The is a detail Analysis on a the subject matter...
Description
Calculation Cover Sheet Calc no
DOC NO.
File
DOC NO.
Project title
GN INFILL PROJECT
Phase/CTR
Client Calculation title Calculation objective
MAJOR OIL Pipeline Stability & Weight Coating Calculations
Deliverable Page 3
Elec file location
1. To determine the on-bottom stability of various GN Ubie phase 2 pipelines in the liquefied swampy terrain and in a typical water crossing 2. If required, calculate the thickness of concrete weight coating (of density 3040 Kg/m3) to give the pipeline a negative buoyancy factor of 1.3 3. Analysis based on the worst case scenario of "decommissioned case corroded pipe empty".
Calculation method The calculations are performed in accordance with the following general equation: Wpipe Wbuoy Where
>= 1.3
Wpipe = Total weight of pipe in air Wbuoy = Weight of water/mud displaced
Method of analysis is based on in-house spread sheet detailed in the section Method of Analysis Basic Data & Assumptions The following basic data and assumptions were applied:Safety Factor
= 1.3
- MAJOR OIL Requirement (Ref. 2)
Specific Gravity of swamp water
= 1.02
- Typical for Niger Delta (from Ref. 2)
Specific Gravity of river bed water/mud
= 1.442
- Assumed (from Ref. 2)
Density of concrete
= 3040 Kg/m3
Concrete coating of less than 25mm is practically not achivable. Therefore a minimum concrete thickness of 25mm will apply where required.
Further Assumptions g pp p and water swamp p or water 1)) Effect of marine g growth has not been considered as there is little evidence of significant marine g growth in the applicable swamp conditions. 2) Stability analysis and weight coating calculations for river crossings have been based solely on forces due to buoyancy of the river water. Forces (lift and drag) due to river current and tidal velocities have not been considered, because the pipelines will be trenched. 3) Calculated wall thickness less corrosion allowance has been used for the weight coating analysis.
References 1 2
GN Ubie Phase II Pipeline Mechanical Design Report MAJOR OIL Standard Pipeline and Flowline Design Manual
March 2002
Conclusions 1) On-bottom stability analysis has been carried out for the various GN Ubie phase 2A Pipelines and weight coating thicknesses have been determined where required. Analysis and results are presented in the individual work sheets, while the recommended coating thicknesses are in the summary sheet. 2) The required Safety Factor of 1.3 - with the determined weight coating thickness - is very adequate to ensure on-bottom stability of the Pipeline under buoyancy conditions. 3) A minimum concrete thicknessof 25mm will always be applied for all submerged pipeline river crossings as mechanical impact protection.
C01
12-Apr-11
Approved For Construction
SH
ET
KLA
A02 A01 R01
16-Feb-11 13-Jan-11 13-Dec-10
Issued for Approval Issued for Review Issued for Interdisciplinary Check
SH SH SH
ET ET ET
KLA KLA KLA
REV
DATE
DESCRIPTION
BY
CHECKED
APPROVED
Page 1 of 4
STABILITY AND WEIGHT COATING CALCULATIONS
Calculation Checklist Calc no DOC NO. File DOC NO. Elec file location Project title GN INFILL PROJECT Phase/CTR Client MAJOR OIL Deliverable Calculation title Pipeline Stability & Weight Coating Calculations Page 4 Please check boxes for all applicable items checked or delete if not appropriate: Calculations:
Calculation number assigned and registered Project title shown. Calculation title shown. Revision history box complete and signed. Index. Appropriate stamp for preliminary issues. Calculation objectives (aims) stated. Calculation method defined or described (including formulae if relevant). Reference made to text, standard or code. Check version/edition with that required for project. Source of input data stated (with revision number and date if relevant). Assumptions stated. Summary of results or conclusions if appropriate. For software based calculations, reference to software verification if available. Method clear and easy to follow. Input data correct. Calculation arithmetically correct OR software previously verified and reference to verification checked. Calculation result within expected limits. Calculation tolerances stated if significant. Units used as required by client. Abbreviations correct. Appropriate cross-references. Sketches included and clearly labelled, where required. bility a Attachments included and referenced, as required. Any precedent calculations updated Checking records: Checked and annotated copy of calculation filed (use "Check Print" stamp). Corrections made as required and calculation dated and signed on cover sheet by checker. Revisions: Changes clouded. Revision history block updated. Calculation re-checked if required. C01 A02 A01 R01
12-Apr-11 16-Feb-11 13-Jan-11 13-Dec-10
Approved For Construction Issued for Approval Issued for Review Issued for Interdisciplinary Check
SH SH SH SH
ET ET ET ET
KLA KLA KLA KLA
REV
DATE
DESCRIPTION
BY
CHECK
APPROVED
Page 2 of 4
STABILITY AND WEIGHT COATING CALCULATIONS
Calculation Sheet Proj No Phase/CTR
Calc No.
