NARRATVE REPORT [REPORT SUBTITLE]
Republic of the Philippines
CARIG CAMPUS COLLEGE
of ENGINEERING – CIVIL CIVIL ENGINEERING DEPARTMENT
TABLE OF CONTENTS I. II. III. IV. V. VI.
TITLE PAGE TABLE OF CONTENTS DEDICATION ACKNOWLEDGEMENT ACKNOWLEDGEMENT INTRODUCTION COMPANY PROFILE PULSAR CONSTRUCTION HISTORY PULSAR VISION AND MISSION PULSAR ORAGANIZATION CHART VII. NARRATIVE REPORT DAILY ACCOMPLISHMENT REPORT NARRATIVE REPORT ON WEEKLY ACTIVITIES LEARNINGS VIII. APPENDICES APPENDICES EVALUATION SHEET CERTIFICATE OF On-the-Job-Training On-the-Job-Training DAILY TIME RECORD LETTERS, WAIVER AND MEMORANDUM OF AGREEMENT
Republic of the Philippines
CARIG CAMPUS COLLEGE
of ENGINEERING – CIVIL ENGINEERING DEPARTMENT
DEDICATION I dedicate my narrative report to my family, my ever-supporting parents, thank you for your financiaI support, trust, love and care for me.
Also dedicate this to our respective adviser Engr. Stiler and to Engr. John Michael B. Casibang (Chairmain of Civil Engineering). I’ve learned a lot from you on how to perform the standard ways, how to be a responsible OJT student trainee, and for the assurance of the document needed for the OJT.
To Pulsar Construction, all supervising and staff. To my co trainees and above all to almighty God, thank you for the guidance, strength, power of mind, protection, and skills and for giving me a healthy life.
Republic of the Philippines
CARIG CAMPUS COLLEGE
of ENGINEERING – CIVIL ENGINEERING DEPARTMENT
ACKNOWLEDGEMENT I want to give an overwhelming thanks and acknowledgement to all people who helped me in accomplishing my On-the Job Training and with all gratefulness.
To the Lord Almighty for the wealth and vitality and for enlightens me to pursue my study.
Republic of the Philippines
CARIG CAMPUS COLLEGE
of ENGINEERING – CIVIL ENGINEERING DEPARTMENT
INTRODUCTION On the job Training are part of a college curriculum that aims to train and orient students about the work and their future career. OJT is very important not only to teach students their chosen career but to show students the reality about working.
As one of the 4th year students that have undertaken the course in Civil Engineering.it was a very special opportunity for me to put my academic training experience into a real world application. The course has provided me the venue to further enhance and broaden my knowledge and competency as a civil engineering student and for future career objectives after graduation. As a student trainee, I have been able to ta ke advantage of the tools and skills I have been equipped by my intensive academic formation in the university, to be competent enough in pursuing different opportunities available in the outside world.
Republic of the Philippines
CARIG CAMPUS COLLEGE
of ENGINEERING – CIVIL ENGINEERING DEPARTMENT
DAILY ACCOMPLISHMENT REPORT DAY 1: Date: June 19, 2017 Time in: 7:00 am Time out: 5:00pm PROJECT TITLE: Road Widening LOCATION: Larion, Tuguegarao City SUPERVISOR: Engr. Myrda Matalang
ACTIVITIES: Orientation Base Preparation Measuring of Retaining Wall
Description of Activities: This is the first day of our On-The-Job Training (OJT). Before we assigned to our designated sites, Engr. Uno (Head bababa) oriented us about the company rules and regulations. Even the Do’s and Don’ts are discussed to. He also introduced us to our supervisor Engr. Myrda Matalang. My group was assigned at Larion Widening. After the introduction, to start with our work, Engr. Myrda oriented us about the project. She tasked us to measure the height and length of the finish retaining. After the She discussed about the design of the retaining wall. In the afternoon we observed road base preparation at Larion near four diamond resort. Our first day was very good start and we was motivated. Lesson learn:
We learned how to design a retaining wall
Republic of the Philippines
CARIG CAMPUS COLLEGE
of ENGINEERING – CIVIL ENGINEERING DEPARTMENT
DAILY ACCOMPLISHMENT REPORT
DAY 2: Date: June 20, 2017 Time in: 7:00 am Time out: 5:00pm PROJECT TITLE: Road Widening LOCATION: Larion, Tuguegarao City SUPERVISOR: Engr. Myrda Matalang
ACTIVITIES: Compaction FDT (Field Density Test) Concrete Pouring
Description of Activities: DPWH engineers arrived at the site for inspection. Before concrete pouring, we conducted Field Density Test (FDT). FDT to determine the moisture content of the soil before pouring. As we perform FDT one DPWH engineer discussed us about FDT, and it’s important, He also lectured us about the different equipment and tools used in road constructions. Concrete pouring started at 10:00 AM. Engr. Myrda assigned us to ge t some concrete sample, Samples were placed in a beam mold. The beam mold is used to prepare concrete specimen for flexural testing of concrete. Available in a 20 in. length with a cross-section of 6x6 inches. We also helped in spraying curing compound. We also help Engr. Mydra to measure the finished widening and record the length and station for their accomplishment report.
