN MOHD TAHIR

2009667776

0135013035

4

NURHAFIZAH FATIN A RAHMAN

2009697746

0194190164

5

SITI ATIEKAH JUSOH

2009815488

0179226492

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT

Contents 1

LIST OF FIGURE....................................................................................4

2

PROJECT...............................................................................................6

3

2.1

PROJECT DESCRIPTION..................................................................7

2.2

SITE ORGANISATION CHART........................................................10

2.3

INTRODUCTION............................................................................11

PLANNING OF EARTHWORK OPERATION MULTI-STOREY PROJECT.....12 3.1

INTRODUCTION............................................................................12

3.2

DESIGN STAGE.............................................................................13

3.2.1

SCOPE...................................................................................13

3.2.2

GENERAL...............................................................................13

3.2.3

TECHNICAL RESPONSIBILITIES...............................................14

3.2.4

SITE INVESTIGATIONS............................................................15

3.2.5

PLANNING AND DESIGN.........................................................17

3.2.6

FINAL DOCUMENTATION........................................................24

3.2.7

PROTECTION OF THE WORKS................................................25

3.2.8

CLEARING AND GRUBBING....................................................29

3.2.9

Disposal of Material...............................................................30

3.3

4

PLANNING STAGE.........................................................................31

3.3.1

COST ESTIMATED..................................................................31

3.3.2

METHOD STATEMENT AND PROJECT PLANNING....................39

3.3.3

CONSTRUCTION METHOD AND USE OF PLANT......................49

CONTROLLING FOR OPERATION OF EARTHWORK..............................58 4.1

INTRODUCTION............................................................................58

4.1.1

SURFACE LEVELLING STATION (MONUMENT)........................59

4.1.2

SETTELEMENT PLATE (ROD EXTENSOMETER)........................60

4.1.3

MAGNETIC EXTENSOMETER...................................................61

4.1.4

USBR SETTLEMENT GAUGE...................................................61

4.1.5

PIEZOMETER..........................................................................62

4.2

SLOPE PROTECTION.....................................................................63

4.2.1

STABILIZATION OF CUT SLOPES............................................64 AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT 4.3

Methods of Groundwater Control.................................................65

4.3.1

Sumps and Ditches................................................................65

4.3.2

Deep-Well Systems...............................................................67

4.3.3

Wellpoint Systems.................................................................71

4.3.4

Vertical Sand Drains..............................................................79

4.3.5

Electro-Osmosis.....................................................................80

4.3.6

Cutoffs...................................................................................82

4.4

CONSTRUCTION PROCEDURES....................................................90

4.4.1

SPECIFICATIONS....................................................................90

4.4.2

FILL CONSTRUCTION.............................................................91

4.4.3

INSPECTION AND QUALITY CONTROL....................................93

4.5

CASE STUDY................................................................................95

4.5.1

SLOPE STABILIZATION/ SLOPE PROTECTION..........................95

4.5.2

DEWATERING SYSTEM.........................................................100

4.5.3

TRAFFIC CONTROL...............................................................104

4.5.4

SAFETY CONTROL................................................................107

4.5.5

SETTLEMENT CONTROL.......................................................110

4.5.6

DOCUMENTATION CONTROL...............................................111

5

CONCLUSION ..................................................................................116

6

Bibliography.....................................................................................117

Error: Reference source not found

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT

1 LIST OF FIGURE FIGURE 1 SUBANG SOHO PROJECT............................................................................6 FIGURE 2 SITE PLAN OF SOHO PROJECT.............................................................................9 FIGURE 3 SITE LAYOUT - SOHO PROJECT......................................................................9 FIGURE 4 THE SOIL THAT WILL EXCAVATE. (35, 000M3).............................................................38 FIGURE 5 CRITICAL PATH METHOD....................................................................................48 FIGURE 6 DEWATERING OPEN EXCAVATION BY SUMP AND DITCH....................................................66 FIGURE 7 SUBMERSIBLE PUMP FOR DEWATERING AN EXCAVATION...................................................66 FIGURE 8 DEEP WELL SYSTEM FOR DEWATERING AN EXCAVATION IN SAND.........................................67 FIGURE 9 DEEP WELLS WITH AUXILIARY VACUUM SYSTEM FOR DEWATERING A SHAFT IN STRATIFIED MATERIALS.68 FIGURE 10 PLAN OF A TYPICAL WELLPOINT SYSTEM..................................................................71 FIGURE 11 A TYPICAL WELLPOINT SYSTEM AT SITE...................................................................71 FIGURE 12 USE OF WELLPOINTS WHERE SUBMERGENCE IS SMALL..................................................72 FIGURE 13 DRAINAGE OF AN OPEN DEEP CUT BY MEANS OF A MULTISTAGE WELLPOINT SYSTEM.................73 FIGURE 14 VACUUM WELLPOINT SYSTEM..............................................................................74 FIGURE 15 A WELLPOINT PUMP USED IN SUNWAY PYRAMID II PROJECT...........................................75 FIGURE 16 SELF-JETTING WELLPOINT..................................................................................76 FIGURE 17 JET-EDUCTOR WELLPOINT SYSTEM FOR DEWATERING A SHAFT..........................................79 FIGURE 18 SAND DRAINS FOR DEWATERING A SLOPE................................................................80 FIGURE 19 INSTALLATION OF MANDRELS USING DRAIN STITCHER....................................................80 FIGURE 20 ELECTRO-OSMOSIS WELLPOINT SYSTEM FOR STABILIZING AN EXCAVATION SLOPE.....................81 FIGURE 21 INSTALLATION OF ELECTRO-OSMOSIS IN A DEWATERING SITE...........................................82 FIGURE 22 GROUT CURTAIN OR CUTOFF TRENCH AROUND AN EXCAVATION........................................83 FIGURE 23 DETAIL OF SLURRY TRENCH...............................................................................85 FIGURE 24 STEEL SHEETING TO TOP OF ROCK. A BOULDER ABOVE THE ROCK CAN AGGRAVATE THE SITUATION. .....................................................................................................................86 FIGURE 25 STEEL SHEETING IN SUNWAY PYRAMID II PROJECT TO CONTROL SEEPAGE AND STABILIZING THE SLOPE..............................................................................................................87 FIGURE 26 EXCAVATION SUPPORTED BY A GRAVITY FREEZEWALL...................................................88 FIGURE 27 TYPICAL SCENARIO OF FREEZE PIPE SPACING AND INDICATION WHICH CAN BE CONNECTED TO A PORTABLE REFRIGERATION PLANT, OR LIQUID NITROGEN TANKER..............................................88 FIGURE 28 CIRCULAR EXCAVATION SUPPORTED BY A FREEZEWALL. (A) PLAN. (B) SECTION....................89 FIGURE 29 A DEEP EXCAVATION SUPPORTED BY FREEZE WALL......................................................89 FIGURE 30 CSP AT THE SOHO PROJECT..........................................................................96 FIGURE 31 RE-BAR OF CSP..........................................................................................97 FIGURE 32 CSP SIDE USE MORTAR..................................................................................97 FIGURE 33 LAYOUT OF CSP..........................................................................................98 FIGURE 34 CANVAS METHOD.........................................................................................99 FIGURE 35 CANVAS TO THE SLOPE...................................................................................99 FIGURE 36 RETAINING WALL........................................................................................100 FIGURE 37 WATER PUMP............................................................................................101 FIGURE 38 WATER FLOW............................................................................................101 FIGURE 39 PONDING AT SITE........................................................................................102 FIGURE 40 TEMPORARY DRAINAGE..................................................................................102

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT FIGURE FIGURE FIGURE FIGURE FIGURE FIGURE FIGURE FIGURE FIGURE FIGURE FIGURE

41 42 43 44 45 46 47 48 49 50 51

TEMPORARY DRAINAGE..................................................................................103 ACCESS ROUTE...........................................................................................104 BARIER GATE.............................................................................................105 WASH PIT...............................................................................................106 HOUSEKEEPING...........................................................................................106 HOARDING...............................................................................................107 WASH PIT................................................................................................108 GATE BARIER............................................................................................108 PROJECT SIGNAGE........................................................................................109 POINT OF STTLEMENT CONTROL.........................................................................110 SETTLEMENT MARKER RECORDS.......................................................................111

FIGURE 51 SETTLEMENT MARKER RECORDS.

2 PROJECT

AP 226 / 1C | JULY – NOVEMBER 2009

Figure 1 SUBANG SOHO PROJECT

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT

2.1

PROJECT DESCRIPTION

PROJECT

SUBANG SOHO CADANGAN PEMBANGUNAN FASA B YANG MENGANDUNGI 1 BLOK SOHO 23 TINGKAT (488 UNIT) TERMASUK 5 TINGKAT TEMPAT LETAK KERETA DI ATAS LOT 20926 (P.T. 11921) H.S (D) 48924, MUKIM DAMANSARA, DAERAH PETALING, SELANGOR DARUL EHSAN UNTUK TETUAN SENDI BANGGA DEVELOPMENT SDN. BHD.

CLIENT

SENDI BANGGA DEVELOPMENT SDN. BHD (whole subsidiary by Titijaya Group) Lot 3-10, 3rd Floor, First Tower, Jalan Meru, 41050 Klang, Selangor. Tel : 03-3341 1111

ARCHITECT

Fax : 03-3341 2992

ARKITEK KDI SDN. BHD 1st Floor, No 87 & 89, Jalan Ipoh 51200 Kuala Lumpur. Tel : 03-4045 3193

STRUCTURAL ENGINEER

Fax : 03-4045 3187

CSI CONSULTANT No. 25-7, Jalan USJ 9/5Q, Subang Business Centre, 47620 UEP Subang Jaya, Selangor

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT Tel : 03-8023 6312

CIVIL ENGINEER

Fax : 03-8023 6316

PETAREKA PERUNDING (M) SDN. BHD No.5, jalan 11/62 A, Bandar Seri Menjalara, 52200 Kuala Lumpur, Malaysia Tel : 03-6272 6878

Fax : 03-6272 8878

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT

M&E

FADHULLAH & ASSOCIATES CONSULTING No. 4A&4B, Jalan BPU 9, 14th Mile, Jalan Puchong, Bandar Puchong Utama, 47100 Selangor. Tel : 03-5891 1535/1536 Fax : 03-5891 1538

LANDSCAPE ARCHITECT

ECO HABITAT 3-3, Jalan Damar SD 15/1, Bandar Sri Damansara, 52200 Kuala Lumpur. Tel : 03-6277 0083

QUANTITY SURVEYOR

Fax : 03-6277 1646

DL QS CONSULT No. 11-2 (2nd Floor), Jalan USJ 10/1E Taipan Business Centre, 47620 UEP Subang Jaya, Selangor. Tel : 03-5638 8267

CONTRACTOR

Fax : 03-5638 0268

G-PILE SISTEM SDN. BHD Lot 1.01 Level 1, KPMG Tower, No. 8 First Avenue, Bandar Utama, 47800 Petaling Jaya, Selangor. Tel : 03-7710 6477/8477 Fax : 03-7710 5477

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT

Figure 2 Site Plan of SOHO Project

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT

Figure 3 SITE LAYOUT - SOHO Project

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT 2.2

SITE ORGANISATION CHART

ASST. SR. G-PILE SENIOR TECHNICAL SAFETY PLANNING DIRECTOR SURVEYOR CONTRACTS PROJECT PROJECT SUPERVISOR SISTEM MANAGER OFFICER MANAGER MANAGER QS MANAGER SDN MANAGER BHD Base in on HQ DING LING LEE IR. RIDZUWAN/ZULKIFLI SHARON LOH FONG YAU AZAHARI WARREN HUA CHENG SHIRLEY MUN KIM EE YONG TAN HUAT WEI HONG CHOO SIM Site

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT

2.3

INTRODUCTION

The subtopics that we get for our case study about Planning and Controlling of Earthwork Operation Multi-Storey Building; for the assigment’s subject in Construction Technology’s (BLD 410). Practicality that can be seen and understand, the planning and controlling by the contractor when get the project. Planning operation is include about cost estimated, method/sequence of work, project planning and also the machineries used during the earthwork operations. For the controlling, included about slope, dewatering system, trafic control, safety control, settlement control, and documantation control. Based on this topic, we are together chosen one of the private companies to do this research. The company is Sendi Bangga Development Sdn. Bhd this company is a wholly owned subsidiary of Titi Jaya Holding Sdn. Bhd. These construction works were done and responsibility by Sendi Bangga Development Sdn. Bhd as a developer of “SUBANG SOHO; Cadangan Pembangunan Fasa B Yang Mengandungi 1 Blok Soho 23 Tingkat (488 Unit) Termasuk 5 Tingkat Tempat Letak Kereta Di Atas Lot 20926 (P.T. 11921) H.S (D) 48924, Mukim Damansara, Daerah Petaling, Selangor Darul Ehsan Untuk Tetuan Sendi Bangga Development Sdn. Bhd.”; 2.7 million project (earthwork operation).

