Piping Hydrostatic Test Procedure. Rev.0

March 11, 2017 | Author: PendriaAdipuspa | Category: N/A
Share Embed Donate


Short Description

procedure hydrostatic testing...

Description

CONSORTIUM OF :

PIPING HYDROSTATIC TESTING PROCEDURE Contractor Document Number

Rev.No.

Vendor‘s Document Number

LHD5&6-V-0-W1-PR-WS5-006R

0

15-112-PR-006-B

PROJECT

:

LOCATION

:

LAHENDONG UNIT 5&6 GEOTHERMAL POWER PROJECT TOMPASO, NORTH SULAWESI

EMPLOYER :

0 Rev

PT. PERTAMINA GEOTHERMAL ENERGY (PGE)

Issued For Review Description

15-Des-2015

PA

AR

NW

Date

Prepared

Checked

Approved

Consortium of Sumitomo Corporation and PT. REKAYASA INDUSTRI

PIPING HYDROSTATIC TESTING PROCEDURE FOR WATER TREATMENT PACKAGE ContractorDocument Number

Rev.No.

Vendor‘s Document Number

LHD5&6-V-0-W1-PR-WS5-006R

0

15-112-PR-006-B

REVISION HISTORICAL SHEET Revision

Date

0

15-Des-15

Description Issued For Review

Page 2 of 6 Consortium of Sumitomo Corporation and PT. REKAYASA INDUSTRI

PIPING HYDROSTATIC TESTING PROCEDURE FOR WATER TREATMENT PACKAGE ContractorDocument Number

Rev.No.

Vendor‘s Document Number

LHD5&6-V-0-W1-PR-WS5-006R

0

15-112-PR-006-B

CONTENTS

Section

Page

1.

SCOPE

4

2.

REFERENCE DOCUMENTS

4

3.

GENERAL REQUIREMENT

4

4.

TESTING PERFORMANCE

5

5.

PRESSURIZING CHART DURING TESTING

6

6.

REPAIRS

6

7.

RECORD

6

Page 3 of 6 Consortium of Sumitomo Corporation and PT. REKAYASA INDUSTRI

PIPING HYDROSTATIC TESTING PROCEDURE FOR WATER TREATMENT PACKAGE

1.

ContractorDocument Number

Rev.No.

Vendor‘s Document Number

LHD5&6-V-0-W1-PR-WS5-006R

0

15-112-PR-006-B

SCOPE This procedure covers for application of a hydrostatic testing of complete piping for Water Treatment Package belong to LAHENDONG UNIT 5&6 GEOTHERMAL POWER PROJECT.

2.

REFERENCES The current edition at the of contract award of the following codes, standards and specification form an integral part of this Specification :

3.



ASME B31.3

: Process piping.



ASME Sec. V

: Non Destructive Examination.



P&ID for Piping

GENERAL REQUIREMENT 3.1. Hydrostatic or pneumatic test shall be conduct on all pressure envelopes after: 3.1.1. All fabrication has been completed. 3.1.2. All NDE have been performed. 3.1.3. Vents shall be provided at the vessel in the position in which it is to be tested to purge possible air pockets while the vessel is filling. 3.1.4. Calibrated gauge having minimum range 1.5 to 4 of test pressure to be used. Two pressure gauge shall be provided for pressure test and one of them shall be located at the End pipe , in the testing position and one of them shall be for recording. 3.1.5. When pressure test done the surface shall be used the thermometer to measure metal temperature during examination. 3.1.6. Before the hydrostatic testing, Ensure internal of piping free from, welding slag and other foreign material. 3.1.7. Vacuum cleaning or other methods so the piping or component will be free of welding slag, flux, weld studs, loose scale, dirt, and debris. 3.1.8. All of Piping shall be hydrostatically tested as per drawing and the holding time pressure shall be maintained for minimum of 30 minutes. 3.1.9. Pressure recorder (pressure time recording device and temperature record) shall be provided with calibrated condition. Page 4 of 6 Consortium of Sumitomo Corporation and PT. REKAYASA INDUSTRI

PIPING HYDROSTATIC TESTING PROCEDURE FOR WATER TREATMENT PACKAGE

4.

ContractorDocument Number

Rev.No.

Vendor‘s Document Number

LHD5&6-V-0-W1-PR-WS5-006R

0

15-112-PR-006-B

TESTING PERFORMANCE 4.1. For test performance shall be provided the manifold for control pressure and filling water on each pressure gauge. 4.2. The manifold manufacture shall have minimum two vent valve for fill, pressure and evacuate to cover hydrostatic test. 4.3. When filling water process one of the manifold shall be connected to fill or pressure pump and make sure that vent valve condition shall be opened to evacuation the water. 4.4. Close the filling valve and disconnect the fill pump. 4.5. Observe the pressure gauge during pumping to inspection test pressure. 4.6. When the Inspection pressure has been reached close the fill valve and observe the pressure gauge to ensure that the inspection test pressure is maintained. If leakage occurs at contact gasket area, the nut and bolt shall be repaired until not found the leakage. 4.7. When the customer is satisfied during the holding time at the Inspection Pressure, step of pressurizing may be increased slowly to the test pressure. 4.8. If the test pressure has been reached, hold at this point and begin examination for leaks Take metal temperature reading to assure that the temperature has not changed significantly (has not exceed 48°C.) 4.9. The fabrication shall show no visible evidence of bulging, distortion and leakage. 4.10. Upon completion of piping hydrostatic testing piping shall be drained and thoroughly cleaned both outside and inside.

Page 5 of 6 Consortium of Sumitomo Corporation and PT. REKAYASA INDUSTRI

PIPING HYDROSTATIC TESTING PROCEDURE FOR WATER TREATMENT PACKAGE

5.

ContractorDocument Number

Rev.No.

Vendor‘s Document Number

LHD5&6-V-0-W1-PR-WS5-006R

0

15-112-PR-006-B

PRESSURIZING CHART DURING TESTING PRESSURE

TEST PRESSURE

30 MINUTES

10 MNT

DESIGN PRESSURE

10 MNT

TIME (MINUTES)

No.

6.

Description

Design Pressure

Test Pressure

1

Sand Filter Piping

4.5 bars (65.3 Psi)

6.75 bars (97.9 Psi)

2

Active Carbon Filter Piping

4.5 bars (65.3 Psi)

6.75 bars (97.9 Psi)

REPAIRS If leaks founds at the weld area during hydrostatic test, the areas of leakage shall be marked and repairs made using applicable and approved WPS. Re-testing shall be performed after the repair is accepted by Client.

7.

RECORDS 7.1. Hydrostatic Test Record shall be completed, reviewed and approved by Client. 7.2. Test pressure shall be recorded by automatic recording device.

Page 6 of 6 Consortium of Sumitomo Corporation and PT. REKAYASA INDUSTRI

LAHENDONG UNIT 5&6

PT. TRACON INDUSTRI

Date

:

Page

:

GEOTHERMAL POWER PROJECT DOC. NO 15-112-PR-006

HYDROSTATIC TESTING REPORT CUSTOMER

:

PT.REKAYASA INDUSTRI

REPORT NO

: 0

JOB NO

:

0

DESIGN PRESSURE

: 0

DWG NO

:

0

MAWP

: 0

DATE OF TEST

:

0

TEST PRESSURE

: 0

TEST MEDIUM

: WATER

( 15 mnt )

psi g

( 15 mnt )

( 30 mnt )

P2 P1

P3

P0

P4

0

1

2

3

4

SEQ NO.

TIME

0~1

09.00 ~ 19.10

5

6

7

8

9

10

PRESSURE ( bar )

P0

:

0 bar

P1

:

0 bar

P2

:

0 bar

P3

:

0 bar

P4

:

0 bar

TEST TEMPERATURE 27 °C

1~2

27 °C

2~3

27 °C

3~4

27 °C

4~5

27 °C

5~6

27 °C

6~7

27 °C

7~8

27 °C

8~9

27 °C

9 ~ 10

27 °C

WITNESSED BY

NO

COMPANY

1

PT.TRACON INDUSTRI

2

PT.REKAYASA INDUSTRI

DATE

REMARKS : Hydrotest result is acceptable, no leakage and no deformation.

NAME

SIGNATURE

View more...