Method Statement for Office Container and Equipment Mobilization

November 11, 2016 | Author: Rachel Flores | Category: N/A
Share Embed Donate


Short Description

Download Method Statement for Office Container and Equipment Mobilization...

Description

METHOD STATEMENT FOR MOBILISATION, DEMOBILISATION AND INSTALLATION OF OFFICE CONTAINER, EQUIPMENT, FENCING AND CARPARK.

Project:

Project No.:

LAYING OF GAS TRANSMISSION PIPELINES FROM MERANTI VIEW TO BANYAN AVENUE IN JURONG ISLAND

P4262

Rev: 00

Date:

Page:

16/02/2015

1 of 12

TABLE OF CONTENTS

1.

GENERAL

2

2.

PURPOSE

2

3.

SCOPE

2

4.

TERMS & DEFINITIONS

2

5.

REFERENCES

2

6.

RESPONSIBILITIES

3

7.

ORGANIZATION CHART

7

8.

MOBILIZATION OF PLANT, EQUIPMENT, TOOLS & MANPOWER

7

9.

PERSONNEL QUALIFICATION

8

10. METHODOLOGY- PREPARATORY WORK, WORK EXECUTION METHOD

8

11. HEALTH SAFETY ENVIRONMENT

11

12. ATTACHMENTS

12

METHOD STATEMENT FOR MOBILISATION, DEMOBILISATION AND INSTALLATION OF OFFICE CONTAINER, EQUIPMENT, FENCING AND CARPARK.

Project:

Project No.:

LAYING OF GAS TRANSMISSION PIPELINES FROM MERANTI VIEW TO BANYAN AVENUE IN JURONG ISLAND

P4262

Rev: 00

Date:

Page:

16/02/2015

2 of 12

1. GENERAL This document covers the sequence activities for the Office Containers & Equipment Mobilization and Demobilization, General lifting operation of construction materials / equipments at The laying of gas transmission pipelines from meranti view to banyan avenue in jurong island project. 2. PURPOSE The purpose of this document is to follow proper methodology and to carry out the activities in sequence for the Office Containers & Equipment Mobilization and demobilization, General loading, unloading and lifting operation of construction materials / equipments at The laying of gas transmission pipelines from meranti view to banyan avenue in jurong island project. 3. SCOPE The scope of the work method statement is to outline the procedure and work sequence for the Office Containers & Equipment Mobilization and Demobilization, general unloading and lifting operation of construction materials / equipments at The laying of gas transmission pipelines from meranti view to banyan avenue in jurong island project. This Works Method details the followings, 

The requirements and procedures in mobilization of office container & equipment.



Responsibilities.



Organisation chart.



Manpower & Equipment used.



Lifting plan.



Lifting sequence.



Roof installation sequence.



Site Location.



Proposed location for WEC site office.



Roof Structure.



Single Line Diagram.



Risk Assessment.

4. TERMS & DEFINITIONS HSE – Health safety & Environment. RA – Risk Assesment. LM – Lifting Machine. LG – Lifting Gear. 5. REFERENCE 

Work Place Safety And Health Act



Work Place Safety And Health(General Provisions) Regulations

METHOD STATEMENT FOR MOBILISATION, DEMOBILISATION AND INSTALLATION OF OFFICE CONTAINER, EQUIPMENT, FENCING AND CARPARK.

Project:

Project No.:

LAYING OF GAS TRANSMISSION PIPELINES FROM MERANTI VIEW TO BANYAN AVENUE IN JURONG ISLAND

P4262

Rev: 00



Work Place Safety And Health(Construction) Regulations 2007



WSH(Operations Of Cranes) Regulations 2011



Code of Practice on Safe Lifting Operations in the Work Places



SS536: Code of practice for the safe use of mobile cranes



SS528: specification for personal fall arrest system



SS537 code of practice for safe use of machinery



Code of practice for working safely at heights.

Date: 16/02/2015

Page: 3 of 12

6. RESPONSIBILITY 6.1 Project Manager 

Undergone Project Manager's Safety Course and possess valid certificate.



Familiarize himself with the Company's environmental, health and safety management system and ensure its effective application.



Take prompt corrective actions to remove any unsafe or unhealthy work conditions and to maintain effectively such corrections made.



Ensure good housekeeping is practiced on site.



Ensure that environmental, health and safety is planned into all operations.



Review all working methods and process, both new and existing to see that all environmental, health and safety are met.



