Method Statement for Conduit Installation Including Accessories PVC & GI

April 7, 2017 | Author: gangadharan000 | Category: N/A
Share Embed Donate


Short Description

Download Method Statement for Conduit Installation Including Accessories PVC & GI...

Description

8/6/2015

Method Statement for Conduit Installation Including Accessories PVC & GI

Home

Download Method Statements

Privacy Policy

Support

Project Management

Inspection Checklists

START A CONVERSATION Like

Share 367 people like this.

SUBSCRIBE You will Receive Each New Method Statement In Your Email as Soon as It Is Published. Enter your email address:

Subscribe Delivered by FeedBurner "We recommend these Project Management Templates for delivering your projects successfully."

2

Tweet

Project HSE Plan

Disclaimer

Request A Method Statement

Method Statement for Conduit Installation Including Accessories PVC & GI Like

Project Quality Plan

0

StumbleUpon  

9

Email

Share

Below  is  a comprehensive  method statement  for  conduit installation  which  can  be  used for purpose of any project and it can  be  approved  easily  by consultants because it covers all

POPULAR METHODSTATEMENTS

List Of Mandatory Tests For Transformers August 5th, 2015

aspects  of  a  standard  conduit installation method.

The following routine tests specified in IEC726 shall be carried out at the manufacturer's works on  [...]

We  have  also  given  the download  link  for  method

List Of Common Tests For Diesel Generator Testing

statement  for  conduit  installation on  below  page  which  will  help you  to  easily  modify  the  word and  excel  files  that  also  include ITP,  inspection  checklists  and

August 5th, 2015 The following site tests shall be carried out in order to determine whether the DG material and appa [...]

Method Statement For Testing And Commissioning Of Laboratory Air Flow Control System & Fumes

http://www.methodstatementhq.com/method­statement­installation­gi­conduits­accessories.html

1/17

8/6/2015

Of Laboratory Air Flow Control System & Fumes Hood Monitoring

Method Statement for Conduit Installation Including Accessories PVC & GI

risk assessment etc.

July 27th, 2015

TABLE OF CONTENTS 1. Purpose

 

METHOD STATEMENT FOR THE COMMISSIONING OF EC2001 EASI­CHECK EMERGENCY LIGHTING MONITORING SYSTEM WITH OR WITHOUT SITE MONITOR/GRAPHICS PACKAGE

2. Scope 3. Legislation and Code of Practice

July 20th, 2015 This method statement is for commissioning of Easi­Check Emergency Lighting Monitoring Systems compr [...]

4. Reference 5. Definitions6. Resources

Below is the method statement description for performing the testing and commissioning of laboratory [...]

 

Download Method Statement for Installation Of Dehumidifiers

6.1. Equipment

July 13th, 2015

6.2. Safety of

Download Method Statement for Installation Of Dehumidifiers  Download package contains the Method S [...]

Equipment’s 7. Safety Precautions

Download Method Statement for Installation Of Earthing & Bonding System & Accessories

7.1. Construction

July 12th, 2015

Hazards

Download Method Statement for Installation Of Earthing & Bonding System & Accessories  Down [...]

7.2. Personal Protective Equipment 7.3. Safety Training and Emergency procedures

Download Method Statement for Installation Of Chilled Water Pressurization Unit & Expansion Tank July 7th, 2015 Download Method Statement for Installation Of Chilled Water Pressurization

7.4. First Aid

Unit & Expansion Tank [...]

