Welcome to Worley Parsons Project Management Process (WPMP) Training Module 9 – Managing Project Procurement

1

Managing Project Procurement About this training session 

Introduction



Overview of Procurement



Responsibilities for Procurement



Commencing the Procurement Process \Procurement Planning



SmartPlant Materials



Procurement Reports



Procurement Initiation



Procurement Execution



Procurement Close-out

2

Learning Objectives

On completion of this module, you will be able to: 

3

Identify and understand the procurement methodologies and tools available to Project Managers for the management of EPCM projects

Learning Outcomes On completion of this module, you will be able to demonstrate an understanding that: 

Early involvement of the Procurement function in project planning is essential



The project’s procurement strategy and procurement plan must align with the overall project strategy



Clear definition of the objectives of the Procurement Process is critical for the project team

4

Procurement in WorleyParsons

5



Procurement is an integral part of the WorleyParsons’ growth strategy



Procurement shall support the company to compete more successfully as a leading provider of professional services worldwide

Overview of Procurement What is procurement? 

Procurement is the process by which materials, equipment and third-party services are acquired for projects



Key procurement interfaces include:

• • • • • • • • 6

Project Management

Engineering HSE Quality

Cost Estimation Project Controls Construction Management

Legal & Risk

Overview of Procurement What does procurement involve? …the acquisition of materials, equipment or third-party services:

7



At the best possible total cost of ownership



In the right quantity and quality



At the right time



In the right place



For the direct benefit of the customer

Procurement and Capex



The Capital Expenditure (Capex) of a Project can be split into a few elements:

• Engineering and design – approx. 10% of Capex • Procurement: − Materials and equipment – approx. 30 to 45% of Capex − Contracts – approx. 30 to 45% of Capex

• Balance is owners’ costs, insurance, land purchases etc 

8

The above is indicative only and dependent on the type and location of a project. However, on average the Capex element managed by procurement ranges between 60% and 90% of the overall project value

Overview of Procurement What is the role of procurement in a project? 

9

Procurement is the bridge between Engineering (design) and Construction (execution)

Overview of Procurement Procurement is divided into 2 functions 

Materials Management

• Purchasing, Expediting, Materials Control, Coordination of Inspection (liaising with Quality), Traffic/Logistics, Warehousing/ Inventory Control etc

• Legal agreement used is a Purchase Order 

Contracts

• Acquisition and management of third-party services • Legal agreement used is a Contract 

10

Both Purchase Orders and Contracts are written and binding legal agreements between relevant parties to supply either goods or services against agreed conditions

Procurement Executive Directive



To minimise risk exposure, procurement services are usually provided for and on behalf of Customers, in the Customer’s name or “on Customer paper” – this is the company’s preferred position



However, this does not preclude provision of procurement services in WorleyParsons’ name or on “WorleyParsons’ paper” – requires CEO to proceed in any event where additional supplier-related risks and liabilities are assumed (eg warranty obligations, delivery commitments, product liability, etc)



In most instances, procurement services are provided on behalf of the Customer, requiring active interaction with the Customer and their various approvals to proceed

11

EMS Workflows and Procedures 1/2 Contracts 

Contracts services cover the provision of third-party services such as construction labor, inspection services, painting and sand blasting



The provision of contract services is governed by the Contracts Workflow in EMS containing a number of procedures, guidelines, forms and templates



Preferred Terminology:

• ITT = Invitation to Tender • Contract = legal agreement for the provision of services

12

EMS Workflows and Procedures 2/2 Materials Management 

Materials Management includes the purchasing of goods and equipment, subsequent expediting, inspection and receipt.



