1

INSTRUCTOR’S RESOURCE MANUAL

CHAPTER NINE Project Scheduling: Networks, Duration Estimation, and Critical Path

To Accompany PROJECT MANAGEMENT: Achieving Competitive Advantage By Jeffrey K. Pinto

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

2

CHAPTER NINE PROJECT FOCUS – The Spallation Neutron Source Project INTRODUCTION 9.1 PROJECT SCHEDULING 9.2 KEY SCHEDULING TERMINOLOGY 9.3 DEVELOPING A NETWORK Labeling Nodes Serial Activities Concurrent Activities Burst Activities Merge Activities 9.4 DURATION ESTIMATION 9.5 CONSTRUCTING THE CRITICAL PATH Calculating the Network The Forward Pass The Backward Pass Laddering Activities Hammock Activities Steps to Reduce the Critical Path Project Management Research in Brief – Software Development Delays and Solutions Summary Key Terms Solved Problems Discussion Questions Problems Internet Exercises MSProject Exercises PMP Certification Sample Questions Bibliography

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

3

TRANSPARENCIES

9.1 RULES FOR DEVELOPING ACTIVITY NETWORKS 1. Some determination of activity precedence ordering must be done prior to creating the network. 2. Network diagrams usually flow from left to right. 3. An activity cannot begin until all preceding connected activities have been completed. 4. Arrows on networks indicate precedence and logical flow. Arrows can cross over each other, although it is helpful for clarity’s sake to limit this effect when possible. 5. Each activity should have a unique identifier associated with it (number, letter, code, etc.). 6. Looping, or recycling through activities, is not permitted. 7. Although not required, it is common to start a project from a single beginning node. A single node point also is typically used as a project end indicator.

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

4

9.2 LABELS FOR ACTIVITY NODE

Early Start

ID Number

Activity Float

Activity Descriptor

Late Start

Activity Duration

Early Finish

Late Finish

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

5

9.3 PROJECT ACTIVITIES LINKED IN SERIES

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

6

9.4 ACTIVITIES LINKED IN PARALLEL (CONCURRENT)

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

7

9.5 MERGE ACTIVITIES

Activity A

Activity B

Activity D

Activity C

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

8

9.6 BURST ACTIVITIES

Activity B

Activity A

Activity C

Activity D

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

9

9.7 EXAMPLE OF CREATING A PROJECT ACTIVITY NETWORK Information for Network Construction Name: Project Delta Activity

Description

Predecessors

A

Contract signing

None

B

Questionnaire design

A

C

Target market ID

A

D

Survey sample

B, C

E

Develop presentation

B

F

Analyze results

D

G

Demographic analysis

C

H

Presentation to client

E, F, G

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

10

9.8 ACTIVITY NETWORK FOR EXAMPLE

E Dev. Present.

B Design

A Contract

D Survey

C Market ID

F Analysis

G Demog.

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

H Present

11

9.9 ACTIVITY DURATION ESTIMATION – BETA DISTRIBUTION

ESTIMATED TIME FORMULA TE =

A + 4(B) + C 6

WHERE: A = MOST OPTIMISTIC TIME B = MOST LIKELY TIME C = MOST PESSIMISTIC TIME

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

12

9.10 CONSTRUCTING THE CRITICAL PATH INFORMATION FOR PROJECT DELTA

Activity

Description

Predecessors

A

Contract signing

None

5

B

Questionnaire design

A

5

C

Target market ID

A

6

D

Survey sample

B, C

13

E

Develop presentation

B

6

F

Analyze results

D

4

G

Demographic analysis C

9

H

Presentation to client

2

E, F, G

Estimated Duration

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

13

9.10 (Con’d) Partial Project Activity Network with Task Durations

B Design 5

A Contract 5

E Dev. Present

6

D Survey 13

C Market ID 6

F Analysis 4

G Demog. 9

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

H Present 2

14

RULES WHEN USING THE FORWARD PASS

1. Add all activity times along each path as we move through the network (ES + Dur = EF),

2. Carry the EF time to the activity nodes immediately succeeding the recently completed node. That EF becomes the ES of the next node, unless the succeeding node is a merge point.

