Activation Schedule ............................................................................................. 3 L i s t o f t h e S u p p o r t T e a m o f H U A W E I ............................................................ 3
2.2
Equipment Health Check on CX600 ................................................................. 3
2.3
Add script for 95075 CX-X8-01&02 .................................................................. 4
Rollback Plan .......................................................................................................................... 5
1 Change Overview 1.1
Site Information
AREA : El salvador Country SITE
: CSG, ASG & RSG
Purpose: Configuration of a Pseudo wire 1.2
Change Objective
Deploy a Pseudo Wire Between Different OSPF areas.
2 Certification Preparation 2.1
Certification Schedule
DATE: x/x/x Migration Team and Responsibility
Name
Responsibility
Tel.
Configuration ATN910 CX600 x2 – CX600 x8
2.2.1 List of the Support Team of HUAWEI Name
Responsibility
Tel.
support
2.2
Equipment Health Check on ATN910 – CX600x2 – CX600x8