Method Statement for Tie-Ins During Shutdown

February 20, 2018 | Author: Anyanele Nnamdi Felix | Category: Pipe (Fluid Conveyance), Welding, Personal Protective Equipment, Specification (Technical Standard), Safety
Share Embed Donate


Short Description

Method statement...

Description

JANUARY, 2016

DOCUMENT NUMBER: [K2S-NG01007551-SOKG1-MX6180-00003]

Shell Petroleum Development Company of Nigeria Classification Status: [Restricted]

FABRICATION AND INSTALLATION OF END FACILITIES AT THE SOKU GAS PLANT [METHOD STATEMENT FOR TIE-IN WORKS DURING SHUTDOWN]

Proprietary Information: This document contains proprietary information and may not be partly or wholly reproduced without prior written permission from Shell Petroleum Development Company The Process Manager for this procedure is the Major Projects General Manager, the Process Owner is the Major Projects Project Services Manager Revision

Date

Description

R01

14.01.2016

Issue for Internal Review

Originator

FELIX ANYANELE

Checker

Approver

T.S. PACURARIU

IKENNA ONYEKONWU

ADDITIONAL AGREEMENT/APPROVAL RECORD PARTY

REF IND.

NAME

SIGN

DATE

Revision Philosophy All revisions for review will be issued at R01, with subsequent R02, R03, etc as required. All revisions approved for issue or design will be issued at A01, with subsequent A02, A03, etc as required. Documents approved for Construction will be issued at C01, C02, and C03 respectively. Documents or drawings revised as “As built” will be issued as Z01, Z02 Z03 etc. Narrative sections revised from previous approved issues are to be noted in the table below and/or highlighted in the RH margin (using the appropriate revision status) thus: | A02 Previous revision highlighting to be removed at subsequent issues. Drawings/diagrams revised from previous approved issues are highlighted by 'clouding' the affected areas and by the use of a triangle containing the revision status.

Revision History REVISION NO.

DATE OF ISSUE

REASON FOR CHANGE

K2S-NG01007551-SOKG1-MX6180-00003

METHOD STATEMENT FOR TIE-IN WORKS DURING SHUTDOWN

Page 2 of 17 This document is controlled electronically and is uncontrolled when printed

TABLE OF CONTENT

S. NO.

DESCRIPTION

PAGE NOS.

1.

INTRODUCTION

4

2.

SCOPE

4

3.

REFERENCES

4

4.

RESPONSIBILITIES

5

5.

MANPOWER, MACHINERY AND EQUIPMENT

6

6.

HSE REQUIREMENTS

7

7.

PROCEDURE

7

8.

ATTACHMENT

17

K2S-NG01007551-SOKG1-MX6180-00003

METHOD STATEMENT FOR TIE-IN WORKS DURING SHUTDOWN

Page 3 of 17 This document is controlled electronically and is uncontrolled when printed

1.0 INTRODUCTION This method statement provides operational guidance and methods to be adopted in carrying out Tie-in activities during shutdown for the EPC FOR KOLO CREEK TO SOKU GAS EXPORT PIPELINE Project as per the technical specification and standards applying best industrial practice and applicable technical specifications and standards.

2.0 SCOPE The scope is to define the detailed activities for the identified tie-ins during plant shutdown of SOKU Plant. This shall include the installation of connecting piping works for the shutdown.

3.0 REFERENCES

 Project Quality Plan

K2S-NG01007551-SOKG1-AA5759-00001

 Project HSSE Management plan

K2S-NG01007551-SOKG1-HX5798-00001

 Construction Plan

K2S-NG01007551-SOKG1-BA5736-00002

 Procedure for Radiographic Examination

K2S-NG01007551-SOKG1-MX6180-00005

 Procedure for Ultrasonic testing

K2S-NG01007551-SOKG1-MX6180-00009

 Procedure for Magnetic Particle Inspection K2S-NG01007551-SOKG1-MX6180-00006  Procedure for Tie-in 

K2S-NG01007551-SOKG1-MX6180-00001

Approved WPS

 Piping – General Requirements

DEP 31.38.01.11-Gen.

