Method Statement for Conduit Installation Including Accessories PVC & GI
April 7, 2017 | Author: gangadharan000 | Category: N/A
Short Description
Download Method Statement for Conduit Installation Including Accessories PVC & GI...
Description
8/6/2015
Method Statement for Conduit Installation Including Accessories PVC & GI
Home
Download Method Statements
Privacy Policy
Support
Project Management
Inspection Checklists
START A CONVERSATION Like
Share 367 people like this.
SUBSCRIBE You will Receive Each New Method Statement In Your Email as Soon as It Is Published. Enter your email address:
Subscribe Delivered by FeedBurner "We recommend these Project Management Templates for delivering your projects successfully."
2
Tweet
Project HSE Plan
Disclaimer
Request A Method Statement
Method Statement for Conduit Installation Including Accessories PVC & GI Like
Project Quality Plan
0
StumbleUpon
9
Email
Share
Below is a comprehensive method statement for conduit installation which can be used for purpose of any project and it can be approved easily by consultants because it covers all
POPULAR METHODSTATEMENTS
List Of Mandatory Tests For Transformers August 5th, 2015
aspects of a standard conduit installation method.
The following routine tests specified in IEC726 shall be carried out at the manufacturer's works on [...]
We have also given the download link for method
List Of Common Tests For Diesel Generator Testing
statement for conduit installation on below page which will help you to easily modify the word and excel files that also include ITP, inspection checklists and
August 5th, 2015 The following site tests shall be carried out in order to determine whether the DG material and appa [...]
Method Statement For Testing And Commissioning Of Laboratory Air Flow Control System & Fumes
http://www.methodstatementhq.com/methodstatementinstallationgiconduitsaccessories.html
1/17
8/6/2015
Of Laboratory Air Flow Control System & Fumes Hood Monitoring
Method Statement for Conduit Installation Including Accessories PVC & GI
risk assessment etc.
July 27th, 2015
TABLE OF CONTENTS 1. Purpose
METHOD STATEMENT FOR THE COMMISSIONING OF EC2001 EASICHECK EMERGENCY LIGHTING MONITORING SYSTEM WITH OR WITHOUT SITE MONITOR/GRAPHICS PACKAGE
2. Scope 3. Legislation and Code of Practice
July 20th, 2015 This method statement is for commissioning of EasiCheck Emergency Lighting Monitoring Systems compr [...]
4. Reference 5. Definitions6. Resources
Below is the method statement description for performing the testing and commissioning of laboratory [...]
Download Method Statement for Installation Of Dehumidifiers
6.1. Equipment
July 13th, 2015
6.2. Safety of
Download Method Statement for Installation Of Dehumidifiers Download package contains the Method S [...]
Equipment’s 7. Safety Precautions
Download Method Statement for Installation Of Earthing & Bonding System & Accessories
7.1. Construction
July 12th, 2015
Hazards
Download Method Statement for Installation Of Earthing & Bonding System & Accessories Down [...]
7.2. Personal Protective Equipment 7.3. Safety Training and Emergency procedures
Download Method Statement for Installation Of Chilled Water Pressurization Unit & Expansion Tank July 7th, 2015 Download Method Statement for Installation Of Chilled Water Pressurization
7.4. First Aid
Unit & Expansion Tank [...]
8.Detailed Construction Sequence (Methodology) 8.1. Procedure 9.Construction Program9.1 Housekeeping9.2 Protection of Executed Works9.3 Responsibilities 9.4 Records 10.Inspection and Testing 11.Related Forms http://www.methodstatementhq.com/methodstatementinstallationgiconduitsaccessories.html
2/17
8/6/2015
Method Statement for Conduit Installation Including Accessories PVC & GI
12.Attachments
1. Purpose This document describes the method statement for conduit installation which includes GI & PVC conduits and accessories for the project, and to ensure that all concerned persons are familiar with the sequence of activities, utilization of resources, and execution of the works in compliance with applicable Safety and Quality Procedures, and Project Documents and Specification. DOWNLOAD METHOD STATEMENT IN WORD FORMAT
2. Scope of Works For Installation of GI Conduits This method statement is intended to outline the activities and the methods used for the Installation of GI conduits and accessories. All activities will be carried out in accordance with the contract details and in full compliance to the Contract Specifications and documents. All work within the rightsofway of the standards and specifications will be done in compliance with requirements issued by authorities.