3. At a merge point, the largest preceding EF becomes the ES for that node.

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

15

9.12 ACTIVITY NETWORK WITH FORWARD PASS

5

0

B 10 Design 5

A 5 Contract 5

10

C 11 Market ID 6

16

6

11

5

E

Dev. Present

D 24 Survey 13

24 F 28 Analysis 4

11

G 20 Demog. 9

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

28

H 30 Present 2

16

9.13 RULES FOR USING THE BACKWARD PASS

1. Subtract activity times along each path as you move through the network (LF – Dur = LS),

2. Carry back the LS time to the activity nodes immediately preceding the successor node. That LS becomes the LF of the next node, unless the preceding node is a burst point.

3. In the case of a burst point, the smallest succeeding LS becomes the LF for that node.

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

17

ACTIVITY NETWORK WITH BACKWARD PASS

5 6

0 0

B 10 Design 5 11

A 5 Contract 5 5

10 22

11 11

5

C 11 Market ID 5 6 11

E

16

Dev. Present

6

D 24 Survey 13 24

28

24

F

28

28

Analysis

24

11

G

4

28

20

Demograph.

19

9

28

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

H

30

Presentation

28

2

30

18

9.15 COMPLETED ACTIVITY NETWORK WITH CRITICAL PATH AND ACTIVITY SLACK TIMES IDENTIFIED Critical Path is indicated in bold

5 1 6

0 0 0

B 10 Design 5 11

A 5 Contract 5 5

10 22

11 0 11

5 C 11 0 Market ID 5 6 11

E

16

12 Dev. Present

6

D 24 Survey 13 24

28

24 0

24

11

G

F

28

28

H

30

Analysis

0 Presentation

4

28

28

2

30

20

8 Demograph.

19

9

28 ES

ID

Slack

Task Name

LS Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

Duration

EF

LF

19

9.16 ACTIVITY NETWORK DEMONSTRATING LADDERING TECHNIQUE

A1 Design

A2 Design

A3 Design

A1 Coding

A2 Coding

A3 Coding

A1 Debugging

A2 Debugging

A3 Debugging

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

20

9.17 NETWORK DEMONSTRATING HAMMOCK ACTIVITY

5 13 18

0 0 0

A 5

5 5

B

9

4

22

5 9 14

5 D 11 0 user needs 5 6 11

12 10 22

C 7

12

G

21

9

31

12 9 21

21

11 0

11

E

25

Coding

14

25

H

22

31

I

35 0

10

25 0

25

31

31

F

31

Debugging

6

31

5 A 31 Hammock 26

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

4

35

21

9.18 STEPS TO REDUCE THE CRITICAL PATH

1. ELIMINATE TASKS ON THE CRITICAL PATH

2. REPLAN SERIAL PATHS TO BE PARALLEL

3. OVERLAP SEQUENTIAL TASKS

4. SHORTEN THE DURATION ON CRITICAL PATH ACTIVITIES

5. SHORTEN EARLY TASKS

6. SHORTEN LONGEST TASKS

7. SHORTEN EASIEST TASKS

8. SHORTEN TASKS THAT COST THE LEAST TO SPEED UP

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

22

DISCUSSION QUESTIONS 1. Define the following terms: a. Path: group of activities sequenced by relationship through project network logic b. Activity: any piece of work that will be performed during the project which has an expected time and cost for completion c. Early start: the earliest possible date upon which an uncompleted activity or project can start based on sequencing and scheduling constraints d. Early finish: the earliest possible date upon which an uncompleted activity or project can be completed e. Late start: the latest date an activity may start without delaying other project milestones or the project’s expected completion date f. Late finish: the latest date an activity may end without delaying other project milestones or the project’s expected completion date g. Forward pass: a process that works forward though the project network to determine the earliest start and earliest finish time for an activity h. Backward pass: a process that works backwards through the project network to calculate the latest finish times for an uncompleted activity i. Node: a convergence point of dependent paths in a network

