Process Failure Mode and Effect Analysis (PFMEA) Company Name

Subject

Manufacturing Location

PFMEA Start Date

Customer Name

PFMEA Revision Date

Model Year(s) / Progm(s)

Cross Functional Team

Structure Analysis (STEP 2) 1. Process Item Connecting Rod Line

2. Process Step 50, Drilling Operation

3. Process Work Element Man: Machine Operator Machine : Drilling Machine Material:- Direce Material Connecting Rod after boring &

chanfering operation (40) IN Direct Material Coolant with correct concentration, Ø3.5 drill Method Defined machine parameter & work instruction Environment :- No special requirement

PFMEA ID Number

Function Analysis (STEP 3)

Process Responsibility Confidentiality Level Risk Analysis ( Step 5)

Failure Analysis (STEP 4)

1. Function Process Item Connecting rod lineManufacturin g of

2. Function Process Step Drilling of two holes (Ø3.5mm) on small end side

Sever 2. Failure 3. Failure Cause (FC) ity Mode (FM) Man To load the part on fixture in Your plant : Internal process : 8 Two holes are Man: Part unload before process correct orientation and remove it 100% production run affected may not drilled completion have to be scapped. Failure may Machine : Drill Broken while after operation completion. operation Machine To dirll holes at angle 15 have a chronic health and / or

connecting rod as per the defined specification

with 15 degree angle (both) from the centre line

degree from centre line Material Direct To do drilling operation on correct part Coolant Proper heat dissipate during drilling operation Drill To make Ø3.5 mm hole Method - To direct / educate the operator for working method & required processing condition Env NA

3 . Fun Functi ctio on nP Prr o oce cess ss W Wor orkk Ele emen mentt

CurrentPrevention

1 . Fa Fa iill u urr e E Eff ffec ects ts

safety risk for the next process worker. Customer: Line shutdown from one hour up to full production shift; stop shipment can be possible; field repair or replacement required End User : Degradation of primary vehicle function due to improper oiling

Method Processing method & desired output are not clear

OCC Cu rr en en t Det ec ec titi on on

Machine not stop before the completetion of operation (Program controlled)

4

DE ET T

Machine-based automated Machine-based detection method that will detect the failure mode downstream & prevent further processing

4

AP

SP

M

NA

Drill life is defined and followed Processing method is clearly defined through WI / SOP & controlled through PLC

7

2

2

7

Optimization ( Step 6) (if AP is High (H) Take action & fill below step 6 Prevention Action

Detection Action

Responsible Person Name

Target Com. on date

Status

Action taken with

Completion on date

SEV

OCC

DET

SP

AP

Remarks

pointer

History / Change Authorization Rev no

Date:

Remarks

Page | 1 of 1