The provision of Materials Management services is governed by the Materials Workflow in EMS containing a number of procedures, guidelines, forms and templates



Materials Management activities are managed and tracked through SmartPlant Materials, WorleyParsons’ Materials Management system which starts from creation of the requisition through to final material reconciliation on site



Preferred Terminology:

13

• RFQ = Request for Quotation • Purchase Order (PO) = legal agreement for the supply of goods

Overview of Procurement WorleyParsons procurement process Project Procurement Plan Determine procurement requirements

Close- out Activities

Procurement Initiation

Conclude the engagement of the suppliers Record the performance against each order & contract

Identify potential suppliers

Materials Field Administration Activities

Pre-award Activities * Materials Management * Contracts

Field Purchasing Transport/ Logistics Receipt on site Warehousing

Obtain quotations Select the preferred suppliers

Post-award Activities

14

Manage the supplier Administer POs and contracts Manage POs/ contract variation Expediting/ Inspection

Responsibilities for Procurement



As Project Manager, you are responsible for the overall management of procurement activities associated with the project



You are not responsible for the execution of procurement activities That is the responsibility of your Project Procurement Manager



15

To fulfill your responsibilities, you should work closely with the Procurement Manager

Responsibilities for Procurement WorleyParsons’ procurement capability 

Procurement specialists in each region



Detailed procurement procedures, guidelines and associated documentation



Deployment of SmartPlant Materials as the company-wide materials control system to record, track and report on procurement activity



Global supplier database for materials, equipment and services



Global Sourcing initiatives



Supply arrangements with key suppliers

16

Responsibilities for Procurement Procurement resourcing 

Procurement staff managing the Materials Management and Contracts activities usually:

• Work either from a core Procurement group in a key company location or

• Form a part of a dedicated project procurement team 

Procurement activities on the project are usually led by an experienced Project Procurement Manager



Where warehousing staff are required for specific customers or projects, they are usually located on site



Inspection may involve in-house or third-party inspectors, depending on the location of the inspection activities

17

Procurement Process Commencing the procurement process for a project 

Establish exactly what the customer requirements are and what WorleyParsons has committed to do



Establish your procurement team and set out their responsibilities



Procurement to participate in the Project Risk Assessment and ensure that risk mitigation is included in the Procurement Plan to be developed



Procurement to incorporate appropriate flow-down conditions from the Prime contract (the agreement between Customer and WorleyParsons) in the Project Conditions to ensure compliance and alignment (e.g. including customer’s confidentiality requirements, alignment of warranty periods etc.)



Procurement to develop the project procurement procedures, based on EMS but incorporating as appropriate Customer’s requirements (e.g. approval interfaces)



Arrange to have the project set up on SmartPlant Materials

 18

Ensure WBS is established

Procurement Planning Planning 

Planning is at the crux of all project activities



Procurement is no exception



The aim of procurement planning is to:

• Know what needs to be procured, when, where and how • Identify critical long lead items and services • Establish order and consistency in the way the procurement activities are performed

• Understand the risks involved in the project environment and identify mitigating actions  19

The Project Procurement Plan is part of the Project Execution Plan

Procurement & Risk Management



20

Procurement is an integral part of risk management on the project



Develop appropriate procurement/ contracts/ materials management strategies, identifying the various risks (market, forex, local content requirements, taxation and importation issues, logistics complexities, etc. to be managed)



Use EMS procurement procedures to the largest extent, however, recognize Customer requirements in the project specific procedure.



Ensure that the project specific procurement procedures are approved by the customer and shared with the project procurement team



Develop the procurement schedule early, in line with the overall project schedule, resulting in correct priorities to achieve the Required on Site Dates

Procurement Planning What you need to plan for

21

Procurement Planning When planning occurs Identify

1

Evaluate

2

Define

3

Execute

4

Procurement Strategy

Procurement Plan

Materials Management Plan , if required

Contracts Plan , if required

Purchasing and Contracts Initiation

Materials Management Plan, if required Contracts Plan, if required Materials Field Administration Materials Management and Contracts Close-out

22

Operate

Procurement Planning Project Procurement Strategy



Project Procurement Strategy (PPS) is the:

• Process for identifying and documenting the procurement opportunities applicable to the project

• First step in developing the Project Procurement Plan 

Typically, the PPS is first developed during the scoping stages of a project



Sometimes the customer provides the initial procurement strategy for further development in the Project Procurement Plan

23

Procurement Planning Project Procurement Strategy

During the development of the PPS, the following factors need to be considered: 

Purchasing activities can involve long lead times



Certain materials and equipment may be particularly critical to a project’s success



Purchasing activities usually involve multiple countries (infrastructure and logistics, local legislation etc.)