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

23

j. AON: Activity on Node; a method of logic that determines activity networks in which a node depicts an activity and arrows indicate sequencing between nodes k. Float: a calculation which determines the amount of time an activity can be delayed from its earliest start date without delaying the project’s completion date

l.

l. Critical Path: the path through the project network having the least amount of float time and the longest time duration m. PERT: Project Evaluation and Review Technique; a network analysis system based on events and probability used when activities and their duration are difficult to define

2. Distinguish between serial activities and concurrent activities. Why do we seek to use concurrent activities as a way to shorten a project’s length? Serial activities begin with the first step and proceeding to subsequent steps one at a time sequentially until the project is completed. Serial activities must be completed in order and one at a time. Therefore, step 2 can not begin until step1 has been completed, and so on. Concurrent activities allow more than one activity to be performed during the same time period. This means step 1 may still be in progress when step 2 is started. Project teams seek out concurrent activities because they allow multiple phases of the project to be progressing simultaneously. Time savings occur from several activities being completed at the same time and delays in one step do not created delays in other concurrent activities. This method allows activities to work more independently which means the project can progress at a faster pace.

3. List three methods for deriving duration estimates for project activities. What are the strengths and weaknesses associated with each method?

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

24

One method for deriving time estimates is past experience. This method is beneficial in that it is easy and uses past examples of similar activities to predict future time estimates. However, it is limited in that estimates can be distorted by extenuating circumstances, changes in time and conditions, and information obsolescence. Another method uses expert opinion. Again, the approach is simple to use and draws on experience and knowledge of experts. The shortcomings here involve potential inadequacy of staff (at least relative to the expert giving the opinion) and project-specific complications. A third method employs mathematical derivations. This approach is more objective and allows multiple estimates (based on best, most likely and worst case analysis). The weaknesses of this method are that it is slightly more difficult to use and it disregards past failures (a.k.a. lessons learned).

4. In your opinion, what are the chief benefits and drawbacks of using beta distribution calculations (based on PERT techniques) to derive activity duration estimates? Beta distribution allows for the likelihood that optimistic and pessimistic times will not be symmetrical. By including realistic estimates of pessimistic and optimistic durations beta distribution creates a more accurate distribution of alternative duration times. One drawback to this method is that it is relies on estimates of pessimistic and optimistic time estimates which not be reliable. There has also been some debate related to how the time estimates in this method should be calculated and/or interpreted.

5. “The shortest total length of a project is determined by the longest path through the network.” Explain the concept behind this statement. Why does the longest path determine the shortest project length? This is based on the concept of critical path. The critical path combines the project activity network (the order to be followed for start/completion of activities) and the estimated time duration of activities in the sequence (how long each activity will take to

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

25

complete) to determine the length of time required to complete the project. The longest path of sequential events is used to establish the project’s duration because the events in the path must be performed one after another. Adding the duration times of activities in the critical path will result in the shortest project length (i.e. how long it will take to perform required serial activities).

6. The float associated with each project task can only be derived following the completion of the forward and backward passes. Explain why this is true. The forward pass establishes the earliest time that activities in the network can begin and end. The backward pass determines the latest time activities in the network can begin and end. Float time is the difference between the task’s latest and earliest end time (or the task’s latest and earliest start time). Hence, float cannot be calculated until the forward and backward pass have been completed.

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

26

PROBLEMS

1. Consider a project, such as moving to a new neighborhood, completing a longterm school assignment, or even cleaning your bedroom. Develop a set of activities necessary to accomplish that project and then order them in a precedence manner to create sequential logic. Explain and defend the number of steps you identified and the order in which you placed those steps for best completion of the project.