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT

3

PLANNING OF EARTHWORK OPERATION MULTI-STOREY PROJECT

3.1 INTRODUCTION Earthwork operations involve the excavation, transportation and placement or disposal of materials. They typically involve repetitive work cycles, expensive fleets and large volumes of work. Consequently, even small improvements in planning result in substantial cost and time savings. It is for these reasons that earthwork operations improvement has been the focus of so many studies. The work is performed outdoors under conditions that are highly variable and that affect the performance of the different pieces of equipment. Factors that affect performance include weather (i.e., trucks cannot travel as fast on wet, muddy haul roads), haul road maintenance (i.e., a wellmaintained road reduces rolling resistance), operator experience, ground conditions, load and dump area layouts, and the material being excavated. Earthwork operations are actively managed with many decisions made dynamically on site in reaction to the evolving status. A truck, for example, may be routed to an alternate load area if the loading unit at the main area is under maintenance or if several other trucks are queuing for it. Sometimes the strategies that guide these dynamic decisions are quite complex but necessary. They can also significantly impact the performance of the operation. The probabilistic nature of the work and the dynamics of earthwork operations make them difficult to plan. They are typically planned using simplified back-of-the envelope calculations, but mainly relying on the experience and insights of the planner. Discrete-event simulation is the only earthwork analysis method that can explicitly incorporate the detailed but significant aspects (e.g., equipment characteristics, haul road conditions, load and dump area configuration, and dynamic context-based decisions) of an operation. AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT

3.2

DESIGN STAGE

3.2.1 SCOPE This part is sets out the recommendations for the carrying out of earthworks or preparation or foundations of multi-storey project at SUBANG SOHO, or both, including: a) The excavation and filling of land to form new contours; b) The assessment and protection of slope stability; c) The suitability of both natural and filled ground for the founding of roads, buildings, d) Services and other works; e) The control of erosion and siltation’s during and after earthworks.

Because of the wide range of soil types, physical conditions and environmental factors which apply in different areas it is not often possible to lay down precise requirements which will be subject in particular instances to the judgement of the Engineer, owner's representative or soils engineer. () 1.1.1 GENERAL Choice of final landform is dependent on many factors which may be specific to the subdivision or development. These include: a) Relation with surrounding landscape; b) Size; c) Roading pattern; d) Preservation of natural features; e) Stability;

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT f) Damage by flood or other natural occurrences such as erosion by sea,

river, or surface storm water run-off. Provision is made in this standard for certification of suitability of land for subdivision and development to meet the requirements of this Standard. This requirement is independent of the requirements under the Building Act 1991. Reference is made to the desirability of using local material which may provide a satisfactory foundation in particular circumstances.

1.1.1 TECHNICAL RESPONSIBILITIES Where any land development or subdivision involves the carrying out of bulk earthworks, the assessment of slope stability, or the detailed evaluation of the suitability of natural ground for the foundations of buildings, roads, services or other works, then a soil engineer should be appointed by the developer to carry out the following instructions: a) Prior to detailed planning of any development to undertake a site inspection and such investigations of subsurface conditions as may be required. b) Before work commences to review the drawings and specifications defining the earthworks proposed, and submit a written report to the Engineer on foundation and stability aspects and any proposed departures from this Code and associated standards. c) Before work commences and during construction to determine the extent of further specialist soils engineering services required (including investigation and geological work). d) Before and during construction to determine the methods and

frequency of construction control tests to be carried out, determine the reliability of the testing, and to evaluate the significance to test results and field inspection reports in assessing the quality of the finished work. AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT e) During construction to provide regular inspection (while a daily visit might be regarded as reasonable on earthwork construction on minor projects, inspection on a nearly full time basis is often necessary). f) On completion to submit a written report to the Engineer attesting to the compliance of the earthworks with the specifications, and as to the suitability of the subdivision for building construction. The owner's representative may act as the soils engineer if he possesses suitable qualifications and experience. The construction control testing should be carried out by a competent person, or, preferably, under the control of the soils engineer, and with Testing Laboratory Registration Council (Telarc) registration in all relevant tests. ()

1.1.1 SITE INVESTIGATIONS 1.1.1.1 PRELIMINARY SITE EVALUATION Prior to any detailed planning or design, the owner's representative or soils engineer, as applicable, should undertake a preliminary evaluation of the general nature and character of the site in sufficient detail to determine the likely requirements for earthworks or the need for further investigations into the suitability of foundation conditions, or both, and the stability of the natural ground. The preliminary evaluations should be carried out in the context of the total surrounds of the site, and should not be influenced by details of land tenure, territorial or other boundary considerations. In simple cases a visual appraisal may be sufficient, but in other cases depending on the nature of the project, its locality, the scale of development proposed and individual site characteristics, particular attention may need to be given to the following matters which should normally be considered prior to preparing a proposal for subdivision or development.

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT a) Drainage. It is important to identify the existing natural drainage pattern of any area and to locate the natural springs or seepage. b) Where any natural drainage paths are interfered with or altered by earthworks then appropriate measures should be taken to ensure that sufficient adequate alternative drainage facilities are provided. c) Slope Stability. Some natural slopes exist in a state of only marginal stability and relatively minor works such as trenching, excavation for road or building platforms, removal of scrub and vegetation, or the erection of buildings, can lead to failure. Signs of instability include cracked or hummocky surfaces, crescent shaped depressions, crooked fences, trees or power poles leaning uphill or downhill, uneven surfaces, swamps or wet ground in elevated positions, plants such as rushes growing on a slope and water seeping from the ground. d) Foundation Stability. A study of the general topography of the site and its surroundings may indicate areas which have previously been built up as a result of natural ground movement or by the deliberate placing of fill material. Unless such fill has been placed and compacted under proper control, long term differential settlement could occur causing damage to superimposed structures, roads, services or other subdivision works. Note: The District contains a number of areas where 'tomos' have developed. These may affect the suitability of a site for development and consequently these will require identification and addressing as part of any development proposal. 1.1.1.1 SPECIALIST SERVICES

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT Where a soils engineer has been appointed as recommended in section Technical Responsibilities then prior to or at the time of submission of an application or subdivision or development he should submit to Council a written report setting out the particulars of any investigations carried out including details of contours, natural features and modifications proposed thereto; and shall furnish to Council a statement of professional opinion as to the suitability of the land for subdivision with details of any special conditions that should be imposed.

1.1.2 PLANNING AND DESIGN 1.1.2.1 LANDFORM The final choice of landform should represent the most desirable compromise between the factors referred to above and the preservation of natural features and the natural quality of the landscape including the retention of natural watercourses. The choice of suitable landform is dependent on many factors which may be specific to a particular site. In general, unnecessary earthworks should be avoided but considerations which may justify the carrying out of earthworks include: a) The minimisation of the possibility of damage to property occurring through ground movement in the form of slips, subsidence, creep, erosion of settlement. b) The minimisation of the possibility of damage to property occurring through flooding, or surface water run-off. c) The development of a more desirable roading pattern with improved accessibility to and within the site and the creation of a better sense of orientation and identity of the area as a whole. d) The efficiency of overall land utilisation including the quality of individual sites and amenity areas around buildings, the economics of

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT providing engineering services, and the standard of roading and onsite vehicular access. e) The need to create suitably graded areas for playing fields and other community facilities. f) The enhancement of the general environmental character of the area by softening the landscape or by artificially creating or emphasizing landforms of visual significance particularly on flat sites or on areas devoid of landscape features, or preservation of some specifically significant feature.

1.1.1.1 SOIL INVESTIGATIONS Where appropriate the general nature and shape of the ground should be studied and particular note taken of: a) The geological nature and distribution of soils and rock; b) Existing and proposed drainage conditions and the likely effects on ground water; c) Previous history of ground movements in similar soils in the area; and d) Performance of comparable cuts and fills (if any) in adjacent areas. Soil data should be obtained for areas which: a) Are intended to form in situ bases for fills; b) Are intended to yield material for construction of fills; and c) Are intended to be exposed as permanent batters. Sufficient borings, probing or open cuts should be made: a) Classify the soil strata by field and visual methods; b) Evaluate the likely extent and variation in depths of the principal soil types, and c) Relating subsequent soil test properties to relevant strata over the site.

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT The test data appropriate in different areas shall be determined by the soils engineer. 1.1.1.1 STABILITY CRITERIA Settlement. The most important factor in ensuring satisfactory performance of stable fills is the limiting of post-construction differential settlements. The design and construction of fills should be such that these settlements are kept within acceptable limits. The weight of residential buildings of one-storey and two-storey construction not requiring specific design, is unlikely to produce significant settlement of fill constructed in accordance with this Code. Local filling placed close to a house during or after construction, for example, for a patio, will produce much larger stress increases which may induce differential settlement of the house. Bearing Capacity. The strength of the ground resisting general shear failure (and resulting gross deformation) under the footings of a house is a local phenomenon distinct from settlement. Fill constructed to minimize settlement in accordance with this Code will have adequate shear strength. It should be noted, however, that despite careful construction there may be localised soft areas in the upper layers of fill within the zone of influence of small foundations. Should the routine foundations inspection by the building or the local authority during construction suggest, or should the Engineer suspect, that localised soft areas are present, then tests should be made to determine the required treatment of the fill material, or of the foundations. These tests should extend to a depth as agreed with the Group Manager Asset Management and may include shear strength tests, field load tests or dynamic penetrometer tests or other recognised soil strength tests.

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT Note: The developer should refer to the Natural Hazards Register contained in Volume 4 of the District Plan. The adequacy of subgrade compaction and proposed pavement depth for road works shall be confirmed by tests on the finished subgrade. This requirement is compulsory for new roads to be vested in Council. Shrinkage and Expansion. Because some clay soils are likely to undergo shrinkage and swelling when subjected to seasonal changes in water content, special examination of welling and shrinkage characteristics should be made in the case of highly plastic soils. Where applicable, the need for a foundation depth or design to minimise these effects, particularly for continuous brittle walls, should be noted in the completion report and statement of the soils engineer. Slope Stability. In most cases, it is unnecessary or impracticable to measure quantitatively the factor of safety of a slope against shear failure. Maximum slopes of cuts and fills may be determined by the soils engineer from experience and from observation of slopes in the vicinity which have a longstanding history of stability, are of similar height to the proposed slope and are of apparently similar geological formation. Where necessary or a precedent is not available, a special soils engineer investigation should be carried out by the soils engineer to determine acceptable limits to cut and fill slopes. In assessing slope stability account should be taken of possible future changes in ground water level or other conditions. Where a fill may be required to act under extreme conditions as a detention dam, investigation should include the ability of the fill to act as a detention dam and upstream effect of the fill.

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT 1.1.1.2 QUALITY OF FILLING MATERIAL The majority of soils, other than organic material, are potentially suitable for fillings under controlled conditions. However, the Group Manager Asset Management retains the right to disallow the use of unsuitable fill material.

1.1.1.3 COMPACTION STANDARDS FOR FILL MATERIAL The standard of compaction should be measured in terms of one of the following: a) Relative Compaction. That is, the ratio of the field dry density of fill to the maximum (laboratory) dry density expressed as a percentage. Unless otherwise required by the soils engineer, fill should be compacted to at least 95% relative compaction, in terms of the standard method of compaction. b) Air Voids and Shear Strength. Used for cohesive soils, where specific test methods and criteria should be determined by the soils engineer, who may, for example, require air voids to be less than 10% and shear strength to be not less than 50 kPa on completion of construction. c) Relative Density. That is, the field dry density expressed in terms of maximum minimum densities established by laboratory test (used for cohesionless soils). The specific minimum value should be determined by the soils engineer who may, for example, require a minimum relative density of 80%. d) Field Relative Compaction (Field Proctor Test). This is the ratio of the

density of the compacted fill material at its in situ moisture content, relative to the density of the same material at the same moisture content after standard compaction (Proctor compaction). (This method gives a quick determination of the actual field compactive effort being applied, relative to Proctor compaction, without need for drying in the testing procedure, and this may be adequate control provided the material is close to optimum moisture content.)

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT 1.1.1.1 EROSION CONTROL Subdivision or development should be carried out in such a manner as to restrict soil erosion to acceptable levels. This can be achieved by adopting sound design and construction procedures. Diversions of natural water and the discharge of water containing silt arising from subdivision or development works are subject to either a land use, water or discharge permit in terms of the Resource Management Act 1991. Where the Regional Council has issued a general authorisation, that is - for the diversion or discharge of water or water containing sediment associated with subdivision or development, the subdividing owner's representative shall comply with the conditions of such authorisation including notification to the Regional Council if required. Where water is to be diverted from one catchment to another, the effect on that catchment should be investigated, and where necessary approvals shall be obtained from the respective authorities or owners, or both. Without prejudice to the conditions of any Resource Consent the following practices should be adopted in the planning and design of land subdivision or development projects involving earthworks: a) Large projects should be programmed for construction in selfcontained stages which can be largely completed within one earthworks season. Where possible, the upper part of a catchment should be developed first. b) Where possible, the permanent storm-water system should be

designed so it can be constructed at an early stage in the project and be used to collect run-off from the site during construction in conjunction with silt control measures. c) The specifications should require the use of construction procedures which minimise concentration of run-off and excessive velocities, which could otherwise result in erosion.

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT d) Silt retention ponds should be constructed and maintained in all earthworks projects where they are feasible and necessary. e) Graded "V" drains (also called contour drains) should be used to divert

run-off water from non-construction areas past site-works or to divert run-off from exposed areas into silt retention ponds and reduce overland flow distances on bar surfaces. Such drains should have a maximum slope of 1 in 30 and a maximum design velocity of flow 2m/s. f) Cut and fill areas should be re-topsoiled and sown as soon as possible after earthworks and drainage works. g) The batter faces of cuts and fills should be protected as soon as possible after construction by grassing, hydroseeding, tree planting, or other suitable surfacing.

1.1.1.1 PROVISION FOR PERMANENT SERVICES Where settlement is expected to occur, all service pipes installed within or under earth filling shall be designed and constructed to ensure adequate capacity, strength and water-tightness to withstand the loads due to settlement and to prevent leakage into the fill. Where surface water could cause erosion of batters or internal instability through soakage in the soil, open interceptor drains should be constructed in permanent materials, and benches in batter faces should be sloped back and graded longitudinally to reduce spillage of storm-water over the batter. Water from storm water systems should be prevented from flowing into a fill or into natural ground near the toe or sides of a fill and no storm-water soak pits should be constructed in a fill whereby the stability of the fill might be impaired.

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT All drains required permanently to protect the stability of fillings or to prevent flooding and erosion should be clearly identified as such on "as built" drawings.