Act as Chairman to the site safety, health and environment committee and conduct monthly site committee inspection and meeting.



Participate in all incident investigation and dangerous occurrences incidents.

6.2 Project Engineers 

Familiar himself with the Company's environmental, health and safety management system.



Review any new or changes in processes, equipment and materials to ensure that safety, health and environment are not disregarded.



Establish and maintain a programme for the identification and assessment of hazards.



Assist in the investigation of every serious or fatal accident and dangerous occurrence and recommend preventive measures.



Ensure that method statements, hazard analysis and safe work procedures for hazardous operations must be submitted by the sub-contractors prior to commencement of work on site.

6.3 WSH Coordinator 

Undergone Building Construction Safety Supervisor Course and WSH Co-coordinator Course possess valid Certificate.

METHOD STATEMENT FOR MOBILISATION, DEMOBILISATION AND INSTALLATION OF OFFICE CONTAINER, EQUIPMENT, FENCING AND CARPARK.

Project:

Project No.:

LAYING OF GAS TRANSMISSION PIPELINES FROM MERANTI VIEW TO BANYAN AVENUE IN JURONG ISLAND

P4262



Rev: 00

Date: 16/02/2015

Page: 4 of 12

Ensure that all rules and regulations as stipulated in the WSHA (Construction) Regulations are met.



Inspect and rectifying any unsafe place of work and unsafe practices.



Checking sub-contractors work to ensure compliance with the WSHA (Construction) Regulations.



Liaison with sub-contractors with respect to environmental, health and safety works undertaken by them.



Assist the Safety Manager, Workplace Safety and Health Officer and Environmental Control Officer in all safety, health & environment matters.



Carry out site safety, health and environment programmes and procedures.



Assist in organizing safety, health and environment awareness activities such as toolbox meetings, safety, health and environment orientation, safety, health and environment promotional activities, etc.



Ensure that issuance of personal protective equipment are properly recorded and documented.



Coordinates and assures compliance with the Risk Assessment Program

6.4 Foremen/ Supervisor 

Responsible for the safety, health & welfare of all workers either assigned or not assigned to him but may be working temporary in his area.



Ensure that workers know safety, health and environment rules and regulations, follow safe job procedures and be aware of all major hazards associated with their work and work areas.



Maintain satisfactory standards of housekeeping in his assigned area.



Investigate all incidents to worker(s) and/or equipment in his area and assist Workplace Safety and Health Officer to put up accurate incident report on all such investigation.



Ensure that all workers working in his area use the appropriate personal protective equipment.

6.5 Lifting Supervisors 

Undergone Lifting Supervisor Safety Course and possess valid certificate



Possess relevant experience in lifting operations for a period of not less than one year before the appointment as a lifting supervisor.



Co-ordinate all lifting activities.



Supervise all lifting operation by a mobile crane or tower crane in accordance with the lifting plan.



Ensure that only registered crane operators, appointed riggers and appointed signalmen participate in any lifting operation involving the use of a mobile crane or a tower crane.

METHOD STATEMENT FOR MOBILISATION, DEMOBILISATION AND INSTALLATION OF OFFICE CONTAINER, EQUIPMENT, FENCING AND CARPARK.

Project:

Project No.:

LAYING OF GAS TRANSMISSION PIPELINES FROM MERANTI VIEW TO BANYAN AVENUE IN JURONG ISLAND

P4262



Rev: 00

Date: 16/02/2015

Page: 5 of 12

Ensure that the ground conditions are safe for any lifting operation to be performed by any mobile crane.



Brief all crane operators, riggers and signalmen on the lifting plan



If any unsatisfactory or unsafe conditions are reported to him by any crane operator or rigger, take such measures to rectify the unsatisfactory or unsafe condition or otherwise ensure that any lifting operation is carried out safely.

6.6 Crane Operators 

Undergone Crane Operator's Training Course and possess valid certificate.



Before the start of every work shift, to carry out operational tests on all limiting and indicating devices under no load conditions before any lifting operation is carried out and shall enter the results of such tests in a log book or log-sheet.



To ascertain whether the ground conditions, in particular the ground surface on which a mobile crane is to be operated, are safe for travel or any lifting operation; and if he is of the opinion that it is not safe for travel or any lifting operation, he shall report this to the lifting supervisor.



To ensure that any outrigger when it is required is fully extended and secured.