SOLUTION: This problem is intended to get students thinking sequentially; that is, developing first a set of activities or tasks and then applying some informal sequential logic to the order so that they can become familiar with concepts such as predecessor and successor activities. The key is to challenge their sequencing to determine if they have correctly identified both the necessary activities and the order in which they should be considered.

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

27

2. What is the time estimate of the following activity in which the optimistic estimate is 4 days, pessimistic is 12 days, and most likely is 5 days? Show your work.

SOLUTION: Using the Beta distribution for probabilistic estimation, the formula is given as:

TE = (a + 4m + b)/6

Where: TE = Estimated time for activity a = most optimistic time to complete the activity m = most likely time to complete the activity, the mode of the distribution b = most pessimistic time to complete the activity

The solution to this problem is:

TE

= (4 + 4(5) + 12)/6, or =6

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

28

3. Consider the following project tasks and their identified best, likely, and worst case estimates of task duration. Assume the organization you work for computes TE based on the standard formula. Calculate the TE for each of the following tasks (round to the nearest integer): Activity

Best

Likely

Worst

A

5

5

20

B

3

5

9

C

7

21

26

D

4

4

4

E

10

20

44

F

3

15

15

G

6

9

11

H

32

44

75

I

12

17

31

J

2

8

10

TE

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

29

SOLUTION: Using the Beta distribution for probabilistic estimation, the formula is given as:

TE = (a + 4m + b)/6 Where: TE = Estimated time for activity a = most optimistic time to complete the activity m = most likely time to complete the activity, the mode of the distribution b = most pessimistic time to complete the activity

Activity

Best

Likely

Worst

TE

A

5

5

20

8

B

3

5

9

5

C

7

21

26

20

D

4

4

4

4

E

10

20

44

22

F

3

15

15

13

G

6

9

11

9

H

32

44

75

47

I

12

17

31

19

J

2

8

10

7

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

30

4. Construct a network activity diagram based on the following information:

Activity

Preceding activities

A

-

B

-

C

A

D

B, C

E

B

F

C, D

G

E

H

F

I

G, H

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

31

SOLUTION:

A

C

F

H

D

I

B

E

G

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

32

5.

Consider a project with the following information:

Activity

Duration

A

3

--

B

5

A

C

7

A

D

3

B, C

E

5

B

F

4

D

G

2

C

H

5

E, F, G

Activity

Duration

A

Predecessors

ES

EF

LS

LF

Slack

3

0

3

0

3

--

B

5

3

8

5

10

2

C

7

3

10

3

10

--

D

3

10

13

10

13

--

E

5

8

13

12

17

4

F

4

13

17

13

17

--

G

2

10

12

15

17

5

H

5

17

22

17

22

--

A. Construct the project activity network using AON methodology and label each node. B. Identify the critical path and other paths through the network.

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

33

Solution: a.

a. The Critical Path is: A – C – D – F - H Alternative paths are:

A–B–E –H A–B–D–F–H A–C–G–H

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

34

6. An advertising project manager has developed a program for a new advertising campaign. In addition, the manager has gathered the time information for each activity, as shown in the table below. a)

Calculate the expected activity times (round to nearest integer).

b)

Calculate the activity slacks. What is the total project length? Make sure you fully label all nodes in the network.

c)

Identify the critical path. What are the alternative paths and how much slack time is associated with each “feeder path?”

d)

Identify the “burst” activities and the “merge” activities.

Activity

Optimistic

A B C D E F G

1 2 3 6 3 6 1

Time Estimates (wk) Most Likely Pessimistic 4 6 3 13 6 8 5

7 7 6 14 12 16 6

Immediate Predecessor(s) B A A, C B D, E, F

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

35

Solution: a) Calculated activity times are: Activity

Expected Duration

A

4

B

6

C

4

D

12

E

7

F

9

G

5

b)

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

36

The total project length is 22 weeks. c) The critical path is: B – C – E – G Path Slack Other paths are:

d)

A–D–G

2 days

A–E –G

1 day

B–F–G

2 days

Burst Activities:

A and B

Merge Activities: E and G

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

37

7. Using the following information, create an AON network activity diagram, calculate each activity TE (rounding to the nearest integer), the total duration of the project, its early start, early finish, late start and late finish times, and slack for each activity. Finally, show the project’s critical path.