Lesson learned:
The process of road widening How to performed Field Density Test How to performed and get concrete sample
Republic of the Philippines
CARIG CAMPUS COLLEGE
of ENGINEERING – CIVIL ENGINEERING DEPARTMENT
DAILY ACCOMPLISHMENT REPORT
DAY 3: Date: June 21, 2017 Time in: 7:00 am Time out: 5:00pm PROJECT TITLE: Road Widening LOCATION: Larion, Tuguegarao City SUPERVISOR: Engr. Myrda Matalang
ACTIVITIES: Continuation of Concrete Pouring
FDT Booming Spraying Curing Compound
Description of Activities: We continued concrete pouring located at larion near camella tuguegarao. We measure the spacing of tie bars and dowels. As the process of road widening we conducted first FDT but we only get one sample. Then during the concrete pouring we get concrete samples. We also helped in spraying cuing compound. Lesson learned:
The process of road widening How to performed Field Density Test How to performed and get concrete sample
Republic of the Philippines
CARIG CAMPUS COLLEGE
of ENGINEERING – CIVIL ENGINEERING DEPARTMENT
DAILY ACCOMPLISHMENT REPORT DAY 4: Date: June 22, 2017 Time in: 7:00 am Time out: 5:00pm PROJECT TITLE: Road Widening LOCATION: Larion, Tuguegarao City SUPERVISOR: Engr. Myrda Matalang
ACTIVITIES: Continuation of Concrete Pouring
FDT Booming Spraying Curing Compound
Description of Activities: Lesson learned:
The process of road widening How to performed Field Density Test How to performed and get concrete sample
Republic of the Philippines
CARIG CAMPUS COLLEGE
of ENGINEERING – CIVIL ENGINEERING DEPARTMENT
DAILY ACCOMPLISHMENT REPORT
DAY 5: Date: June 23, 2017 Time in: 7:00 am Time out: 5:00pm PROJECT TITLE: Road Widening LOCATION: Larion, Tuguegarao City SUPERVISOR: Engr. Myrda Matalang
ACTIVITIES: Continuation of Concrete Pouring
FDT Booming Spraying Curing Compound
Description of Activities:
Lesson learned:
The process of road widening How to performed Field Density Test How to performed and get concrete sample
DAILY ACCOMPLISHMENT REPORT
Republic of the Philippines
CARIG CAMPUS COLLEGE
of ENGINEERING – CIVIL ENGINEERING DEPARTMENT
DAY 6: Date: June 24, 2017 Time in: 7:00 am Time out: 5:00pm PROJECT TITLE: Road Widening LOCATION: Larion, Tuguegarao City SUPERVISOR: Engr. Myrda Matalang
ACTIVITIES: Continuation of Concrete Pouring
FDT Booming Spraying Curing Compound
Description of Activities: Lesson learned:
The process of road widening How to performed Field Density Test How to performed and get concrete sample
Republic of the Philippines
CARIG CAMPUS COLLEGE
of ENGINEERING – CIVIL ENGINEERING DEPARTMENT
DAILY WORK ACTIVITIES WEEK 1 DAY
DATE
DAILY ACTIVITIES
NO OF WORKING HOURS
MONDAY
JUNE 19,2017
Road Base preparation (Compaction)
9
TUESDAY
JUNE 20,2017
WEDNESDAY
JUNE 21,2017
THURSDAY
JUNE 22,2017
FRIDAY
JUNE 23,2017
SATURDAY
JUNE 24,20177
Road Base preparation and installation of forms
Week 1 The Pulsar Construction assigned our group in Camasi, Penablanca which the project is road widening. Engr. Myrda and Engr. Rose Ann are the project supervisors, they orient us with the project which there are different sections; the bridge in Camasi, the road widening in Caggay and in Larion. Our group was assigned in Caggay for the whole week. The activities in our first day is the preparation for road widening. We observed how they prepare for the road. and We measure the depth or the road which is 0.4 meters. The road consist of 0.3 m concrete and 0.1 m item 201( ). There are some problems in the project which is an existing road and drainage. But the slightly serious problem is the water line system beneath the road. More than 8 water pipes has been damaged when they are excavating, 1 main line was damaged and in this situation Engr. Rose Ann give us some tips on how to manage this problems. Our second day was tiring yet exciting. Engr. Rose Ann and Engr. Myrda let our group observed the pouring concrete in the road widening of Larion.
