One pass and two pass tunnel lining

January 27, 2017 | Author: Gelai Santos | Category: N/A
Share Embed Donate


Short Description

Download One pass and two pass tunnel lining...

Description

One-pass and Two-pass Precast Segmental Linings Wern-ping (Nick) Chen Jacobs

Applicable to: Tunnel Boring Machine (TBM) tunneling

Not for: Hand mining, such as drilled and blast or excavation by roadheader or other mechanized means

UT Austin Seminar, April 4, 2007 Presentation starts from big questions and narrows down to details

Outline 1. Definitions 2. Factors that drive the use of segmental lining 3. Tunnel alignments 4. Rationale for choosing one or the other 5. Types of precast segmental linings/Material 6. Geometries 7. Segment joints 8. Segment construction tolerance 9. Design/Modeling 10. Construction considerations 11. References 12. Q/A

1. Definitions Primary/initial lining • The ground support installed immediately after the excavation • It is a temporary structure for safety and operation during tunneling • Normally in associated with hard rock tunneling • Examples are rock dowels, steel set, or shotcrete

1. Definitions

1. Definitions

Secondary/final lining

One-pass lining

• Tunnel support or lining installed following and independent of excavation to satisfy user/function requirement • Normally it is cast-inplace concrete

• Lining used as both initial support and final lining of a tunnel; normally it is precast segmental lining

1

1. Definitions

1. Definitions

Two-pass lining

Two-pass Segmental lining





With primary/initial support installed as temporary ground support and followed by an insitu final concrete lining

1. Definitions

Use segmental lining as initial ground support and cast-inplace (CIP) concrete as final tunnel lining

Segment, Open Face, Single Shield

TBM Shield/Segment

TBM Shield/

1. Cutterhead 2. Shield 3. Articulation (option) 4.Thrust ram 5. Segment erector 6. Muck extraction conveyor 7. Muck transfer Conveyor 8. Gathering arm 9. Muck hopper 10. Motor 11. Tailskin articulation (option) 12. Thrust ring

Schematic Earth Pressure Balance Machine (EPBM)

Schematic Slurry Shield Machine

2

Open Gripper TBMs

1. Definitions Main Beam TBM • • •

The family of open TBMs is developed for excavating in rock. The thrusting force is obtained by reacting on the grippers. The head is equipped with cutting disks.

1. Cutter head 2. Cutter head shield 3. Erector to place rib and mesh 4. Inner kelly 5. Outer kelly in two positions with grippers and telescope jacks 6. Push jacks 7. Cutter head drive 8. Rear support 9. Belt conveyer 10. Roof bolting drill 11. Probe drill

2. Factors that drive the use of segmental lining •

• •

Ground stability during tunneling 1. Soft ground tunneling 2. Adverse geological condition in hard rock tunneling; such as in laminated shale, embedded with clay Construction schedule – pending on the contractor, the construction schedule may be reduced Potential of excessive groundwater infiltration

2. Factors that drive the use of segmental lining Case Study - Upper Rouge Tunnel Project Limy Shale – Fissile (disking) behavior; 30 ft ID

Notes: • To be cost effective of employing a TBM, the length of the tunnel shall be roughly greater than 1.2 miles (2 Kilometer) long • Generally speaking, the cost of a two-pass lining is lower than the onepass segmental lining

2. Factors that drive the use of segmental lining URT case study • •

Original design – Rock dowel and steel rib as initial ground support with CIP concrete final lining Final design – Revised to one-pass or two-pass segmental lining

3

URT – Shallow cover tunnel in Antrim Shale

4. Rationale for choosing one or the other

3. Tunnel alignments • Horizontal – public right of way; geological

One-pass Segment Advantages:

features; 3rd party issues (transportation and muck handling); distance/function

• • •

• Vertical – cover above tunnel crown; 1 to 2 D, pending on ground condition (design issue); function/operation; geological condition

• •

• Radius of curvature of tunnel Diameter of TBM (D) in meters

Smaller excavation diameter Better concrete quality control (precast) May shorten tunnel total construction schedule (but longer mucking duration) Robust – designed for the worst ground condition Less water treatment required (TSS &Ph)

Minimum Radius of curvature in meters

10

400

7

300

4

80

4. Rationale for choosing one or the other

4. Rationale for choosing one or the other

One-pass Segment Disadvantages

One-pass Segment Disadvantages

• • • • •



Higher cost Tight alignment tolerance/control Difficult to repair Difficult interface design and construction Relatively delayed initial support