DOC NO.
Project
GN INFILL PROJECT
Deliverable
Subject
Pipeline Stability and Weight Coating Calculations
Client
MAJOR OIL
Sheet
5
Pipeline REV
DATE
BY
CHK
APP
C01
4/12/2011
SH
ET
KLA
PIPELINE WEIGHT COATING AND STABILITY ANALYSIS DESCRIPTION
SYMBOLS
INPUT
PIPE OUTSIDE DIAMETER
ODpipe
in/m
DATA
WALL THICKNESS
WTpipe
mm/m
INTERNAL CORROSION ALLOWANCE
WTcorr
mm
FBE PRIMER THICKNESS
WT FBE
mm
PE ADHESIVE COATING THICKNESS
WT Adh
mm
PE 3-LAYER COATING THICKNESS
WT3LPE
mm
CONCRETE COATING THICKNESS
WTconc
mm
MARINE GROWTH THICKNESS
WTmar
mm
pipe fbe
Kg/m
ADHESIVE COATING DENSITY
rAdh
Kg/m
COATING 3 LAYER PE DENSITY
3 LPE
Kg/m3
CONCRETE COATING DENSITY
conc
Kg/m
MARINE GROWTH DENSITY
mar
Kg/m
PRODUCT DENSITY
cont
Kg/m3
mud water
Kg/m
SWAMP MUD DENSITY RIVER BED WATER/MUD DENSITY
Case 2
Case 3
Case 4
Case 5
Case "n"
Values for Concrete Coating thickness obtained using Goal Seek with SG >= 1.3
FBE DENSITY
PIPE DENSITY
Case 1
UNIT
3
Kg/m3 3
3 3
3
Kg/m3
FORMULAE /METHOD OF ANALYSIS OUTPUT
INTERNAL DIAMETER
IDpipe
m
DATA
OVERALL DIAMETER
ODtotal
m 2
m
INT. X-SECTION AREA
Apipe
PIPE X-SECTION AREA
Asteel
m
PIPE WEIGHT
Wpipe
Kg/m
FBE COAT WEIGHT
W FBE
Kg/m
2
IDpipe = ODpipe - 2 x WTpipe ODtotal = ODpipe + 2 x WT FBE + 2 x WT Adh + 2 x WT 3LPE + 2 x WTconc Apipe = /4 x (IDpipe)2 Apipe = /4 x ((ODpipe)2 -(IDpipe)2) Wpipe =Apipe x Ppipe
N/m
W Fbe = /4 ((ODpipe + 2 x WT FBE)2 -(ODpipe)2) x Fbe
N/m ADHEHSIVE COATING WEIGHT
W Adh
Kg/m
W Adh = /4 x ((ODpipe + 2 x WT FBE + 2 x WT Adh)2 - (ODpipe + 2 x WT FBE)2) x Adh
N/m COATING 3 LAYER PE WEIGHT
W 3 LPE
Kg/m N/m
CONCRETE COATING WEIGHT
Wconcrete
Kg/m
MARINE GROWTH WEIGHT
Wmarine
Kg/m
PRODUCT WEIGHT
Wproduct
Kg/m
Wdry
Kg/m
WEIGHT OF DISPLACED WATER
Wbuoy
Kg/m
WEIGHT OF DISPLACED MUD
Wmud
Kg/m
N/m N/m N/m TOTAL WEIGHT IN AIR
N/m N/m WEIGHT OF PIPE IN WATER
Wsuba
Kg/m
WATER FILLED SUBMERGED WEIGHT
Wsubw
Kg/m
PRODUCT FILLED SUBMERGED WEIGHT
Wsubp
Kg/m
W3LPE = /4 ((ODpipe + 2 x WT FBE + 2 x WT Adh + 2 x WT3LPE)2 - (ODpipe + 2 x WT FBE + 2 x WT Adh)2) x 3LPE Wconc =P/4 x ((ODpipe + 2 x WT FBE + 2 x WT Adh + 2 x WT3LPE + 2 x WTconc)2 (ODpipe + 2 x WT FBE + 2 x WT Adh + 2 x WT 3LPE)2) x conc Wmar = /4 ((ODpipe + 2 x WT FBE + 2 x WT Adh + 2 x WT3LPE + 2 x Wtconc+ 2 x WTmar )2 - (ODpipe + 2 x WT FBE + 2 x WT Adh + 2 x WT 3LPE + WTconc)2) x mar Wcont = Apipe x cont Wdry = Wpipe + WFBE + WAdh + W3LPE + Wconc + Wmar + Wcont Wbuoy = /4(ODtotal)2 x water Wmud = /4(ODtotal)2 x mud Wsuba = Wdry - Wbuoy
N/m
Wsubw = Wdry - (Wbuoy - Apipe x Pwater)
