One Storey Building Constructions Bar Chart Schedule

December 13, 2017 | Author: Angelinne Catalan | Category: N/A
Share Embed Donate


Short Description

One Storey Building Constructions Bar Chart Schedule...

Description

Work Activity 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. 17. 18. 19. 20. 21. 22. 23. 24. 25. 26. 27. 28. 29. 30. 31. 32.

Move-in Stake-out Excavate, Column Footings Excavate, Wall Footings Excavate, Drain Pipes and Catch Basins Install Forms & Rebars, Column Footings Install Forms & Rebars, Wall Footings Install Drain Pipes and Catch Basins Backfill and Compact Draiange Excavation Pour Concrete, Column Footings Pour Concrete, Wall Footings Fabricate Timber Trusses Pour Concrete Columns Install Forms, Columns Erect 1st New Layers of CHB Erect Next Layers of CHB Erect Trusses & Cross Frames Install Girts and Tie Girts Install Purlins Backfill, Grade & Compact Ground Install Forms and Rebars, Slab Pour Concrete, Slab Concrete Works, Sidewalk Install G.I. Roof Sheets & Gutters Install Ceilings Install Doors & Windows Plaster Walls Erect Double-Wall Partition Paint Roof Install PVC Downspouts Paint Interior/Exterior Clean-up

No. of Days (c.d.) 0 2 2 2 4 3 2 3 3 2 1 2 10 3 3 4 8 4 3 6 3 2 2 2 4 6 2 5 3 4 1 5 2

12

3

4

5

6

7

8

9 10

DURATION (Calendar Days) 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50