Inspection and Test Plan Motors RSAE-ITP-QA-EL-010
CONTROL DOCUMENT
Revision:
ACCEPTANCE CRITERIA
A1
VERIFICATION DOCUMENT
Page:
1 of 1
INVOLVEMENTS RC MHI Owner
1 Installation Inspection
gland 1- Check cable glanding and
1.1
2345-
termination Check earthing 3935 E321-00100 3935 E321-00200 Check rating plate Check space heater (MV motor and outdoor LV motor only) Check motor type according to location Instruction Manual: Method of Statement for 3935 E421-00110 (WEG) Motors 3935 E421-00120(HHI)
As per drawing
Spec./DWG
RSAE-FRM-226 >100Mohm (WEG, HHI) >50Mohm (Others)
LV Motors: 500 VDC 1 Min >50 MOhm RSAE-FRM-226 Motors: 2500 MVMV Motors: 1000V DC VDC 1Min1 (WEG) Min 2500V DC 1Min (HHI) (SEIMENS) Mohm >50 >100Mohm
R W
S W
S
W R
WS
S-
1.2
Insulation Resistance Test
1.3
Phase Rotation Test
Method of Statement for Motors
Method of Statement for Motors
RSAE-FRM-226
W R
W S
S-
1.4
Motor Solo Run Test
Method of Statement for Motors
Method of Statement for Motors
XXX RSAE-FRM-226
H W
H W
S
(MV motor and outdoor LV motor)
Method of Statement for Motors and Vibration limit shall be referred to IEC 60034-14
ATTACHMENT: 1. RSAE-FRM-226 Inspection Check List for Motor 2. RSAE-FRM-xxx Inspection Check List for Motor Solo Run Owner
LEGEND
RC: Renaissance Construction, MHI: Mitsubishi Heavy Industries, GNS: Gazprom Neftekhim Salavat, W: Witness, R: Review, H: Mandatory Hold Point, S: Surveillance (Random Check)
0AO
Acrylic Acid Plant SALAVAT, BASHKORTOSTAN, RUSSIAN FEDERATION To be included " Check the nameplate and Tag number"
INSPECTION CHECK LIST
Location Area
Date: DWG No.: Power (HP/kW)
Rated Current
Check List Ref. No. :
Tag. No. Motor Tag Rated Voltage
Type / Serial Number
Before Connection of Cable
RC
Verify that if the motor installed in accordance with project design and the vendor manual
3
Check earthing system connection
4
Ensure that the motor is clean and dry. End bells, covers, filters, and accessories shall be firmly attached.
5
Check visually if the conduits, bushings are sealed
6
Rotate the motor shaft manually (if possible) to ensure that the rotor moves freely, without rubbing
7
Verify that the motor protection circuits have been set and all protective relays tested
8
Ensure that motor cables checked and tested
Motor Insulation Resistance testing After 1 Min After 10 Min PI
Test Voltage : __V DC Minimum resistance : _________MΩ
2 3 No 1 2
Owner GNS
Remarks
Phase-PE (MΩ)
cable gland is connected tightly/cable is connected correct torque strength/Torque marking
Phase - Ground Result (OK/NG)
Motor solo run test to be separated sheet, referred to attached "Format_Motor_Solo Run Test_(Sample).xls"
After Connection of Cable Check Cable connection, ensure that it is torqued and marked Check Insulation Resistance of Motor and Motor Cable together against Earth Check the functionality of Space heater and Insulation Resistance against Earth
______________ Mohm ______________ Mohm
Motor Solo Run Test Record direction of rotation Record Starting Current
________________A Min 1
3
4
MHI
Check for any damage
2
No 1
RSAE-FRM-226
RFI Ref. No. :
RPM
No 1
Inspection and Check List for Motor
Record No Load Current
Record Vibration (mm/s RMS)
Name
________________A
Min 5
________________A
Min 10
________________A
Min 15
________________A
Min 20
________________A
Min 25
________________A
Min 30
________________A
DE
_______________
NDE
_______________
Testing Instruments List [The calibration certificate of the testing instruments shall be attached] Manufacturer Equipment serial No
Calibration date
MHI suppose the motor solo run will be done until saturate the temperature. generally it is 2hours.