8.Detailed Construction Sequence (Methodology) 8.1. Procedure 9.Construction Program9.1 Housekeeping9.2 Protection of Executed Works9.3  Responsibilities 9.4 Records 10.Inspection and Testing 11.Related Forms http://www.methodstatementhq.com/method­statement­installation­gi­conduits­accessories.html

2/17

8/6/2015

Method Statement for Conduit Installation Including Accessories PVC & GI

12.Attachments

1. Purpose This  document  describes  the method  statement  for  conduit installation  which  includes  GI  & PVC  conduits  and  accessories for  the  project,  and  to  ensure that  all  concerned  persons  are familiar  with  the  sequence  of activities, utilization of resources, and  execution  of  the  works  in compliance  with  applicable Safety  and  Quality  Procedures, and  Project  Documents  and Specification. DOWNLOAD METHOD STATEMENT IN WORD FORMAT

2. Scope of Works For  Installation  of GI Conduits This  method  statement  is intended  to  outline  the  activities and  the  methods  used  for  the Installation  of  GI  conduits  and accessories.  All  activities  will  be carried  out  in  accordance  with the  contract  details  and  in  full compliance  to  the  Contract Specifications  and  documents. All  work  within  the  rights­of­way of  the  standards  and specifications  will  be  done  in compliance  with  requirements issued by authorities.

2 Like

0 Tweet

3.  Legislation  and  Code  of http://www.methodstatementhq.com/method­statement­installation­gi­conduits­accessories.html

3/17

8/6/2015

Method Statement for Conduit Installation Including Accessories PVC & GI

Practice All related codes and standards referenced in the project electrical specifications.

9

4. Reference Email

Contract Specifications

Share

Approved Drawings

5. Definitions 6. Resources 6.1. Equipment / Tools NO.

DESCRIPTION

1

Bending machine

2

Die sets

3

Measuring tape

4

Screw driver

5

Chalk mate thread

6

Oil

7

Drill machine

8

Screw driver

6.2 Safety of Equipment’s Necessary  measures  will  be taken  for  the  safety  of  the equipment  and  any  other  works affected  by  the  works  subject  of this  document.  Relevant  entities which  might  require  protection include  any  such  works  in  the vicinity of the area of work or on the  service  access  or  discharge path. http://www.methodstatementhq.com/method­statement­installation­gi­conduits­accessories.html

4/17

8/6/2015

Method Statement for Conduit Installation Including Accessories PVC & GI

The  construction  team  will ensure  that  any  such requirements are documented.

  7.  Health,  Safety  & the Environment The hazards identified above will be controlled under the overall Project Safety Plan which is a separate document communicated to all parties on the project. 7.2. Personal Protective Equipment (tick as appropriate) The works subject of this document requires that the PPE must be used as required. 7.3. Safety Training and Emergency procedures Before commencing any works, all employees will attend a site safety induction training to ensure all safety measures are understood and implemented and to cover specific procedures in case of emergency. If necessary, practical training exercises will be conducted on escape routes, signage, evacuation and rescue. DOWNLOAD METHOD STATEMENT IN WORD FORMAT 7.4. First Aid Prior to the commencement of work, arrangements will be made for medical facilities and medical personnel to be available from prompt attention to the injured person. The contractor’s vehicle assigned to the job site will be used for transporting the injured person to the first aid station and to the nearest hospital when required. http://www.methodstatementhq.com/method­statement­installation­gi­conduits­accessories.html

5/17

8/6/2015

Method Statement for Conduit Installation Including Accessories PVC & GI

8. method statement for conduit installation General Procedure for conduit installation is given below after which area wise details are provided like method statement for conduit installation in slab, walls and exposed areas etc. Steps for exposed conduit installation on walls & ceilings etc. Step 1: Take the following drawings approved for construction. GI  conduits  complete  with 

layout section

details. MEP  coordination  drawing complete  with  section details. Architectural Drawing Step 2: Procedure of method statement for conduit installation 1.  Check  the  route  of  GI conduiting  to  make  sure that  it  is  free  from  debris and  obstruction  of  any other activity. 2.  Arrange  scaffolding  of sufficient  height  which  is checked  by  scaffolding http://www.methodstatementhq.com/method­statement­installation­gi­conduits­accessories.html