Not to carry out any lifting operation unless he has been briefed by the lifting supervisor on the lifting plan.



Not to hoist any object if he is unable to ascertain the weight of the load.



Not to hoist any load unless he has received a clear signal from a signalman.



Not to engage in any act or manoeuvre which is not in accordance with safe and sound practice.



Not to hoist any load if there is any obstruction in the path of manoeuvre and if there is any such obstruction, he shall report this immediately to the lifting supervisor.



Not to manoeuvre or hold any suspended load over any public road or public area unless that road or area has been cordoned off



Not to operate a mobile crane or a tower crane within 3 metres of any live overhead power line.



Not to use the crane for any operation for which it is not intended, including pulling or dragging a load



To ensure that any stationary truck mounted or wheel mounted crane is adequately and securely blocked while it is on a slope.



To report any failure or malfunction of the crane to the lifting supervisor and to make an appropriate entry of the failure or malfunction in the log book or log-sheet of the crane.

6.7 Riggers

METHOD STATEMENT FOR MOBILISATION, DEMOBILISATION AND INSTALLATION OF OFFICE CONTAINER, EQUIPMENT, FENCING AND CARPARK.

Project:

Project No.:

LAYING OF GAS TRANSMISSION PIPELINES FROM MERANTI VIEW TO BANYAN AVENUE IN JURONG ISLAND

P4262



Rev:

Date:

00

16/02/2015

Page: 6 of 12

Appoint a rigger in a workplace unless the person has successfully completed rigger training course acceptable to the Commissioner.



Check the slings to be used for slinging the loads to ensure that the slings are of good construction, sound and suitable material, and adequate strength and free from patent defect.



Ensure that an adequate number of legs of the sling are used and that the slinging angle is correct so as to prevent the sling from being overloaded during the hoisting.



Determine the weight of the load which is to be lifted and inform the crane operator of the weight of the load;



Ensure that only proper lifting gears are used in conjunction with the sling.



Ensure that the load to be lifted is secure, stable and balanced.



Ensure that any loose load (which includes any stone, brick or tile) is placed in a receptacle to prevent the load or part thereof from falling during the lifting operation.



Place adequate padding at the edges of the load which come in contact with the sling so as to prevent the sling from being damaged; and



Report any defect in the lifting gear to the lifting supervisor.

6.8 Signalmen 

Undergone Signalman's Training Course and possess valid certificate.



Ensure or verify with the rigger that the load is properly rigged up before he gives a clear signal to the crane operator to lift the load.



Give correct and clear signals to guide the crane operator in the maneuver of the load safely to its destination.

6.9 Banksmen 

He will be in-house trained, with a whistle and hi-visibility vest.



Assist in assessing the ground conditions prior to the entry of equipment/ machinery/ vehicle.



Use standard signals to guide the movements of machinery/equipment/vehicle at/to the location of works to be carried out.



Communicate

to

the

drivers/operators

during

the

movements

of

the

machinery/equipment/Vehicle. 

Station full time on site assisting in guiding all vehicular movements on site.



Report any incidents/accidents to his immediate supervisor, sembcorp site/safety personnel



The movements of machinery/equipment/vehicle will be stopped during the absence of the banksman to prevent any incidents on site.



The operator/driver must be able to see the banksman during the communication process.



The banksman must be stationed in such a way not to be in the line of fire (front, behind or in-between) of the equipment movement

METHOD STATEMENT FOR MOBILISATION, DEMOBILISATION AND INSTALLATION OF OFFICE CONTAINER, EQUIPMENT, FENCING AND CARPARK.

Project:

Project No.:

LAYING OF GAS TRANSMISSION PIPELINES FROM MERANTI VIEW TO BANYAN AVENUE IN JURONG ISLAND

P4262

Rev: 00

Date:

Page:

16/02/2015

7 of 12

6.10 Workers 

Accepting individual responsibility for their own safe behavior as well as sharing responsibility with their fellow workers and line supervision to look out for their own as well as their co-workers.



Work in a safe manner at all times.



Complying with HSE requirements which apply to an individual’s work activities.



Keeping the work area in an orderly condition.



Wear PPE provided to them and inspect it daily.



Comply with work instructions and permits.



Attend daily tool box/pre-task meetings



Inspect all tools before use and on a daily basis.

7. ORGANIZATION CHART

METHOD STATEMENT FOR MOBILISATION, DEMOBILISATION AND INSTALLATION OF OFFICE CONTAINER, EQUIPMENT, FENCING AND CARPARK.

Project:

Project No.:

LAYING OF GAS TRANSMISSION PIPELINES FROM MERANTI VIEW TO BANYAN AVENUE IN JURONG ISLAND

P4262

Rev: 00

Date: 16/02/2015

Page: 8 of 12

METHOD STATEMENT FOR MOBILISATION, DEMOBILISATION AND INSTALLATION OF OFFICE CONTAINER, EQUIPMENT, FENCING AND CARPARK.

Project:

Project No.:

LAYING OF GAS TRANSMISSION PIPELINES FROM MERANTI VIEW TO BANYAN AVENUE IN JURONG ISLAND

P4262

Rev: 00

Date: 16/02/2015

8. MOBILIZATION OF PLANT, EQUIPMENT, TOOLS AND RESOURCES 8.1 Equipments 8.1.1

Mobile Crane.

8.1.2

Lorry Crane.

8.1.3

Crowler Crane.

8.1.4

Excavator.

8.1.5

Trailer

8.1.6

Transportation Trucks

8.1.7

Welding machines

8.1.8

Vibrating machines

8.1.9

Road Roller

8.1.10 Personal Protective Equipments 8.1.11 Electrical Generators 8.1.12 Roofing Frame 8.1.13 Roofing Sheet 8.2 Tools 8.2.1

Measuring and Leveling Tools

8.2.2

Clamping Tools

8.2.3

Hand held Tools- Spanner, screw driver, plumb etc.

8.2.4

Lifting Tools- Belts, Sling, Chain Block, Hoist, Shackle, Ropes etc.

8.2.5

Portable power Tools like Grinding machine, Drilling Machine etc.

8.2.6

Stepladder & Extension ladder

8.2.7

Nails for the metal roofing

8.2.8

Heavy duty hammer & half a pound 2” sized roofing nails

8.2.9

Hand Saw

8.2.10 Scaffolding pipe. 8.2.11 GI wire. 8.2.12 Welding Torch. 8.2.13 Portable power Tools like Grinding machine, Drilling Machine etc. 8.2.14 Power & Welding cables 8.2.15 Fire blanket. 8.3 Man Power 8.3.1

Project Engineer

1 person

8.3.2

Safety Co ordinator

1 person

8.3.3

Lifting supervisor

1 person

8.3.4

Crane operator

1 person

Page: 9 of 12

METHOD STATEMENT FOR MOBILISATION, DEMOBILISATION AND INSTALLATION OF OFFICE CONTAINER, EQUIPMENT, FENCING AND CARPARK.

Project:

Project No.:

LAYING OF GAS TRANSMISSION PIPELINES FROM MERANTI VIEW TO BANYAN AVENUE IN JURONG ISLAND

P4262

8.3.5

Rigger man

2 persons

8.3.6

Banks man

1 person

8.3.7

signal man

1 person

8.3.8

General worker

2 persons

Rev: 00

Date: 16/02/2015

Page: 10 of 12

9. PERSONNEL QUALIFICATION 

All personnel delegated to the work would have undergone the relevant mandatory and project specific in-house training



All personnel would be competent for the tasks that they will be carrying out,



Supervisory personnel will act as “vehicle commanders” by following and guiding the vehicle into and around the plant



Please refer the attachment for the competency personnel certificates.

10. METHODOLOGY 10.1 Preparatory Work 

Ensure that the document received bear the stamp “Issued for Construction” and are of latest revision.



The documents submitted/referred with this method statement shall be considered as an integral part of this method statement and shall be read in conjunction with the same.



LG & LM certificate to be submitted.



All vehicles & equipment to be used in the work should be initially checked and approved by the authorized personnel.



Survey and measurement should be taken and marked.



Cable detection must be carried out.



Lifting Supervisor & crane operator will check & plan the travel routes prior to mobilization. Ensure travel routes & access to the jobsite is in good condition and free from obstruction.



Check and confirm crane set-up positioning.



Soil combaction must be carried out to set adequate ground condition for container and lifting work.



Concreting and steel reinforcement works must be finished and checked before lifting the container.

METHOD STATEMENT FOR MOBILISATION, DEMOBILISATION AND INSTALLATION OF OFFICE CONTAINER, EQUIPMENT, FENCING AND CARPARK.

Project:

Project No.:

LAYING OF GAS TRANSMISSION PIPELINES FROM MERANTI VIEW TO BANYAN AVENUE IN JURONG ISLAND

P4262

Rev: 00

Date: 16/02/2015

Page: 11 of 12



Container must be placed at least 300mm above from the ground level.



Working area shall be barricaded with proper devices & warning signs to display.



Unauthorized person are not allowed in the area barricaded off



Workers shall wear appropriate PPE for the task.



Safety Coordinator & Lifting supervisor shall be present at all time during lifting activity.

10.2 Work Execution Method 9.2.1 Lifting Work: 

All lifting tools, equipments and ropes used for lifting shall be inspected and certified by WSH regulations. Activities shall be done according to the proper method statement for lifting and mobilization.



Submit method statement and RA for review and approval by authorised person before commencing the mentioned work.



Lifting plan (as per attachment) shall be filled up and attached with load chart and LM certificate shall be submitted during application for permit.



Apply the lifting permit before work commence. Lifting supervisor will conduct tool box and brief the safe lifting operation before work start.



Prior to Lifting Works, it must have an approved Lifting permit and Lifting Plan. Which indicate the type of cranes & lifting gears accessories indicated. The lifting plan must be attached with the lifting permit and display in the lifting area.



Before starting the lifting work, the assigned people must wear proper PPE and adequate safety procedure must be implemented.



All employee and worker involved in the work should first undergo training or safety induction with Sembcorp WEC shall employ an experienced, competent and responsible Lifting supervisor to plan and execute lifting operations.

 

Barricade the marked location scheduled for unloading and lifting operation with safety signages.



To Provide safe work during mobilization and demobilization of office containers, there are consideration which take according to weight of the container.



The site supervisor should prepare the site area to be clean and clear from obstruction.



Positioned the Crane near the designated storage area and steel plate should be place over the landed of the crane out-rigger.



Attached the four hooks lifting gear with tag line to the hook attached to the tip of

METHOD STATEMENT FOR MOBILISATION, DEMOBILISATION AND INSTALLATION OF OFFICE CONTAINER, EQUIPMENT, FENCING AND CARPARK.

Project:

Project No.:

LAYING OF GAS TRANSMISSION PIPELINES FROM MERANTI VIEW TO BANYAN AVENUE IN JURONG ISLAND

P4262

Rev: 00

Date: 16/02/2015

Page: 12 of 12

lifting boom. 

Attached the four hooks to the four lifting slot corners of steel plates, container and ensure that the hooks were locked.



Lift one steel plate / sheet pile and container at a time and unload at the nearby designated storage area.



The load shall be controlled by means of tag lines to prevent the load from turning or swinging.



Repeat the process until all materials were unloaded.



Safety equipment must always present and ready for immediate use.

9.2.2 Fencing Work 

Manual and Machinery excavation work must be carried out safely for every 3m once as shown in the dwg.



The maximum depth of the excavation is 300mm.



Pre fabricated poles should be placed in the excavation and refilled again.



Hoarding sheet (860x600) must be installed using self tapping screw.

9.2.3 Roofing Work 

Determine the roofing material required.



Cut the timber to the precise length.



Fix the scaffolding pipe using clamp in the container vane edge.



Use stepladder to reach the top of container & hang up the hook to scaffold pipes to prevent falling.



Lift up timber one by one and fixed using GI wire to scaffolding pipe.



When the roof structure is finish, put the roofing sheet using 2” nails.



Finally do proper house keeping.

9.2.4 Installation of lightining protection. 

Bolt one No. of Air terminal in each corners of the top layer of the container.



Connect the four air terminal each other with the use of aluminium tape.



Connect the air terminal with copper rod in underground using aluminium tape.



Finally do proper house keeping.

METHOD STATEMENT FOR MOBILISATION, DEMOBILISATION AND INSTALLATION OF OFFICE CONTAINER, EQUIPMENT, FENCING AND CARPARK.

Project:

Project No.:

LAYING OF GAS TRANSMISSION PIPELINES FROM MERANTI VIEW TO BANYAN AVENUE IN JURONG ISLAND

P4262

Rev: 00

Date: 16/02/2015

Page: 13 of 12

9.2.5 Generator Installation. 

D……………………………….

9.2.6 Apron work. 

Setting out alignment and elevation



Power saw existing flexible pavement



Licensed operator will use an hydraulic excavator SK 100 with breaker attachment to break up existing flexible pavement



During the breaking / excavation, a bench men will be appointed to assist and guide the operator



After breaking the existing pavement, proceed to excavate to the sub grade level



The excavated material will be disposed off.

9.2.7 Erection of car park. 

The sub grade will be leveled and compacted by the 6 ton road roller machine



300mm thick of graded aggregate will be laid in two layer and compact by the 6 ton road roller machine



Expansion point will be provided at every 25m interval.



The car park erection and installation should be according to LTA/RD/SD99/PAV/6



Longitudinal joint will be provided at every lane though out (LTA/RD/SD99/PAV/6).



Formwork to be erected at site if necessary



225mm thick Grade 40 concrete will be laid with a layer of reinforcement B8 BRC, leveled, trowelled and roughen with broom finish to the proposed design level

9.2.2 Welding work. 

Welding shall be carried out in the 2G position (flat) wherever possible.



Prior to welding, the surfaces shall be cleaned free from rust, oil, paint, and moisture and other contaminants detrimental to welding.



Piping components to be welded shall be aligned in such a manner as not to result in developing residual stress.



The internal lining shall be cut back a minimum of 50mm to eliminate any blistering, prior to fit up.

METHOD STATEMENT FOR MOBILISATION, DEMOBILISATION AND INSTALLATION OF OFFICE CONTAINER, EQUIPMENT, FENCING AND CARPARK.

Project:

Project No.:

LAYING OF GAS TRANSMISSION PIPELINES FROM MERANTI VIEW TO BANYAN AVENUE IN JURONG ISLAND

P4262

Rev: 00

Date: 16/02/2015

Page: 14 of 12



Either grinding or gas cutting shall be applied in removing bridges etc.



In gas cutting, the toe of the weld shall be cut and finished to the base metal surface by grinding.



Welders carrying out welding, including tack welding shall be qualified in accordance with ASME Section IX or API 1104 as approved by the Client.



Welding consumables shall conform to the requirements of ASME Section II, Part C and shall be controlled in accordance with Control of Consumables Procedure.

9.2.2 Electrical work.

11. HEALTH, SAFETY AND ENVIRONMENT 

WEC HSE Manager shall ensure that the work is performed accordance to the approved Construction Safety Manual and precautions specified in the work permit. He shall ensure that barricades, warning tapes, warning signs, firefighting equipments and first aid kits are readily available at the working area.



Tool box talk shall be conducted on a daily basis to inform the workers of the recent safety issues and incidents and to get feedback of any unreported unsafe acts. Feedback will then be processed and resolved.

11.1 Safety Procedures 11.1.1 Area shall be barricaded adequately with warning barriers prior to any lift. 11.1.2 All Equipment shall be checked for good conditions before commencing the work. 11.1.3 Unauthorized persons shall be excluded from the area. 11.1.4 Lifting equipment capacity and correct load slinging will be verified. 11.1.5 When lifting, the personnel shall not remain in the lifting equipment work area. 11.1.6 Adequate standards shall be adopted for the construction of stages, planks, scaffolds, etc. 11.1.7 Adequate caution boards and warning signs shall be provided.

METHOD STATEMENT FOR MOBILISATION, DEMOBILISATION AND INSTALLATION OF OFFICE CONTAINER, EQUIPMENT, FENCING AND CARPARK.

Project:

Project No.:

LAYING OF GAS TRANSMISSION PIPELINES FROM MERANTI VIEW TO BANYAN AVENUE IN JURONG ISLAND

P4262

Rev: 00

Date: 16/02/2015

Page: 15 of 12

11.1.8 All lifting equipment shall have valid certificates. 11.1.9 Only trained and authorized personnel shall operate the vehicles / Machinaries. 11.1.10 All lifting gears and shackles used shall be approved type with valid certificates. 11.1.11 Electrical installations and equipment shall conform to standards. 11.1.12 Do not stand under suspended loads. 11.1.13 On completion of job, the area shall be cleared of any materials and keep clean and tidy. 11.1.14 Hazard analysis for hazardous operation shall be carried out prior to commencing the works. 12. ATTACHMENT 1. 2. 3. 4. 5. 6. 7. 8. 9. 10.

Proposed location for site plan. Proposed site office and worker rest area. Roof structure. Single line drawing for site office container. Certificates. Lifting Plan. Plot Plan LM, LG & callibration certificates. Appointment letter. Training matrix.

View more...

Comments

Copyright ©2017 KUPDF Inc.
SUPPORT KUPDF