N/m
Wsubp = Wdry - (Wbuoy - Apipe x Pproduct
N/m SPECIFIC GRAVITY OF PIPELINE IN WATER
SGwater = Wdry / Wbuoy SGmud = Wdry / Wmud (Set to a 1.3 factor in Goal Seek as per MAJOR OIL requirement) IF SGwater >= 1.3, NO, otherwise, YES IF SGmud >= 1.3, NO, otherwise, YES
SGwater
1.3
SPECIFIC GRAVITY OF PIPELINE IN MUD
SGmud
1.3
CONCRETE WEIGHT COATING REQ. (WATER CRO
YES/NO
CONCRETE WEIGHT COATING REQ. (SWAMP)?
YES/NO
CONCRETE COATING THICKNESS (WATER CROSS
WTconc
mm
Recommended Concrete Coating thickness from values in Row 21 rounded to the nearest 5mm
CONCRETE COATING THICKNESS (SWAMP)
WTconc
mm
Recommended Concrete Coating thickness from values in Row 21 rounded to the nearest 5mm
Page 3 of 4
STABILITY AND WEIGHT COATING CALCULATIONS
Calculation Sheet Proj No Phase/CTR
Calc No.
Project
File
GN INFILL PROJECT
DOC NO.
Subject
Pipeline Stability and Weight Coating Calculations
Client
MAJOR OIL
Pipeline
12" Koroama - CPF NAG Bulkline - CS
Sheet
9
REV
DATE
BY
CHK
APP
C01
4/12/2011
SH
ET
KLA
PIPELINE WEIGHT COATING CALCULATIONS DESCRIPTION
SYMBOLS
UNIT m
Case 1 Case 2 Case3 Case4 Case3 Installed '12" Corroded 12"+ Installed '12" Corroded '12" Installed '12" +3LPE df 0.72 3LPE DF 0.72 +3LPE DF 0.6 +3LPE DF 0.6 +3LPE DF 0.5 SWAMP SWAMP RIVER X RIVER X RIVER X 0.3239 0.3239 0.3239 0.3239 0.3239
Case4 Corroded '12" +3LPE DF 0.5 RIVER X 0.3239
INPUT
PIPE OUTSIDE DIAMETER
ODsteel
DATA
WALL THICKNESS
WTsteel
m
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
INTERNAL CORROSION ALLOWANCE
WTcorr
mm
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
FBE EXTERNAL THICKNESS
WT FBE
mm
0.5000
0.5000
0.5000
0.5000
0.5000
ADHESIVE COATING THICKNESS
WT FBE
mm
0.5000
0.5000
0.5000
0.5000
0.5000
0.5000
COATING 3 LAYER PE THICKNESS
WT 3 Layer PE
mm
3.0000
3.0000
3.0000
3.0000
3.0000
3.0000
CONCRETE COATING THICKNESS
WTconc
mm
0.0000
MARINE GROWTH THICKNESS
WTmar
mm
4.8393
20.9921
0.5000
0.0000
3.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
7850.0000
7850.0000
7850.0000
7850.0000
7850.0000
7850.0000
Kg/m
FBE DENSITY
pipe fbe
1950.0000
1950.0000
1950.0000
1950.0000
1950.0000
1950.0000
ADHESIVE COATING DENSITY
fbe
Kg/m
1400.0000
1400.0000
1400.0000
1400.0000
1400.0000
1400.0000
coat 3 LPE conc mar cont mud water
Kg/m3
940.0000
940.0000
940.0000
940.0000
940.0000
940.0000
Kg/m
3040.0000
3040.0000
3040.0000
3040.0000
3040.0000
3040.0000
Kg/m3
0.0000
Kg/m3
1.2000
Kg/m3
1442.0000
1442.0000
1442.0000
1442.0000
1442.0000
1442.0000
1020.0000
1020.0000