6/17

8/6/2015

Method Statement for Conduit Installation Including Accessories PVC & GI

inspector/  safety  officer before  using  the  same  for installation. 3.  Mark  the  reference  points on wall/ column as per civil architectural drawing. 4.  Identify  the  circuit  start point  and  end  points  to mark  the  conduit  route  as per approved drawings. 5.  Make  hole  in  wall/concrete using  drill  machine  for rawal  plug,  fix  rawal  plug inside  hole  and  then  fix base  of  saddle  by  screw every 2 meter span. 6.  Use  recommended  and approved  GI  conduiting  & bends as per site condition and  drawing.  Remove sharp edge of cut length of conduit by filing. 7.  Install  conduits  and  all accessories  as  per approved  shop  drawing and  tight  with  saddle  and screw,  make  joints  using threaded fittings. 8.  Installation  of  GI  conduits shall  be  checked  by internal quality engineer as per drawings and quality of installation  before  offering consultant/client  inspection.

for

9.  Conduits  are  not  to  cross pipe  shafts,  vents  or opening. 10.  Additional threaded cuts on GI  conduits  are  to  be painted  with  zinc  based coating  corrosion.

resistant 

to

11.  Approved  clamps  to  be used for the supports. 12.  Maximum  spacing  of supports  for  different conduit  sizes  to  be http://www.methodstatementhq.com/method­statement­installation­gi­conduits­accessories.html

7/17

8/6/2015

Method Statement for Conduit Installation Including Accessories PVC & GI

clarified. 13.  Conduits on walls are to be run  neatly,  horizontally  or vertically. 14.  Conduits are to be used for exposed  installations  over false  ceilings  when  the false  ceiling  is  used  as return plenum. 15.  Conduits  is  to  be  used  for all  installation  in  elevator machine  room  and  shafts, electrical  equipment rooms,  parking  floor,  solid waste rooms, etc. 16.  All  works  on  site  will  be  as per  electrical  specifications and  as  per  applicable electrical  wiring regulations. 17.  The  risk  mentioning 

assessment necessary

control  measures  shall  be attached  to  this  method statement  to  follow  and implement  the requirements

method statement for conduit installation In Concrete Slab Following tools should be arranged before starting the job. Dia (20 & 25 ) mm pipe Bender Mini Hacksaw Frame with Blades Choke Lime Powder with sufficient length of Thread 500gm Hammer Measuring Tape End Cutter ( Kalwa )

http://www.methodstatementhq.com/method­statement­installation­gi­conduits­accessories.html

8/17

8/6/2015

Method Statement for Conduit Installation Including Accessories PVC & GI

PVC Conduit Installation Procedure  Ensure that the civil people have finished ply/post tension work on the slab. Arrange the approved shop drawings for the area of installation. Mark first the wall location for lower floor in slab as per latest Architecture layout so that it will be easy to locate the drops for switch, thermostat and any other drops required for electrical system. Mark the opening size in Electrical Room and Telephone room as per approved electrical drawing. Mark the Electrical points on the slab as per approved Electrical Layout and fix proper shape and size of the Circular Box with the help of nail/mess in case of plywood slab and provide steel bar chairs for fixing the box in case of post tension slab. Just after completing the first layer of steel, start pvc conduiting work with different sizes of conduit based on electrical system requirements and as per drawings. Always loop the two way switches with 20 mm conduit as the number of wires will be more and only switch drop pipe will not be sufficient for pulling all these wires. Try to avoid the overlapping of conduits and keep some distance between the conduits for http://www.methodstatementhq.com/method­statement­installation­gi­conduits­accessories.html

9/17

8/6/2015

Method Statement for Conduit Installation Including Accessories PVC & GI

low current and power/Lights. Just after completing the work tight the conduits with binding wire and mark the circuit numbers. identification for the raised pipe in slab for upper slab to be done for power, TV and telephone systems and closing the mouth of pipe with the help of masking tape . The site Engineer/Foreman should check the proper size of conduit and circular box, opening size in both Electrical and Telephone room and be sure the work is completed as per approved Electrical shop drawing. Before the concrete pouring the PVC conduit installation to be inspected and approved by consultant/client/contractor. During concrete pouring, keep electricians for taking care of conduit to avoid any damage by others or dislocation of joints.