Market and technology developments can impact on the success of a project and therefore need to be monitored on an ongoing basis 24

Procurement Planning Project Procurement Strategy



The PPS is a hierarchical matrix covering the entire work scope of a project, broken down into separate ‘work packages’



Only the major critical items are separately identified as work packages



These packages are created and identified according to:

25



Unique technical and commercial attributes of the work activities they comprise



Methods by which they are to be executed

Procurement Planning Example of a PPS matrix Components Physical   Discipline

Special Equipment Item B

Balance of Plant

Civil Works

Project Management

Project Management Services Contractor – Reimbursable Costs with Incentives Fee – $ 70m total

Design

Design Contract – Lump Sum – $10m

Procurement

Materials Control

Specialist Supplier A – Lump Sum Purchase Order – $200m total

Construction / Erection Services

Installation Contract – Lump Sum – $10m

Quality Inspection

Specialist Quality Contract – All-in rates – $10m

Part of Project Management Services

Commissioning / Start-up Assistance

Part of Supplier A Purchase Order

Contract

Fabrication

26

Special Equipment Item A

Specialist Supplier B – Lump Sum Purchase Order – $100m total

Part of Supplier B Purchase Order

Facilities E & P Contract – Reimbursable Costs with Fixed Fee – $30m total

Construction Contract – Reimbursable Cost and Equipment Rates with Incentives Fee - $100M total

N/A

Procurement Planning Project Procurement Strategy



The structure of the PPS depends on the:

• Scope of work • Nature and complexity of the project • Requirements of the customer 

The PPS assists in:

• Administrative and commercial planning • Cost/schedule control functions of a project 27

Procurement Planning Benefits of a PPS 

Allows a concise, high-level overview of how procurement activities relate to the execution strategy of the project



Illustrates alternative ways of executing the project procurement activities



Identifies where:

• Consolidation (or further break-down) of work scopes can work to the project’s advantage

• Gaps may occur in hand-offs during execution 

28

A Procurement Strategy is a deliverable that can be provided for projects in Identify and Evaluate phase

Procurement Planning When planning occurs Identify

1

Evaluate

2

Define

3

Execute

4

Procurement Strategy

Procurement Plan

Materials Management Plan , if required

Contracts Plan , if required

Purchasing and Contracts Initiation

Materials Management Plan, if required Contracts Plan, if required Materials Field Administration Materials Management and Contracts Close-out

29

Operate

Procurement Planning Planning in the various WMPM project phases 

Projects in Identify and Evaluate phases:



While you might not be able to fully identify these requirements, you should be able to identify them in broad scope Concentrate on Procurement Strategy approach



Projects in Define phase:



The procurement needs of the project should be sufficiently identified to support the Customer’s overall project schedule Full fledged procurement plan can be developed



Projects in Execute phase:



The procurement needs are clearly identified and a procurement plan shall be developed to achieve the timely delivery of the project Full fledged procurement plan must be developed

30

Procurement Planning Project Procurement Plan



Documents the basis for obtaining and managing materials, equipment and third-party services required for project execution



Addresses relevant aspects of both materials management and contracts for the project



Maps out the various anticipated risks and constraints and identified mitigating actions



Identifies critical supplies (see also Procurement Strategy) and outlines general strategy



Ensures that the procurement activities align with the overall project schedule

31

Procurement Planning Project Procurement Plan



The Project Procurement Plan:

• Must clearly define the deliverables of the procurement process • Needs to be ‘fit for its purpose’

32

Procurement Planning Project Procurement Plan

Criticality-Value Assessment High





The Project Procurement Plan may also include details about the targeting of procurement efforts The Project Procurement Manager will consider the assessment in the strategy development

Criticality

Bottleneck, e.g. special alloy steel grade

Critical, e.g. turbine compressor

Ensure continuity Develop alternatives Revise specifications

Form closer relationships Direct negotiations

Routine, e.g. piping bulk blanket orders

Leverage, e.g. customer’s standard agreement

Simplify procurement process Automate Rationalise supplier base

Maximise commercial advantage Competitive tender Standardisation

Low High

Low

Value Potential

33

Procurement Planning Project Procurement Plan



Where the complexity and / or size of the project warrant it, the Project Procurement Plan may be further developed in separate plans:

• A detailed Project Materials Management Plan • Separate detailed Project Contracts Plan for major contract packages

• Separate detailed Procurement Plans for key procurement packages

34

Procurement Planning Materials Management planning The various elements of the Procurement Plan are further defined in the Materials Management Plan, including: 

Specific strategies for buying materials and equipment



Associated activities for managing the expediting, traffic/logistics etc



The materials control and reporting systems



Prioritization of procurement activities and associated engineering deliverables in line with the ROS (Required on Site dates) as defined in the project schedule

35

Procurement Planning Materials Management planning (cont’d) 

Level of procurement effort based on cost, schedule, criticality, and other relevant factors



POs/activities already executed and/or underway prior to engagement of WorleyParsons



Transition of early purchase agreements from the customer



Material control systems



Quality management, verification and inspection, which includes an outline of inspection to be undertaken



Site materials management plans

36

Procurement Planning Materials Management planning Subsets of the Material Management Plan 

Engineered equipment planning



Bulk materials planning



Prefabrication planning and modularization

37

Procurement Planning Engineered equipment planning 

The primary objective is to ensure that items are acquired and released in time to meet the overall project schedule



The dates on which items are required on site to meet construction needs drive the engineering and procurement planning and activity for engineered equipment



A major equipment list for the project needs to be developed early

38

Procurement Planning Bulk material planning 

Planning for bulk materials can be more complex than planning for engineered equipment



Bulk materials control starts with an examination of the project schedule to assess:

• What bulk materials are required over time • Critical required on site (ROS) dates

39

Procurement Planning Prefabrication planning and modularization 

Procurement planning:

• Is usually very complex for extensive prefabrication • modularization often involving multiple sites 

40

An extensive prefabrication program demands an early procurement planning effort that addresses the interfaces between vendors, fabricators and site construction

Procurement Planning Contracts planning 

The Contracts Plan can be:

• Subset of the Project Procurement Plan or • Separate plans—complex projects 

The main focus of project contracts planning is the selection the best contractor under the best available terms and conditions



Needs to:

• Analyze the options and the marketplace for the required services

• Define the number, type, scope, timing, interfaces, compensation basis, etc of major contracts to be developed for the project from early planning through start-up 41

Procurement Planning Contracts Planning in Define Phase 

For Projects in the Define phase the Project Contracts Plan needs to document:

• Critical contracting issues (e.g. labour resource constraints, market constraints) for the major contracts

• How will the impact be managed and the risk mitigated? • What is the schedule to meet timely completion of the Project?

42

Procurement Planning Contracts Planning in Execute Phase 

For Projects in the Execute phase, the Project Contracts Plan review the constraints and identify mitigation measures similar to the Define phase projects but not just for major contracts.