 Piping Classes - Refining and Chemicals

DEP 31.38.01.12-Gen.

K2S-NG01007551-SOKG1-MX6180-00003

METHOD STATEMENT FOR TIE-IN WORKS DURING SHUTDOWN

Page 4 of 17 This document is controlled electronically and is uncontrolled when printed

4. RESPONSIBILITIES 

CONSTRUCTION MANAGER Shall be responsible for: 

The construction team by coordinating the various tie-in activities involved during construction.



The implementation of the Work Procedure and the Inspection and Test Plan during the shutdown window.



LEAD FIELD SUPERVISOR Shall be responsible for: 

Managing all the resources, developing and managing procedures and processes.



Ensuring that the construction works is sufficiently supported and conducted in accordance with approved procedures, documents and drawings.



Shall report to the Construction Manager.



Shall be responsible for all raw data quality checks and coordinate with the QA/QC Inspector in the implementation of the checks as mentioned in the Inspection and Test plan (ITP).



QA/QC MANAGER Shall be responsible for: 

Preparation of quality plans to ensure the required quality of WORK is attained in accordance with applicable DEPs, and project specifications.



Verification of activities to ensure shutdown work is in compliance with the procedures or method statement.



Preparation, monitoring and execution of the Quality Audit Programme.



Liaison with COMPANY representative on all matters relating to the shutdown work and the planned quality delivery.



QA/QC INSPECTOR Shall be responsible for: 

Reporting to the QA/QC Manager.



Carrying out all field inspections and checking as specified in the ITP in addition to coordinating with the Company representative.

K2S-NG01007551-SOKG1-MX6180-00003

METHOD STATEMENT FOR TIE-IN WORKS DURING SHUTDOWN

Page 5 of 17 This document is controlled electronically and is uncontrolled when printed



HSE COORDINATOR He shall be responsible for: 

Coordinating safety programs regarding the work.



Enforcing safety regulation and maintains safety records



Developing and maintaining the Project Safety Plan.



Verifying program and implementation of HSE procedure by conducting audits.

5.0 PERSONNEL, MACHINERY & EQUIPMENT 5.1 Personnel S. NO.

Personnel

1.

Qualified Welders (Structural & Piping)

2.

Supervisors (Structural & Piping)

3.

Fitters

4.

Welder Mates

5.

HSE Officers

6.

QC Inspectors

7.

Hydrotest Team

8.

Torquing Team

9.

Scaffolders

10.

Approved NDT Party

11.

Painters (where applicable)

12.

Operators (crane, manlift)

5.2 MACHINERY & EQUIPMENT: S. NO.

DESCRIPTION

1.

Crane

2.

Welding Machines

3.

Baking Ovens

K2S-NG01007551-SOKG1-MX6180-00003

METHOD STATEMENT FOR TIE-IN WORKS DURING SHUTDOWN

Page 6 of 17 This document is controlled electronically and is uncontrolled when printed

4.

PPE’s

5.

Loader Truck

6.

Man Lift

7.

Hydrotest equipment e.g. pressure pump, chart recorder, gauges, hose, manifold etc)

8.

Torque Wrench

6.0 HSE REQUIREMENTS  Prior to commencing the works a detailed Job Hazard Analysis shall be carried out. After all known, suspected or potential hazards and risks have been identified, the work force shall be informed of the hazard and control measures that must be put in place to eliminate or control the hazard and potential risk.  All personnel involved in the shutdown activity shall receive safety training induction  All personnel to be engaged in this work shall be properly mobilized and inducted. This is to enable them to appreciate the risk hazards involved in the operations.  All workers shall be medically fit to work.  The health, safety and environment of all personnel shall be safeguarded to avoid injuries and illness.  There shall be a qualified first aider, fully equipped with first aid drugs required in the first aid administration.  Dedicated site HSE officers shall man all work sites.  An authorized Gas Tester shall carry out Gas Monitoring tests before any isolation work is carried out, and will then continuously monitor the work atmosphere, he shall ensure that gas monitoring records are kept.  Warning signs and barriers shall be positioned around all work areas.  All personnel shall wear the appropriate PPE reference Job Specific JHA. All the work force shall comply with the Contractor’s Health, Safety and Environment requirements as per the HSE plan.  Only authorized personnel shall be allowed into the work area. All necessary measures as per Client’s requirements or manufacturer’s recommendations shall be adhered to. K2S-NG01007551-SOKG1-MX6180-00003