method statement for conduit installation (GI Box & GI/PVC Conduit in Walls) Following tools should be arranged before starting the job. 9” Grinder with cutting disc Mini Hacksaw Frame with Blades White chalk /Marker 1 KG Hammer Measuring Tape Sprit Level Water Level Pipe http://www.methodstatementhq.com/method­statement­installation­gi­conduits­accessories.html

10/17

8/6/2015

Method Statement for Conduit Installation Including Accessories PVC & GI

Point & Flat Chisels Trowel Pipe Bender

Method Statement for Conduit Installation inside the Wall – PVC Ensure that the civil people have finished block wall and clearance is given to proceed for electrical works. Check the required reference markings are available for FFL (finished floor levels). Mark the location of switch/socket and conduit route on proper height based on approved shop drawing. Ensure the box size and accordingly cut a bit larger size of box in marked place of block wall with sufficient depth. Start cutting the marked place for conduit run with the help of grinder and chip with hammer after cutting. Fix the GI Metal box of appropriate size and level with the help of spirit level. The bottom portion of box should match the marked level as per consultant approved height for switch/ socket and/or as per local applicable wiring regulation requirements. Apply cement filler to fix the box properly and leave for setting, insert the required lengths of conduits on their http://www.methodstatementhq.com/method­statement­installation­gi­conduits­accessories.html

11/17

8/6/2015

Method Statement for Conduit Installation Including Accessories PVC & GI

paths and don’t connect with boxes until next day. Next day, after setting of box connect the dropped conduits for switch/socket to the box. Make sure the conduits are not visible from outside their route which could lead improper plastering. Before the plastering work issue the inspection requests for client so that approval can be taken.

GI Conduit Installation (Exposed Conduiting) Take the following shop drawings approved for construction. GI Conduiting layout complete with section details. MEP coordination drawing complete with section details. Architectural Drawing

Check  the  route  of  GI Conduiting free from debris and  no  obstruction  of  any other  activity.  Arrange scaffolding  of  sufficient height  approved  by  HSE officer. Mark  the  reference  points on wall/ column as per civil architectural drawing. Identify  the  circuit  start point  and  end  &  mark  GI Conduiting  route  as  per http://www.methodstatementhq.com/method­statement­installation­gi­conduits­accessories.html

12/17

8/6/2015

Method Statement for Conduit Installation Including Accessories PVC & GI

approved drawings. Make  hole  in  concrete  for anchor  bolts/rawel  plug  & fix  rawel  plug  inside  hole then  fix  base  of  saddle  by screw every 1m span. Use  approved  GI Conduiting  &  bends  as  per site  condition  and  drawing. Remove  sharp  edge  of  cut length of conduit by filing. Join  the  lengths  using  the threaded joints and fittings. Install  conduit  and  tight with saddle and screw. Make  earthing  of  GI Conduiting  &  Check  for continuity. Apply  the  zinc  paint  on  the exposed  threaded  area which is not covered. Installation  of  GI Conduiting  shall  be checked by internal QA/QC Engineer  as  per  drawings and  quality  of  installation before  offering consultant/client  for inspection. 9. Construction Program As per main project program 9.1 Housekeeping The work area shall be maintained neat and tidy as reasonably practical at all times.  9.2 Protection of Executed Works Executed works in areas were other works are still being carried out shall be protected as per the contract requirements.  9.3 Responsibilities 9.4 Records http://www.methodstatementhq.com/method­statement­installation­gi­conduits­accessories.html