1.1.2 FINAL DOCUMENTATION

1.1.2.1 "AS-BUILT" DRAWINGS On completion of the earthworks an "as-built" plan should be prepared showing the extent and depth of fill in the form of lines joining all points of equal depth of fill at vertical intervals of for example, 500mm or 1m as appropriate. The "as-built" plans should also record the position, type and size of all subsoil drains, and their outlets. The plans should also show areas of filling of low density and any fill areas which the soils engineer considers do not comply with this Standard.

1.1.2.2 SOILS ENGINEER'S REPORT On completion of construction, the soils engineer should furnish for the engineer a report describing the extent of the inspection and the results of testing together with a statement of professional opinion as to the compliance of the filled ground to the specification, the suitability of filled ground for specified types of building construction, and where applicable, the suitability of original ground for specified types of building construction.

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT

1.1.3 PROTECTION OF THE WORKS The Contractor's responsibility for care of the Works shall include the protection of earthworks. The Contractor requires an Environment Protection Agreement or an Authorisation with the Environment Management Authority for all construction or building activities on a site more than 0.3 hectare and must be obtained prior to commencement of work. No extensions of time will be granted or allowed relative to any delay with obtaining of the necessary Agreement and other approvals unless it is shown to the satisfaction of the Superintendent that all necessary steps have been taken on time by the Contractor. Where the Contract documents include a suggested Sediment and Erosion Control Concept Plan, the Contractor is still responsible for the adequacy of those arrangements. The Contractor may choose to adopt those concept arrangements as the basis for applying for approval, or alternatively the Contractor may propose his own measures as the basis for approval. Prior to commencement of work the Contractor must provide two copies of the Sediment and Erosion control measures plan to Environment ACT – Water Unit for approval. Two copies of the endorsed as approved drawing(s) shall be provided to the Superintendent. In addition to those erosion and sediment control measures suggested in the Contract documents and the Sediment and Erosion Control Measures Plan the Contractor shall generally plan and manage the works to minimise erosion on the site. It is expected that control measures may include the following 1) Control over surface run-off by: a. construction of interception drains to divert run-off from undisturbed areas around the works area b. installation of temporary drains AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT c. early stabilisation of floodways d. use of straw bales, silt fences, swales, contour ploughing or rip dozer cleat impressions, spreader banks. 1) Limit movement of vehicles and equipment to: a. a single approved stabilised construction entrance b. prepared parking areas by the construction of temporary fencing. 1) Minimise the area exposed by: a. staging of clearing operations b. progressive stabilisation of the works as completed c. provision of temporary grassing d. contour ploughing to disturbed areas. 1) Construction of sediment control measures such as: a. sediment retention ponds, b. sediment basins c. sediment traps (various types) d. silt fences e. buffer zones Refer to "Erosion and Sediment Control During Land Development – Environment ACT" for details. Where the approved control measures include sediment retention ponds, and notwithstanding the requirements arising elsewhere in the Contract documents or from Environment ACT and, then: a) The ponds shall be kept empty of water for the longest practical

duration. During periods of high in-flow of water and sediment, causing overtopping over the pond spillway, the Contractor shall regularly test the quality of the waters being released and treat the water with chemicals as and when necessary in order to achieve a water quality for the released water complying with the above legislation and licence AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT and to maintain sufficient residual gypsum or an acceptable chemical in solution to sustain treatment of subsequent inflow. When there is an inflow which is insufficient to cause overtopping over the pond spillway, then the water is to be treated as necessary and emptied within three days of the inflow occurring. b) The Contractor shall remove and dispose of accumulations of materials from the ponds as often as is necessary to maintain their interception capacity to at least ninety percent (90%) of the design volume of the pond. c) The Contractor shall develop and implement procedures and a programme and provide all necessary equipment, materials and labour to carry out water testing; calibration test; dosing with chemicals; and the controlled release of waters so as to comply with the requirements of the legislation and licence. The testing procedure shall be developed using a turbidity meter which shall be calibrated with a series of test results on water samples with a range of NonFilterable Residue levels. The Contractor shall arrange laboratory tests for Non-Filterable Residue and obtain advice on dosage rates ensuring that the pH is within acceptable limits, and then if possible develop a simple field correlation technique for assessing the suitability of the water for release. Dosing can be carried out using an acceptable chemical such as gypsum, using a simple slurry mixing and spreading technique designed to achieve acceptable water quality. Gypsum is preferred because it does not change the pH and unless there are problems in effectiveness it shall be the chemical used. Unless specified elsewhere within the Contract, or directed otherwise by the Superintendent, then the sediment and erosion quality control measures will be provided, operated and managed, maintained or replaced as necessary for the period of the contract, including the consolidation period and/or the Defects Liability Period as required to fulfil the requirements of the Pollution Control Act. AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT 1.1.1.1 PROTECTION OF EARTHWORKS Protect earthworks and in particular road formations from the effects of erosion and deposition. Grade earthworks and particularly subgrades to drain at all stages without ponding. Where run-off must cross the formation, ensure that the stream is a broad sheet flow which crosses roughly at right angles to the alignment and minimises the likelihood of subgrade softening. When rain is likely or when work is not proposed to continue in a working area on the following day, precautions shall be taken to minimise ingress of any excess water into earthworks material. Ripped material remaining in cuttings and material placed on embankments shall be sealed off by adequate compaction to provide a smooth tight surface. Should insitu or stockpiled material become over wet as a result of the Contractor not providing adequate protection of earthworks, the Contractor shall be responsible for replacing and/or drying out the material and for any consequent delays to the operations.

1.1.1.2 PROTECTION OF COMPLETED EARTHWORKS In areas where earthworks, including open drains, have been completed and no further treatment is specified other than topsoiling and grassing or hydroseeding, then the topsoiling and seeding shall be carried out as specified at the earliest practicable date. Areas of exposed completed earthworks shall, if directed, be stabilised using temporary grassing, within 28 days of formation.

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT

1.1.2 CLEARING AND GRUBBING

1.1.2.1 GENERAL Unless otherwise specified, remove all vegetation, logs, stumps, boulders, roots, scrub, debris and dumped material and items within the limits of clearing. Demolish and dispose of any minor man-made structures (such as fences and livestock yards), all rubbish and other materials that are unsuitable for use in the Works. Grass and topsoil shall not be removed as part of this initial clearing. In advance of clearing and grubbing operations, effective erosion and sedimentation control measures shall be implemented in accordance with this Specification. All trees and stumps, on or within the limits of clearing, unable to be felled and removed by the clearing methods used by the Contractor shall be removed by grubbing. Grub out stumps and roots over 75mm diameter to a minimum depth of 0.5m below the natural surface or 1.5m below the finished surface level, whichever is the lower. Backfill grub holes with suitable spoil from excavations compacted in layers to the density of the surrounding undisturbed soil. The Contractor shall take all measures to prevent damage to existing underground and overhead utility services. Every precaution shall be taken to prevent timber from falling on private property and the Contractor shall dispose of any timber so fallen or produce the written consent of the owner to its remaining there. The cost of disposal of such fallen timber shall be borne by the Contractor. Prior to entering private property, the Contractor shall obtain consent from the Superintendent and the property owner. Damage of any kind, including damage to trees and fencing occurring during clearing operations shall be made good by the Contractor. The cost of repair of such damage shall be borne by the Contractor. AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT Limits of clearing are defined as lines one metre outside the intersections of excavation or embankment slopes with the natural surface or the outside limits of slope rounding together with any other limits detailed. For services trenches outside the general limits of clearing, limit of clearing is defined as trench width plus one (1) metre either side of the trench. The Contractor shall ensure that only the absolute minimum necessary for construction is cleared.

1.1.3 Disposal of Material Unless otherwise specified, all materials cleared and grubbed in accordance with this Specification shall become the property of the Contractor and shall be removed from the site and legally disposed of. Unless otherwise specified elsewhere, disposal of timber and other combustible materials by burning shall not be permitted. Where permitted, the Contractor shall comply with all Statutory requirements applicable to burning off, and any such burning off shall be carried out in such a manner that no damage is done to any trees outside the limits of clearing. Smoke resulting from such burning off shall not cause a traffic hazard or a nuisance to adjacent landholders.

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT

1.2

PLANNING STAGE

1.2.1 COST ESTIMATED Construction cost estimating is demanding work, no matter what type of construction is involved. But, estimating earthwork is the hardest of all. That is because, excavation has more variables and unknowns; don’t know what’s down there until start digging. Also have to rely on information from many sources – some of which may not be accurate. That’s why every earthwork estimator needs special skills: a) The ability to read plans and specifications b) An understanding of surveying and engineering practice c) A facility with mathematical calculations d) The ability to anticipate environmental and legal issues e) An abundance of good common sense In the past, many smaller dirt jobs were bid as a lump sum rather than by the cubic yard. Dirt contractors based their bid on guesses – what equipment was needed and how long should it takes? They didn’t bother estimating soil quantities. Making estimates this way overcome one problem; most excavation contractors didn’t know how to estimated soil and rock quantities. Fuel and labour costs are too high now. And the competition is too intense. There’s too much risk in “seat-of-the-pants” guesses. A few mistakes, a couple of surprises and to be looking for some other type of work. Only the best survive for long in this business. Most of the survivors know how to make accurate bids by the cubic yard. Fortunately, making good quantity estimates isn’t too hard if mastered a few simple skills. () 1.1.1.1 THE SITE VISIT A site visit is an important part of every earthwork estimate. If skip this important step, the estimate is just a guess. AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT 1) Review the plans first Before go to the site, take time to review the plans completely. Make an itemized list of any special problems or unusual requirements; pick up from plans and specifications. Take that list and check each item while in the field. The amount of information provided on the plans will determine how much work have to do to prepare for the site visit. If have a complete set of plans and specifications, it’s easy to list the questions that need answers. When go into the field on a site visit take along two lists. The first is a list of specific questions based on the current plans and specifications. The second is standard checklist for site visit. Every estimator needs a checklist to work from. Maybe overlooked something once; put it on the list. 2) Make the visit productive The visit to the site can make a significant difference in the amount of the bid – and size of contractor’s profit. Analyze the job site anticipate problems that might interrupt work scheduling, situations that require specialized equipment, or shortcuts to speed the work along. It takes knowledge and experience to make the site visit productive. Most of the know-how comes from experience on past projects. Also can use common sense to come up with a more cost-effective way to d the job. Use the site visit to plan the construction scheduling and to anticipate equipment and labour requirements. The actual conditions of the site will dictate the type of equipment needed and the way the work is done.

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT

3) Accessibility First, consider the physical location of the site. How remote is it? What roads or streets lead to the site? Are the any one-way streets leading to the site? All this will have a direct bearing on the work. If have to bring dirt in or take it out, consider the distance to the borrow or dump site. In fact, recommend driving the route several times, using different roads to find the shortest and best route. If the surrounding streets carry heavy traffic, it will slow down the movement of equipment to and from the work site. Will traffic problems require the use of one or more flagmen? Look for any other safety-related problems that might require additional manpower. Is the site near any homes or business? Is there a noise ordinance and its enforced? Take complete notes during the site visit on any variable that will affect the profit and works. 4) Degree of job difficulty Are there any steep slopes that would require unusual equipment? Is the area open, or are these obstructions like buildings, trees, sidewalks, or utility lines in the way? Any of these will slow down the production. If specialized equipment is needed, will it e available in the area or will have to bring it in from a distance. This is a good time to decide what size and type of earthmoving equipment to use. Consider whether there’s enough room for the equipment to turn and move economically. When making the decision, consider the ground conditions, traction, and the distances and directions have to move. Remember, the track machines have a slower working speed. 5) Surface condition Drainage problems, steep slopes, dense vegetation, and sharp or large rocks scattered on the surface will all hamper production. Drainage is one of the biggest problems. Provide the drainage

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT channels to reroute water during construction. But can’t divert water onto streets or roads. 6) Subsurface conditions Even have the soil tests on the site, the actual conditions of the soil below the surface are really anybody’s guess. Water running on the surface indicates underground water seeps. If the work limits are below the local water table, have to pump water from trenches and the excavation portions of the job. 7) Utilities Try to determine if utility lines are shown in the correct location on the plans. Utility lines sometimes aren’t where the plans show them. A variation of just a few feet can make a big difference in time when working in a confined area. If there exist storm or sewer lines, check the manholes for conditions, material and depth to flow line. Also check for size, direction and number of inlets and outlets in the manhole.

Check for overhead wires that would be in the way of

working equipment. Will the temporary electric or phone connection are needed. 8) Project size Consider whether building materials and equipment can be stored on the job site without interfering with the work. 9) Local needs Locate local suppliers of fuel, repairs, parts and any other operations needs. Find out the policy on credit or payments. Get an agreement in writing if possible. Plan to use local workers, expected wages for the labour.

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT

10)Traffic control If the project will need traffic control, check with the local authorities to see what they require. Most of them spell out traffic control requirements very clearly. There are exact standards for barricades, delineators, flashing light and other safety precaution. 11)Security The job site is isolated or in an area with high crime rate, may want to hire a security company. Vandalism to equipment or material, theft, and destruction of completed work can be a major financial loss. Most of it won’t be covered by the insurance. That makes it a cost of doing business. Also consider public safety. Job will probably drawn sidewalk superintendents. Everyone loves watching heavy equipment at work. So, need to protective fencing around the area, to keep people out of danger. 12)Existing and imported soil Look at the soil itself, both the existing soil any soil that must be trucked in. Checked the compaction requirements. The more compaction needed, the more time required for rollers.

