NFPA 20: 2013 to 2016 Major Changes PENTAIR FIRE PUMP TRAINING June 18-19, 2015

ENGINEERED SOLUTIONS

NFPA 20: 2013 to 2016 Major Changes • Chapter 3 – Definitions

– Added definitions for churn, discharge pressure, net pressure, peak load, rated pressure, and suction pressure – Added definition for multistage multiport pump • Chapter 4 – General Requirements

– Added requirements for multistage multiport pumps: • Defined bypass location • Defined discharge piping • Each discharge port shall have its own individual sensing line to the controller. • Defined circulation relief valve installation

– Circulation Relief Valve – Added clarification for minimum setting of circulation relief valve for variable speed pressure limiting controller. – Defined Hazard Group 1 for electric fire pump room in sprinklered buildings – Defined emergency lighting intensity and duration. – Changed low suction throttling valve to suction pressure regulating valve

PENTAIR

ENGINEERED SOLUTIONS DISTRIBUTOR PRESENTATION, NFPA 2015

2

NFPA 20: 2013 to 2016 Major Changes • Chapter 4 – General Requirements

– Defined pressure relief valve setting for variable speed pressure limiting control. – Added requirement that circulation relief valve actuate below the set point of the pressure relief valve when piped back to suction. – Added requirement for visual indicator and audible alarm at controller for high cooling water temperature signal for diesel driven pump. – Added requirement that all pumps that are part of series fire pump unit be located in same fire pump room unless following conditions are met: • Each pump shall be arranged so that all pumps operating in series can be manually stopped or started from all pump rooms housing the series fire pumps. • The suction and discharge pressures from all pumps operating in series shall be displayed in all pump rooms housing the series fire pumps. • The alarms and signals shall be annunciated in the other pump rooms for all pumps that are a part of the series fire pump unit • The interconnect control wiring between the controllers in different pump rooms shall comply with 4.20.2.7 and 4.20.2.8. • A pump room communication system

PENTAIR

ENGINEERED SOLUTIONS DISTRIBUTOR PRESENTATION, NFPA 2015

3

NFPA 20: 2013 to 2016 Major Changes • Chapter 4 – General Requirements

– No more than 2 variable speed pumps shall be allowed to operate in series as part of a series fire pump unit. – Added requirement that retroactive installation of backflow prevention device shall not reduce the suction pressure below what the standard permits and shall not result in a discharge pressure that does not meet maximum system demand. – Clarified wording for seismic loading requirements for pumps, drivers, controllers, and appurtenances. Requires seismic protection of any appurtenances that are required for post earthquake operation of the fire pump. – Removed language for break tank requirements and refers to NFPA 22. • Chapter 5 – Fire Pumps for High Rise Buildings

– Change auxiliary power requirement to either reliable emergency power source or a diesel engine back up fire pump

PENTAIR

ENGINEERED SOLUTIONS DISTRIBUTOR PRESENTATION, NFPA 2015

4

NFPA 20: 2013 to 2016 Major Changes • Chapter 6 – Centrifugal Pumps

– Added requirements for multistage multiport pumps so each discharge port shall meet same hydraulic requirements of a single discharge pump. • Chapter 8 – Positive Displacement pumps

– Changed requirements for piping of relief valves back to suction or tank return line. • Chapter 9 – Electric Drive for Pumps

– Added single phase motors NEMA Design N or L standards. – Updated locked rotor current table and added tables for single phase and 380V at 50Hz. – Added requirement that single phase motor shall only be used in across the line applications. – Added requirement that circuit breakers shall have supervision by remote monitoring.

PENTAIR

ENGINEERED SOLUTIONS DISTRIBUTOR PRESENTATION, NFPA 2015

5

NFPA 20: 2013 to 2016 Major Changes • Chapter 10 – Electric Drive Controllers and Accessories

– For multistage multiport pumps requires dedicated pressure actuated switch or pressure sensor and a dedicated pressure recorder for each discharge port as part of controller. – Added requirements for controller monitoring of electronic pressure sensor conditions. – Added requirement for controller automatic no flow testing as required by NFPA 25 – Defined conditions for automatic shutdown after automatic start. • Chapter 11 – Diesel Engine Drive

– Means provided for signaling high cooling water temperature with a visible and audible alarm on the controller. Means provided on engine for testing the operation of the high cooling water temperature signal to the controller. – Added requirement that charging voltages of chargers are coordinated to meet requirements of specific batteries installed. – Added requirement for active fuel management return connection in tank

PENTAIR

ENGINEERED SOLUTIONS DISTRIBUTOR PRESENTATION, NFPA 2015

6

NFPA 20: 2013 to 2016 Major Changes • Chapter 11 – Diesel Engine Drive

– Vent outlet shall terminate at least 12 ft above ground level. – Vent piping from interstitial space of double wall tanks shall not be manifolded with vent from primary compartment of tank. – Tank overfill prevention shall be required – Allows for check valve in fuel return line when required by engine manufacturer – Requires that exhaust piping is supported independently of engines flexible exhaust connector. – Added requirements for active fuel maintenance system where provided. • Chapter 12 – Engine Drive Controllers

– For multistage multiport pumps requires dedicated pressure actuated switch or pressure sensor and a dedicated pressure recorder for each discharge port as part of controller. – Added requirements for controller monitoring of electronic pressure sensor conditions. – Added requirement for controller automatic no flow testing as required by NFPA 25 – Defined conditions for automatic shutdown after automatic start.

PENTAIR

ENGINEERED SOLUTIONS DISTRIBUTOR PRESENTATION, NFPA 2015

7

NFPA 20: 2013 to 2016 Major Changes • Chapter 14 – Acceptance Testing, Performance, and Maintenance

– Added requirement that all instrumentation used for measurement be calibrated within +/-1% at a minimum of annually. – Added requirement for certified shop test data for each discharge port of a multistage multiport pump. – Allows for voltage and current readings from controller to be used in lieu of calibrated volt/amp meters if controllers are factory calibrated and adjusted to +/-3% – Fixed outlet flow devices shall be inspected for damage but do not require calibration. – Requirement that each discharge port of multistage multiport pump be tested to this standard. – Revised Annex material to include new acceptance test form which is revised to meet current requirements including variable speed and multi pump operation. • Annex C – Fire Pump Controller Connectivity

– Annex C added for informational purposes – Considerations relative to access of fire pump controllers including access methods, security considerations, use of information, and standardization.