Method statement for Lightning Protection System.docx

August 19, 2017 | Author: shareyhou | Category: Personal Protective Equipment, Electrical Conductor, Lightning, Safety, Electricity
Share Embed Donate


Short Description

Download Method statement for Lightning Protection System.docx...

Description

United Engineers (Singapore) Pte. Ltd. 257 Jalan Ahmad Ibrahim Singapore 629147 Tel: +6562660988 Fax: +6562686993

CONTENTS:

1. Scope of works 2. Project organization for Health & Safety Control 3. Health & Safety Risk and Control 4. Access / Egress 5. Lighting 6. Plant & Equipment 7. Personnel Training Certificate 8. Hazardous Materials & Substances 9. Waste Management 10. Special Control Measures Appendixes Appendix 1: Checklist for Lightning Protection System Appendix 2: Project Organization for Health & Safety control Appendix 3: Risk Assessment Appendix 4: Personnel Training Certificate

United Engineers (Singapore) Pte. Ltd. 257 Jalan Ahmad Ibrahim Singapore 629147 Tel: +6562660988 Fax: +6562686993

1. Scope of Works Scope of Activities This scope defines the minimum standards to be adopted when installing Lightning Protection System according to construction co-ordination drawings. A lightning protection system performs a simple task. It provides a specified path on which lightning can travel. When a building structure is equipped with a lightning protection system, the destructive power of the lightning strike is directed safely into the ground, leaving the structure and personal belongings unharmed. Site Procedure Site mobilization shall be done with real time monitoring the conditions & progress of builder works. Before commencement of the work, carry out examination of the physical condition of the area. Photographs should be taken where necessary, prior to commencement and during works.

United Engineers (Singapore) Pte. Ltd. 257 Jalan Ahmad Ibrahim Singapore 629147 Tel: +6562660988 Fax: +6562686993

Method Statement I.

Preparation stage a. The principle components of a conventional structural lightning protection system are 1. Air Termination Network 2. Down Conductors 3. Earth Termination Network 4. Bonding b. Specification allows the use of 'natural conductors' such as rebars and structural steelwork, provided that they are electrically continuous and adequately earthed. c. Prior to install lightning protection system examine paths to ensure all areas free of debris that may interfere with the installation. d. Inventory all items immediately after unloading, using manufactures packing list. e. All the related material should be stored away from high traffic areas.

II.

Installation Stage a. Site survey of the proposed Lightning Protection System based on approved CSD by foreman/sub-contractor together with Engineer. b. Installation must be carried out based on approved shop drawings & samples by foreman/ sub-contractor. c. Method and material used for the installation of Lightning protection system shall comply BS6651. (Protection of structure against lightning). d. The earth electrode pits location shall be marked out on site before commencement of hammering in electrodes. The earth pits shall be near the location of the down conductors. e. Those earth pits located in the basement shall be provided with seals to prevent f.

penetration of the ground slab. Electrodes are hammered into the ground and reading is taken to ensure that the

resistance is less than 10 ohms per electrode. g. Lightning Protection System accessories.

United Engineers (Singapore) Pte. Ltd. 257 Jalan Ahmad Ibrahim Singapore 629147 Tel: +6562660988 Fax: +6562686993

Earth rods

Earth rod clamps

Earth plates

Bonds and clamps

Earth points and bosses

Earth bars and disconnecting links

Static earthing kits

Compression connectors

Compression tools

Inspection pits and Earth rod seals

Accessories

h. Earth termination network: The means of dissipating the current to the general mass of earth. Choose an earth electrode to suit the ground conditions in the locality of the structure. Electrodes are available in the form of rods and plates (lattice or solid)

i.

Earth rod clamps: Select a high copper content alloy earth rod clamp for the connection of the earthing conductor to the earth rod. In this below ground

United Engineers (Singapore) Pte. Ltd. 257 Jalan Ahmad Ibrahim Singapore 629147 Tel: +6562660988 Fax: +6562686993

application, the clamp must ensure a good electrical contact and resist corrosion throughout the lifetime of the installation.

j.

Earth inspection chambers: Select an earth inspection chamber to protect the earth electrode connections.

k. Bonding: Bonding is the most commonly employed method of avoiding the damaging effects of side flashing. All continuous metalwork should be considered for bonding. All metallic services, eg cable armouring, gas, water or steam piping, entering the building should also be bonded as directly as possible to the earth termination network.

Select the correct type of metalwork bond for the application, ie a flat column face, a circular rainwater pipe or a ribbed reinforcing bar l.