1.1.1.1 THE BULK AND SHRINK FACTORS Using the bulk and shrink factors to make the estimated more accurate. That’s because a given quantity of soil has no constant volume. Add moisture and the soil bulks, expanding in volume. Soil volume also increases when it’s loosened or disturbed by excavation. Conversely, the soil volume shrinks or contracts when apply pressure to compact the fill. Actual bulk and shrink factors consider the combined effect of: a) Moisture content b) Density (compact versus loose) c) Soil type AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT The volume of soil in the original ground will change when the soil is excavated and loosened, or when it is filled and compacted. The volume of soil should be adjusted so as to compute the volume to be excavated, hauled and embankment on a common basis. 1) Bulking Factors

Bulking factors (L) =

Volume of loosened soil after excavation Volume in the ground before excavation

Soils and rocks usually swell when they are excavated; thus 1m 3 of material in the ground will occupy more than 1m3 in the transporting vehicle. This must be allowed for in assessing the amount of transport required and their number of trips and therefore the cost of transporting materials. 2) Shrinkage Factors

Shrinkage factors (L) =

Volume after compaction Volume in the ground before excavation

Excavated soils except some firm granular materials usually shrink when they are compacted. Necessary to plan how much volume of soils is to be hauled to which parts of embankments; to estimate how much volume of soil in the ground shall be cut and borrowed to form an embankment. Both factors are assisting to measure the output productivity before run the construction. It does also can calculate the number of excavator, Lorries and labour needed to carry out soil from the site or embankment the soil to the

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT site. There are also help to preparing the budget and time duration for earthwork operations. Bulking and shrinkage factor of various soil Type of soil

Bulking factor (L)

Shrinkage factor (C)

1.65 – 2.00

1.30 – 1.50

1.30 – 1.70

1.00 – 1.30

1.10 – 1.20

0.95 – 1.05

1.10 – 1.20

0.85 – 1.05

1.10 – 1.30

0.85 – 1.00

1.25 – 1.45

1.10 – 1.30

1.10 – 1.20

0.85 – 0.95

1.15 – 1.20

0.90 – 1.00

1.20 – 1.30

0.85 – 0.95

1.40 – 1.45

0.90 – 1.00

1.20 – 1.45

0.85 – 0.95

1.30 – 1.45

0.90 – 1.00

1.40 – 1.45

0.90 – 1.00

Rocks a) Hard rocks b) Loose rocks c) Boulders/cobbles

Gravelly Soils a) Gravels b) Gravelly soils c) Solidified gravelly soil

Sands a) Sandy b) Sandy & cobble Common soil a) Sandy soils b) Sandy soils with cobbles Cohesive soil a) Cohesive soils b) Cohesive soil with gravels c) Cohesive soil with cobbles

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT

1.1.1.1 CALCULATION

Figure 4 The soil that will excavate. (35, 000m3)

This site will be excavate soil from reduce level 21.00 to 15.00 and the soil had to dispose to the dumping area. The total volume of soil to be disposed is about 35,000 m3. Below show the calculation how many excavator and lorries required for this project done in 9 weeks. If duration to complete

= 9 weeks = 54 days

Bulking Volume 35, 000m3 x 1.15 (bulking factor) = 40, 250 m3 Excavator required 40, 250 m3 1, 300 m3 (output excavator/day) x 54 days

= 0.57 = 1 unit excavator

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT

Lorries required a) Nos of trip 40, 250 m3 10 m3 (capacity lorry per trip – unlicensed lorry)

= 4, 025 trip

b) Time taken per trip 60 minute 30 km/hour (lorry speed)

x 1km (distance) x 2

= 4 minutes

c) Time to load and upload Assume

= 7 minutes + 4 minutes (time taken per trip) = 11 minutes

d) Total time taken 4, 025 trip x 11 minutes = 44, 275 minutes e) No of lorries required 44, 275 minutes 54 days x 60 minutes x 8 hour (per day)

= 1.7 = 2 units Lorries

So, for this project, they are requiring to have 1 unit of excavator and 2 units of unlicensed lorry to complete the project in 9 weeks. This calculation is help to measure the requirement more accuracy and the contractor will know their profit also can budget the cost and planning of earthwork operations.

1.1.1 METHOD STATEMENT AND PROJECT PLANNING This Construction Method Statement (CMS) provides a summary and explanation of the construction methods and sequencing of contractors on site in earthwork operation of this project. This CMS is not intended to AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT provide a detailed specification for the proposed works. Rather it outlines the sequence and extent of construction activities that may not be obvious from the design drawings alone and that need to be considered in terms of their impact on the surrounding environment. Detailed specifications for each type of work will be prepared prior to the start of construction and these will incorporate any restrictions on working practices demanded by the outcome of the various environmental and planning studies that will accompany the planning application, together with any Planning Conditions that may subsequently be applied.

1.1.1.1 EARTHWORK 1) Scope of Works The main purpose of this method statement is to outline the activities and method, which will be used in general to carry out the earthworks in accordance with the Contract Specification, and details shown in the drawings. 2) Resources a) Hydraulic Excavator PC300 for excavation and shifting material. b) Hydraulic Excavator EX200 for excavation and shifting material. c) Unlicensed 10–Wheeled Dump Truck for transport material. d) Back pusher Tractor Ford 5000 for levelling.

e) Vibratory Compacting Roller CA25 for compaction of earth. f) Concrete mixer. g) Manpower etc.

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT

1) Sequence of Works a) Survey Setting Out

Confirm pre–computation plan and other given references for establishment of points or lines for our setting out of the Works (e.g. control stations, level pegging etc). These lines or points will be referenced to enable their re– establishments as construction proceeds. Original Ground Level (OGL) survey will be checked on site and verified against the construction drawing progressively after the site clearing for any discrepancies.

b) Site Clearing Site clearance shall be carried out within the limit of contract by removal of fallen trees, shrubs etc. to approved tips. Stripping of topsoil will be carried out up to about 150mm layer of soil that can support vegetation.

c) Earth excavation For earth cut fill within the site, earth will be excavated in bulk from designated high areas within the site to the required depths and levels in accordance with the drawings. Prior to filling with earth excavated area need to be survey to confirm excavation level verified by C.O.W/client representative. For excess excavated earth, these shall be transported, spread and levelled along side of the site boundary. Compaction of the earth shall be carried out in layers with a vibratory compacting roller of 20–tonnes capacity or more in operation. The thickness for fill shall be 300mm each layer according to specification. However, the swell factories are various from 0.6 to 0.8 depend on the properties of the earth. Hence, at the loose state, the loose measure thickness various. A trial compaction test will be carried out to demonstrate the compaction method and numbers of passes to be used. The method statement of the trial compaction will be submitted AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT separately. Field density tests as per compaction requirements shall be carded out on requests and at an agreed interval depths at earth fill areas and to be witnessed by authorized Representative. Close turfing to slopes shall be carried out upon completion of sizeable area. As built level survey shall be carried out upon work completion and submit to Engineer.

d) Rock excavation & blasting Excavation in solid rock in open excavation shall mean in rock found in ledges or masses in its original position, which would normally have to loosened either by drilling and blasting or be pneumatics tools. All solid boulders or detached piece of rock exceeding 9 cubic feet in size, but not otherwise, shall be regarded as solid rock. The solid rock shall be joint measured with Clerk–of–Work prior to commencement of blasting operation. The crawler drilling machine shall used to drill the 3" diameter blast–holes with interval of 1.8m to 3.Om depend on the site condition. Blast–holes shall be placed in lines parallel to the rock face because a rectangular patter gives better breakage and vibration control. Depth of drill holes is determined by height of face desired and distance it is necessary to drill below grade so that bottom can be controlled. Air compressor shall be used to –remove water capture inside the blast–hole prior to insert explosive to the blast–hole. ANFO consists of ammonium nitrate (AN) and fuel oil (FO) at the ratio of 6% (FO) and 94% AN. Ammonium nitrate shall be used as explosive for blasting rock into pieces small enough to be handled efficiently by hydraulic excavator.

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT

The recommended method of making primer with a small diameter cartridge as below: i. Punch a hole through the plastic film with wooden pricket near the middle of the cartridge. ii. Fully insert the plain detonator into the cartridge. iii. Wrap electrical insulation tape, around the cartridges from the detonator to the end of the cartridge along safety fuse, securing the detonator. When priming the blast hole, ensure that the detonator points to the bottom of the blast hole so that the safety fuse is not bent sharply. iv. It is necessary to vary the length of safety fuses when firing multiple blast hole so that the blast holes fire in the desired sequence. All safety fuses shall be connected into series and joint to exploder to commence the blasting works. v. Safety signboard and red flag shall be placed in the necessary places prior to commencement of blasting works. vi. Blasted rock shall be removed and deposited to the area within the site directed by S.O.

a) Field Density Test A trial compaction test will be carried out to demonstrate the compaction method and numbers of passes to be used. The method statement of the trial compaction will be submitted separately. Field density tests (Sand cone replacement method) as per compaction requirements shall be carried out on requests and at agreed interval depths at earth fill areas and to be witnessed by authorized Representative.

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT

The requirement of the degree of compaction are: i. For the topmost 12 in below formation level less than 95% of the maximum dry density obtained from BS Heavy Compaction Tests. ii. For the remainder below formation level less than 90% of the maximum dry density obtained from BS Heavy Compaction Tests.

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF EARTHWORK OPERATION MULTI- BLD STOREY PROJECT 410 1.1.1.1 EXAMPLE OF METHOD STATEMENT FORM

NO

OPERATION

1.

Site Clearance and Stripping Top Soil

SEQUENT OF DIAGRAM

MACHINERIE S/PLANT

REMARKS

1 Excavator, 1 Bulldozer,

- For a site condition that full of bushes and vegetation, as well as several huge trees that existed in that area. Site clearance is carried out to all areas occupied by the works area. All the trees, scrub, stumps and bushes within the site boundary are removed completely, including grubbing out of all roots.

1 Back pusher.

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF EARTHWORK OPERATION MULTI- BLD STOREY PROJECT 410

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF EARTHWORK OPERATION MULTI- BLD STOREY PROJECT 410

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT 1.1.1.2 PROJECT PLANNING This is an example for preparing the Critical Path Method. The project planning must included the time duration, cost, resource, management and sequence of work for this SOHO project.

Figure 5 Critical Path Method

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT

1.1.2 CONSTRUCTION METHOD AND USE OF PLANT

1.1.2.1 PLANNING OF WORK Prior to the commencement of excavation all the relevant data should be collected and drawings prepared showing the location of the excavation, tipping and filling. On these drawings both the excavation and filling should be divided into section and the quantity of material to be excavated and filled stated in these sections. This information is required to ensure economic hauls throughout the work, in which connexion a ‘mass-haul’ diagram is often. () Where the material is to be excavated consists of different types, and if the various types have to be used separately in the fill or run to spoil tip, the quantities of each class of material in each area should be shown on the drawing. From the nature of the material to be excavated and the method of its disposal, the type of excavation, the length of haul, and the amount of compaction necessary, it is possible to select the most suitable type of plant for: a) Excavating (when quantities are large it may be economical to use diffrent types of equipment for the various materials to be excavated). b) Transporting the excavated material (the length of haul, the nature of the route selected, the conditions of tiping or speading, and the type of excavator adopt, should be considered). c) Placing the material (the methods and plant used for transporting and compacting the material should be considered). d) Compacting the material (the nature of the material and the relative compaction specified are essential considerations).

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT 1.1.1.1 SETTING OUT When setting out earthworks it is first necessary to set out the centre line or other reference lines, and then the lines indicating the top of the cutting or the toe of embankment. These lines should be ascertained from cross sections of the existing ground the finished work. Reference pegs should also be driven into the ground at a fixed distance outside the peg marking the top of the cutting or the toe of embankment. All levels should be referred to an established bench mark not subject to subsidence or interference. Batten profiles are useful to indicate the slopes to which embankments are to be constructed. In setting out both cuttings and embankments, allowance should be made for hand trimming and soiling. Method of Excavation The types of excavating plant to be used will depend on the materials to be excavated. For soft or loose materials, e.g. topsoil, gravel, sand, and most clays, all types of excavating plant referred to in Clause 7.05 are most suitable and the choose for a particular job will depend on the conditions of working and possibly, on the plant available. When excavation has to be carried out below water level, draglines or grabs are generally used. In deep or wide water, floating dredgers may be desirable. For hardest materials, e.g. stiff clays, shale’s, marls, soft chalk, heavier and more powerful models than those used for soft or loose materials are generally required. It may also be necessary to employ rooters or scarifies to break up the surface of the material before the excavating plant can be used.

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT For hard rocks, e.g. all rocks which require drilling and blasting before they can be excavated, face shovels are most suitable excavators for loading after blasting. Draglines or grab can be used but not so useful as face shovels.

1.1.1.2 OBSTRUCTIONS In general, obstructions such as trees, roots, and boulders should be removed if they are detrimental to or likely to hinder the works. a) Trees Trees can be removed using mechanical equipment such as tree pullers, bulldozers, special rooting attachments fitted to crawler tractors, and power-operated logging winches mounted at the rear of track laying tractor. Alternatively, the trees may cut off at a height of not more than 3 ft above the ground and the stumps grubbed out by means of winch gear or high-velocity explosives, or a combination of both. b) Boulders Generally boulders which may interfere with the work should be removed, after breaking down if necessary. In the case of embankments they may instead be broken down to a size not exceeding the thickness of the compacted layer of fill. Boulders are usually broken down by means of explosives although plugs and feathers or hydraulic cartridges may be used, particularly when the use of explosives is inadmissible. There are three methods of dealing with boulders by explosives: i) Bore a hole about halfway through the boulder into which the

explosive charge is placed and thoroughly tamped.

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT ii) Plaster Shot methods. The surface of the boulder should be roughened by means of a chisel or other implement, removing any moss or clay coating and thus ensuring a clean surface. iii) Place a sufficient charge underneath and in contact with the

boulder in a hole made in the ground by means of crowbar. a) Safety Precautions Blasting methods should be carried out only by persons thoroughly conversant with the working methods and precaution and regulations to be observed in using explosives, and with local police requirements. To avoid the danger of injury from flying debris all personnel in a blasting area should retreat several hundred feet and take adequate cover.