METHOD STATEMENT FOR TIE-IN WORKS DURING SHUTDOWN

Page 7 of 17 This document is controlled electronically and is uncontrolled when printed

 PTW and the JHA shall be signed off.

7.0 PROCEDURE Before beginning any shutdown activities Client and Contractor shall agree the programme for the shutdown work and all the Tie-in area has been verified and checked by the SPDC Operation Representative. 7.1 Flanged Tie -In: 7.1.1

Production Manifold Tie-in No.

From

To existing

TP-006A

12”-P-11901-153451

20”-P-10502-15350X

TP-006B

12”-P-11902-153461

20”-P-11902-K2S153834

The mode of operation for the above mentioned tie-in is as indicated in the below table: S/No

TASK STEPS

STEP DESCRIPTION

 1

Work area Inspection

 

 2

Position the equipment & pipes



  3

Operation



REMARKS

Ensure that the lines to be tied into are well isolated and free of hydrocarbon. Conduct Gas test prior to the commencement of the operation. Ensure that hot work permit is obtained prior to start of work.

SPDC/ Nestoil responsible for purging of hydrocarbon if necessary. Use of appropriate PPE Personnel to work carefully at all times.

Carefully position required equipment Ensure the use of correct and spool on designated work space. tools and the right PPE. Lift the spool into position and align it to Ensure that all hand held the tie-in position. tools and equipment are in a good working condition. to work Slack Bolts and remove the existing blind Personnel flange on 20”-P-10502-15350X & 20”-P- carefully at all times. 10840-153832. Connect the 12” spool as well as double Ensure the use of correct block and bleed valves for TP006A (10-BV- tools and the right PPE. 132, 10-BV-133 & 10-BV-134) & TP006B (10-BV-135, 10-BV-136, 10-BV-137) in Ensure that all hand held tools and equipment are closed position to the existing flanges. Ensure bolts and blind flange are properly in a good working installed and torqued to the approved condition. values.

K2S-NG01007551-SOKG1-MX6180-00003

METHOD STATEMENT FOR TIE-IN WORKS DURING SHUTDOWN

Page 8 of 17 This document is controlled electronically and is uncontrolled when printed

7.1.2

Process flow line from fiscal metering (EGGS-1) to slug catcher Tie-in No.

From

To existing

TP-015

2”-P-11904-91412

24”-P-36009-91410-H

The mode of operation for the above mentioned tie-in is as indicated in the below table: S/No

1

TASK STEPS

Work area Inspection

STEP DESCRIPTION

REMARKS



SPDC/ Nestoil responsible for purging of hydrocarbon if necessary.

 

Ensure that the lines to be tied into are well isolated and free of hydrocarbon. Conduct Gas test prior to the commencement of the operation. Ensure that hot work permit is obtained prior to start of work.

Use of appropriate PPE Personnel to work carefully at all times.

 2

Position the equipment & pipes





 3

Operation



Carefully position required equipment Ensure the use of correct and spool on designated work space. tools and the right PPE. Lift the spool into position and align it to Ensure that all hand held the tie-in position. tools and equipment are in a good working condition. Personnel to work Slack Bolts and remove the existing 2” carefully at all times. blind flange from line 24”-P-36009-91410H. Ensure the use of correct Connect new 2” spool including a double tools and the right PPE. block and bleed valves in closed position (11-BV-008, 11-BV-009, and 11-BV-010). Ensure that all hand held Ensure bolts and blind flange are properly tools and equipment are installed and torqued to the approved in a good working values. condition.

K2S-NG01007551-SOKG1-MX6180-00003

METHOD STATEMENT FOR TIE-IN WORKS DURING SHUTDOWN

Page 9 of 17 This document is controlled electronically and is uncontrolled when printed

7.1.3

Chemical line Tie-in No.

From

To existing

TP-001

2”-C-64319-151412

2”-C-64564-151410

The mode of operation for the above mentioned tie-in is as indicated in the below table: S/No

1

TASK STEPS

Work area Inspection

STEP DESCRIPTION

REMARKS



SPDC/ Nestoil responsible for freeing the system of methanol if necessary.

 

Ensure that the lines to be tied into are well isolated and free of methanol. Conduct Gas test prior to the commencement of the operation. Ensure that hot work permit is obtained prior to start of work.

Use of appropriate PPE Personnel to work carefully at all times.

 2

Position the equipment & pipes



  3

Operation



Carefully position required equipment Ensure the use of correct and spool on designated work space. tools and the right PPE. Lift the spool into position and align it to Ensure that all hand held the tie-in position. tools and equipment are in a good working condition. Personnel to work carefully at all times. Loosen blind on line 2”-C-64564-151410. Install 2” spool with double block and Ensure the use of correct bleed valves (64-BV-001, 64-BV-002, and tools and the right PPE. 64-BV-023). Ensure bolts and blind flange are properly Ensure that all hand held installed and torqued to the approved tools and equipment are values. in a good working condition.

K2S-NG01007551-SOKG1-MX6180-00003

METHOD STATEMENT FOR TIE-IN WORKS DURING SHUTDOWN

Page 10 of 17 This document is controlled electronically and is uncontrolled when printed

7.1.4

Blow down line to HP Flare Tie-in No.

From

TP-007

20”-B-11905-13451

To existing 24”-B-66001-1149

The mode of operation for the above mentioned tie-in is as indicated in the below table: S/No

1

TASK STEPS

Work area Inspection

STEP DESCRIPTION

REMARKS



SPDC/ Nestoil responsible for purging of hydrocarbon if necessary.

 

Ensure that the lines to be tied into are well isolated and free of hydrocarbon. Conduct Gas test prior to the commencement of the operation. Ensure that hot work permit is obtained prior to start of work.

Use of appropriate PPE Personnel to work carefully at all times.

 2

3

Position the equipment & pipes

Operation



  

Carefully position required equipment Ensure the use of correct and spool on designated work space. tools and the right PPE. Lift the spool into position and align it to Ensure that all hand held the tie-in position. tools and equipment are in a good working condition. No AFC drawing from Nestoil Loosen 14” blind on line and remove. Install 14” valve and blind. Ensure bolts and blind flange are properly installed and torqued to the approved values.

K2S-NG01007551-SOKG1-MX6180-00003

METHOD STATEMENT FOR TIE-IN WORKS DURING SHUTDOWN

Page 11 of 17 This document is controlled electronically and is uncontrolled when printed

7.1.6

Condensate from slug catcher to condensate drum Tie-in No.

From

To existing

TP-005

8”-P-11905-91432

12”-P-51020-9143

The mode of operation for the above mentioned tie-in is as indicated in the below table: S/No

1

TASK STEPS

Work area Inspection

STEP DESCRIPTION

REMARKS



SPDC/ Nestoil responsible for purging of hydrocarbon if necessary.

 

Ensure that the lines to be tied into are well isolated and free of hydrocarbon. Conduct Gas test prior to the commencement of the operation. Ensure that hot work permit is obtained prior to start of work.

Use of appropriate PPE Personnel to work carefully at all times.

 2

Position the equipment & pipes



  3.

Operation



Carefully position required equipment Ensure the use of correct and spool on designated work space. tools and the right PPE. Lift the spool into position and align it to Ensure that all hand held the tie-in position. tools and equipment are in a good working condition. Nestoil to provide AFC. Loosen blind on line 12”-P-51020-9143. Install 8” spool with double bock and Isometric to confirm exact bleed valves (11-BV-024, 11-BV-025, and tie-in position. 11-BV-026) in closed position. Ensure bolts and blind flange are properly Ensure the use of correct installed and torqued to the approved tools and the right PPE. values.

K2S-NG01007551-SOKG1-MX6180-00003

METHOD STATEMENT FOR TIE-IN WORKS DURING SHUTDOWN

Page 12 of 17 This document is controlled electronically and is uncontrolled when printed

7.1.7

Instrument air Tie-in No.

From

To existing

TP-017

2”-A-68600-11412

2”-A-68021-1841

The mode of operation for the above mentioned tie-in is as indicated in the below table: S/No

TASK STEPS

STEP DESCRIPTION

 1

Work area Inspection

 

 2

Position the equipment & pipes



 3.

Operation

 

REMARKS

Ensure that the lines to be tied into are Use of appropriate PPE well isolated. Conduct Gas test prior to the commencement of the operation. Ensure that hot work permit is obtained prior to start of work. Personnel to work carefully at all times. Carefully position required equipment Ensure the use of correct and spool on designated work space. tools and the right PPE. Lift the spool into position and align it to Ensure that all hand held the tie-in position. tools and equipment are in a good working condition. Personnel to work carefully at all times. Loosen 2” blind flange on line 2”-A-680211841. Ensure the use of correct Install 2” isolation valve in closed position. tools and the right PPE. Ensure bolts and blind flange are properly installed and torqued to the approved Ensure that all hand held tools and equipment are values. in a good working condition.

K2S-NG01007551-SOKG1-MX6180-00003

METHOD STATEMENT FOR TIE-IN WORKS DURING SHUTDOWN

Page 13 of 17 This document is controlled electronically and is uncontrolled when printed

7.2

Threaded Tie-In:

7.2.1

Instrument air Tie-in No.

From

To existing

TP-018

3”-A-68008-11412

3”-A-68507-18410

The mode of operation for the above mentioned tie-in is as indicated in the below table: S/No

TASK STEPS

STEP DESCRIPTION

 1

Work area Inspection

 

 2

Position the equipment & pipes



 3.

4.

Qualification of Personnel and WPS

Operation

     

REMARKS

Ensure that the lines to be tied into are Use of appropriate PPE well isolated and free of hydrocarbon. Conduct Gas test prior to the commencement of the operation. Ensure that hot work permit is obtained prior to start of work. Personnel to work carefully at all times. Carefully position required equipment Ensure the use of correct and pipes to be welded on designated tools and the right PPE. work space. Lift the spool into position and align it to Ensure that all hand held the tie-in position. tools and equipment are in a good working condition. Ensure that the WPS to be used is Ensure the use of Qualified Personnel at all approved. Ensure that the Welders are qualified in times accordance with the approved WPS. Personnel to work Cut cap on line 3”-A-68507-18410. carefully at all times. Thread existing line with dicing machine. Install coupling on existing line. Ensure the use of correct Tie-in 3” spool on existing line. tools and the right PPE. Ensure bolts and blind flange are properly installed and torqued to the approved Ensure that all hand held values. tools and equipment are

K2S-NG01007551-SOKG1-MX6180-00003

METHOD STATEMENT FOR TIE-IN WORKS DURING SHUTDOWN

Page 14 of 17 This document is controlled electronically and is uncontrolled when printed

in a good condition.

7.2

Weld Tie-In:

7.2.2

Closed drain from NAG slug catcher & Pig receiver Tie-in No.

From

To existing

TP-015A/B

4”-D-11904-11482

4”-D-45092-91481

working

The mode of operation for the above mentioned tie-in is as indicated in the below table: S/No

TASK STEPS

STEP DESCRIPTION

 1

Work area Inspection

 

 2

Position the equipment & pipes



 3.

Qualification of Personnel and WPS

 

4.

Operation

 

REMARKS

Ensure that the lines to be tied into are Use of appropriate PPE well isolated and free of hydrocarbon. Conduct Gas test prior to the commencement of the operation. Ensure that hot work permit is obtained prior to start of work. Personnel to work carefully at all times. Carefully position required equipment Ensure the use of correct and pipes to be welded on designated tools and the right PPE. work space. Lift the spool into position and align it to Ensure that all hand held the tie-in position. tools and equipment are in a good working condition. Ensure that the WPS to be used is Ensure the use of Qualified Personnel at all approved. Ensure that the Welders are qualified in times accordance with the approved WPS. to work Carry out probing for underground Personnel facilities prior to the commencement of carefully at all times. the excavation. Excavate and expose the existing Ensure the use of correct tools and the right PPE. underground close drain piping. Cold cut the existing 4” portion of the pipe where the new connection is to be welded Ensure that all hand held and block the opening using clay in order tools and equipment are

K2S-NG01007551-SOKG1-MX6180-00003

METHOD STATEMENT FOR TIE-IN WORKS DURING SHUTDOWN

Page 15 of 17 This document is controlled electronically and is uncontrolled when printed

   

7.2.3

to prevent the gas from the line from in a good escaping. condition. Connect the new line and execute the field weld. Flush the clay plug with water under pressure. Ensure that NDT is carried out as per the inspection class and in accordance with the project DEP. Ensure bolts and blind flange are properly installed and torqued to the approved values.

working

Open drain from NAG slug catcher & Pig receiver Tie-in No.

From

To existing

TP-016A/B

4”-D-10310-11432

4”-D-46101-11481

The mode of operation for the above mentioned tie-in is as indicated in the below table: S/No

TASK STEPS

STEP DESCRIPTION

 1

Work area Inspection

 

 2

Position the equipment & pipes



 3.

Qualification of Personnel and WPS



REMARKS

Ensure that the lines to be tied into are Use of appropriate PPE well isolated and free of hydrocarbon. Conduct Gas test prior to the commencement of the operation. Ensure that hot work permit is obtained prior to start of work. Personnel to work carefully at all times. Carefully position required equipment Ensure the use of correct and pipes to be welded on designated tools and the right PPE. work space. Lift the spool into position and align it to Ensure that all hand held the tie-in position. tools and equipment are in a good working condition. Ensure that the WPS to be used is Ensure the use of Qualified Personnel at all approved. Ensure that the Welders are qualified in times accordance with the approved WPS.

K2S-NG01007551-SOKG1-MX6180-00003

METHOD STATEMENT FOR TIE-IN WORKS DURING SHUTDOWN

Page 16 of 17 This document is controlled electronically and is uncontrolled when printed

   4.

Operation

  

Carry out probing for underground facilities prior to the commencement of the excavation. Excavate and expose the existing underground close drain piping. Cold cut the existing 4” portion of the pipe where the new connection is to be welded. Connect the new line and execute the field weld. Ensure that NDT is carried out as per the inspection class and in accordance with the project DEP. Ensure bolts and blind flange are properly installed and torqued to the approved values.

Personnel to work carefully at all times. Ensure the use of correct tools and the right PPE. Ensure that all hand held tools and equipment are in a good working condition.

8.0 ATTACHMENT Document No.

a) b) c) d) e) f) g) h) i)

Tie-in No.

K2S-NG01007551-SOKG1-MP2343-00002-001 K2S-NG01007551-SOKG1-MP2343-00002-001 K2S-NG01007551-SOKG1-MP2343-00002-001 K2S-NG01007551-SOKG1-MP2343-00002-001 K2S-NG01007551-SOKG1-MP2343-00002-001 K2S-NG01007551-SOKG1-MP2343-00002-001 K2S-NG01007551-SOKG1-MP2343-00002-001 K2S-NG01007551-SOKG1-MP2343-00025-001 K2S-NG01007551-SOKG1-MP2343-00027-001

K2S-NG01007551-SOKG1-MX6180-00003

TP-001 TP-005 TP-006A TP-006B TP-015 TP-017 TP-018 TP-016A/B TP-015A/B

METHOD STATEMENT FOR TIE-IN WORKS DURING SHUTDOWN

Page 17 of 17 This document is controlled electronically and is uncontrolled when printed