CHAPTER NINE Project Scheduling: Networks, Duration Estimation, and Critical Path
To Accompany PROJECT MANAGEMENT: Achieving Competitive Advantage By Jeffrey K. Pinto
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall
2
CHAPTER NINE PROJECT FOCUS – The Spallation Neutron Source Project INTRODUCTION 9.1 PROJECT SCHEDULING 9.2 KEY SCHEDULING TERMINOLOGY 9.3 DEVELOPING A NETWORK Labeling Nodes Serial Activities Concurrent Activities Burst Activities Merge Activities 9.4 DURATION ESTIMATION 9.5 CONSTRUCTING THE CRITICAL PATH Calculating the Network The Forward Pass The Backward Pass Laddering Activities Hammock Activities Steps to Reduce the Critical Path Project Management Research in Brief – Software Development Delays and Solutions Summary Key Terms Solved Problems Discussion Questions Problems Internet Exercises MSProject Exercises PMP Certification Sample Questions Bibliography
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall
3
TRANSPARENCIES
9.1 RULES FOR DEVELOPING ACTIVITY NETWORKS 1. Some determination of activity precedence ordering must be done prior to creating the network. 2. Network diagrams usually flow from left to right. 3. An activity cannot begin until all preceding connected activities have been completed. 4. Arrows on networks indicate precedence and logical flow. Arrows can cross over each other, although it is helpful for clarity’s sake to limit this effect when possible. 5. Each activity should have a unique identifier associated with it (number, letter, code, etc.). 6. Looping, or recycling through activities, is not permitted. 7. Although not required, it is common to start a project from a single beginning node. A single node point also is typically used as a project end indicator.
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall
4
9.2 LABELS FOR ACTIVITY NODE
Early Start
ID Number
Activity Float
Activity Descriptor
Late Start
Activity Duration
Early Finish
Late Finish
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall
5
9.3 PROJECT ACTIVITIES LINKED IN SERIES
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall
6
9.4 ACTIVITIES LINKED IN PARALLEL (CONCURRENT)
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall
7
9.5 MERGE ACTIVITIES
Activity A
Activity B
Activity D
Activity C
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall
8
9.6 BURST ACTIVITIES
Activity B
Activity A
Activity C
Activity D
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall
9
9.7 EXAMPLE OF CREATING A PROJECT ACTIVITY NETWORK Information for Network Construction Name: Project Delta Activity
Description
Predecessors
A
Contract signing
None
B
Questionnaire design
A
C
Target market ID
A
D
Survey sample
B, C
E
Develop presentation
B
F
Analyze results
D
G
Demographic analysis
C
H
Presentation to client
E, F, G
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall
10
9.8 ACTIVITY NETWORK FOR EXAMPLE
E Dev. Present.
B Design
A Contract
D Survey
C Market ID
F Analysis
G Demog.
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall
H Present
11
9.9 ACTIVITY DURATION ESTIMATION – BETA DISTRIBUTION
ESTIMATED TIME FORMULA TE =
A + 4(B) + C 6
WHERE: A = MOST OPTIMISTIC TIME B = MOST LIKELY TIME C = MOST PESSIMISTIC TIME
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall
12
9.10 CONSTRUCTING THE CRITICAL PATH INFORMATION FOR PROJECT DELTA
Activity
Description
Predecessors
A
Contract signing
None
5
B
Questionnaire design
A
5
C
Target market ID
A
6
D
Survey sample
B, C
13
E
Develop presentation
B
6
F
Analyze results
D
4
G
Demographic analysis C
9
H
Presentation to client
2
E, F, G
Estimated Duration
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall
13
9.10 (Con’d) Partial Project Activity Network with Task Durations
B Design 5
A Contract 5
E Dev. Present
6
D Survey 13
C Market ID 6
F Analysis 4
G Demog. 9
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall
H Present 2
14
RULES WHEN USING THE FORWARD PASS
1. Add all activity times along each path as we move through the network (ES + Dur = EF),
2. Carry the EF time to the activity nodes immediately succeeding the recently completed node. That EF becomes the ES of the next node, unless the succeeding node is a merge point.