13/17

8/6/2015

Method Statement for Conduit Installation Including Accessories PVC & GI

In accordance with the Quality Management System, the following records will be maintained as documentary evidence of the establishment of this method statement: 10. Inspection and Testing In Process works shall be monitored for quality of workmanship and installation against approved shop drawings by the relevant supervisor. All works shall be inspected for conformance to specification. The inspection formats shall be used in accordance with the requirements of the main contractor UNEC. An inspection request for the PVC conduits and boxes shall be submitted one day prior to the consultant. 11. Related Forms As per required forms, from main contractor and consultant. 12. Attachments ITP Installation Checklists Risk Assessment DOWNLOAD METHOD STATEMENT IN WORD FORMAT Share this:

 Facebook

2

 Reddit

 Google

 Tumblr

More Method Statements: http://www.methodstatementhq.com/method­statement­installation­gi­conduits­accessories.html

14/17

8/6/2015

Method Statement for Conduit Installation Including Accessories PVC & GI

1.  Method Of Statement For Installation of GI Conduits & Accessories For Electrical Works Method Of Statement For Installation of GI Conduits & Accessories For Electrical Works is given below for the reference of our visitors if you want to use this method statement...

2.  Method Statement For Installation of Motor Control Centre MCC Panel This below procedure shall be followed for the installation of MCC panels.All components / materials received at site shall be inspected and ensured against approved material submittal. Any  discrepancies, damages etc...

3.  Testing & Commissioning Of CCTV Cameras – Method Statement The objectives of the process of testing and commissioning of CCTV camera is to verify proper functioning of the equipments and system after installation, and to ensure the performance of the installed system...

4.  Method Statement For Installation Of CCTV Camera Security System The purpose of this method statement is to provide guidelines and steps for the cctv installation of security systems by describing the Work to be executed, how it is to...

5.  Method Statement For Fire Alarm System Installation & Testing Below is the method statement for the installation of fire alarm system which can be modified for different type of systems like HSSD or Vesda etc. The steps are very...

http://www.methodstatementhq.com/method­statement­installation­gi­conduits­accessories.html

15/17

8/6/2015

Method Statement for Conduit Installation Including Accessories PVC & GI

6.  Method Statement For Installation Of Emergency Lighting System The below method statement describes some standard operating steps to install the emergency lighting system for any kind of project the method statement can be modified as per different project...

7.  Method Statement For Installation Of Electric Water Heaters The procedures for the installation and fixing of electric water heaters with supports and accessories shall be done as per the manufacturer’s recommended guidelines and installation instructions and as per...

8.  METHOD STATEMENT FOR TESTING & COMMISSIONING OF PRESSURIZATION UNIT The purpose of this procedure is to define the step by step method to implement the correct practices for the pre­commissioning & commissioning of Pressurization Unit through the guidelines contained...

9.  Method Of Statement For Installation of wires and cables – Wiring Below is the list of equipment / Tools required for installation of wires and cables, which cab be used for different projects after doing the customization as per the project...

10.  METHOD STATEMENT FOR INSTALLATION OF MDB, SMDB, DB, MCC & CAPACITOR BANK 1.0 PURPOSE The purpose of generating this method statement is to define the procedure step by step to implement the correct practices for Installation of MDB, SMDB, DB, MCC &...

http://www.methodstatementhq.com/method­statement­installation­gi­conduits­accessories.html

16/17

8/6/2015

Method Statement for Conduit Installation Including Accessories PVC & GI

Tags: architectural, GI Conduit, Installation of GI Conduits & Accessories, Method Statement, Method Statement For Conduit Installation, PVC Conduit, statement, works ◀ Installation & Leakage Testing Of Drainage Piping Method Of Statement for Testing & Commissioning Of Water Filtration System ▶

Copyright 2015. All Rights Reserved. Copying and republishing of our content is not allowed.

http://www.methodstatementhq.com/method­statement­installation­gi­conduits­accessories.html

17/17

View more...

Comments

Copyright ©2017 KUPDF Inc.
SUPPORT KUPDF