• All anticipated contracts are identified. • If the project is a continuation of a Define phase project, the Contracts Plan developed for the Define phase will be reviewed and updated by the Project Procurement Manager to reflect project progress and significant new developments 

43

A list of matters that typically need to be considered are listed on page 32 of the participants manual

Procurement Planning Approving the Project Procurement Plan 

44

The customer must approve the Project Procurement Plan as part of the Project Execution Plan

SmartPlant Materials 

45

WorleyParsons uses a suite of project management systems to record, track, control and report on projects

SmartPlant Materials 

SmartPlant Materials is used to:

• Identify • Record • Track materials and equipment required and purchased for a project

46

SmartPlant Materials SmartPlant Materials has four integrated modules, which are described on page 36 of the workbook

47

SmartPlant Materials 

Maintains the Material Stock Code catalogue



Generates bulk requisitions via interface to design systems (e.g. PDS)



Generates equipment and services requisitions



Preparation of RFQs



Supports bid evaluations



Creates and, if required, amends POs



Facilitates expediting



Facilitates Traffic/Logistics



Facilitates stores management



Can undertake invoice reconciliation via Invoice Matching Interface module

48

SmartPlant Materials 

SmartPlant Materials imports bills of materials from 2-D/3-D engineering design software and other sources



SmartPlant Materials supports better material planning on site and material reconciliation through the ability to track imported bills of materials from Requisition to Material Issue



Materials are identified as being in any of the following phases:

• • • • • • • • 49

Requisition

RFQ Purchasing Expediting Shipping Warehouse receipt Storage Material Issue

SmartPlant Materials Using SmartPlant Materials for recording and tracking contracts 

SmartPlant Materials was designed as a system for controlling materials and equipment, not for administering contracts



SmartPlant Materials can, however, be used to record basic information about contracts

50

SmartPlant Materials Setting up SmartPlant Materials for a project 

Each individual project needs to be set up in SmartPlant Materials so that its procurement activities can be recorded, monitored and reported



SmartPlant Materials should be set up as soon as the Project Procurement Plan or Materials Management Plan has been approved



You are responsible for ensuring that SmartPlant Materials is set up properly



You work with the project Procurement Manager to identify and obtain the information for the set up

51

SmartPlant Materials—Training Training in SmartPlant Materials 

When you need to start using SmartPlant Materials, you will receive specific training on how to use it



Contact the Business Systems Group to arrange the training

52

Procurement Reports Procurement reports 

Procurement activities are monitored and reviewed regularly



SmartPlant Materials generates a range of reports which you use to monitor progress and identify actions to be taken to address issues



Two particularly important reports for the management of procurement activities are the:

• Procurement Status Report • Procurement Expediting Report

53

Procurement Initiation Overview of procurement initiation 

The Project Procurement Manager is responsible for completing the activities that enable purchasing and contracts to be initiated



The initiation activities should be completed during the early stages of the project



The initiation activities are:

• • 

54

Purchasing initiation Contracts initiation and formulation

Part of the initiation activities is the development of the Project terms and conditions for purchase orders and contracts.



These may be provided by the Customer as we will typically be acting on their behalf.



The conditions shall be checked for alignment with the Prime contract.

Procurement Initiation Overview of purchasing initiation (Materials Management) 

Purchasing initiation involves setting up the project base for the Purchasing documentation and databases



The main activities are:

• Identifying PO provisions (including standard Terms and Conditions)

• Preparing standard documentation, including Instructions to Bidders, master Request for Quotation, master purchase order document

• Carrying out vendor pre-qualification • Establishing a project vendor list

55

Procurement Initiation Overview of Contracts initiation and formulation 

Contract initiation and formulation involves:

• Setting up the project base for contracts documentation (including standard Terms and Conditions)

• Establishing the contracts system for the project 

The main activities are:

• Establishing the contract types, sites conditions, HSE etc • Preparing common enquiry requirements and special contract provisions

• Carrying out contractor pre-qualifications • Establishing the contractor list

56

Procurement Execution Overview of procurement execution 

All procurement execution activities are undertaken by the Project Procurement Manager and the Procurement team