3. At a merge point, the largest preceding EF becomes the ES for that node.
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall
15
9.12 ACTIVITY NETWORK WITH FORWARD PASS
5
0
B 10 Design 5
A 5 Contract 5
10
C 11 Market ID 6
16
6
11
5
E
Dev. Present
D 24 Survey 13
24 F 28 Analysis 4
11
G 20 Demog. 9
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall
28
H 30 Present 2
16
9.13 RULES FOR USING THE BACKWARD PASS
1. Subtract activity times along each path as you move through the network (LF – Dur = LS),
2. Carry back the LS time to the activity nodes immediately preceding the successor node. That LS becomes the LF of the next node, unless the preceding node is a burst point.
3. In the case of a burst point, the smallest succeeding LS becomes the LF for that node.
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall
17
ACTIVITY NETWORK WITH BACKWARD PASS
5 6
0 0
B 10 Design 5 11
A 5 Contract 5 5
10 22
11 11
5
C 11 Market ID 5 6 11
E
16
Dev. Present
6
D 24 Survey 13 24
28
24
F
28
28
Analysis
24
11
G
4
28
20
Demograph.
19
9
28
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall
H
30
Presentation
28
2
30
18
9.15 COMPLETED ACTIVITY NETWORK WITH CRITICAL PATH AND ACTIVITY SLACK TIMES IDENTIFIED Critical Path is indicated in bold
5 1 6
0 0 0
B 10 Design 5 11
A 5 Contract 5 5
10 22
11 0 11
5 C 11 0 Market ID 5 6 11
E
16
12 Dev. Present
6
D 24 Survey 13 24
28
24 0
24
11
G
F
28
28
H
30
Analysis
0 Presentation
4
28
28
2
30
20
8 Demograph.
19
9
28 ES
ID
Slack
Task Name
LS Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall
Duration
EF
LF
19
9.16 ACTIVITY NETWORK DEMONSTRATING LADDERING TECHNIQUE
A1 Design
A2 Design
A3 Design
A1 Coding
A2 Coding
A3 Coding
A1 Debugging
A2 Debugging
A3 Debugging
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall
20
9.17 NETWORK DEMONSTRATING HAMMOCK ACTIVITY
5 13 18
0 0 0
A 5
5 5
B
9
4
22
5 9 14
5 D 11 0 user needs 5 6 11
12 10 22
C 7
12
G
21
9
31
12 9 21
21
11 0
11
E
25
Coding
14
25
H
22
31
I
35 0
10
25 0
25
31
31
F
31
Debugging
6
31
5 A 31 Hammock 26
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall
4
35
21
9.18 STEPS TO REDUCE THE CRITICAL PATH
1. ELIMINATE TASKS ON THE CRITICAL PATH
2. REPLAN SERIAL PATHS TO BE PARALLEL
3. OVERLAP SEQUENTIAL TASKS
4. SHORTEN THE DURATION ON CRITICAL PATH ACTIVITIES
5. SHORTEN EARLY TASKS
6. SHORTEN LONGEST TASKS
7. SHORTEN EASIEST TASKS
8. SHORTEN TASKS THAT COST THE LEAST TO SPEED UP
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall
22
DISCUSSION QUESTIONS 1. Define the following terms: a. Path: group of activities sequenced by relationship through project network logic b. Activity: any piece of work that will be performed during the project which has an expected time and cost for completion c. Early start: the earliest possible date upon which an uncompleted activity or project can start based on sequencing and scheduling constraints d. Early finish: the earliest possible date upon which an uncompleted activity or project can be completed e. Late start: the latest date an activity may start without delaying other project milestones or the project’s expected completion date f. Late finish: the latest date an activity may end without delaying other project milestones or the project’s expected completion date g. Forward pass: a process that works forward though the project network to determine the earliest start and earliest finish time for an activity h. Backward pass: a process that works backwards through the project network to calculate the latest finish times for an uncompleted activity i. Node: a convergence point of dependent paths in a network
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall
23
j. AON: Activity on Node; a method of logic that determines activity networks in which a node depicts an activity and arrows indicate sequencing between nodes k. Float: a calculation which determines the amount of time an activity can be delayed from its earliest start date without delaying the project’s completion date
l.