Republic of the Philippines
CARIG CAMPUS COLLEGE
of ENGINEERING – CIVIL ENGINEERING DEPARTMENT
DAILY ACCOMPLISHMENT REPORT DAY 1: Date: June 26, 2017 Time in: 7:00 am Time out: 5:00pm PROJECT TITLE: Ballroom/Hotel SUPERVISOR: Engr. John Jarvis Guzman
LOCATION:
Pulsar Hotel, Caggay, Tuguegarao City
ACTIVITIES: Orientation Removing concrete sample Site inspection
Description of Activities: My group were assigned at Pulsar Hotel, Caggay, Tuguegarao City for six days. The project is construction of ballroom and Hotel owned by Jojo La sam Lara. Engr. John Jarvis Guzman is our supervisor this week. He oriented us ab out the project and showed the architectural and structural plan of the project. Before we went to the site for visitation, he assigned us to removed the concrete sample from the cylindrical mold. T hen we submerged the sample into the water for curing. In the afternoon Engr. Jarvis accompanied us to the site for site inspection. We asked question about what observed at the site, we learned a lot that day. Lesson Learned:
Republic of the Philippines
CARIG CAMPUS COLLEGE
of ENGINEERING – CIVIL ENGINEERING DEPARTMENT
DAILY ACCOMPLISHMENT REPORT DAY 2: Date: June 27, 2017 Time in: 7:00 am Time out: 5:00pm PROJECT TITLE: Ballroom/Hotel SUPERVISOR: Engr. John Jarvis Guzman
LOCATION:
Pulsar Hotel, Caggay, Tuguegarao City
ACTIVITIES: Installation of tire wire Mearusing slab Estimation of concrete
Description of Activities: Engr. Jarvis assigned us to compute the volume of concrete to the un fineshed slap at ballroom mezanime. We do it in actual measurement, after we measured slab we estimated how many cubic meter to be pour at that area. We noticed that some of the reinforcement were not tie, so we helped the workers. And in the afternoon we joined their meeting. Lesson Learned:
Republic of the Philippines
CARIG CAMPUS COLLEGE
of ENGINEERING – CIVIL ENGINEERING DEPARTMENT
DAILY ACCOMPLISHMENT REPORT DAY 3: Date: June 28, 2017 Time in: 7:00 am Time out: 5:00pm PROJECT TITLE: Ballroom/Hotel SUPERVISOR: Engr. John Jarvis Guzman
LOCATION:
Pulsar Hotel, Caggay, Tuguegarao City
ACTIVITIES: Estimation
Description of Activities:
Engr. Jessi Mercader assigned us to compute the number of stirrup at hotel level 6. Engr. Jarvis
Republic of the Philippines
CARIG CAMPUS COLLEGE
of ENGINEERING – CIVIL ENGINEERING DEPARTMENT
DAILY WORK ACTIVITIES WEEK 2 DAY
DATE
DAILY ACTIVITIES
NO OF WORKING HOURS
MONDAY
JUNE 26,2017
Road Base preparation (Compaction )
9
TUESDAY
JUNE 27,2017
WEDNESDAY
JUNE 28,2017
THURSDAY
JUNE 29,2017
FRIDAY
JUNE 30,2017
SATURDAY
JULY 01,20177
Road Base preparation and installation of forms
Republic of the Philippines
CARIG CAMPUS COLLEGE
of ENGINEERING – CIVIL ENGINEERING DEPARTMENT
DAILY ACCOMPLISHMENT REPORT
DAY 13 DATE:
JULY 03, 2017
TIME IN:
7:00 AM
TIME OUT:
7:00 PM
SUPERVISOR: Engr. John Jarvis Guzman LOCATION:
Pulsar Hotel, Caggay, Tuguegarao City
ACTIVITIES:
Orientation
DESCRIPTION OF ACTIVITIES
Republic of the Philippines
CARIG CAMPUS COLLEGE
of ENGINEERING – CIVIL ENGINEERING DEPARTMENT
DAILY ACCOMPLISHMENT REPORT
DAY 14 DATE:
JULY 04, 2017
TIME IN:
7:00 AM
TIME OUT:
5:00 PM
SUPERVISOR: Engr. John Jarvis Guzman LOCATION:
Pulsar Hotel, Caggay, Tuguegarao City
ACTIVITIES:
Orientation
DESCRIPTION OF ACTIVITIES
Republic of the Philippines
CARIG CAMPUS COLLEGE
of ENGINEERING – CIVIL ENGINEERING DEPARTMENT
DAILY ACCOMPLISHMENT REPORT
DAY 15 DATE:
JULY 05, 2017
TIME IN:
7:00 AM
TIME OUT:
5:00 PM
SUPERVISOR: Engr. John Jarvis Guzman LOCATION:
Pulsar Hotel, Caggay, Tuguegarao City
ACTIVITIES:
Orientation
DESCRIPTION OF ACTIVITIES
Republic of the Philippines
CARIG CAMPUS COLLEGE
of ENGINEERING – CIVIL ENGINEERING DEPARTMENT
DAILY ACCOMPLISHMENT REPORT
DAY 16 DATE:
JULY 06, 2017
TIME IN:
7:00 AM
TIME OUT:
5:00 PM
SUPERVISOR: Engr. John Jarvis Guzman LOCATION:
Pulsar Hotel, Caggay, Tuguegarao City
ACTIVITIES:
Orientation
DESCRIPTION OF ACTIVITIES
Republic of the Philippines
CARIG CAMPUS COLLEGE
of ENGINEERING – CIVIL ENGINEERING DEPARTMENT
DAILY ACCOMPLISHMENT REPORT
DAY 17 DATE:
JULY 07, 2017
TIME IN:
7:00 AM
TIME OUT:
5:00 PM
SUPERVISOR: Engr. John Jarvis Guzman LOCATION:
Pulsar Hotel, Caggay, Tuguegarao City
ACTIVITIES:
Orientation
DESCRIPTION OF ACTIVITIES
Republic of the Philippines
CARIG CAMPUS COLLEGE
of ENGINEERING – CIVIL ENGINEERING DEPARTMENT
DAILY ACCOMPLISHMENT REPORT
DAY 18 DATE:
JULY 08, 2017
TIME IN:
7:00 AM
TIME OUT:
5:00 PM
SUPERVISOR: Engr. John Jarvis Guzman LOCATION:
Pulsar Hotel, Caggay, Tuguegarao City
ACTIVITIES:
Orientation
DESCRIPTION OF ACTIVITIES
Republic of the Philippines
CARIG CAMPUS COLLEGE
of ENGINEERING – CIVIL ENGINEERING DEPARTMENT
DAILY WORK ACTIVITIES WEEK 3 DAY
DATE
MONDAY
JULY 03,2017
TUESDAY
JULY 04,2017
WEDNESDAY
JULY 05,2017
THURSDAY
JULY 06,2017
FRIDAY
JULY 07,2017
SATURDAY
JULY 08,20177
DAILY ACTIVITIES
NO OF WORKING HOURS 9
Republic of the Philippines
CARIG CAMPUS COLLEGE
of ENGINEERING – CIVIL ENGINEERING DEPARTMENT
DAILY ACCOMPLISHMENT REPORT
DAY 19 DATE:
JULY 10, 2017
TIME IN:
7:00 AM
TIME OUT:
5:00 PM
SUPERVISOR: Engr. Marlon Engr. Ed Visaya LOCATION:
Namabbalan Sur, Tuguegarao City
ACTIVITIES:
Orientation
DESCRIPTION OF ACTIVITIES
Republic of the Philippines
CARIG CAMPUS COLLEGE
of ENGINEERING – CIVIL ENGINEERING DEPARTMENT
DAILY ACCOMPLISHMENT REPORT
DAY 20 DATE:
JULY 11, 2017
TIME IN:
7:00 AM
TIME OUT:
5:00 PM
SUPERVISOR: Engr. Marlon Engr. Ed Visaya LOCATION:
Namabbalan Sur, Tuguegarao City
ACTIVITIES:
Orientation
DESCRIPTION OF ACTIVITIES
Republic of the Philippines
CARIG CAMPUS COLLEGE
of ENGINEERING – CIVIL ENGINEERING DEPARTMENT
DAILY ACCOMPLISHMENT REPORT
DAY 21 DATE:
JULY 12, 2017
TIME IN:
7:00 AM
TIME OUT:
5:00 PM
SUPERVISOR: Engr. Marlon Engr. Ed Visaya LOCATION:
Namabbalan Sur, Tuguegarao City
ACTIVITIES:
Orientation
DESCRIPTION OF ACTIVITIES
Republic of the Philippines
CARIG CAMPUS COLLEGE
of ENGINEERING – CIVIL ENGINEERING DEPARTMENT
DAILY WORK ACTIVITIES WEEK 4 DAY
DATE
DAILY ACTIVITIES
NO OF WORKING HOURS
MONDAY
JULY 10,2017
Road Base preparation (Compaction)
9
TUESDAY
JULY 11,2017
WEDNESDAY
JULY 12,2017
THURSDAY
JULY 13,2017
FRIDAY
JULY 14,2017
SATURDAY
JULY 15,20177
Road Base preparation and installation of forms