Fuel Gas Supply System

1. General Plant name Country/ Town Plant type Revision

: : : :

Pengerang Cogen Johor, Malaysia 1 x KA26 - 6 26-7-2013

: : : : :

20 / 34 / 40 60 / 85 / 95 Tropical, Coastal + 8.5 Seismic zone 1 (UBC 1997)

: :

400 / 230 V, 3 phase / 50 Hz 11 kV, 3 phase / 50 Hz

Site Conditions Temperature (Min./ Max.) Rel. Air Humidity (Min./ Max.) Atmosphere st 1 Storey Level Earthquake zone Electrical Supply

°C % RH

Low voltage / frequency (< 185 kW) Medium voltave/frequency (>185 kW)

V / Hz V / Hz

m

Mechanical Design [ x ] ASME [ x ] IEC [ ] ……….. Electrical Design [x] [x] [ ]

IEC ISO CENELEC

Identification System [x]

KKS

QA Standard [] [x] []

Manufacturer standard ISO 9000 …..

Special requirements [ ] Duty Natural gas equipments. Natural gas scrubbing and filtering.

Pengerang Based on: 53840s01.doc - Rev. 2 - 2000-07-04

Page 1 / 6

Fuel Gas Supply System

2. Performance Data All data are given at skid limit 2.1 ESD valve Quantity × duty Total fuel flow (min. / design ) Duty per train Fuel gas inlet pressure (min. / max.) Fuel gas inlet temperature (min. / max.) Pressure drop

kg/s kg/s bar (a) °C bar

: : : : : :

3 × 50% 16.1 / 119 59.5 38.6 / 49.4 14.8 / 40 < 0.1

Quantity × duty Total fuel flow (min. / design / max.) Duty per train

kg/s kg/s

: : :

3 × 50% 16.1 / 119 59.5

Fuel gas inlet pressure (min. / max.) Fuel gas inlet temperature (min. / max.)

bar (a) °C

: :

38.5 / 49.3 14.7 / 40

Fuel gas outlet pressure (min. / max) Pressure drop

bar (a) bar

: :

37.7 / 48.5 0.8

Condensate tank size

m3

:

2

: : : : : : : : :

2 × 100% 3.7 / 22.4 22.4 35.9 / 46.6 9.0 28.7 / 34.1

2.2 Scrubbing and Filter Liquid/dust separator

2.7 Pressure Reducing Station (only for HRSG) Quantity × duty Total fuel flow (min. / design ) Duty per train Fuel gas inlet pressure (min. / max.) Fuel gas outlet pressure (set point) Fuel gas inlet temperature (min. / max.) Connection (inlet / outlet) Flange rating Pressure drop

kg/s kg/s bar (a) bar (a) °C bar

< 1.5 at full aperture

3. Scope of Supply 3.1 Emergency Shut Down valve equipment [ x ] 3 × 50 % Fast acting Emergency Shut Down valve spring loaded incl. instrumentation and equalizing line, skid mounted [ x ] Internal piping including double isolation valve on drains and vents [ x ] Internal power and signal cabling [ x ] First filling of consumables [ x ] Name plates [ x ] Special tools - if required [ x ] Recommended spare parts for commissioning **

Pengerang Based on: 53840s01.doc - Rev. 2 - 2000-07-04

Page 2 / 6

Fuel Gas Supply System

[x] [x]

Spare and wear parts for 2 years ** rd th Recommended spare part for 3 & 4 year (optional) **

3.2 Liquid/dust Separator equipments [] [x] [x] [x] []

2 × 100 % Cyclone separator station incl. instrumentation 3 × 50 % Liquid/dust separator station incl. instrumentation Automatic condensate discharge system for separator station Drain tank incl. instrumentation Drain tank discharge

[]

… No. (2 × 100 %) Cartridge filter station(s) (one per GT), each consisting of: [] []

[x] [x] [x] [x] [x] [x] [x] [x] [x]

Cartridge filter section Internal piping, valves and instrumentation

Local motor control center - if applicable Local control cubicle - if applicable Internal power and signal cabling First filling of consumables Name plates Special tools - if required Recommended spare parts for commissioning ** Spare and wear parts for 2 years ** rd th Recommended spare part for 3 & 4 year (optional) **

3.3 Pressure Reducing Station equipments [x]

2 No. 1 × 100 % Pressure reducing station(s), each consisting of: [x] [] [x] [] [] [x]

[ x] [x] [x] [x] [x] [x] [x] [x] [x]

Pressure reducing valve Slam shut valve(s) Pressure relief valve Noise reduction package Check valve at gas outlet Unit internal piping, valves and instrumentation

Local motor control center - if applicable Local control cubicle Internal power and signal cabling First filling of consumables Name plates Special tools - if required Recommended spare parts for commissioning Spare and wear parts for 2 years rd th Recommended spare part for 3 & 4 year (optional) **

** Please provide cost breakdown for easy accessment 3.5 Services [x] [x] [x] [x]

Equipment design Manufacturing and manufacture supervision Shop assembly Inspections, examinations and tests

Pengerang Based on: 53840s01.doc - Rev. 2 - 2000-07-04

Page 3 / 6

Fuel Gas Supply System

[x] [x] [x] [] [] [] []

Cleaning, painting and coating Documentation Protection and packing for shipment Erection Erection supervision only Commissioning Commissioning supervision only

3.3 Exclusions [x] []

Civil works .….

4. Design Features Location Equipment Design Pressure Equipemnt Design Temperature

: : :

shelter 65 bar 70 deg C

:

99.99 % of particles ≥ 5 µm

dB (A)

:

85

kg m

: :

vendor to advise vendor to advise

:

March 2014

:

seaworthy

Separation Efficiency Liquid/Dust Separator Noise Requirements Sound pressure level at 1 m distance 5. Transport Information Weight Dimensions (L × W × H)

6. Erection / Commissioning Information n.a.

7. Time Schedule Estimated order date:

8. Commercial 8.1 Delivery Conditions [x] [x]

EXW Packing

8.2 Pricing [x]

Firm price

8.3 Warranty / Guarantee

Pengerang Based on: 53840s01.doc - Rev. 2 - 2000-07-04

Page 4 / 6

Fuel Gas Supply System

[x]

[x]

Duration of material warranty after successful commissioning

:

24 months (Mandatory) + 10 months extension (optional)

Performance guarantee

9. Documents to be submitted with the Proposal [x] [x] [ ] [x] [x]

Price Technical data and descriptions Tender documents Outline drawing Schedules and comments (Please advise the delivery schedule)

10. Submittal Dates [x]

Entire proposal

:

th

7 Aug 2013

11. Enclosures [x] [x] [ ] [x] [ ] [ ] [ ] [ x]

Flow sheet Medium analysis Principle arrangement Data sheet to be filled in Client’s schedules Client’s specification Project time Schedule Sub-vendor list (Please provide equipment according to vendor list)

Pengerang Based on: 53840s01.doc - Rev. 2 - 2000-07-04

Page 5 / 6

Fuel Gas Supply System

Pengerang Based on: 53840s01.doc - Rev. 2 - 2000-07-04

Page 6 / 6