1.1.1.1 EXCAVATING PLANT Some notes on the types and use of excavating plant are given below: a) General purpose excavator This machine is a versatile and universal construction tool capable of carrying out many different type of front end or jib equipment it can be used as a dragline, backater or drag-shovel, grab, crane, shovel, skimmer, or pile driver. b) Face (or crowd) shovel Face shovels will dig soft or reasonably hard materials, including soft chalk, shale and marl, and hard rock when reduced by blasting. They are a quickly-acting type of machine and work from the bottom of excavation, digging upwards from the level on which they stand. They can produce a reasonably clean bottom in many materials. Generally, the face shovel requires vehicles for transporting the material away from the excavation.

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT c) Dragline The dragline is suitable for a wide range of materials but it will not dig such hard material or leave such a clean surface as the face shovel. It operates from the surface of the material to be excavated, digging below itself. Where access of vehicles to the bottom of the excavation is difficult, the dragline working from the top is to the face shovel working on the bottom; the time cycle of operation is slightly longer than of the face shovel and its output is rather less. For digging narrow cuts and depositing alongside it have great advantages over the face shovel as it has a much greater reach. It is, therefore, used extensively for cleaning out river beds, forming flood banks alongside rivers and stripping overburden from mineral deposits. In trench work, this machine is generally used, with buckets varying in capacity from ¼ to 2 cu.yd, for wide trenches with roughly battered sides. It is particularly useful for excavating water-logged materials. d) Backwater or drag-shovel (trench hoe)

This type of excavator is generally used for excavating trenches of comparatively narrow width and in materials whichare too hard for a dragline. It is commonly of ¼ to ¾ cu.yd bucket capacity, working on the surface, will dig in a single cut vertical trenches up to about 15 ft deep and from 2 to 5 ft wide. e) Grab A grab may be used with a dragline excavator or crane on sites such as foundation pits and trenches where the dragline bucket cannot be employed. It is also largely used for under water work. f) Track-laying tractor and scaper This equipment is capable of both excavating and transporting the material, and can in certain materials and where suitably routed give a considerable degree of compaction in the fill without the use of any AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT other compacting equipment. It is suitable for use in the softer materials, but can be used for harder materials if the material to be excavated is first scarified or broken up with a rooter, or with the help of booster. It may become uneconomic to use this type of tractor and scraper for lengths of haul over about 600 yd. g) Grader or blade grader Graders or blade graders are used principally for the finished grade for roadways, aerodrome runways, or similar types of work, and for spreading a sub-base of ashes or similar material over the area being treated. They may also be used for bank trimming where the slope of the embankment is not to steep, and for cutting V-Shaped ditches up to 3 ft deep in open country. Heavy types of graders are capable of moving large quantities of earth over short distances and may be used for constructing the whole earthworks for a roadway from virgin ground to completed soil information. Heavy types of graders can be fitted with scarifiers, bulldozer blades, snow ploughs, and side or rear end elevator loader attachments of the endless belt type. h) Bulldozer and angle dozer These machines are primarily designed for spreading and levelling operations, but are also used for backfilling and excavating shallow cuttings. They will work satisfactorily in soft or loose materials provided the tracks will gap. The usual length of push does not normally exceed 100 – 200 ft.

1.1.1.1 TRANSPORT PLANT a) Tractor-drawn equipment Scrapers or wagons drawn by track-laying tractors are satisfactory for the transportation of excavated materials over short distances and rough ground, or where tipping is difficult. Normally the distance should not exceed about 600 yd. If a suitable road is available, AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT wheeled tractors are preferable and, in any case, where long hauls are involved they should be used; the larger types then become more economical. The advantages of the wheeled tractor over the tracklaying type are in the speed of operation, the greater capacities and the freedom from expensive track renewals. The capacities of scrapers and wagons range from 4 to 40 cu.yd or more. Hauls of 2 to 3 miles are common for wheeled tractors. b) Lorries and other rubber-tyred vehicle Many types of lorries and other from 5 to 20 tons. They include steelbodied tipping trucks, and end- or side- tipping or bottom-opening dump wagons. Special rubber-tyred vehicles not suitable for operating over public roads are made up to40 cu.yd capacity. Dumpers, with capacities of up to 5 cu.yd, are suitable for hauls of up to about 1 mile. c) Belt conveyors Belt conveyors are finding increasing use for the transport of excavated material both on short and long hauls. Operating with suitable loading and spreading equipment to ensure uniform flow, there are very suitable for moving large volumes of excavation. They are most frequently used for handling materials of fairly even consistency, such as sand and gravel, over short distance, but really large quantities may justify the expense of installing them for moving almost any excavated material over long distances.

1.1.1.1 COMPACTION PLANT a) Vibrating rollers and plates These machines are particularly effective on granular soils. The vibrating roller is a smooth wheeled machine fitted with an engine driven vibrating unit. It is made in various sizes ranging from about 3 cwt (hand propelled) to 3½ tons (tractor drawn). Power-propelled machines, both of the single roller and tandem-type, are available in AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT the intermediate sizes, the smaller models being hand-guided. Vibrating rollers have a tendency to dig themselves in when used on too thick a layer. b) Construction equipment Plant used for construction purposes will provide useful compaction if it is suitably routed to cover the whole area, and if the soil is spread in sufficiently thin layers. Such compaction may in certain cases be useful in minimizing or even obviating the use of special compacting plant. Where material is transported by scraper equipment, the fill may be distributed in shallow lifts by the scrapers themselves. Where lorries or dumpers are used, bulldozers and angle dozers should be used to spread the fill material.

1.1.1.1 EFFECT OF WEATHER ON CONSTRUCTION OPERATION Very little can be done to protect earthworks from weather as the nature of the works and their extent generally preclude the use of any covering. a) Effect of wet weather on plant operation. Rainfall may so affect the exposed surface of cohesive soils as to result in interruptions both in the use of excavating plant in the transport of materials. Airfield works, with their extensive use of pneumatic-tyred plant over shallow cuts fills, are particularly affected by intermittent wet periods. Where construction roads are required in connection with earthworks they should be adequate for the anticipated traffic, and if possible, laid out and constructed during dry weather. b) Effect of weather on compaction of earthworks. The moisture content of any soil governs the degree to which it may be compacted. AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT If the soil is very wet it may be impossible to achieve a satisfactory degree of compaction. If the soil is very dry, a large amount of rolling or tamping may be required to compact is satisfactory. Thus, in wet weather, work may have to be stopped entirely owing to excessive moisture near the surface of the soil, while in dry weather it may be necessary to add water to the soil before compacting it in a fill or embankment. Both of these difficulties may be diminished if the soil required for filling is protected as much as possible from direct exposure to the weather, e.g. by leaving the topsoil or over-burden in place until the time has come to excavate the subsoil. It is advisable to compact the soil in its final position in the fill or embankment immediately after it is placed.

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT

1 CONTROLLING FOR OPERATION OF EARTHWORK 1.1 INTRODUCTION Earthworks monitoring checks the performance of the fill during or post-filling, depending upon the design of the equipment. Normally, the engineering quantities measured are fill settlement or groundwater level, since both may have significant effects on performance. Thus if the specification required a certain maximum settlement after embankment construction, post-filling settlement monitoring would indicate whether or not settlement was within the stated limits. Hence monitoring is a control on the engineering performance of the fill platform. Monitoring should be regarded as essential for sensitive structures and where groundwater rise within the fill is a possibility. The techniques available include: Surface leveling stations (monuments) to measure settlement of the fill surface (post-filling). Settlement plates (rod extensometers) to measure the settlement of the fill thickness (during and post-filling) Magnetic extensometers to measure the settlement at incremental depths of the fill (during and post-filling) USBR settlement gauges (during and post-filling) Piezometers to measure to measure the water level in the fill (postfilling) Instrument reading should be made for as long as possible after construction, if necessary during commissioning the structure. In practice, except for large sites, it is difficult for continuous monitoring to extend beyond a year or so but, for sensitive structures, it is vitally important that measurements should be obtained during at least one wet season. If collapse settlement in

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT occurring, due to inundation, some indication may be obtained during this period. 1.1.1 SURFACE LEVELLING STATION (MONUMENT) Such stations should be positioned as soon as an area of fill has been brought up to finished level. This will mean that the maximum time will be available for settlement readings, noting that, for obvious reasons, none can be made using this form of equipment during fill placement itself. Because of the heavy plant frequenting construction sites, a surfacing leveling station should be robust, comprising a concrete block about 1 m³ in size, sunk about 300 mm into the fill surface; a metal stud should be cast into the top, from which optical leveling may be conducted. Readings will give the total settlement of the fill and that of the underlying soils, if they were not removed prior to filling.

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT 1.1.2 SETTELEMENT PLATE (ROD EXTENSOMETER) Unless the natural ground is stiff and will not deform significantly under fill (and structure) load, surface leveling stations measure settlement of the underlying soils as well as the settlement of the fill. This is problem where the natural ground is soil and rock, and where the settlement of the soil beneath the fill could represent a significant proportion of the total settlement at the fill surface. In cases such as these, settlement plates (rod extensometers) may be employed. They monitor fill settlement continuously during and after placement and not from completion of filling only. Settlement plates comprise a base plate, usually of the order of one metre diameter, on to which a suitable length of casing is welded. The base plate is placed on to natural ground surface with the casing upstanding and fill carefully placed and compacted around it, during filling works. If it is necessary to extend the casing vertically upwards in order to cope with greater fill thickness, additional casing lengths may be welded or screwed on. From time to time, a rod of known length is introduced into the casing from the surface to the base plate and a reading of the settlement of the underlying natural ground is taken by leveling the top of the rod. The surface of the fill, say 2 m from the casing, is leveled at the same time at say four position (N, S, E and W) and the result averaged. The difference between the settlement of the underlying natural ground and the fill surface is the settlement of the fill. Settlements may be measured a different time during and after filling and a graph plotted showing settlement against time. Friction between the fill and the casing means that the fill can hang-up on the casing, so that the settlement at the surface close to the casing may be less than the true value. To avoid this undesirable feature, reading of the fill surface should not be taken too close to the casing. Care should also be taken to site the settlement plate on reasonably flat natural ground beneath the fill.

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT 1.1.3 MAGNETIC EXTENSOMETER This equipment is often employed where, for example, the compressibility of one fill type is being compared with the compressibility of another, or where it is necessary to separate the settlement of the fill from that of the underlying soil upon which the fill is placed. Magnets are located is the fill about a central plastic tube grouted into a borehole sunk to hard ground beneath the fill. A probe lowered down the tube locates the magnets and measures their position with respect to the base of the borehole (presumed fixed). Results of the settlements recorded by a magnetic extensometer installed at the site referred to in Section 8.7.2 are illustrated in Figure 8.8, where the settlement are recorded as percentage change in fill thickness. A device which can be built up from the base of the fill, along the lines of the settlement plate and USBR gauge (describe in the next section) is also available. It therefore has the distinct advantage over the surface leveling station in monitoring fill settlement continuously during and after placement and not from completion of filling only.

1.1.4 USBR SETTLEMENT GAUGE The USBR settlement gauge (United States Bureau of Reclamation Manual, 1974) comprises a series of cross –arm being separated by standard length spacers. The basal pipe sections is grouted into hard ground beneath the fill (perfumed fixed) and further sections added at a rate consistent with the rate of fill being deposited. Settlements of the various cross-arms are measured by a torpedo unit lowered down the central pipe sections. Unlike the settlement plate which provides the total fills settlement, the USBR gauge indicates the settlement of the fill at each cross-arm location. In this respect, the device compares with the magnetic extensometer. Results obtained from a USBR gauge installed in 59 m of the open-cast fill arm (expressed as percentage change in fill thickness) are plotted against fill thickness t a log scale and an approximately linear relationship results. There

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT is some scatter about the trend lie but this should be expected given the variable nature of the open-cast fill concerned. 1.1.5 PIEZOMETER A piezometer (preferably a porous ceramic pot, equipped with granular surround) provides a direct indication of the water level at the location installed. Dipped at the same intervals at which settlement readings are recorded it provides direct evidence of any link between settlement and water rising in the fill (Figure 8.7 is an example). Because of the importance of establishing such a link, piezometers should be positioned as close as possible to the settlement measuring device: not only does this procedure provide maximum information at the position at which settlement readings are being taken but, by ring-fencing the top of the piezometer and the settlement device, allows better protection from construction plant. Where pore pressures measurements are desired in clay fill, hydraulic ceramic piezometers are normally employed. They required a much more sophisticated level of monitoring, with each piezometer controlled via twin nylon tubes to a manometer in an adjoining gauge hut. Unlike the Casagrande piezometer which measures positive pore pressures only; such equipment can measure both positive and negative pore pressures. Further information may be had from Hanna (1985) or Dunnicliff (1988).

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT 1.2

SLOPE PROTECTION. Often excavations for earthwork construction intercept the existing

groundwater table, thus interrupting the natural flow of groundwater. This does not affect the building until the groundwater flow emerges on the cut slope. If the flow is small, there may be no adverse effects. However, when the flow is significant and the conditions at the site are favorable, flowing water can cause seepage forces that will in turn cause the slope to slough or fail. To stabilize slopes under these conditions, a heavy material is placed on the face of the slope. This material is heavy enough to hold down the existing soil even though seepage forces are acting in an outward direction. At the same time, it is open enough to carry all the water emerging from the existing soil. A coarse-graded stone, slag or gravel blanket on top of a recommended geotextile has proven to be effective in these cases. The drainage blanket should be designed before construction, but weather condition during construction will substantially influence the actual need for such treatment.

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT 1.2.1 STABILIZATION OF CUT SLOPES 1.2.1.1 INTRODUCTION Cut slopes may require stabilization for the following reasons: Failure of the slope as originally designed Strictly limited land-take, requiring steeper slopes than the ground would safety provide unaided. This is common in an urban or suburban environment. Ground conditions at the time of construction are found to be less favourable than those foreseen at time of the site investigation. As a consequence, either slacker slope have to be adopted (resulting in increased land –take) or the originally planned side slopes are maintained but a form of stabilization has to be adopted Road widening is necessary For these conditions, stabilization may be achieved by retaining wall, soil nails, anchors or reticulated mini-piles. Other methods of the stabilization include drainage and embedded gravity, gabion or crib walls. An excellent account of the various methods available for slope stabilization.