l. Critical Path: the path through the project network having the least amount of float time and the longest time duration m. PERT: Project Evaluation and Review Technique; a network analysis system based on events and probability used when activities and their duration are difficult to define
2. Distinguish between serial activities and concurrent activities. Why do we seek to use concurrent activities as a way to shorten a project’s length? Serial activities begin with the first step and proceeding to subsequent steps one at a time sequentially until the project is completed. Serial activities must be completed in order and one at a time. Therefore, step 2 can not begin until step1 has been completed, and so on. Concurrent activities allow more than one activity to be performed during the same time period. This means step 1 may still be in progress when step 2 is started. Project teams seek out concurrent activities because they allow multiple phases of the project to be progressing simultaneously. Time savings occur from several activities being completed at the same time and delays in one step do not created delays in other concurrent activities. This method allows activities to work more independently which means the project can progress at a faster pace.
3. List three methods for deriving duration estimates for project activities. What are the strengths and weaknesses associated with each method?
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall
24
One method for deriving time estimates is past experience. This method is beneficial in that it is easy and uses past examples of similar activities to predict future time estimates. However, it is limited in that estimates can be distorted by extenuating circumstances, changes in time and conditions, and information obsolescence. Another method uses expert opinion. Again, the approach is simple to use and draws on experience and knowledge of experts. The shortcomings here involve potential inadequacy of staff (at least relative to the expert giving the opinion) and project-specific complications. A third method employs mathematical derivations. This approach is more objective and allows multiple estimates (based on best, most likely and worst case analysis). The weaknesses of this method are that it is slightly more difficult to use and it disregards past failures (a.k.a. lessons learned).
4. In your opinion, what are the chief benefits and drawbacks of using beta distribution calculations (based on PERT techniques) to derive activity duration estimates? Beta distribution allows for the likelihood that optimistic and pessimistic times will not be symmetrical. By including realistic estimates of pessimistic and optimistic durations beta distribution creates a more accurate distribution of alternative duration times. One drawback to this method is that it is relies on estimates of pessimistic and optimistic time estimates which not be reliable. There has also been some debate related to how the time estimates in this method should be calculated and/or interpreted.
5. “The shortest total length of a project is determined by the longest path through the network.” Explain the concept behind this statement. Why does the longest path determine the shortest project length? This is based on the concept of critical path. The critical path combines the project activity network (the order to be followed for start/completion of activities) and the estimated time duration of activities in the sequence (how long each activity will take to
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall
25
complete) to determine the length of time required to complete the project. The longest path of sequential events is used to establish the project’s duration because the events in the path must be performed one after another. Adding the duration times of activities in the critical path will result in the shortest project length (i.e. how long it will take to perform required serial activities).
6. The float associated with each project task can only be derived following the completion of the forward and backward passes. Explain why this is true. The forward pass establishes the earliest time that activities in the network can begin and end. The backward pass determines the latest time activities in the network can begin and end. Float time is the difference between the task’s latest and earliest end time (or the task’s latest and earliest start time). Hence, float cannot be calculated until the forward and backward pass have been completed.
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall
26
PROBLEMS
1. Consider a project, such as moving to a new neighborhood, completing a longterm school assignment, or even cleaning your bedroom. Develop a set of activities necessary to accomplish that project and then order them in a precedence manner to create sequential logic. Explain and defend the number of steps you identified and the order in which you placed those steps for best completion of the project.
SOLUTION: This problem is intended to get students thinking sequentially; that is, developing first a set of activities or tasks and then applying some informal sequential logic to the order so that they can become familiar with concepts such as predecessor and successor activities. The key is to challenge their sequencing to determine if they have correctly identified both the necessary activities and the order in which they should be considered.