• • • • •



Quality of installed bolted/gasketed system Tight segment construction & installation tolerance Need to patch bolt pockets and caulking groves (water/wastewater tunnel) Segment flotation during construction Bolt corrosion (water/wastewater tunnel) Design consideration for internal pressure at gaskets (water/wastewater tunnel) Maintenance

Gasket Precast Segment

Radial Joint Detail

4

4. Rationale for choosing one or the other Two-pass Segment Advantages

Two-pass Segment Advantages •

Pattern Dowels

Less stringent construction tolerance; easy for erecting Easier alignment control Highest TBM production rate

• •

4. Rationale for choosing one or the other







Two-pass - Dowels & Rib



High cost if not using “junk” segment Design the worst ground condition for initial support ($) Few, about four (4) in the US, contractors have done junk segment The largest expanded segment in the US is NBC of 26’ ID tunnel Required more contact grout



5. Types of precast segmental linings/Material

Two-pass Rib only

2 1.8 1.6 1.4 1.2 1 0.8

Two-pass Segment Disadvantages •

URT South Tunnel Cost Analysis

One-pass segment

Robust initial ground support Easier alignment control Less joints in final lining Easier interface design and construction

Two-pass ExpandedSegment

• • • •

4. Rationale for choosing one or the other

South Tunnel Baseline - 30-ft ID; 19,000 ft long; 20% steel rib + 6” shotcrete ; 20% 16’ pattern dowels with mesh; 12’ dowels and mesh for the rest of the tunnel

5. Types of precast segmental linings/Material • Selection of segment type to suit the tunnel usage, ground condition, construction methods, and cost. • For present time in US, concrete segment is the most popular one (highest compression capacity, but is the heaviest for handling)

(RC/FRC)

Cross Section of Segments

5

5. Types of precast segmental linings/Material

5. Types of precast segmental linings/Material • As light (thin) as possible • High strength concrete (> 6,000 psi) to accommodate shear force • Low W/C ration (>0.4; 0.35 is normal); Adding silica film or fly ash, as cementitious replacement to Portland cement, to reduce permeability; however, with the consequence of excessive spalling in a fire event • Small rebar cover to avoid spalling and chipping during erection (1 to 11/2” cover) • Consider fiber to prevent cracking

Segment Components

5. Types of precast segmental

5. Types of precast segmental linings/Material

linings/Material

Spalling of joints

Welding a segment cage for a large diameter highway tunnel

Cracking and splaaing during erection

6. Geometries

Cross Section

Segment cage for a large diameter highway tunnel

6. Geometries

Side View

K segment inserted in radial direction

K segment inserted in longitudinal direction

6

6. Geometries • αr = θk /2 + θω • θω - determined based on

6. Geometries • αl - based on construction consideration; the length of the shield; and the length of the segment; normally from 17 -20o • αl = 0o

workability and design to transmit thrust; as small as possible; it is about 2 -5o; 3o is recommended

Segment inserted in radial direction

6. Geometries • Shape and width of segments normally based on handling and transportation considerations

Section a-a

Segment inserted in longitudinal direction

6. Geometries Shape and dimensions of steel segment (in mm)

• The thickness is normally determined from design requirements

6. Geometries Shape and dimensions of concrete segment (in mm)

6. Geometries Case 1 - key segment inserted in radial direction

Thickness is based on security load case

7

6. Geometries

6. Geometries Case 2 - key segment inserted in longitudinal direction

6. Geometries

6. Geometries •

6. Geometries

Tapered ring – to accommodate curved tunnel alignment/or alignment adjustment

6. Geometries

8

7. Segment Joints

7. Segment Joints

Circumferential Joints Radial Joints

Curve bolt (out of date)

Dowell

7. Segment Joints

Straight bolt and sleeve

Shear Cone

7. Segment Joints

Connection by drifting

Dowell

Radial joint by bolt and sleeve Circumferential joint by dowel

7. Segment Joints

Radial joint by rod

7. Segment Joints

Circumferential joint by cone

9

7. Segment Joints – Gasket Seal

7. Segment Joints – Gasket Seal

T configuration testing

Elastomeric gasket Typical pressure curve for a given displacement

7. Segment Joints – Gasket Seal •

Typical load deflection curve

8. Segment Construction Tolerance

The selected gasket must meet watertightness rating and tolerance specified

8. Segment Construction Tolerance

8. Segment Construction Tolerance

10

8. Segment Construction Tolerance

8. Segment Construction Tolerance

Sample ring built (normally without gasket)