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT

1.1 METHODS OF GROUNDWATER CONTROL 1.1.1 Sumps and Ditches Installation of ditches, French drains, and sumps within an excavation is one of dewatering procedure. The water entering the excavation can be pumped out. This method of dewatering generally lower groundwater head more than a few feet but seepage into the excavation may impair the stability of excavation slopes or have a detrimental effect on the integrity of the foundation soils. Therefore, filter blankets or drains may be included in a sump and ditch system to overcome minor raveling and facilitate collection of seepage. The disadvantages of a sump dewatering system are slowness in drainage of the slopes, potentially wet conditions during excavation and backfilling which may impede construction and adversely affect the subgrade soil, the space required in the bottom of the excavation for drains, ditches, sumps, and pumps and the frequent lack of workmen who are skilled in the proper construction or operation of sumps. A common method of excavating below the groundwater table in confined areas is called as cofferdam. Wood or steel sheet piling are drove below subgrade elevation and bracing are installed to excavate the earth. Any seepage that enters the cofferdammed area will be pumped out. Dewatering a sheeted excavation with sumps and ditches is subject to the same limitations and disadvantages as for open excavations. However, the danger of hydraulic heave in the bottom of an excavation in sand may be reduced where the sheeting can be driven into an underlying impermeable stratum, thereby reducing the seepage into the bottom of the excavation. Excavations below the water table using sheeting and sump pumping can sometimes be successful. However, the sheeting and bracing must be designed for hydrostatic pressures and reduced toe support caused by upward seepage forces. The bottom of the excavation can be covered with

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT an inverted sand and gravel filter blanket to facilitate construction and pumping out seepage water.

Figure 6 Dewatering open excavation by sump and ditch.

The necessary characteristics of a sump are as follow: 1) The final sump must be deep enough so that when it is pumped out, the entire excavation will be drained. Digging the sump down that extra several feet is difficult and sometimes risky. Therefore, temporary sump at shallower level should be constructed to improve conditions so that the final sump can be safely constructed to the proper depth. 2) Water flowing to the sump will carry fines, which are abrasive and damaging to pumping equipment. The approaches to the sump should be arranged to remove much of the fines by sedimentation or filtration. 3) The size of the sump should be substantially larger than that necessary to physically accommodate the pumps. Ample size allows for a reduction in water velocity so that fines settle out, and the space provides storage for the sediment between cleanings. 4) The sump should be arranged for convenient servicing of the pumps and so that accumulated sediment can be readily removed.

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT

Figure 7 Submersible pump for dewatering an excavation.

1.1.1 Deep-Well Systems Deep wells can be used to dewater pervious sand, rock formations or to relieve artesian pressure beneath an excavation. They are suited for dewatering large excavations which require high rates of pumping. Deep wells also can be used for dewatering deep excavations such as dams, tunnels, locks, powerhouses, and shafts. Turbine or submersible pumps are used to dewater by pumping from deep wells for deep excavations. The advantages of deep wells are that they can be installed around the periphery of an excavation and thus leave the construction area unencumbered by dewatering equipment.. Besides, the excavation can be predrained for its full depth.

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT

Figure 8 Deep well system for dewatering an excavation in sand.

Deep wells for dewatering have a screen with a diameter of 6 to 24 inches with lengths up to 300 feet. They are generally installed with a filter around the screen to prevent the infiltration of foundation materials into the well and to improve the yield of the well. In order to dewater small, deep excavations for tunnels, shafts, or caissons sunk, deep wells may be used by adding a vacuum system to the well screen and filter. The addition of a vacuum will create a vacuum within the surrounding soil. This will prevent or minimize seepage from perched water into the excavation. Installations of this type, require adequate vacuum capacity to ensure efficient operations of the system.

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT

Figure 9 Deep wells with auxiliary vacuum system for dewatering a shaft in stratified materials.

One of the method to install deep wells is by the reverse-rotary drilling method. A casing is being drive and jetted into the ground and a bailer or jet or a bucket auger is used to clean it. In the reverse-rotary method, the hole for the well is made by rotary drilling. Soil from the drilling is removed from the hole by the flow of water circulating from the ground surface down the hole and back up the (hollow) drill stem from the bit. AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT Construction dewatering in fine soils can be difficult, because well yields are often low and it is usually necessary to apply a vacuum to assist drainage. Ejector systems are therefore ideally suited to groundwater control in fine soils and have been used increasingly in the UK in recent years (W. Powrie et al., 1994). A centrifugal or jet-eductor pump pumps the flow from the drill stem into a sump pit to circulate the drill water. The soil particles settle out in the sump pit and the muddy water flows back into the drill hole through a ditch cut from the sump to the hole. The sides of the drill hole are stabilized by seepage forces acting against a thin film of fine grained soil that forms on the wall of the hole. Some silt soil may need to be added to the drilling water to attain the desired degree of muddiness if the hole is drilled in clean sands. The sump pit should be large enough to allow the sand to settle out but small enough so that the silt is kept in suspension. In order to install a straight and plumb screen and riser, the holes for deep wells should be vertical and deeper than the well screen and riser. The additional depth of the hole should be provided to put wasting filter material in the tremie pipe if used. The filter is tremied in after the screen is in place. The tremie pipe should be 4 to 5 inches in diameter, be perforated with slots 1/16 to 3/32 inch wide and about 6 inches long, and have flush screw joints. The slots will allow the filter material to become saturated, thereby breaking the surface tension and “bulking” of the filter in the tremie. The tremie pipe should be filled with filter material after it has been lowered to the bottom of the hole. It then slowly raised, keeping it full of filter material at all times, until the filter material is 5 to 10 feet above the top of the screen. After the filter is placed, the well should be developed to obtain the maximum yield and efficiency of the well. The purpose of the development is to remove any film of silt from the walls of the drilled hole and to develop the filter immediately adjacent to the screen to permit an easy flow of water into the well. Development of a well should be accomplished as soon after the hole has been drilled so that the efficiency assumed in well design will maintain the same. A well may be developed by surge pumping or surging it with a loosely fitting surge block diameter 1 to 2 inches smaller than the AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT inside diameter of the well screen and should be slightly flexible. The surge block is raised and lowered through the well screen at a speed of about 2 feet per second. The amount of material deposited in the bottom of the well should be determined after each cycle (about 15 trips per cycle) and surging should continue until the accumulation of material pulled through the well screen in any one cycle becomes less than about 0.2 foot deep. If the accumulation of material in the bottom of the screen becomes more than 1 to 2 feet at any time during surging, it should be bailed clean and recleaned after surging is completed. The well should be pumped at approximately the design discharge from 30 minutes to several hours to clear it of muddy water and sand after it has been developed. Measurements of well discharge and drawdown may be used to determine the efficiency and degree of development of the well. The performance of the well filter may be evaluated by measuring the accumulation of sand in the bottom of the well and in the discharge. An airtight seal around the well riser pipe from the ground surface down for a distance of 10 to 50 feet is required in which a vacuum is to be maintained. The seal may be made with compacted clay, nonshrinking grout or concrete, bentonitic mud, or a short length of surface casing capped at the top. The seal is impossible to attain a sufficient vacuum in the system if improper or careless placement. This will cause the dewatering system failing to operate as designed. Besides, the top of the well must also be sealed airtight. After the wells are developed and satisfactorily tested by pumping, the pumps, power units, and discharge piping may be installed.

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT 1.1.2 Wellpoint Systems Another commonly used dewatering method are wellpoint systems as they are applicable to a wide range of excavations and groundwater conditions. Wellpoint systems are installed by first laying the header at the location and elevation called for by the plans. After the header pipe is laid, the stopcock portion of the swing connection should be connected to the header on the spacing called for by the design, and all fittings and plugs in the header made airtight using a pipe joint compound to prevent leakage. Installation of the wellpoints generally follows layout of the header pipe.

Figure 10 Plan of a typical wellpoint system.

Figure 11 A typical wellpoint system at site

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT A wellpoint pump uses a combined vacuum and a centrifugal pump connected to the header to produce a vacuum in the system and to pump out the water that drains to the wellpoints. When additional air handling capacity is required, one or more supplementary vacuum pumps may be added to the main pumps. Generally, wellpoints connected to a header at a common elevation capable of lowering the groundwater table about 15 feet. To lower the groundwater more than 15 feet, A wellpoint system is usually the most practical method for dewatering at accessible site, the excavation and waterbearing strata to be drained are not too deep. It may be more practical to use eductor-type wellpoints or deep wells with turbine or submersible pumps and wellpoints as a supplementary method of dewatering for large or deep excavations where the depth of excavation is more than 30 or 40 feet or where artesian pressure in a deep aquifer must be reduced. Wellpoints are more suitable than deep wells where the submergence available for the well screens is small and close spacing is required to intercept seepage. ()

Figure 12 Use of wellpoints where submergence is small

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT

Figure 13 Drainage of an open deep cut by means of a multistage wellpoint system.

Vacuum wellpoint systems are installed in the same manner as ordinary wellpoint systems. It uses a jet casing and filter, except the upper 5 feet of the riser is sealed airtight to maintain the vacuum in the filter. A vacuum wellpoint system is used to stabilized silts and sandy silts (D10 < 0.05 milimetre) with a low coefficient of permeability (k = 0.1 x 10-4 to 10 x 10-4 centimetres per second) where it cannot be drained successfully by gravity methods. It is a conventional well system. The partial vacuum is maintained in the sand filter around the wellpoint and riser pipe. This vacuum will increase the hydraulic gradient producing flow to the wellpoints and will improve drainage and stabilization of the surrounding soil. It may be necessary to provide additional vacuum pumps if there is much air loss to ensure maintaining the maximum vacuum in the filter column. The required capacity of the water pump is small.

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT

Figure 14 Vacuum wellpoint system

Wellpoint pumps, are used to provide the vacuum and to remove water flowing to the system. The suction intake of the pump should be set level with the header pipe to obtain the maximum possible vacuum. Wellpoint pumps should be protected from the weather by a shelter and from surface water or sloughing slopes by ditches and dikes. The discharge pipe should be watertight and supported independently of the pump.

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT

Figure 15 A wellpoint pump used in Sunway Pyramid II project.

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT Self-jetting wellpoints are installed by jetting into the ground. Water is forced out the tip of the wellpoint under high pressure. It can be installed in medium and fine sand. The water pressures is about 50 pounds per square inch. To carry out the heavier particles in the coarse sand and gravel, more water and higher water pressures (about 125 pounds per square inch) are required. A hydrant or a jetting pump of appropriate size for the pressures and quantities of jetting water required can be used. The jetting hose which is attached to the wellpoint riser is picked up either by a crane or hand and held in a vertical position as the jet water is turned on. The diameter is usually 2 to 3 inches.

Figure 16 Self-jetting wellpoint.

The wellpoint is allowed to sink and raised slowly in the ground. This is to ensure that all fine sand and dirt are washed out of the hole. Jet water should be returned to the surface otherwise the point may “freeze” before it AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT reaches grade. Therefore, care should be taken. If the return of jet water disappears, the point should be quickly raised until circulation is restored and then slowly relowered. It may be necessary to supplement the jet water with a separate air supply at about 125 pounds per square inch to lift the gravel to the surface in gravelly soils. Filter sand is required around the wellpoint to increase its efficiency and prevent infiltration of foundation soils. In order to form the hole for the wellpoint and filter, the wellpoints should be installed using a hole puncher and a jet casing. The two halves of a swing connection, if used, should be lined up for easy connection when the jet water is turned off and the jetting hose disconnected. Generally, a wellpoint should be installed in a hole formed by jetting down a 10- to 12- inch heavy steel casing at where it is to be installed with a filter. The casing may be fitted with a removable cap at the top. Air and water may be introduced through and a return of air and water along the outside of the casing when the casing is jetted into the ground. Jetting pressures of 125 pounds per square inch are commonly used. The casing may have to be raised and dropped with a crane to chop through and penetrate to the required depth when resistant strata are encountered. Most of the return water from a ‘hole puncher” rises inside the casing causing less disturbance of the adjacent foundation soils. The jet is allowed to run until the casing is flushed clean with clear water after the casing is installed to a depth of 1 to 3 feet greater than the length of the assembled wellpoint. Another type of dewatering system is the jet-eductor wellpoint system. Jet-eductor wellpoints are usually installed using a hole puncher and surrounding the wellpoint and riser pipe with filter sand. It is installed in the same manner as conventional wellpoints with a filter as required by the foundation soils. It consists of an eductor installed in a small diameter well or a wellpoint screen attached to a jet-eductor installed at the end of double riser pipes. A pressure pipe is used to supply the jet-eductor and another pipe for the discharge from the eductor pump. Eductor wellpoints may also be pumped with a pressure pipe within a larger return pipe. The advantage of this type of system compare to conventional wellpoint system is able to lower AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT the water table as much as 100 feet from the top of the excavation. Jeteductor wellpoint systems are most advantageously used to dewater deep excavations where the volume of water to be pumped is relatively small because of the low permeability of the aquifer.

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT

Figure 17 Jet-eductor wellpoint system for dewatering a shaft.

1.1.3 Vertical Sand Drains Vertical drains accelerate the consolidation process by reducing the drainage path and by reorienting the direction of flow into a more permeable (horizontal) direction. The earliest version of vertical drains was sand drains which consisted of a borehole filled with sand (Basu, D. et al., 2000). The water table in the upper stratum can be lowered by means of sand drains when a stratified semipervious stratum with a low vertical permeability overlies a pervious stratum and the groundwater table has to be lowered in both strata. Sand drains will intercept seepage in the upper stratum and conduct it into the lower when properly designed and installed Sand drains consist of a column of pervious sand placed in a cased hole. The cased hole is either driven or drilled through the soil, with the casing subsequently removed. Installation of a slotted 1% or 2 inch pipe inside the sand drain can significantly increase the capacity of sand drains. This is to conduct the water down to the more pervious stratum. The installation of mandrels into the soil using a drain stitcher.

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT

Figure 18 Sand drains for dewatering a slope.

Figure 19 Installation of mandrels using drain stitcher.

1.1.4 Electro-Osmosis When soils such as silts, clayey silts, and clayey silty sands cannot be dewatered by pumping from wellpoints or wells, it can be drained by wells or wellpoints combined with a flow of direct electric current through the soil toward the wells. Creation of a hydraulic gradient by pumping from the wells or wellpoints with the passage of direct electrical current through the soil causes the water contained in the soil voids to migrate from the positive electrode (anode) to the negative electrode (cathode). The water that migrates to the cathode can be removed by either vacuum or eductor AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT pumping by making the cathode a wellpoint. The installation of electroosmosis on a dewatering site.

Figure 20 Electro-osmosis wellpoint system for stabilizing an excavation slope.

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT

Figure 21 Installation of electro-osmosis in a dewatering site.

1.1.5 Cutoffs In order to stop or minimize seepage into an excavation, cutoff curtains can be used. Cutoff can be installed down to an impervious formation. There are many methods to construct cutoff curtains. Such cutoffs can be constructed by driving steel sheet piling, grouting existing soil with cement or chemical grout, excavating by means of a slurry trench and backfilling with a plastic mix of bentonite and soil, installing a concrete wall, possibly consisting of overlapping shafts, or freezing. However, groundwater within the area enclosed by a cutoff curtain, or leakage through or under such a curtain will have to be pumped out with a well or wellpoint system.

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT

Figure 22 Grout curtain or cutoff trench around an excavation.

A cutoff around an excavation in coarse sand and gravel or porous rock can be created by injecting cement or chemical grout into the voids of the soil. The voids in the rock or soil must be large enough to accept the grout for grouting to be effective. Besides, the holes must be close enough together so that a continuous grout curtain is obtained. Pervious soil or rock formations are grouted from the top of the formation downward through pipes installed in the soil or rock. The hole for the grout pipe is first cored or drilled down to the first depth to be grouted, the grout pipe and packer set, and the first zone grouted. The hole is redrilled after the grout is set for the second stage of grouting. This process is repeated until the entire depth of the formation has been grouted. The type of grout that can be used varies. It depends on the size of voids in the sand and gravel or rock to be grouted. The commonly used grouts are portland cement and water, cement, bentonite, an admixture to reduce surface tension, and water, silica gels, or a commercial product. Grouting of fine or medium sand is not very effective for blocking seepage. Mixing tanks and pump equipment for pressure injection of cement or chemical grouts vary depending upon the materials being handled. Ingredients for a grout mix are loaded into a mixing tank equipped with an agitator. Then, grout are pumped to a storage tank which also equipped with an agitator. Pumps for grouting with cement are generally duplex, positive AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT displacement, reciprocating pumps similar to slush pumps used in oil fields. Cement grouts are highly abrasive. So the cylinder liners and valves should be of case-hardened steel. Chemical grouts can be pumped with any type of pump that produces a satisfactory pressure because of their low viscosity and nonabrasive nature. There are two types of distribution system for grouting which are the single-line system and the recirculating system. The line must occasionally be flushed to ensure that the grout being pumped into the formation is homogeneous and has the correct viscosity. The grout in a single-line system is flushed through a blowoff valve onto the ground surface and wasted. A recirculating system has a return line to the grout storage tank so that the grout is constantly being circulated through the supply line, with a tap off to the injection pipe where desired. Slurry wall is one of cutoff method to prevent or minimize seepage into an excavation. It can be formed by digging a narrow trench around the area to be excavated and backfilling it with an impervious soil. Slurry cutoff trenches can be dug with a trenching machine, backhoe, dragline, or a clam bucket, typically 2 to 5 feet wide. Such a trench can be constructed in almost any soil. It can be constructed either above or below the water table. Generally, the trench is backfilled with a well-graded clayey sand gravel mixed with bentonite slurry. Thick bentonitic slurry as shown in figure 2.23 is used to stabilize the walls of the trench until the trench can be backfilled. It is best mixed at a central plant and delivered to the trench in trucks or pumped from slurry ponds. () Cleaning of the slurry is commenced in order to remove gravelly or sandy soil particles that have collected in the slurry, especially near the bottom of the trench. Fair cleanup can be obtained using a clamshell bucket. More thorough cleaning can be obtained by airlifting the slurry to the surface for circulation through desanding units. Cleaning of the slurry makes it less viscous and ensures that the slurry will be displaced by the soilbentonite backfill. After cleaning the “in-trench” slurry, the trench is generally backfilled with a well-graded mix of sand-clay-gravel and bentonite slurry with a slump of about 4 to 6 inches. The backfill material and slurry may be mixed either AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT along and adjacent to the trench or in a central mixing plant and delivered to the trench in trucks.

Figure 23 Detail of slurry trench.

The other cutoff method is by constructing concrete walls. Concrete cutoff walls can be constructed by overlapping cylinders and also as continuous walls excavated and concreted in sections. These walls can be reinforced and are sometimes incorporated as a permanent part of a structure. Steel sheet piling is a very effective method to reduce seepage. The effectiveness of steel sheet piling depends on the perviousness of the soil, the tightness of the interlocks and the length of the seepage path. Some seepage through the interlocks should be expected. Precautions should be taken in handling and driving sheet piling to ensure that the interlocks are tight for the full depth of the piling and that all of the sheets are driven into the underlying impermeable stratum at all locations along the sheet pile cutoff. Driving steel sheet piling around the structure, excavate the soil underwater, AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT and then tremie in a concrete seal is desirable when constructing small structures in open water. The concrete tremie seal must withstand uplift pressures. In restricted areas, it may be necessary to use a combination of sheeting and bracing with wells or wellpoints. Wells or wellpoints can be installed inside or outside of the sheeting. Sheet piling is not very effective in blocking seepage where boulders or other hard obstructions may be encountered because of driving out of interlock. The sheet piling used in Sunway Pyramid II project in blocking seepage and stabilizing the slope.

Figure 24 Steel sheeting to top of rock. A boulder above the rock can aggravate the situation.

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT

Figure 25 Steel sheeting in Sunway Pyramid II project to control seepage and stabilizing the slope.

Seepage into an excavation or shaft can be prevented by freezing the surrounding soil. However, freezing is expensive and requires expert design, installation, and operation. If the soil around the excavation is not completely frozen, seepage can cause rapid enlargement of a fault (unfrozen zone) with consequent serious trouble, which is difficult to remedy. Freezing the soil around a shaft or tunnel requires the installation of pipes into the soil and circulating chilled brine through them. These pipes generally consist of a 2inch inflow pipe placed in a 6-inch closed-end “freezing” pipe installed in the ground by any convenient drilling means. Two headers are required for a freezing installation. One is to carry chilled brine from the refrigeration plant and the other to carry the return flow of refrigerant. The refrigeration plant should be of adequate capacity and should include standby or auxiliary equipment to maintain a continuous operation. An excavation supported by freeze wall, a typical scenario of freeze pipe spacing, plan and section view

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT of circular excavation by a freeze wall and a deep excavation supported by freeze wall.

Figure 26 Excavation supported by a gravity freezewall.

Figure 27 Typical scenario of freeze pipe spacing and indication which can be connected to a portable refrigeration plant, or liquid nitrogen tanker.

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT

Figure 28 Circular excavation supported by a freezewall. (a) Plan. (b) Section.

Figure 29 A deep excavation supported by freeze wall.

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT 1.2

CONSTRUCTION PROCEDURES

1.2.1 SPECIFICATIONS Before any earthworks are commenced, areas of cut and fill should be clearly defined. Where necessary, sufficient fencing or barriers should be provided around trees or other features to be protected. All site activities including clearing, storage, cutting and filling should be kept away from the root zone of trees (best defined as the extent of the canopy). Adequate provision should also be made for the control of erosion, surface water run-off and siltation. () The normal necessary specifications are to be prepared to control the earthwork construction as follows: i.

All rubbish, vegetation and debris should be removed from earthworks areas prior to the commencement of topsoil stripping. Areas on which fill is to be placed, or from which cut is to be removed, and haul roads should be stripped of all topsoil and such unsuitable soft or organic material as determined by the soils engineer. Special care should be taken to ensure that organic materials and areas of old uncompacted filling are not overlooked through being overlaid by other soils.

ii. Stripping should be carried out as a specific operation with areas

being stripped in large enough increments to ensure that there is an adequate margin of stripped ground beyond any current cutting or filling operation. Particular care should be taken to ensure that overspill is not left in an uncompacted state anywhere on the site, when constructing temporary haul roads. iii. All stripped material should be deposited in temporary stockpiles or

permanent dumps, in locations where there is no possibility of the material being unintentionally covered by, or incorporated into, structural fills. iv. Where a fill abuts against sloping ground, benches should be cut into

the ground to prevent the development of a continuous surface of low shear strength. AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT v. Previous drains or similar subsoil seepage control systems should be installed (as necessary) to lead seepage away from all springs and potential areas of ground water under or adjacent to fills in order to a) Prevent saturation of the fill before construction of the fill is complete; b) Prevent

internal

ground

water

pressures

which

would

detrimentally reduce shear strengths. vi. Subsoil drains should discharge via flexible jointed pipes to an outlet

approved by the Engineer, preferably a stable watercourse or a piped storm-water system. The position of all subsoil drains should be recorded on the "as-built' plan. vii. The stripped ground surface should be prepared and then inspected

by the soils engineer before any fill is placed thereon.

1.1.1 FILL CONSTRUCTION The quality of fill material and required control testing should be determined and specified before the placing of fill commences. Fill should be placed in a systematic and uniform manner with near horizontal layers of uniform thickness (less than 225mm) of material being deposited and compacted progressively across the fill area. Before any loose layer of fill is compacted, the water content should be suitable for the compaction required and as uniform as possible. Any compacted layer which has deteriorated after an interruption in the earthmoving operation, should be rectified before further material is placed over it. Fill batter faces should be compacted as a separate operation, or alternatively, overfilled and cut back.

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT Where testing shows the compaction achieved in the field to be below the specified minimum, all material represented by the test should be further compacted or removed as necessary. Temporary Drainage and Erosion Control During the construction period, measures should be taken to prevent excessive water-logging of surface materials yet to be excavated or compacted or both, and to prevent fill material from being eroded and redeposited at lower levels. Such measures should include: i.

The surfaces of fills and cuts should be graded to prevent ponding.

ii. Temporary drains should be constructed at the toe of steep slopes to

intercept surface run-off and to lead drainage away to a suitable watercourse or pipe storm-water system. iii. Surface water should be prevented from discharging over batter faces

by drains formed to intercept surface run-off and discharge via stable channels or pipes, preferably into stable watercourses or piped stormwater systems. iv. The upper surface of fills should be compacted with rubber tyres or

smooth wheeled plant when rain is impending, or when the site is to be left unattended. v. The completed battered surfaces of fills should be compacted with

sheepsfoot or similar non-smooth compaction plant to reduce runoff velocities. vi. Silt traps and retention ponds should be constructed where they are

feasible and necessary. These should be cleaned out, as required to ensure that adequate silt storage is maintained. vii. Temporary barriers or fences choked with brush, sacking or the

like,should be used to reduce flow velocities and to trap silt. viii.Section of natural ground should be left unstripped to act as grass (or

other vegetation) filters for run-off from adjacent areas. ix. All

earthwork

areas

should

be

retopsoiled

and

grassed

or

hydroseeded as soon as possible after completion of the earthworks and drainage works. AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT

1.1.1 INSPECTION AND QUALITY CONTROL The soils engineer should provide an adequate level of inspection and testing, in order to enable him to evaluate properly the general quality of the finished work, and to enable him to furnish a report as to the compliance of the work with the specifications. This is not to be construed as a guarantee or warranty but rather a record of his professional opinion based on reasonable care. Visual inspection should be made by the soils engineer or a competent inspector acting on his behalf at the following times: i.

After any part of the existing ground has been finally stripped and prepared and before the placing of any fill on that ground.

ii. After any drain has been installed and before the drain is covered by

fill. iii. At such other times as the soils engineer considers necessary to enable him to assess the general standard of earthworks and to reasonably satisfy himself that; a) Fill is not placed over soft or organic material; b) All areas of existing ground showing seepage or potential seepage emission have relief drains provided; c) Compaction operations are systematic, the water content of fill

material appears on visual inspection to be suitable and the degree of compaction appears to be consistently satisfactory. During the construction of earth fills some or the entire following quantitative control test should be made on the fill material: i. Tests to determine whether the water content is suitable; ii. In situ density tests to determine whether the degree of compaction is up to the specified minimum; iii. Where appropriate tests to determine the maximum dry density for the

soil tested in each in situ field density test; AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT iv. Such other tests as may be specified by the soils engineer for control

testing of fills or particular soil types, providing that the soil property tested shall be related to in situ density or water content of the fill by a laboratory investigation. Such tests include shear strength tests, cone penetrometer tests, and other Proctor needle tests. Once the filling work is progressing as a steady operation with uniform construction methods, and provided that:i. Adequate construction effort is being maintained; ii. Adequate visual inspection is being maintained; iii. The specification requirements are being met. Then minimum frequency of control testing shall generally be one in site density test (or equivalent) for each 2000m3 or 1.0m lift of fill. Testing shall be more frequent than specified above, under any of the following circumstances: i. During the first 4000m3 of filling carried out on the project. ii. On the final layer of not less than 1.0m depth. iii. When soil type or conditions are variable. iv. When the soils engineer or his inspector is in any doubt about the adequacy of construction methods or soil properties. v. When a decision to reject work based on the judgement of the soils engineer or his inspector is disputed, and; vi. When relatively small quantities of fill are concentrated in localized areas or placed discontinuously over a long period of time. The locations of tests should be decided by the soils engineer or his inspector, who should select them so as to test material likely to be furthest from the specified quality. In addition, a proportion of tests should be taken at random locations to check the average standard being obtained.

