PROPOSAL FOR BUILDING A HOME +/- 350 sqm

Prepared Prepared by Ngara Ngara Property Property Develop Developments ments

Plan 350 sq sqm House

Project Plan TIME-LINE IN WEEKS TASK

Foundation Ground Floor 1st Floor Slab 1st Floor Roof Plastering Rhinolite Boundary Wall Tiling Cladding Stone Cladding Plumbing Electrical Painting Kitchen & BIC's Paving Yard preparation

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

Cost Overview Start up costs House design and approval

R 23 000

NHBRC Enrolment

R 18 500 R 41 500

Foundation Superstructure

R 97 945 R 616 500 R 714 445

Finishes

R 560 000

Labour Cost

R 546 000

Equipment Hire

Total Building Cost

R 30 000

R 1 891 945

Labour Cost WORK DETAIL COST

COST

Procurement Management Fee

R 30 000

SECTION A: FOUNDATION

R 44 500

SECTION B: GROUND FLOOR

R 55 000

SECTION C: SLAB

R 22 000

SECTION D: FIRST FLOOR

R 47 000

SECTION E: BOUNDARY WALL

R 55 000

SECTION F: PLASTERING (including screed)

R 65 000

TOTAL SUPERSTRUCTURE

R 318 500

SECTION G: FINISHES Ceiling Installation

R 12 000

Rhinoli Rhinolite te Ceiling Ceiling

R 21 000

Rhinoli Rhinolite te Walls Walls

R 30 000

Installation of doors and cornices Skirting @ R28/m

R 9 000 12000

Waterproofing (Labour & Material)

R 12 000

Plumbing

R 32 000

Electrical

R 32 000

Tiling

R 36 000

Painting

R 32 000

FINISHES TOTAL

R 228 000

TOTAL LABOUR COST

R 546 500

Indicative Material Costs Foundation

R 97 945

Superstructure

R 616 500

Kitchens & BIC's

R 150 000

Other Finishes

R 410 000

Total Materials

R 1 277 445

Unit

Quantity

Unit Price

Total

GENERAL FINISHES Tiles & Carpets

sqm

460

R 200

R 92 000

Vanities

Each

3

R 7 500

R 22 500

Light Fittings

Set

1

R 40 000

R 40 000

Bathroom Fittings

Set

4

R 900

R 3 600

Paint

20 litre drum

40

R 900

R 36 000

Balustrades (Mild Steel)

set

1

R 50 000

R 50 000

Main entrance door

Each

1

R 7 000

R 7 000

Doors

Each

13

R 950

R 12 350

Door handles & Locks

Each

13

R 600

R 7 800

Hardware

Set

1

R 15 000

R 15 000

Skirting and Cornices

set

2

R 15 000

R 30 000

Sub-total

R 316 250

PLUMBING FINISHES Basins

Each

5

R 800

R 4 000

Bath Tubs

Each

2

R 1 800

R 3 600

Showers

Each

3

R 8 000

R 24 000

Geysers & Trays

set

2

R 5 500

R 11 000

Mixers

Each

9

R 1 200

R 10 800

Toilets

Each

4

R 1 500

R 6 000

Sub-total

R 59 400

KITCHEN, BIC & GARDEN FINISHES Kitchen Bedroom Cupboards

1

R 90 000

R 90 000

4.5

R 14 000

R 63 000

Paving

sqm

120

R 150

R 18 000

Grass

sqm

225

R 60

R 13 500

Sub-total

R 184 500

TOTAL FINISHES COST

R 560 150

Start-Up Cost Drawing up plans & approval

R 23 000

NHBRC Enrolment

R 17 000

30,000 Bricks

R 27 600

20 Cubes 20MPA Concrete

R 19 000

20 Cubes 25MPA Concrete

R 20 500

DPC Re-inforcement

R 3 500 R 14 000

Pesticide

R 1 200

Brick Force

R 1 450

Cement 100 Bags

R 7 500

Equipment Hire

R 6 000

Total Material Costs Progress Payment for Foundation Total Start Up Costs

R 140 750 R 67 000 R 207 750

Progress Payments Schedule STAGE

% PAYMENT

Foundation

10

1st Floor Slab

23

Roof Level

35

Roofing and Plastering

50

Finishes

100

Contact Details Allen Chimhandamba Chimhandamba Managing Member E-mail: [email protected] Cell: 082 775 0699