9. Design/Modeling – Beam/FEM

9. Design/Modeling Radial joint model: • • • • • •

Empirical formula by Allan Muir-Wood (1975) homogenous rigid ring by reducing the bending I = IS + In • (4 / m)² I … reduced area-wise moment IS … area-wise moment of the force transmission zone In … area-wise moment of complete section m … number of segments (small key-segment not counted)

Other joint simulations:

Solid beam with full or partial bending rigidity

Ring with hinges

Ring with shear and rotational springs

9. Design/Modeling

• •

Radial – Janssen (1983) Circumferential - Gijsbers and Hordijk (1997)

9. Design/Modeling

Design Loads: • • • • •

Ground load – soil, long term rock, rock wedge… Hydrostatic pressure Functional – vehicular (highway, transit), surge (water/wastewater), insert support (M&E, Utility…) Contact grouting pressure - > 30 psi net (offset the groundwater pressure) Construction loads – stacking, lifting/transportation, jacking, gasket compression…

Moment distribution because of the joints Stacking load

11

9. Design/Modeling – construction loads

9. Design/Modeling – construction loads

Lift/Grout socket

Lifting load Contact grout

9. Design/Modeling –

9. Design/Modeling – construction loads

construction loads

Ring erector

Jacking load

10. Construction Considerations –

9. Design/Modeling – construction loads

Work Shaft •

Work shafts – shaft size to accommodate TBM access and exist, specifically considering the shield size and its interaction with vent duct, convey belt, and other utilities in the shaft during construction.

EPDM (Ethylene Propylene Diene Monomer) gasket compression

12

10. Construction Considerations

10. Construction Considerations – Work Shaft Length of tail section



Work Shaft Length (L) to Diameter (D) Ratio

L/D

Cutter outside diameter (mm)

10. Construction Considerations –

10. Construction Considerations – lining match mark

lining placement Lifting lug

Match Marks

10. Construction Considerations



Contact Grout

Segment ID

10. Construction Considerations



Contact Grout

Grouting Criteria – by refusal or by volume Removable Lifting Insert Grout Tube

Non Return Valve

13

10. Construction Considerations



Tunnel Break-in

10. Construction Considerations



Tunnel Break-in (launching pit and cradle)

Mostly required in soft ground tunnelling

10. Construction Considerations – Break-in, TBM Jacking Frame

10. Construction Considerations – Break-in, TBM Jacking Frame

Front/Middle/ Tail shields with Jacking Frame

TBM Tail Initial Lining

10. Construction Considerations



Tunnel Break-in (w/o ground modification)

10. Construction Considerations



Tunnel Break-out

Mostly required in soft ground tunnelling

14

10. Construction Considerations



Tunnel Break-out

10. Construction Considerations



Tunnel Break-out

Receiving Pit

10. Construction Considerations



Tunnel Break-out

10. Construction Considerations Tunnel Break-out

10. Construction Considerations



Tunnel Break-out



10. Construction Considerations



Tunnel Break-out (w/o ground modification)

15

10. Construction Considerations



Tunnel Break-out (w/o ground modification)

10. Construction Considerations • Obstructions – headache to the shield tunneling in soft ground; identified and removed as soon as possible or baselined

• Contract documents • Specifications – GC; DRB, VECP, EBD, Division 1, technical specifications, measurement and payment • Drawings • GBR – baseline for DSC • GDR • Alternative Bid concept

11. Reference 1. 2. 3. 4. 5.

6. 7. 8. 9.

Design Philosophy of Concrete Linings for tunnels in soft soils by C.B.M. Blom, 2002. Gijsberg, F.B.J., Hordijk, D.A., 1997, “Experimenteel onderzoek naar het afschuifgedrag von ringvoegen”,TNO-rapport COB K111 ITA Guidelines for the Design of Tunnels, in Tunnelling and Underground Space Technology, 1988 ITA Guidelines for the Design of Shield Tunnel Lining, in Tunnelling and Underground Space Technology, 2000 Janssen, P., 1983, "Tragverhalten von Tunnelausbauten mit Gelenktübbings", Report-No. 83-41 University of Department of civil engineering, Institute for structural analysis. Japan Society of Civil Engineer 1996. Japanese Standard for Shield Tunneling. Muir Wood, A.M., 1975, "The circular tunnel in elastic ground", Géotechnique 25(1) Tunnel Boring Machines, Trends in Design & Construction of Mechanized Tunnelling. 1996 Specification and Guidelines for the use of Specialist Products in Mechanized Tunnelling (TBM) in Soft Ground and Hard Rock, EFNARC, April 2005.

Q and A [email protected]

16

View more...

Comments

Copyright ©2017 KUPDF Inc.
SUPPORT KUPDF