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT All field and laboratory test data should be recorded in a systematic manner that will allow the results to be identified and allow the calculations to be checked at a later date, if necessary. All control test results should have recorded the time, date, location and elevation. Test results relating to sections of fill that have been subsequently removed or reworked and recompacted should be noted accordingly.

1.1

CASE STUDY

1.1.1 SLOPE STABILIZATION/ SLOPE PROTECTION For these conditions, stabilization may be achieved by retaining wall, soil nails, anchors or reticulated mini-piles. Other methods of the stabilization include drainage and embedded gravity, gabion or crib walls. An excellent account of the various methods available for slope stabilization. Types of method to be use for slope protection is:1.1.1.1 CONTIGUOUS SPUN PILE A certain exposed slope to be contiguous spun pile immediately to control soil erosion during excavation works. The CSP for slope protection to be use after 6 meters excavation from original level, the original level is 21 meter.

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT

Figure 30 CSP at the SOHO Project.

The method of excavation work step by step, where the contractor made a few of the slope. This method use because it more effective for site area to control soil erosion. And then after 6 meter excavated and disposed of the soil, the contractors use the contiguous spun pile for slope protection. The contiguous spun pile buried into the soil, the figure show how the contiguous spun pile to be buried at the third level.

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT

Figure 31 Re-bar of CSP.

And then the reinforcement bar and concrete work started after all contiguous spun pile buried into the soil. The gaps between the CSP will closed using the mortar because to ensure the erosion does not happen and disturb the working area soon. So, the contractor ensures the retaining wall strong and safety following the standard in the contract.

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT

Using the grout cement

Figure 32 CSP side use Mortar.

The figure shows the using use to fill the gaps between the contiguous spun piles. It’s important to control erosion and for slope protection.

Figure 33 Layout of CSP.

1.1.1.2 CANVAS METHOD The contractor also use the canvas method for slope protection, its mean that the rain water does not give effected for the soil properties and the strength AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT of the soil. Its can prevent from the erosion, and also as an additional method for slope protection. The canvas lay at each slope; the reason is to ensure the rain water only flow on the canvas. The figure below show how the canvas lay by the slope.

Figure 34 Canvas Method

Figure 35 Canvas to the Slope

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT 1.1.1.3 RETAINING WALL Third method for slope protection is retaining wall. The area of retaining wall constructed is beside the railway KTM, to separate between disposal area and railway KTM. This method as a slope protection to ensure the erosion does not happen. The construction for retaining wall is important and following the standard specification from CIDB. The retaining wall is use the precast and in-situ method of construction where the materials make at the factory and then bring to the site and fixed. After that, the construction continues by the in-situ method until fixed level. These figures show the construction of retaining wall using the precast and in-situ method.

Figure 36 Retaining Wall.

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT

1.1.2 DEWATERING SYSTEM

1.1.2.1 USE THE SUMP PUMPING SYSTEM The rain water will damage the soil properties, so the strength of the soil will decrease and settlement will be happen. To protect the strength of the soil, the water must be flow out from the site area. In this case, the pumping system is use to flow out the water from the construction site. Where the water in the site will remove by the water pump and flowing into the temporary drainage. The temporary drainage located outside of site area where it located beside the railway KTM. The method how the water removed by using the pumping system:a) The water at the foundation will remove by the water pump.

Figure 37 Water Pump.

b) The water flowing through the pipe to temporary sump.

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT

Figure 38 Water Flow.

c) And then, from the temporary hole the water will flow through the circle culvert with diameter 2 feet.

Figure 39 Ponding at site.

d) The water flow to the temporary drainage before flow to the large drainage.

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT

Figure 40 Temporary drainage.

Using the pumping system is effective dewatering system in the construction site because it easy to set up the system. During earthwork, this system helps to remove the water in the site. The water pump had maintained to make sure the project not delay because of the water. Its also depend on the size of project and condition of the site. The other method of dewatering system is well point system, sump pump system, deep-well system, vertical sand drain and electro-osmosis.

1.1.1.1 TEMPORARY DRAINAGE. The temporary drainage located near the railway (KTM) where at the out off construction site. The perimeter of the drainage is half construction site; it’s around 500 m until main drainage. During the construction period, measures had take to prevent excessive water logging of surface materials yet to be excavated or compacted or both, and to prevent fill material from being eroded and redeposited at lower levels. Temporary drains should be constructed at the toe of steep slopes to intercept surface run-off and to lead drainage away to a stable watercourse. For monitoring, ensure that the Developer/ Contractor maintain the temporary drain regularly (each one week). It AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT important to make sure drainage will flowing the water smooth such as dispose any material and rubbish inside. All earthwork areas should be retopsoiled and grassed or hydroseeded as soon aspossible after completion of the earthworks and drainage works.

. Figure 41 Temporary drainage.

1.1.2 TRAFFIC CONTROL Traffic control is important to make sure the site access smooth and must logistic. The machineries can move to other position using the access road. For examples, the tipper lorry can bring the soil from excavation area to the disposal area without obstructions. This site area provided two ways for access road is access and exit road. In site area has two ways (to excavation area and to the disposal area). So, any machinery can move clearly to bring the soil or other material and also make earthwork smoothly.

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT

Figure 42 Access route.

The figures show the access road for the lorry or vehicles access the site area and exit road. It effective traffic control to make sure no obstruction during move the soil and other material.

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT

Figure 43 Barier gate.

The access road and exit road is logistic, that means easy to going and goes out after finish work and also easy to see by the people and parties involve also.

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT

Figure 44 Wash Pit

Figure 45 Housekeeping.

So, the contractor must make sure the access road in good condition always. That means, the access road must clean always and remove any material have on the road such as soil and other materials. The figure shows two worker cleaning the wash pit area and access road.

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT 1.1.3 SAFETY CONTROL The safety control is very important to make sure no accident will be happen and also trespassers. The contractor had provided a few of the safety control in this site area such as hoarding, wash pit or wash through, barrier and signboard. 1.1.3.1 HOARDING Hoarding fixed at surrounding area of construction site, the high for hoarding is 3 meters. It important and must provide at any construction site following the CIDB standard because its can protect from the trespassers, illegal and as the site boundary. For this site, hoarding also likes a separator between construction site area and railway KTM.

Figure 46 Hoarding.

1.1.3.2 WASH PIT / WASH THROUGH Wash pit located at the exit road behind the public road. Areas of wash pit makes from steel, concrete and have the hole for trap the water. There are using the manual operation where the workers used the water pipe to clean the machineries or vehicles. The main function for wash pit is to ensure that vehicles leaving the site are clean and does not dirty the public road.

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT

Figure 47 Wash pit.

1.1.3.3 GATE BARRIER The barrier will be open at the working hours and will be close after working hour. Usually it’s open from 8.00 am until 5.00 pm., using the manual system.

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT

Figure 48 Gate Barier.

1.1.3.4 PROJECT SIGNBOARD The signboard is reference or announcement for peoples about the project. All construction sites must have the signboard; it usually located at front site area or at some location where people can see. The information at the project signboard is title of the project, duration of the project and also the parties involve in the project.

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT

Figure 49 Project signage.

1.1.3.5 SAFETY EQUIPMENT Contractor has to make sure their workers should wearing the safety equipments such as safety boot safety helmet and etc... The equipment is very important especially for workers and parties involve also when enter the construction site. Contractor should provide precautions of unexpected events. Contractor should provide the good working space for their workers to work in a good condition. The good working area can increase the workers productivity and indirectly provide the good quality of work. 1.1.4 SETTLEMENT CONTROL Many type of how to control the settlement at the site, such as leveling method or surface leveling station. Such stations should be positioned as soon as an area of fill has been brought up to finished level. This will mean that the maximum time will be available for settlement readings, noting that, AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT for obvious reasons, none can be made using this form of equipment during fill placement itself. Because of the heavy plant frequenting construction sites, a surfacing leveling station should be robust.

Figure 50 Point of sttlement control.

Figure 51 Settlement Marker Records.

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT

The settlement Marker Record are needed during the measured the level that had been decided to control. If the level are falling down, the settlement are occur and must create a solution to settle the problems.

1.1.5 DOCUMENTATION CONTROL 1.1.5.1 STATEMENT OF QUALITY POLICY AND AUTHORITY

It is

SENDI BANGGA DEVELOPMENT SDN. BHD. (SBD) objective to

supply client with materials and services to the highest possible quality level consistent with the requirements of our Client job specification. SBD recognize the importance of maintaining a high quality system in order to assure the safety to the general public. The Quality Assurance Plan defines philosophy, policies and applicability of our Quality Assurance Program and describes SBD’s organization, procurement and construction. The quality control specifications and procedures which are referred to in this Quality Assurance Plan provide instructions for the implementation of the Quality Assurance Program. Compliance to this Quality Assurance Plan and referenced specifications and procedures is mandatory and shall consistently applied within SBD.

1.1.5.2 QUALITY CONTROL PROCEDURE

PURPOSE All documents and data are reviewed, approved and controlled to ensure that. The correct revision of appropriate documents are available at the point of work. Obsolete documents are promptly removed from all points of issue or use.

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT

APPLICATION The following types of documents shall be controlled : 1. Project Quality Procedures / Method Statement 2. Quality Assurance Quality Control 3. Specifications / Standards / Method Statement 4. Operation documents including drawings, design calculation etc.

1.1.1.1 PROCEDURE

Control of Document Issue 1. All controlled documents shall, be reviewed and approved for

adequacy by authorized person prior to issue. They shall have their issue number, date and signature or initials of authorized person entered on them. 2. All documents shall be controlled by the department that issues the

document and shall be protected against damage and misuse. 3. It shall be the responsibility of the manager of the department that

issue the documents carry the necessary authorizing signatures and dates of issue and distributed to the points of use throughout the company.

Control of Document Use 1. It shall be the responsibility of the supervisor or manager of each work

area to ensure that the correct documents and correct revisions of such documents are the ones in use in that area at all times.

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT 2. At no time shall the supervisor or manager permit wrongful marking,

use or other action would be defeat the intent of document control. 3. At all times the documents shall be readily available to Client needing

access to their contents.

Control of Document Change 1. Each change in a controlled document shall be initiated / signed and

dated by the authorized person making change. 2. The document carrying changes shall be subject permanent revision

and reissue at the earliest practicable time. 3. Documents shall be directly identified with their revision level using

consecutive numbering. 4. Where practicable, the nature of the change shall be identified in

document by placing description of the change in Revision History Sheet. Only Cover page and Revision History Sheet shall be transmitted to the concerned personnel using transmittal form. 5. Changes to the documents shall be reviewed and approved by the

same department that performed the original review and approval unless specifically designated otherwise. 6. The review and reissue of the documents shall be reviewed by and

shall receive approval of the department manager. . 7. It shall be the responsibility of the managers and supervisors who are

responsible for performing work affected by the reissued or revised documents to remove and destroy all obsolete documents from all points of use upon receiving the revised or reissued documents. 8. Any obsolete documents retained for legal and/or knowledge

preservation purposes shall be stamped "Void - For Information Only" and kept separate from current documents to preclude unintended use. 9. It shall be the responsibility of the department that issue, reissue or

revise the documents: a) to distribute documents to their destinations AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT b) to maintain distribution / master list 1. To notify immediately the Quality Assurance Department and forward

copy of the document to the Quality Assurance Department. 2. Documents issued to personnel and outside company who need a

copy for information only shall be stamped "Uncontrolled".

RETENTION OF DOCUMENTATION 1. It shall be the responsibility of the supervisor or manager at each work

area to maintain and retain all documentation in accordance with legal and contractual requirements in retrievable and secure manner. 2. The company departments shall establish and maintain active files for

documents. The company departments shall retain all documents in active files for a minimum of two years and for as long as they deem necessary. 3. Unless, otherwise specified, all documents shall be removed from the

active files at the end of two years, indexed and stored in bonded area for a minimum five years and as long as necessary. While in storage all documents shall be protected from damage, loss and deterioration.

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT

1

CONCLUSION

For the conclusion, earthworks sites are amongst the most dangerous because of the variety of work being conducted and because of the speed at which some earth moving plant can operate. However, nothing can be built without some excavation and some transfer soil (or rock) from a one part of a side to another. That’s why; a proper planning and controlling of earthwork must have to any contractors. Danger includes: a) Failing objects from overhead plant and during demolition of existing structures b) Collapse of excavations during site clearance c) Damage to public utilities such as electricity and gas d) Blasting operations e) Heavy plant left at the edges of embankments or at part-completed retaining wall f) Heavy earth moving plant on haul roads and elsewhe g) Reversing plant all over the site

Staffs on site are particularly at risk from earth moving and compaction plant. They should be protected by warning lights and barriers. Haul surface should be well maintained because this improves breaking distance; watering during dry weather helps to reduce the nuisance. Plant should be restricted to travelling parallel t the dip of the slope, wherever possible.

AP 226 / 1C | JULY – NOVEMBER 2009

PLANNING AND CONTROLLING OF BLD EARTHWORK OPERATION MULTI-STOREY 410 PROJECT

1 BIBLIOGRAPHY Burch, D. (2007). Estimating Excavation. Carlsbad: Craftsman Book Company. Institution, B. S. (2003). Earthworks. Park Street, London: British Standard House. John, G. (2007). Earthworks. Waikato District Council. UTM. (2006). GROUNDWATER CONTROL IN THE CONSTRUCTION OF BUILDING. BA. Civil Engineering.