Petronas Overall SCC Project Briefing
Short Description
Petronas Rapid Program...
Description
ENGINEERING, PROCUREMENT, CONSTRUCTION AND COMMISSIONING (EPCC)FOR REFINERY AND PETROCHEMICAL INTEGRATED DEVELOPMENT (RAPID) STEAM CRACKER COMPLEX (SCC) PROJECT
Date: Venue:
Introduction Project Title
RAPID Steam Cracker Complex (SCC) Project
Business Objective
To meet both domestic and Asia’s energy and chemicals demand.
Project OWNER
PRPC Refinery and Cracker Sdn. Bhd.
CONTRACTOR
Consortium of Toyo Engineering Corporation and Toyo Engineering & Construction Sdn. Bhd.
Project Coverage
1. 2. 3. 4. 5. 6.
Steam Cracker Unit Pygas Hydrogenation Unit Butadiene Extraction Unit Benzene Extraction Unit Isobutylene Extraction Unit Utilities
RAPID Project Overview – Overall Scope RAPID
3rd Parties
Toyo’s scope
RAPID Project Petronas Refinery & Petrochemical Corp. (PRPC)
Refinery
SCC
Petchem
Utilities
Tank Farm
Offsite & Interconnect
NonProcess
External Facilities
Evonik
PDWT
RGT2
PCP
(chem.)
(marine)
(regas)
(power)
State Projects
Other Projects
RAPID Project Overview – Overall Matrix PETRONAS – PROJECT LEADERSHIP TEAM (PLT)
: Critical : Non‐critical : Site, Infra, Building
INTEGRATED PROGRAM MANAGEMENT TEAM (IPMT) DIRECTORATE STEAM CRACKER PACKAGE 5
REFINERY PACKAGE 1,2,3,4
PETROCHEMICAL PACKAGE 6A,6B,7,8,9,11,26*
FLARE PACKAGE 14
Evonik
Regas Terminal 2 PDWT (Pengarang Deep Water Terminal)
INTERCONNECTING PACKAGE 14
TANKAGE PACKAGE 22A
SOLID HANDLING & WAREHOUSING PACKAGE 12 OFFSITES & UTILITIES PACKAGE 14 INDUSTRIAL GAS PRODUCTION PACKAGE 15 EFFLUENT PLANT TREATMENT PACKAGE 16 INCINERATOR PACKAGE 17 HV POWER DISTRIBUTION PACKAGE 13
SITE PREPARATION WORKS PACKAGE 18 NON PROCESS BUILDING PACKAGE 19 CONSTRUCTION INFRA PACKAGE 20 RAW WATER TREATMENT PLANT PACKAGE 20 TECHNICAL CONTRACTS PACKAGE 21
PCP (Pengerang Co‐generation Plant)
*6A: LLDPE, 6B: LDPE, 7: Polypropylene, 8: CPU, PPU, BPA, 9: Elastomers, 11: EO/EG, 26: Poly Carbonate
RAPID Project Overview – EPCC Contractors PKG No.
Plants (Awarded at the same time)
EPC Contractor
Pkg.1
Refinery 1 (RFCC, PRU, etc.)
CTCI / Chiyoda
Pkg.2
Refinery 2 (CDU, ARDS, HCDU)
Sinopec
Pkg.3
Refinery 3 (CCR, NHT, DHT, etc.)
T-R
Pkg.4
Refinery 4 (SRU, ARU, SWS, etc.)
Petrofac
Pkg.5
Steam Cracker Complex (SCC)
TOYO
Storage Tank Yard
Punj Lloyd
Pkg.22A PKG No.
Other Facilities
EPC Contractor
Pengerang Co-generation Plant (2000MW)
Siemens, MMC
PDWT
Pengerang Deep Water Terminal (Tanks/Jetty)
Dialog, Vopak, Johor Government
RGT-2
Regasification Terminal 2 (2.0MMT/Y)
Samsung C&T
MOLF
Material Offloading Facility
Zelan Construction
Pkg.14
Utility and Offsite Facilities for RAPID
Technip-Fluor (EPCm)
Site Preparation Phase 1 & 2
Menta Construction Gadang Holdings
PCP
S/P
Project Outline ‐ Location (Pengerang)
Pelabuhan Tanjung Pelepas (Public Port) Pengerang to Tanjung Pelepas : ~145km Pengerang to Pasir Gudang: ~75km
Pasir Gudang and Tanjung Langsat (Public Port)
RAPID SITE Marine Terminal Ramunia Yard (PDWT) & Regas 2 and Jetty
3. Project Outline ‐ Block Flow Raffinate 1
Methanol
ISBL Facilities Ethylene Propylene
Refinery
Butadiene ROG
RFCC (PKG 1)
MTBE C3 Cut Raw C4
CDU (PKG 2)
NHT (PKG 3)
BDU Unit 2400 (185 kTA)
MTBE Unit 3420 (550 kTA)
Raffinate 2
BZU Unit 2600 (175 kTA)
Benzene
C4 Specialty MEK
Full Range Naphtha isoButane Recycle
HDT Naphtha
Raffinate 2
SCU Unit 2100 (1,291 kTA)
Raffinate 3
Raw PyGas H2
SGP (PKG 3)
Raffinate 1
C3/C4 LPG
PGH Unit 2500 (660 kTA) as feed
C6
C5 Recycle
C7-C8, C9+
C6 Recycle
Utility Center
Power & Utilities
(PKG 13, 14 & 15) Effluent
OSBL Facilities SCC Cooling Tower Unit 4730 (28 cells)
SCC Tank Farm Unit 5210 (41 units)
Effluent Plant (PKG 16A)
SCC Flare Stack Unit 6420 (2 stacks) Petchem Flare Stack Unit 6430 (2 stacks)
Petchem Plants
Project Outline ‐ Overall Timeline EDC (= LOA) 18 Jul 14
RFSU (M52) 30 Nov 18
CD (T0) 15 Aug14
51.5 Months
28 Days
PA (M58) 29 May 19
6 Months
Time Guarantee : 57.5 Months (BD to PA) KOM (M1) 25 Aug 14
MC (M49) 31 Aug 18
(48.5 Months)
(3 Months)
Engineering / Procurement / Construction 28 Days Signing the Contract Performance Bond Insurance Certificate Parent Company Guarantee Tripartite Agreement w/Licensor Consortium Agreement Legal Opinion
Commissioning
1st Invoice
Start Up PTR
Project Outline ‐ Key Milestones 01 Jul 2015 Handover of Site Area Haulage Road available
30 Nov 2015 MOLF available for offloading
M12(b)
31 Aug 2017 Water & Air available at BL
M16(e)
M37(e)
01 Apr 2016 Heavy lifting start M21(b)
30 Nov 2017 Power & Steam available at BL
30 Nov 18 Facility RFSU
M40(e)
M52(e)
01 Aug 2016 Piping installation start
01 Dec 2017 Commissioning start
M25(b)
M41(b)
CD T0
M12(b)
01 Nov 2015 Deep U/G work start M16(b)
M37(e)
M16(e)
01 Dec 2015 Piling start M17(b)
M49(e) M52(e)
01 Nov 2017 Loop testing start
01 Jun 2016 Piping fabrication start M23(b)
M40(e)
M40(b)
01 Aug 2017 Loop testing start M37(b)
31 Aug 2018 Mechanical Completion M49(e)
THANK YOU Q & A