Depending on the specification, the down conductor tapes can be thermal weld to the rebar and casted in the column or run in a continuous strip on the surface of the

United Engineers (Singapore) Pte. Ltd. 257 Jalan Ahmad Ibrahim Singapore 629147 Tel: +6562660988 Fax: +6562686993

external wall. m. For casting of column, floor, continuous supervision is necessary to ensure that the tape is extended before the main builder close up form work before casting. Approved clamps to be used for extension tape. n. Down conductor network: The down conductor system is the means of carrying the current of a lightning strike safely to the earth termination network.

o. Conductor fixings: Select the correct system of fixings for each part of the conductor system

p. Air termination network: The air termination network is the point of connection for a lightning strike. It typically consists of a meshed conductor arrangement covering the roof of the structure. Use air terminals in the form of vertical air rods for the protection of prominent roof top features or equipment. Use strike pads to expose concealed conductors

United Engineers (Singapore) Pte. Ltd. 257 Jalan Ahmad Ibrahim Singapore 629147 Tel: +6562660988 Fax: +6562686993

q. Air terminal bases: Choose the correct air terminal base. This will ensure that the vertical air rods are both solidly fixed to the fabric of the structure and have a low resistance connection to the conductor network

r.

Conductor jointing clamps: Select a component for the interconnection of multiple conductors or for changes of direction. Jointing clamps will ensure a low resistance, corrosion resistant connection.

s. Test clamps: In order to allow periodic disconnection and testing of the earth termination network, select a test clamp to be placed within the run of each down conductor.

United Engineers (Singapore) Pte. Ltd. 257 Jalan Ahmad Ibrahim Singapore 629147 Tel: +6562660988 Fax: +6562686993

t.

After installation, Engineer- in-charge shall check the complete works and complete the inspection check list for Lightning Protection System installation works (See Annecure:1)

u. Engineer-in-charge shall arrange and request for inspection with the Owner’s representative Residential Technical Officer (RTO) using approved Main con Request for Inspection (RIN) form.

III.

Preferred Materials

Lightning Protection

Furse, Emtech and Heng

System

2. Project organization for Health & Safety Control (See annex. 3) 3. Health & Safety risks and controls (Please refer to attach Risk assessment in respect to above scope of works – Annex.4)

4. Acess / Egress Proper step ladders shall be provided for access and egress into Distribution board as applicable.

5. Lighting Adequate temporary/task lighting shall be provided if work to be carried at night or at dark places.

United Engineers (Singapore) Pte. Ltd. 257 Jalan Ahmad Ibrahim Singapore 629147 Tel: +6562660988 Fax: +6562686993

6. Plant & Equipment S/N 1 2 3 4

Description Center punch Brace Hammer Electrical drill (only for surface installation works)

Unit 1 lot 1 lot 1 lot 1 lot

5

Diagonal-Cutting Pliers

1 lot

6

Wire Stripper/Cutter with Spring

1 lot

7

Side-Cutting Pliers

1 lot

8

Level

1lot

9

Shank Screwdriver

1 lot

10

P.P.E. – Personal Protective Equipment (safety helmet, Boots, gloves & safety vest )

1 set per worker

*The above machinery & Equipment used quantity will be varied depending on site conditions and production rate.

7. Personnel Training Certificate (Annexure 4)

8. Waste management The Rubbish which would be created from our scope of works will be disposed to the designated dumping ground.

9. Special Control measures The following general control measures against Safety, Environment and Quality shall be required for our scope of work and special control measures are not applicable for us 

Proper PPE must be worn at all time



Permit to work at height > 2m where applicable

United Engineers (Singapore) Pte. Ltd. 257 Jalan Ahmad Ibrahim Singapore 629147 Tel: +6562660988 Fax: +6562686993



Lifting operation permit (using crane) where applicable.



Confined space permit where applicable.

 Approved work method statement and risk assessment will be made available to site. All workers doing the work shall be briefed on this method statement and risk assessment. Appendix

United Engineers (Singapore) Pte. Ltd. 257 Jalan Ahmad Ibrahim Singapore 629147 Tel: +6562660988 Fax: +6562686993

ANNEX 1: Checklist for Light Protection System Installation

United Engineers (Singapore) Pte. Ltd. 257 Jalan Ahmad Ibrahim Singapore 629147 Tel: +6562660988 Fax: +6562686993

ANNEX 2: Project Organization for Health & Safety Control

United Engineers (Singapore) Pte. Ltd. 257 Jalan Ahmad Ibrahim Singapore 629147 Tel: +6562660988 Fax: +6562686993

ANNEX 3: Risk Assessment

United Engineers (Singapore) Pte. Ltd. 257 Jalan Ahmad Ibrahim Singapore 629147 Tel: +6562660988 Fax: +6562686993

ANNEX 4: Personnel Training Certificate

View more...

Comments

Copyright ©2017 KUPDF Inc.
SUPPORT KUPDF