Activity

Preceding activities

Best

Likely

Worst

TE

A

-

12

15

25

16

B

A

4

6

11

7

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

38

C

-

12

12

30

15

D

B, C

8

15

20

15

E

A

7

12

15

12

F

E

9

9

42

15

G

D, E

13

17

19

17

H

F

5

10

15

10

I

G

11

13

20

14

J

G, H

2

3

6

3

K

J, I

8

12

22

13

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

39

Solution:

Total duration of the project is 82 days. Critical Path: A-B-D-G-I-K

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

40

a. Now, assume that activity E has taken 10 days past its anticipated duration to complete. What happens to the project’s schedule? Has the duration changed? Is there a new critical path? Show your conclusions.

Solution: Because Activity E has 10 days of slack associated with it, delaying the completion of E by 10 days uses up all the slack; therefore, Activity E is now part of the project’s critical path. The overall project’s schedule remains unchanged except there is a new critical path: A-E-G-I-K

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

41

MSProject EXERCISES Exercise 9.1 Consider the following information that you have compiled regarding the steps needed to complete a project. You have identified all relevant steps and have made some determination regarding predecessor/successor relationships. Using MSProject, develop a simple Network diagram for this project, showing the links among the project activities. Activity

Predecessors

A – Survey site

-

B – Install sewer and storm drainage

A

C – Install gas and electric power lines

A

D – Excavate site for spec house

B, C

E – Pour foundation

D

Solution: Entering the activities and assigning the predecessor relationships using MSProject, the Network Diagram should resemble the following:

Microsoft product screen shot(s) reprinted with permission from Microsoft Corporation.

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

42

Exercise 9.2 Suppose we have a complete activity predecessor table (shown below) and we wish to create a Network diagram highlighting the activity sequence for this project. Using MSProject, enter the activities and their predecessors and create a complete activity Network diagram for this project.

Project - Remodeling an Appliance Activity

Predecessors

A.

Conduct competitive analysis

-

B.

Review field sales reports

-

C.

Conduct tech capabilities assessment

-

D.

Develop focus group data

A, B, C

E.

Conduct telephone surveys

D

F.

Identify relevant specification improvements

E

G.

Interface with Marketing staff

F

H.

Develop engineering specifications

G

I.

Check and debug designs

H

J.

Develop testing protocol

G

K.

Identify critical performance levels

J

L.

Assess and modify product components

I, K

M.

Conduct capabilities assessment

L

N.

Identify selection criteria

M

O.

Develop RFQ

M

P.

Develop production master schedule

N, O

Q.

Liaison with Sales staff

P

R.

Prepare product launch

Q

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

43

Solution: Entering the above values and predecessor relationships, we would derive the following network diagram. Note that as in the case of Exercise 9.1, without duration estimates, all activities are assumed to be of similar duration, making every activity in the network part of the critical path.

Microsoft product screen shot(s) reprinted with permission from Microsoft Corporation.

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

44

Exercise 9.3 Suppose that we add some duration estimates to each of the activities from exercise 9.1. A portion of the revised table is shown below. Recreate the Network diagram for this project and note how MSProject uses nodes to identify activity durations, start and finish dates, and predecessors. What is the critical path for this network diagram? How do we know? Activity

Duration

Predecessors

A – Survey site

5 days

-

B – Install sewer and storm drainage

9 days

A

C – Install gas and electric power lines

4 days

A

D – Excavate site for spec house

2 days

B, C

E – Pour foundation

2 days

D

Solution: Entering the above values and durations, the network diagram would resemble the following. If this network were shown on a computer screen, you would note that the critical path is highlighted in red, identifying the activities A – B – D – E as lying on the critical path.

Microsoft product screen shot(s) reprinted with permission from Microsoft Corporation.

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall