Gulf Cooperation Council Interconnection Authority GCCIA Engineer
GCC Interconnection Project - Phase I
TRANSMISSION & DISTRIBUTION
Site Acceptance Test Report MiCOM P921 27/59
P921
Bay Ref: Substation: REVISION PAGES 1 2
SUMMARY 1
PURPOSE OF TESTS
2
X
2
REFERENCE DOCUMENT
2
X
3
SCOPE
2
X
4
RELAY TERMINLOGY
3
X
5
TEST EQUIPMENT
3
X
6
PRE-REQUISTES
3
X
7
PROCEDURES
4
X
8
RECORD TEST SHEET
6
X
8.1 RELAY INFORMATION 8.2 VT DATA: 8.3 PRODUCT CHECKS 8.4 MEASURMENT VALUE TEST: 8.5 OVER VOLTAGE PROTECTION
X
8.6 UNDER VOLTAGE PROTECTION 8.7 BINARY INPUT TEST : 8.8 BINARY OUTPUT TEST: 8.9 FIXED LED INDICATIONS TEST: 8.10
LED INDICATIONS TEST:
8.11
FINAL CHECK
AREVA T&D
GCCIA / SNCL
Signature
Signature
Name Date Doc. No.
Name Date REV-2
Page 1 of 10
Gulf Cooperation Council Interconnection Authority GCCIA Engineer
GCC Interconnection Project - Phase I
P921 1
TRANSMISSION & DISTRIBUTION
Site Acceptance Test Report MiCOM P921 27/59
Bay Ref: Substation:
PURPOSE OF TESTS
The purpose of the tests is to check the full functionality of the protection relay. This procedure does not intend to check that all alarms and trips are correctly sent to the DCS or SCADA level. This part is already developed into dedicated DCS or SCADA Commissioning procedures. This procedure does not intend to check all tripping matrix and PSL logic tests, this, when applicable, is described into a separate document, dedicated to the specific substation and feeder type. 2
REFERENCE DOCUMENTS DOCUMENT REFERENCE
DOCUMENT
VERSION/ DATE
REMARKS
Protection Line Diagram Schematic Drawing Service Manual Operation Manual Protection Relay Coordination Principles Relay setting Calculation LED Display Configuration
3
SCOPE
Substation Name :Diameter: Bay : Panel Number : Relay Denomination in Scheme Scheme to be Checked
Relay Functionality Test.
AREVA T&D
GCCIA / SNCL
Signature
Signature
Name Date Doc. No.
Name Date REV-2
Page 2 of 10
Gulf Cooperation Council Interconnection Authority GCCIA Engineer
GCC Interconnection Project - Phase I
P921 4
Bay Ref: Substation:
TERMINOLOGY
Code ( ANSI) 27/59
5
TRANSMISSION & DISTRIBUTION
Site Acceptance Test Report MiCOM P921 27/59
Terminology Over/Under Voltage Relay
TEST EQUIPMENT USED
Sl No 1.
Description
Make
Equipment Sl No.
Calibration date
2.
Secondary Injection Kit Multimeter
3.
Laptop
NA
Setting software
Type : MICOM S1 Studio Version : 2.14
6
Calibration due date
PRE - REQUISITES PRE-REQUISITES
REMARKS
All Safety Condition Are Ok All Competent Personnel Available For The Test Ac & Dc Supply Availability And Security PPE Safety Available. All Other Relevant Safety Instructions Been Followed Coordination With Other Parties ( GIS, Transformer, Etc..)
AREVA T&D
GCCIA / SNCL
Signature
Signature
Name Date Doc. No.
Name Date REV-2
Page 3 of 10
Gulf Cooperation Council Interconnection Authority GCCIA Engineer
GCC Interconnection Project - Phase I
P921 7
TRANSMISSION & DISTRIBUTION
Site Acceptance Test Report MiCOM P921 27/59
Bay Ref: Substation:
TEST PROCEDURES The following procedures are written for demonstrating the main protection functions of the P921 relay using an Omicron test set or similar. The tests do not test the boundaries of all available function characteristics. They do test that the function is operating at a point on one chosen characteristic. This document is to be referred to when performing commissioning tests in association with the commissioning section of the service manual.
NOTE : All the Test are performed in the Test Switch. Omicron CMC156 Test Equipment or Any Equivalent To Be Used ..
7.1 Testing Over/Under Voltage function Values to be measured: 1. stage (V>) or (V) or (tV) check: 1. If time delay (tV>) is short, gradually inject the voltage into the 3 phases up to the Stage value: tripping should occur for a voltage equal to the stage (V>) to within ±2% 2. If time delay (tV>) is long, inject a voltage equal to 0.98x(V>) into the 3 phases and check that tripping does not occur. Then inject 1.2x(V>) and check that tripping occurs. 3. Gradually reduce the voltage on one of the phases and measure the value of the dropoff stage (V>) : the function must reset for a voltage less than or equal to the programmed hysteresis. 7.1.2 Stage (V
Thank you for interesting in our services. We are a non-profit group that run this website to share documents. We need your help to maintenance this website.