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall
27
2. What is the time estimate of the following activity in which the optimistic estimate is 4 days, pessimistic is 12 days, and most likely is 5 days? Show your work.
SOLUTION: Using the Beta distribution for probabilistic estimation, the formula is given as:
TE = (a + 4m + b)/6
Where: TE = Estimated time for activity a = most optimistic time to complete the activity m = most likely time to complete the activity, the mode of the distribution b = most pessimistic time to complete the activity
The solution to this problem is:
TE
= (4 + 4(5) + 12)/6, or =6
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall
28
3. Consider the following project tasks and their identified best, likely, and worst case estimates of task duration. Assume the organization you work for computes TE based on the standard formula. Calculate the TE for each of the following tasks (round to the nearest integer): Activity
Best
Likely
Worst
A
5
5
20
B
3
5
9
C
7
21
26
D
4
4
4
E
10
20
44
F
3
15
15
G
6
9
11
H
32
44
75
I
12
17
31
J
2
8
10
TE
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall
29
SOLUTION: Using the Beta distribution for probabilistic estimation, the formula is given as:
TE = (a + 4m + b)/6 Where: TE = Estimated time for activity a = most optimistic time to complete the activity m = most likely time to complete the activity, the mode of the distribution b = most pessimistic time to complete the activity
Activity
Best
Likely
Worst
TE
A
5
5
20
8
B
3
5
9
5
C
7
21
26
20
D
4
4
4
4
E
10
20
44
22
F
3
15
15
13
G
6
9
11
9
H
32
44
75
47
I
12
17
31
19
J
2
8
10
7
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall
30
4. Construct a network activity diagram based on the following information:
Activity
Preceding activities
A
-
B
-
C
A
D
B, C
E
B
F
C, D
G
E
H
F
I
G, H
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall
31
SOLUTION:
A
C
F
H
D
I
B
E
G
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall
32
5.
Consider a project with the following information:
Activity
Duration
A
3
--
B
5
A
C
7
A
D
3
B, C
E
5
B
F
4
D
G
2
C
H
5
E, F, G
Activity
Duration
A
Predecessors
ES
EF
LS
LF
Slack
3
0
3
0
3
--
B
5
3
8
5
10
2
C
7
3
10
3
10
--
D
3
10
13
10
13
--
E
5
8
13
12
17
4
F
4
13
17
13
17
--
G
2
10
12
15
17
5
H
5
17
22
17
22
--
A. Construct the project activity network using AON methodology and label each node. B. Identify the critical path and other paths through the network.
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall
33
Solution: a.
a. The Critical Path is: A – C – D – F - H Alternative paths are:
A–B–E –H A–B–D–F–H A–C–G–H
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall
34
6. An advertising project manager has developed a program for a new advertising campaign. In addition, the manager has gathered the time information for each activity, as shown in the table below. a)
Calculate the expected activity times (round to nearest integer).
b)
Calculate the activity slacks. What is the total project length? Make sure you fully label all nodes in the network.
c)
Identify the critical path. What are the alternative paths and how much slack time is associated with each “feeder path?”
d)
Identify the “burst” activities and the “merge” activities.
Activity
Optimistic
A B C D E F G
1 2 3 6 3 6 1
Time Estimates (wk) Most Likely Pessimistic 4 6 3 13 6 8 5
7 7 6 14 12 16 6
Immediate Predecessor(s) B A A, C B D, E, F
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall
35
Solution: a) Calculated activity times are: Activity
Expected Duration
A
4
B
6
C
4
D
12
E
7
F
9
G
5
b)
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall
36
The total project length is 22 weeks. c) The critical path is: B – C – E – G Path Slack Other paths are:
d)
A–D–G
2 days
A–E –G
1 day
B–F–G
2 days
Burst Activities:
A and B
Merge Activities: E and G
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall
37
7. Using the following information, create an AON network activity diagram, calculate each activity TE (rounding to the nearest integer), the total duration of the project, its early start, early finish, late start and late finish times, and slack for each activity. Finally, show the project’s critical path.