1020.0000
1020.0000
1020.0000
1020.0000
STEEL DENSITY
COATING 3 LAYER PE DENSITY CONCRETE COATING DENSITY MARINE GROWTH DENSITY PRODUCT DENSITY MUD DENSITY SWAMP WATER DENSITY
3 3
Kg/m
3
3
3
Kg/m
0.0000 1.2000
0.0000 1.2000
0.0000 1.2000
0.0000 1.2000
0.0000 1.2000
Pipeline Stability and Weight Coating Calculations OUTPUT INTERNAL DIAMETER DATA
IDsteel
m
OVERALL DIAMETER
ODtotal
m
INT. X-SECTION AREA
Apipe
m
2 2
#REF!
#REF!
0.3405
0.3728
#REF! 0.3309
#REF! 0.3369
#REF! 0.3309
#REF! 0.3309
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
STEEL X-SECTION AREA
Asteel
m
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
PIPE WEIGHT
Wsteel
Kg/m
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
N/m
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
FBE COAT WEIGHT
W FBE
Kg/m
0.99
0.99
0.99
0.99
0.99
N/m
9.74
9.74
9.74
9.74
9.74
0.99 9.74
0.72
0.72
0.72
0.72
0.72
0.72
ADHEHSIVE COATING WEIGHT
W FBE
Kg/m N/m
7.02
7.02
7.02
7.02
7.02
7.02
COATING 3 LAYER PE WEIGHT
W 3 LPE
Kg/m
2.91
2.91
2.91
2.91
2.91
2.91
N/m
28.57
28.57
28.57
28.57
28.57
28.57
CONCRETE COATING WEIGHT
Wconc
Kg/m
15.56
70.74
0.00
9.59
0.00
0.00
N/m
152.61
693.74
0.00
94.09
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
MARINE GROWTH WEIGHT
Wmar
Kg/m
PRODUCT WEIGHT
Wcont
Kg/m N/m
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
TOTAL WEIGHT IN AIR
Wdry
Kg/m
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
N/m
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
N/m
WEIGHT OF DISPLACED WATER WEIGHT OF DISPLACED MUD WEIGHT OF PIPE IN WATER
Wmud Wsuba
0.00 #REF!
0.00 #REF!
0.00 #REF!
0.00 #REF!
0.00 #REF!
0.00 #REF!
Kg/m
92.90
111.36
87.69
90.90
87.69
87.69
N/m
911.31
1092.42
860.24
891.73
860.24
860.24
Kg/m
131.33
157.43
123.97
128.51
123.97
123.97
N/m
1288.34
1544.39
1216.15
1260.66
1216.15
1216.15
Kg/m
#REF!
#REF!
#REF!
#REF!
#REF!
N/m
#REF!
#REF!
#REF!
#REF!
#REF!
#REF! #REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
WATER FILLED SUBMERGED WEIGHT
Wsubw
Kg/m N/m
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
PRODUCT FILLED SUBMERGED WEIGHT
Wsubp
Kg/m
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
SPECIFIC GRAVITY OF PIPELINE IN WATER SG Water
N/m
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
SPECIFIC GRAVITY OF PIPELINE IN MUD Is Wsubp >0.25*Wdry (for River Crossings)? (RE
Thank you for interesting in our services. We are a non-profit group that run this website to share documents. We need your help to maintenance this website.