You are responsible for ensuring that the procurement activities are executed in accordance with the Project Procurement Plan



You and your Project Procurement Manager need to hold regular meetings to:

• Review the status of procurement activities • Identify issues early and determine the action required to minimize any adverse impact

57

Procurement Execution Materials Management execution—purchasing pre-award process 

The purpose of the Purchasing Pre-award Process is to award the POs under which the project’s materials and equipment are obtained



The pre-award process ensures that all bidders are treated fairly and equitable, that the confidentiality of the information is maintained and that the recommendation to award is in accordance with the agreed evaluation criteria



Agreed evaluation criteria may be as simple as ‘Technically acceptable, lowest cost’ or more complex ‘Total Cost of Ownership’ (TCO). Consider that TCO often requires Customer input as well.



Competitive bidding is indicated. However, if single source is considered for purchase orders, justification must be provided. This may include proprietary technology or customer’s standardisation preference.



Project Purchasing pre-award activities occur predominantly during the Execution phase

 58

For long-lead items some activities may occur in the Define phase

Procurement Execution Materials Management execution—purchasing pre-award process 

Preparing enquiry packages, including special terms and requirements (for example, supplier data, support, spares)



Issuing the enquiry packages and managing bid preparation and receipt process



Managing all communications with bidders during bidding and evaluation



Evaluating the bids



Preparing recommendations for award, conducting post-bid negotiation and facilitating final issue



Entering all data related to the purchases into SmartPlant Materials

59

Procurement Execution Materials Management execution—purchasing pre-award process As Project Manager, you will need to ensure that the procurement team: 

Maintains the required level of confidentiality of information



Ensures that engineering deliverables are aligned to support timely procurement activities



Maintains the interfaces between Engineering, Quality and Construction



Involves the Project Procurement Manager in the regular team progress meetings



Undertakes and completes procurement activities in accordance with the Project Procurement Plan

60

Procurement Execution Materials Management execution—purchasing award process 

Purchase Order documents are to be prepared by Engineering and Procurement on receipt of the approved Award Recommendation



Kick-off meetings are arranged as required



Post-award activities are initiated by the project procurement team



Once internal and other approvals have been obtained to place a contract or a PO the Procurement Manager is the only person with the authority to confirm the commitment for the contract or PO with the supplier on behalf of WorleyParsons and/or our customers

61

Procurement Execution Materials Management execution—purchasing award process You are responsible for ensuring that the award process is properly undertaken You need to:

62



Confirm that the cost of the awarded POs is within the project budget



Provide relevant information to the project’s Cost Controls Manager

Procurement Execution Materials Management execution—purchasing post-award process 

This process covers award of a PO through to receipt at site and financial close-out



The purpose of the Purchasing Post-award Process is to:

• Administer the POs to obtain the project’s materials and

equipment on schedule and in accordance with specifications

• Provide cost and schedule information to Project Services • Identify PO issues for Risk Management activities • Liaise with Inspection to ensure compliance to specifications 

The Purchasing Post-award Process covers the technical and commercial activities in the manufacture and delivery of materials and equipment



Ensure all meetings and vendor contact are coordinated by Procurement.

63

Procurement Execution Materials Management execution—purchasing post-award process The main activities in the Purchasing Post-award Process are: 

Expediting (including Supplier documentation)



Inspection coordination



Traffic/Logistics



Receiving on site, warehousing and preservation



Change/Claim administration



Invoice payment

64

Procurement Execution Materials Management execution—purchasing post-award process Effective procurement performance requires: 

Use of SmartPlant Materials



Monitoring the vendor’s engineering and manufacturing processes



Meeting documentation obligations



Measuring and assuring conformance to the technical specification



Administering delivery of the materials and equipment



Managing any changes to the PO technical and commercial provisions



Managing any claims by the vendor for additional payment or schedule time

65

Procurement Execution Materials Management execution—purchasing post-award process As Project Manager you are responsible for ensuring that: 

The Construction Manager involves the Project Procurement Manager in construction progress review meeting



For most items, weekly status meetings are sufficient



For critical items, daily review meetings between the Construction and Procurement Managers may be required

66

Procurement Execution Materials Management execution—purchasing materials field administration process 

The Materials Field Administration Process governs the day-to-day procurement activities on site



The actual administration is the responsibility of your Project Procurement Manager



Materials Field Administration may include site administration, purchasing and contracting

You are responsible for ensuring that the requirements for materials field administration are included in the Project Procurement Plan

67

Procurement Execution Contracts execution—contract pre-award process 

The purpose of the Contracts Pre-award Process is the contracting of third-party services



Project Contracts pre-award activities predominantly occur during the Execution phase



For early contracts, some activities may occur in the Define phase



The deliverables of the Contracts Pre-award Process are:

• • • • 

68

Bidders lists Enquiry packages

Approved recommendations for award Contract documents

Cost and schedule information provided to Project Services and contracts issues input into Risk Management activities

Procurement Execution Contracts execution—contract award process Contractor selection 

A thorough prequalification process will normally be executed for major contracts, e.g. fabrication contracts. This will involve multiple disciplines to prepare the questionnaire for the relevant work scope, typically including construction, engineering, quality, HSE as well as project controls and procurement.



Competitive, sealed bids are indicated for major contracts



If single source is considered for service contracts, justification must be provided. This may include proprietary technology (e.g. software) or customer’s preference.



Once internal and other approvals have been obtained to place a contract or a PO the Procurement Manager is the only person with the authority to confirm the commitment for the contract or PO with the supplier on behalf of WorleyParsons and/or our customers

69

Procurement Execution Contracts execution—contracts post-award process 

The Contracts Post-award Process covers the technical and commercial activities



The main activities are:

• • • • •

Awarding contracts

Administering and monitoring the contractors Managing any changes to the contract Managing any claims

Processing any payments and back charges, reconciling quantities and finalizing all contract obligations

• Providing cost and schedule information to Project Services • Identifying any contracts issues for Risk Management activities 70

Procurement Execution Purchase order and contracts variation 

PO and contract variation must be processed in accordance with the Management of Project Change Process



You and the Procurement Manager must sign-off any variances before they can take effect

71

Case study—group discussion 

The scenario for the case study is on page 55 of your workbooks

Discussion topics: 

What would you say are the key procurement issues on the project?



What can be done to remedy the situation?

72

Procurement Close-out Responsibilities for procurement close-out 

The Procurement team completes the procurement close-out tasks



You are responsible for ensuring that the Project Procurement Manager and the procurement team do this

73

Procurement Close-out Materials Management close-out 

Project Materials Management close-out activities generally occur late in the Execution phase



Close-out must follow the requirements for finalization of supply as set out in the Project Procurement Plan



The main objectives of materials close-out are:

74

• • • • • •

Materials reconciliation Surplus management

Final inspection (this is a Quality activity) Receipt Final Vendor Documentation Claims resolution Closing out of all PDs

Procurement Close-out Contracts close-out 

Close-out must follow the requirements for finalization of supply as set out in the Project Procurement Plan



The main objectives of contracts close-out are:

• • • • • 

75

Provision of acceptance certificates

Confirmation of warranties Handover of documentation Final inspections (Quality activity)

Claims resolution and payment reconciliation

Demobilization of the site by WorleyParsons and the contractor does not necessarily indicate final close-out of the project

Summary and Feedback 

Review learning objectives and outcomes



Summary

• • • • • • • •

Overview of Procurement Responsibilities for Procurement Commencing the Procurement Process \Procurement Planning SmartPlant Materials Procurement Reports Procurement Initiation Procurement Execution Procurement Close-out



Questions



Evaluation

76

Module 9 Managing Project Procurement Thank you for your participation