Activity
Preceding activities
Best
Likely
Worst
TE
A
-
12
15
25
16
B
A
4
6
11
7
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall
38
C
-
12
12
30
15
D
B, C
8
15
20
15
E
A
7
12
15
12
F
E
9
9
42
15
G
D, E
13
17
19
17
H
F
5
10
15
10
I
G
11
13
20
14
J
G, H
2
3
6
3
K
J, I
8
12
22
13
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall
39
Solution:
Total duration of the project is 82 days. Critical Path: A-B-D-G-I-K
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall
40
a. Now, assume that activity E has taken 10 days past its anticipated duration to complete. What happens to the project’s schedule? Has the duration changed? Is there a new critical path? Show your conclusions.
Solution: Because Activity E has 10 days of slack associated with it, delaying the completion of E by 10 days uses up all the slack; therefore, Activity E is now part of the project’s critical path. The overall project’s schedule remains unchanged except there is a new critical path: A-E-G-I-K
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall
41
MSProject EXERCISES Exercise 9.1 Consider the following information that you have compiled regarding the steps needed to complete a project. You have identified all relevant steps and have made some determination regarding predecessor/successor relationships. Using MSProject, develop a simple Network diagram for this project, showing the links among the project activities. Activity
Predecessors
A – Survey site
-
B – Install sewer and storm drainage
A
C – Install gas and electric power lines
A
D – Excavate site for spec house
B, C
E – Pour foundation
D
Solution: Entering the activities and assigning the predecessor relationships using MSProject, the Network Diagram should resemble the following:
Microsoft product screen shot(s) reprinted with permission from Microsoft Corporation.
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall
42
Exercise 9.2 Suppose we have a complete activity predecessor table (shown below) and we wish to create a Network diagram highlighting the activity sequence for this project. Using MSProject, enter the activities and their predecessors and create a complete activity Network diagram for this project.
Project - Remodeling an Appliance Activity
Predecessors
A.
Conduct competitive analysis
-
B.
Review field sales reports
-
C.
Conduct tech capabilities assessment
-
D.
Develop focus group data
A, B, C
E.
Conduct telephone surveys
D
F.
Identify relevant specification improvements
E
G.
Interface with Marketing staff
F
H.
Develop engineering specifications
G
I.
Check and debug designs
H
J.
Develop testing protocol
G
K.
Identify critical performance levels
J
L.
Assess and modify product components
I, K
M.
Conduct capabilities assessment
L
N.
Identify selection criteria
M
O.
Develop RFQ
M
P.
Develop production master schedule
N, O
Q.
Liaison with Sales staff
P
R.
Prepare product launch
Q
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall
43
Solution: Entering the above values and predecessor relationships, we would derive the following network diagram. Note that as in the case of Exercise 9.1, without duration estimates, all activities are assumed to be of similar duration, making every activity in the network part of the critical path.
Microsoft product screen shot(s) reprinted with permission from Microsoft Corporation.
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall
44
Exercise 9.3 Suppose that we add some duration estimates to each of the activities from exercise 9.1. A portion of the revised table is shown below. Recreate the Network diagram for this project and note how MSProject uses nodes to identify activity durations, start and finish dates, and predecessors. What is the critical path for this network diagram? How do we know? Activity
Duration
Predecessors
A – Survey site
5 days
-
B – Install sewer and storm drainage
9 days
A
C – Install gas and electric power lines
4 days
A
D – Excavate site for spec house
2 days
B, C
E – Pour foundation
2 days
D
Solution: Entering the above values and durations, the network diagram would resemble the following. If this network were shown on a computer screen, you would note that the critical path is highlighted in red, identifying the activities A – B – D – E as lying on the critical path.
Microsoft product screen shot(s) reprinted with permission from Microsoft Corporation.
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall