P740 BB Protection Test Report Rev 1

November 12, 2017 | Author: samiahmedmansour | Category: Electrical Substation, Gulf Cooperation Council, Relay, Electronic Circuits, Scada
Share Embed Donate


Short Description

PROTECTION...

Description

Gulf Cooperation Council Interconnection Authority GCCIA Engineer

GCC Interconnection Project - Phase I

TRANSMISSION & DISTRIBUTION Site Acceptance Test Report Bay Ref: LOW IMPEDANCE BB PROETCTION Substation:

P740

REVISION PAGE 0 1

SUMMARY 1

PURPOSE OF TESTS

2

X

2

REFERENCE DOCUMENT

2

X

3

SCOPE

2

X

4

RELAY TERMINLOGY

2

X

5

TEST EQUIPMENT

3

X

6

PRE-REQUISTES

3

X

7

PROCEDURES

3

X

8

RECORD TEST SHEET

6

X

8.1 TOPOLOGY 8.2 BB PROTECTION DETAILS 8.3 RELAY ASSIGNMENTS 8.4 SYSTEM DATA 8.5 SETTINGS 8.6

CT PARAMETER

8.7

BB PROTECTION TEST

AREVA T&D

GCCIA / SNCL

Signature

Signature

Name Date Doc. No.

Name Date REV-1

Page 1 of 18

Gulf Cooperation Council Interconnection Authority GCCIA Engineer

GCC Interconnection Project - Phase I

TRANSMISSION & DISTRIBUTION Site Acceptance Test Report Bay Ref: LOW IMPEDANCE BB PROETCTION Substation:

P740

1 PURPOSE OF TESTS The purpose of the tests is to check the full functionality of the protection relay and the complete scheme related. This procedure does not intend to check that all alarms and trips are correctly sent to the DCS or SCADA level. This part is already developed into dedicated DCS or SCADA Commissioning procedures. 2 REFERENCE DOCUMENTS DOCUMENT

DOCUMENT REFERENCE

VERSION/ DATE

REMARKS

Protection Line Diagram Schematic Drawing Service Manual Operation Manual 3 SCOPE Substation Name :Diameter: Bay : Panel Number : Relay Denomination in Scheme Scheme to be Checked 4 TERMINOLOGY Code ( ANSI) 87B1

Terminology Low Impedance Busbar Protection

AREVA T&D

GCCIA / SNCL

Signature

Signature

Name Date Doc. No.

Name Date REV-1

Page 2 of 18

Gulf Cooperation Council Interconnection Authority GCCIA Engineer

GCC Interconnection Project - Phase I

P740

TRANSMISSION & DISTRIBUTION Site Acceptance Test Report Bay Ref: LOW IMPEDANCE BB PROETCTION Substation:

5 TEST EQUIPMENT USED Sl No 1.

Description

2.

Secondary Injection Kit Multimeter

3.

Laptop

Make

Equipment Sl No.

Calibration date

Calibration due date

NA

6. PRE - REQUISITES PRE-REQUISITES

REMARKS

All Safety Condition Are Ok All Competent Personnel Available For The Test AC & DC Supply Availability And Security PPE Safety Available. All Other Relevant Safety Instructions Been Followed Coordination With Other Parties ( GIS, Transformer, Etc..) 7. TEST PROCEDURES The following procedures are written for demonstrating the main protection functions of the P740 relay using an Omicron test set or similar. This document is to be referred to when performing commissioning tests in association with the commissioning section of the service manual. 7.1 ID>1 threshold (circuitry fault current) : The ID>1 threshold is a CU’s parameter, this setting is : ID>1 = A tID>1 = s For simplify the test put K ID>1

= 0%

For the search of the current threshold the ID>1 alarm timer is set at the minimum value (100 ms).With the OMICRON CMC 156, applied a current on I1 of each PU and increase the current by step of 0,01 A until appear the circuitry fault alarm. (Output relay 3 of CU “circuitry fault”) Repeat this sequence for the phase I2 and I3. AREVA T&D

GCCIA / SNCL

Signature

Signature

Name Date Doc. No.

Name Date REV-1

Page 3 of 18

Gulf Cooperation Council Interconnection Authority GCCIA Engineer

GCC Interconnection Project - Phase I

P740

TRANSMISSION & DISTRIBUTION Site Acceptance Test Report Bay Ref: LOW IMPEDANCE BB PROETCTION Substation:

The ID>1 alarm timer is checked for each PU after the measurement of the current threshold, the setting of the ID>1 alarm timer is set at the original value. (5 Sec) The time delay is measured for a differential current upper than ID>1,the start of the clock is when the current is applied and the stop of the clock is when the circuitry fault alarm appeared. 7.2 ID>2 threshold (tripping current): The ID>2 threshold is a CU’s parameter, this setting is : ID>2 = IDCZ>2 = K2 = KCZ = The tripping time is less of one cycle ( 2 = IDCZ>2 K1 ID>1 Ibias = A

I Bias

The trip appears in the colored area. Methodology of 2 current on bus : With Omicron box put : AREVA T&D

GCCIA / SNCL

Signature

Signature

Name Date Doc. No.

Name Date REV-1

Page 4 of 18

Gulf Cooperation Council Interconnection Authority GCCIA Engineer

GCC Interconnection Project - Phase I

TRANSMISSION & DISTRIBUTION Site Acceptance Test Report Bay Ref: LOW IMPEDANCE BB PROETCTION Substation:

P740

I1 => on phase I1 of one PU I2 => on phase I1 of another PU 1. Fixed a bias current > Ibias0 2. Increase the differential current until the busbar trip, by 2 opposite ramps of current on I1 and I2 with the same speed so that the bias current is always constant. The trip of the busbar differential protection appeared when the two conditions are respected : 1. Idiff > ( K2 * Ibias = KCZ * Ibais ) 2. Idiff > ( ID>2 = IDCZ>2 ) IDCZ>2

ID>2 Ibias =

=

K2

KCZ

3. Idiff > K x Ibias 4. Idiff > Id>2 I Bias = I1 + I 2 I Diff = I1 – I 2 Slope K = I Diff operated / I Bias 7.4 Dead Zone threshold and Timing Test : The I>DZ threshold is a PU’s parameter, this setting is : I> DZ DZ Time

= =

With the OMICRON CMC 156, applied a current on I1 of each PU and increase the current by step of 0,01 A until the trip of the PU (output relay N° 1, 2 or 3). The CMC 156 is programmed to stop when the tripping relay switch on.Repeat this sequence for the phase I2 and I3. The tDZ timer is checked for each PU after the measurement of the current threshold, the setting of the tDZ alarm timer is set at the original value. ( Sec) The time delay is measured for a differential current upper than I>DZ,the start of the clock is when the current is applied and the stop of the clock is when the circuitry fault alarm appeared.

AREVA T&D

GCCIA / SNCL

Signature

Signature

Name Date Doc. No.

Name Date REV-1

Page 5 of 18

Gulf Cooperation Council Interconnection Authority GCCIA Engineer

GCC Interconnection Project - Phase I

TRANSMISSION & DISTRIBUTION Site Acceptance Test Report Bay Ref: LOW IMPEDANCE BB PROETCTION Substation:

P740

8.1- TOPOLOGY :-

8.2- BB Protection Details : 8.2.1- Central Unit : Quantity

1

Model Number

Serial Number

Address

Soft issue

8.2.2 Peripheral Unit : Quantity

5

Model Number

Serial Number

Address

Soft issue

AREVA T&D

feeder

GCCIA / SNCL

Signature

Signature

Name Date Doc. No.

Name Date REV-1

Page 6 of 18

Gulf Cooperation Council Interconnection Authority GCCIA Engineer

GCC Interconnection Project - Phase I

P740

TRANSMISSION & DISTRIBUTION Site Acceptance Test Report Bay Ref: LOW IMPEDANCE BB PROETCTION Substation:

8.4

Relay Assignments :

8.41

P741 logic I/O assignment

Opto N#

1 2 3 4 5 6 7 8

P741 TERMINAL N# K1-K2 K3-K4 K5-K6 K7-K8 K9-K10 K11-K12 K13-K14 K15-K16

Assignment

Test

SPARE SPARE SPARE SPARE SPARE SPARE SPARE SPARE

AREVA T&D

GCCIA / SNCL

Signature

Signature

Name Date Doc. No.

Name Date REV-1

Page 7 of 18

Gulf Cooperation Council Interconnection Authority GCCIA Engineer

GCC Interconnection Project - Phase I

P740 Relay N#

1 2 3 4 5 6 7 8 Led N# 1 2 3 4 5 6 7 8

TRANSMISSION & DISTRIBUTION Site Acceptance Test Report Bay Ref: LOW IMPEDANCE BB PROETCTION Substation:

P741 TERMINAL N# J1-J2 J3-J4 J5-J6 J7-J8 J9-J10 J11-J12 J13-J15 (R) J14-J15 (T) J16-J18 (R) J17-J18 (T) Color Red Yellow Green Red Yellow Green Red Yellow Green Red Yellow Green Red Yellow Green Red Yellow Green Red Yellow Green Red Yellow Green

Assignment

Test

SPARE SPARE SPARE SPARE SPARE SPARE SPARE SPARE Assignment 87BB Fault Phase A SPARE SPARE 87BB Fault Phase B SPARE SPARE 87BB Fault Phase C SPARE SPARE 87BB Trip Zone 1 SPARE SPARE Circuitry faulty Zone 1 SPARE SPARE Zone 1 Blocked Zone 1 Checked Zone 1 Protected Fiber Comm. Error Fiber Comm. Change Fiber Comm. OK SPARE SPARE SPARE

AREVA T&D

Test

GCCIA / SNCL

Signature

Signature

Name Date Doc. No.

Name Date REV-1

Page 8 of 18

Gulf Cooperation Council Interconnection Authority GCCIA Engineer

GCC Interconnection Project - Phase I

P740

TRANSMISSION & DISTRIBUTION Site Acceptance Test Report Bay Ref: LOW IMPEDANCE BB PROETCTION Substation:

8.3.2 P742 logic I/O assignment( P742@7,8,9,10,11) Opto N#

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 Relay N# 1 2 3 4 5 6 7 8 WD

P742 terminal N# C1-C2 C3-C4 C5-C6 C7-C8 C-9C10 C11-C12 C13-C14 C15-C16 A1-A2 A3-A4 A5-A6 A7-A8 A9-A10 A11-A12 A13-A14 A15-A16 P742 terminal N# D1-D2 D3-D4 D5-D6 D7-D8 D9-D10 D11-D12 D13-D15 (R) D14-D15 (T) D16-D18 (R) D17-D18 (T) E11-E12 (R) E12-E13(T)

Assignment

Test

SPARE SPARE 50BF INT ( Ext 3 Ph Trip ) SPARE SPARE SPARE 3 ph CB Open 3 ph CB Closed SPARE SPARE SPARE SPARE SPARE SPARE SPARE SPARE Assignment

Test

BB PROTECTION TRIP SPARE SPARE SPARE SPARE SPARE SPARE SPARE

RELAY FAULTY (WATCHDOG CONTACT)

AREVA T&D

GCCIA / SNCL

Signature

Signature

Name Date Doc. No.

Name Date REV-1

Page 9 of 18

Gulf Cooperation Council Interconnection Authority GCCIA Engineer

GCC Interconnection Project - Phase I

P740

TRANSMISSION & DISTRIBUTION Site Acceptance Test Report Bay Ref: LOW IMPEDANCE BB PROETCTION Substation:

Led N# 1 2 3 4 5 6 7 8

Assignment CB OPEN CB CLOSED CB STATUS ALARM DEAD ZONE FAULT 87BB TRIP FIBER COMM ERROR EXT CBF INITATION SPARE

8.4

System Data :

8.41

CT Data :-

feeder

8.42

TYPE

Make

Ratio

Test

Class KSCC Vk

Imag Burden

Network Data :-

Network current Independent bar Icc min Iload max Iload min I bias max (1Bar) Biggest PW

Value

Feeder name

8.5 – Settings : 8.5.1 CU setting:

Differential phase fault : Actived

KCZ IDCZ>2 K2 ID>2 ID>1

= = = = =

% A % A A AREVA T&D

GCCIA / SNCL

Signature

Signature

Name Date Doc. No.

Name Date REV-1

Page 10 of 18

Gulf Cooperation Council Interconnection Authority GCCIA Engineer

GCC Interconnection Project - Phase I

P740 K1 = ID>1 Timer = 

TRANSMISSION & DISTRIBUTION Site Acceptance Test Report Bay Ref: LOW IMPEDANCE BB PROETCTION Substation: % Sec

Differential earth fault : not actived

8.5.2. PU Setting: 

Dead Zone Protection : Actived

I>DZ = I>DZ Time =

A Sec

8.6 CT parameters : Measurement of loop resistance: The CT secondary are wired like following schematic:

AREVA T&D

GCCIA / SNCL

Signature

Signature

Name Date Doc. No.

Name Date REV-1

Page 11 of 18

Gulf Cooperation Council Interconnection Authority GCCIA Engineer

GCC Interconnection Project - Phase I

P740

TRANSMISSION & DISTRIBUTION Site Acceptance Test Report Bay Ref: LOW IMPEDANCE BB PROETCTION Substation:

PU’s

BURDEN RESISTANCE Ran

PU’s

Ratio

Rbn

Class

RBph / RBN

Rcn

Rab

Standard input

CT SECONDARY RESISTANCE RA RB RC

Rated burden

KSCC or Vk

RCT

Eff burden

Eff. burden : It’s the highest of the 3 loop resistances Rba, RBb and RBc, multiplied by 1.25 for taking into account the high temperature. RBph / RBn : It’s the ratio between the highest of the 3 loop resistances Rba, RBb and RBc and the loop resistance Rab. RCT : It’s the highest of the 3 secondary resistances of the CT.

AREVA T&D

GCCIA / SNCL

Signature

Signature

Name Date Doc. No.

Name Date REV-1

Page 12 of 18

Gulf Cooperation Council Interconnection Authority GCCIA Engineer

GCC Interconnection Project - Phase I

P740

TRANSMISSION & DISTRIBUTION Site Acceptance Test Report Bay Ref: LOW IMPEDANCE BB PROETCTION Substation:

Relay Characteristics:

Idiff ≥ ID>2 Idiff Idiff ≥ ≥ ID>1 IDCZ>2

Point C

8.7. BB Protection Tests : 8.7.1 Measurements : Injected secondary current = 1A PU’s

CT ratio

Idiff Idiff ≥ ≥ K2*Ibais s> ID>1 KCZ*Ibais K1*Ibais than the current ) .mer,, ,,,,, ,,,,, ,,,,, ,,,,, ,,,,, ,,,,, ,,,,, ,,,,, ,,,,, ,,,,, ,,,,, ,,,,, ,,,,, ,,,,, ,,,,, ,,,,, ,,,,, Current measured by the relay IY IB ,,,,,IR ,Point A B

AREVA T&D

GCCIA / SNCL

Signature

Signature

Name Date Doc. No.

Name Date REV-1

Page 13 of 18

Gulf Cooperation Council Interconnection Authority GCCIA Engineer

GCC Interconnection Project - Phase I

TRANSMISSION & DISTRIBUTION Site Acceptance Test Report Bay Ref: LOW IMPEDANCE BB PROETCTION Substation:

P740

8.7.2 Checking of 87BB current threshold : 8.7.2.1. ID>1 threshold (circuitry fault current) : PU’s

8.7.3

CT ratio

Time delay Sec

I3

ID>2 threshold (tripping current):

PU’s

CT ratio

8.7.3

I1

Current measured I2

I1 In A

ID>2 , IDCZ>2 and tripping time measured Trip. I2 Trip. Time I3 Trip. Time Time In A In (ms) In A In (ms) In (ms)

Slope Test :

Phase

PU@7-Q01

PU@8-Q02

CT Ratio

2000/1

2000/1

BAIS

DIFFERENTIAL

SLOPE

PH-R PH-Y PH-B

AREVA T&D

GCCIA / SNCL

Signature

Signature

Name Date Doc. No.

Name Date REV-1

Page 14 of 18

Gulf Cooperation Council Interconnection Authority GCCIA Engineer

GCC Interconnection Project - Phase I

P740

TRANSMISSION & DISTRIBUTION Site Acceptance Test Report Bay Ref: LOW IMPEDANCE BB PROETCTION Substation:

Phase

PU@7-Q01

PU@8-Q02

CT Ratio

2000/1

2000/1

Phase

PU@7-Q02

PU@8-Q03

CT Ratio

2000/1

2000/1

Phase

PU@7-Q03

PU@8-Q04

CT Ratio

2000/1

2000/1

Phase

PU@7-Q04

PU@8-Q05

CT Ratio

2000/1

2000/1

BAIS

DIFFERENTIAL

SLOPE

BAIS

DIFFERENTIAL

SLOPE

BAIS

DIFFERENTIAL

SLOPE

BAIS

DIFFERENTIAL

SLOPE

PH-R PH-Y PH-B

PH-R PH-Y PH-B

PH-R PH-Y PH-B

PH-R PH-Y PH-B AREVA T&D

GCCIA / SNCL

Signature

Signature

Name Date Doc. No.

Name Date REV-1

Page 15 of 18

Gulf Cooperation Council Interconnection Authority GCCIA Engineer

GCC Interconnection Project - Phase I

P740

TRANSMISSION & DISTRIBUTION Site Acceptance Test Report Bay Ref: LOW IMPEDANCE BB PROETCTION Substation:

8.7.3 Topology Test : Case 1:Circuit

PU Add.

Q01

7

Q02

8

Q03

9

Q04

10

Q05

11

CB Status

Fault Loc.

TRIP

NO TRIP

TRIP

NO TRIP

TRIP

NO TRIP

HERE

C = Close, O = Open, Y = Yes, N = No Case 2:Circuit

PU Add.

Q01

7

Q02

8

Q03

9

Q04

10

Q05

11

CB Status

Fault Loc. HERE

C = Close, O = Open, Y = Yes, N = No Case 3:Circuit

PU Add.

Q01

7

Q02

8

Q03

9

Q04

10

Q05

11

CB Status

Fault Loc.

HERE

C = Close, O = Open, Y = Yes, N = No Case 4:AREVA T&D

GCCIA / SNCL

Signature

Signature

Name Date Doc. No.

Name Date REV-1

Page 16 of 18

Gulf Cooperation Council Interconnection Authority GCCIA Engineer

GCC Interconnection Project - Phase I

P740 Circuit

TRANSMISSION & DISTRIBUTION Site Acceptance Test Report Bay Ref: LOW IMPEDANCE BB PROETCTION Substation:

PU Add.

Q01

7

Q02

8

Q03

9

Q04

10

Q05

11

CB Status

Fault Loc.

TRIP

NO TRIP

TRIP

NO TRIP

HERE

C = Close, O = Open, Y = Yes, N = No Case 5:Circuit

PU Add.

Q01

7

Q02

8

Q03

9

Q04

10

Q05

11

CB Status

Fault Loc.

HERE

C = Close, O = Open, Y = Yes, N = No 8.7.3 Dead Zone Fault : PU’s

CT ratio

I1

Current measured I2

Time delay Sec

I3

8.8 FINAL CHECKS AREVA T&D

GCCIA / SNCL

Signature

Signature

Name Date Doc. No.

Name Date REV-1

Page 17 of 18

Gulf Cooperation Council Interconnection Authority GCCIA Engineer

GCC Interconnection Project - Phase I

P740

TRANSMISSION & DISTRIBUTION Site Acceptance Test Report Bay Ref: LOW IMPEDANCE BB PROETCTION Substation:

Item

Description

Result

1

All test equipment, leads, shorts and test block removed safely?

2

Disturbed customer wiring re-checked?

3

All commissioning tests disabled?

4

Circuit breaker operations counter reset?

5

Current counters reset?

6

Event records reset?

7

Fault records reset?

8

Disturbance records reset?

9

Alarms reset?

10

LEDs reset?

11

Secondary front cover replaced? (If applicable)

REMARKS ……………………………………………………………………………………………………………… ……………………………………………………………………………………………………………… ……………………………………………………………………………………………………… END OF REPORT

AREVA T&D

GCCIA / SNCL

Signature

Signature

Name Date Doc. No.

Name Date REV-1

Page 18 of 18

View more...

Comments

Copyright ©2017 KUPDF Inc.
SUPPORT KUPDF