2 Like
0 Tweet
3. Legislation and Code of http://www.methodstatementhq.com/methodstatementinstallationgiconduitsaccessories.html
3/17
8/6/2015
Method Statement for Conduit Installation Including Accessories PVC & GI
Practice All related codes and standards referenced in the project electrical specifications.
9
4. Reference Email
Contract Specifications
Share
Approved Drawings
5. Definitions 6. Resources 6.1. Equipment / Tools NO.
DESCRIPTION
1
Bending machine
2
Die sets
3
Measuring tape
4
Screw driver
5
Chalk mate thread
6
Oil
7
Drill machine
8
Screw driver
6.2 Safety of Equipment’s Necessary measures will be taken for the safety of the equipment and any other works affected by the works subject of this document. Relevant entities which might require protection include any such works in the vicinity of the area of work or on the service access or discharge path. http://www.methodstatementhq.com/methodstatementinstallationgiconduitsaccessories.html
4/17
8/6/2015
Method Statement for Conduit Installation Including Accessories PVC & GI
The construction team will ensure that any such requirements are documented.
7. Health, Safety & the Environment The hazards identified above will be controlled under the overall Project Safety Plan which is a separate document communicated to all parties on the project. 7.2. Personal Protective Equipment (tick as appropriate) The works subject of this document requires that the PPE must be used as required. 7.3. Safety Training and Emergency procedures Before commencing any works, all employees will attend a site safety induction training to ensure all safety measures are understood and implemented and to cover specific procedures in case of emergency. If necessary, practical training exercises will be conducted on escape routes, signage, evacuation and rescue. DOWNLOAD METHOD STATEMENT IN WORD FORMAT 7.4. First Aid Prior to the commencement of work, arrangements will be made for medical facilities and medical personnel to be available from prompt attention to the injured person. The contractor’s vehicle assigned to the job site will be used for transporting the injured person to the first aid station and to the nearest hospital when required. http://www.methodstatementhq.com/methodstatementinstallationgiconduitsaccessories.html
5/17
8/6/2015
Method Statement for Conduit Installation Including Accessories PVC & GI
8. method statement for conduit installation General Procedure for conduit installation is given below after which area wise details are provided like method statement for conduit installation in slab, walls and exposed areas etc. Steps for exposed conduit installation on walls & ceilings etc. Step 1: Take the following drawings approved for construction. GI conduits complete with
layout section
details. MEP coordination drawing complete with section details. Architectural Drawing Step 2: Procedure of method statement for conduit installation 1. Check the route of GI conduiting to make sure that it is free from debris and obstruction of any other activity. 2. Arrange scaffolding of sufficient height which is checked by scaffolding http://www.methodstatementhq.com/methodstatementinstallationgiconduitsaccessories.html
6/17
8/6/2015
Method Statement for Conduit Installation Including Accessories PVC & GI
inspector/ safety officer before using the same for installation. 3. Mark the reference points on wall/ column as per civil architectural drawing. 4. Identify the circuit start point and end points to mark the conduit route as per approved drawings. 5. Make hole in wall/concrete using drill machine for rawal plug, fix rawal plug inside hole and then fix base of saddle by screw every 2 meter span. 6. Use recommended and approved GI conduiting & bends as per site condition and drawing. Remove sharp edge of cut length of conduit by filing. 7. Install conduits and all accessories as per approved shop drawing and tight with saddle and screw, make joints using threaded fittings. 8. Installation of GI conduits shall be checked by internal quality engineer as per drawings and quality of installation before offering consultant/client inspection.
for
9. Conduits are not to cross pipe shafts, vents or opening. 10. Additional threaded cuts on GI conduits are to be painted with zinc based coating corrosion.
resistant
to
11. Approved clamps to be used for the supports. 12. Maximum spacing of supports for different conduit sizes to be http://www.methodstatementhq.com/methodstatementinstallationgiconduitsaccessories.html
7/17
8/6/2015
Method Statement for Conduit Installation Including Accessories PVC & GI
clarified. 13. Conduits on walls are to be run neatly, horizontally or vertically. 14. Conduits are to be used for exposed installations over false ceilings when the false ceiling is used as return plenum. 15. Conduits is to be used for all installation in elevator machine room and shafts, electrical equipment rooms, parking floor, solid waste rooms, etc. 16. All works on site will be as per electrical specifications and as per applicable electrical wiring regulations. 17. The risk mentioning
assessment necessary
control measures shall be attached to this method statement to follow and implement the requirements
method statement for conduit installation In Concrete Slab Following tools should be arranged before starting the job. Dia (20 & 25 ) mm pipe Bender Mini Hacksaw Frame with Blades Choke Lime Powder with sufficient length of Thread 500gm Hammer Measuring Tape End Cutter ( Kalwa )
http://www.methodstatementhq.com/methodstatementinstallationgiconduitsaccessories.html
8/17
8/6/2015
Method Statement for Conduit Installation Including Accessories PVC & GI
PVC Conduit Installation Procedure Ensure that the civil people have finished ply/post tension work on the slab. Arrange the approved shop drawings for the area of installation. Mark first the wall location for lower floor in slab as per latest Architecture layout so that it will be easy to locate the drops for switch, thermostat and any other drops required for electrical system. Mark the opening size in Electrical Room and Telephone room as per approved electrical drawing. Mark the Electrical points on the slab as per approved Electrical Layout and fix proper shape and size of the Circular Box with the help of nail/mess in case of plywood slab and provide steel bar chairs for fixing the box in case of post tension slab. Just after completing the first layer of steel, start pvc conduiting work with different sizes of conduit based on electrical system requirements and as per drawings. Always loop the two way switches with 20 mm conduit as the number of wires will be more and only switch drop pipe will not be sufficient for pulling all these wires. Try to avoid the overlapping of conduits and keep some distance between the conduits for http://www.methodstatementhq.com/methodstatementinstallationgiconduitsaccessories.html
9/17
8/6/2015
Method Statement for Conduit Installation Including Accessories PVC & GI
low current and power/Lights. Just after completing the work tight the conduits with binding wire and mark the circuit numbers. identification for the raised pipe in slab for upper slab to be done for power, TV and telephone systems and closing the mouth of pipe with the help of masking tape . The site Engineer/Foreman should check the proper size of conduit and circular box, opening size in both Electrical and Telephone room and be sure the work is completed as per approved Electrical shop drawing. Before the concrete pouring the PVC conduit installation to be inspected and approved by consultant/client/contractor. During concrete pouring, keep electricians for taking care of conduit to avoid any damage by others or dislocation of joints.
method statement for conduit installation (GI Box & GI/PVC Conduit in Walls) Following tools should be arranged before starting the job. 9” Grinder with cutting disc Mini Hacksaw Frame with Blades White chalk /Marker 1 KG Hammer Measuring Tape Sprit Level Water Level Pipe http://www.methodstatementhq.com/methodstatementinstallationgiconduitsaccessories.html
10/17
8/6/2015
Method Statement for Conduit Installation Including Accessories PVC & GI
Point & Flat Chisels Trowel Pipe Bender
Method Statement for Conduit Installation inside the Wall – PVC Ensure that the civil people have finished block wall and clearance is given to proceed for electrical works. Check the required reference markings are available for FFL (finished floor levels). Mark the location of switch/socket and conduit route on proper height based on approved shop drawing. Ensure the box size and accordingly cut a bit larger size of box in marked place of block wall with sufficient depth. Start cutting the marked place for conduit run with the help of grinder and chip with hammer after cutting. Fix the GI Metal box of appropriate size and level with the help of spirit level. The bottom portion of box should match the marked level as per consultant approved height for switch/ socket and/or as per local applicable wiring regulation requirements. Apply cement filler to fix the box properly and leave for setting, insert the required lengths of conduits on their http://www.methodstatementhq.com/methodstatementinstallationgiconduitsaccessories.html
11/17
8/6/2015
Method Statement for Conduit Installation Including Accessories PVC & GI
paths and don’t connect with boxes until next day. Next day, after setting of box connect the dropped conduits for switch/socket to the box. Make sure the conduits are not visible from outside their route which could lead improper plastering. Before the plastering work issue the inspection requests for client so that approval can be taken.
GI Conduit Installation (Exposed Conduiting) Take the following shop drawings approved for construction. GI Conduiting layout complete with section details. MEP coordination drawing complete with section details. Architectural Drawing
Check the route of GI Conduiting free from debris and no obstruction of any other activity. Arrange scaffolding of sufficient height approved by HSE officer. Mark the reference points on wall/ column as per civil architectural drawing. Identify the circuit start point and end & mark GI Conduiting route as per http://www.methodstatementhq.com/methodstatementinstallationgiconduitsaccessories.html
12/17
8/6/2015
Method Statement for Conduit Installation Including Accessories PVC & GI
approved drawings. Make hole in concrete for anchor bolts/rawel plug & fix rawel plug inside hole then fix base of saddle by screw every 1m span. Use approved GI Conduiting & bends as per site condition and drawing. Remove sharp edge of cut length of conduit by filing. Join the lengths using the threaded joints and fittings. Install conduit and tight with saddle and screw. Make earthing of GI Conduiting & Check for continuity. Apply the zinc paint on the exposed threaded area which is not covered. Installation of GI Conduiting shall be checked by internal QA/QC Engineer as per drawings and quality of installation before offering consultant/client for inspection. 9. Construction Program As per main project program 9.1 Housekeeping The work area shall be maintained neat and tidy as reasonably practical at all times. 9.2 Protection of Executed Works Executed works in areas were other works are still being carried out shall be protected as per the contract requirements. 9.3 Responsibilities 9.4 Records http://www.methodstatementhq.com/methodstatementinstallationgiconduitsaccessories.html
13/17
8/6/2015
Method Statement for Conduit Installation Including Accessories PVC & GI
In accordance with the Quality Management System, the following records will be maintained as documentary evidence of the establishment of this method statement: 10. Inspection and Testing In Process works shall be monitored for quality of workmanship and installation against approved shop drawings by the relevant supervisor. All works shall be inspected for conformance to specification. The inspection formats shall be used in accordance with the requirements of the main contractor UNEC. An inspection request for the PVC conduits and boxes shall be submitted one day prior to the consultant. 11. Related Forms As per required forms, from main contractor and consultant. 12. Attachments ITP Installation Checklists Risk Assessment DOWNLOAD METHOD STATEMENT IN WORD FORMAT Share this:
Facebook
2
Reddit
Google
Tumblr
More Method Statements: http://www.methodstatementhq.com/methodstatementinstallationgiconduitsaccessories.html
14/17
8/6/2015
Method Statement for Conduit Installation Including Accessories PVC & GI
1. Method Of Statement For Installation of GI Conduits & Accessories For Electrical Works Method Of Statement For Installation of GI Conduits & Accessories For Electrical Works is given below for the reference of our visitors if you want to use this method statement...
2. Method Statement For Installation of Motor Control Centre MCC Panel This below procedure shall be followed for the installation of MCC panels.All components / materials received at site shall be inspected and ensured against approved material submittal. Any discrepancies, damages etc...
3. Testing & Commissioning Of CCTV Cameras – Method Statement The objectives of the process of testing and commissioning of CCTV camera is to verify proper functioning of the equipments and system after installation, and to ensure the performance of the installed system...
4. Method Statement For Installation Of CCTV Camera Security System The purpose of this method statement is to provide guidelines and steps for the cctv installation of security systems by describing the Work to be executed, how it is to...
5. Method Statement For Fire Alarm System Installation & Testing Below is the method statement for the installation of fire alarm system which can be modified for different type of systems like HSSD or Vesda etc. The steps are very...
http://www.methodstatementhq.com/methodstatementinstallationgiconduitsaccessories.html
15/17
8/6/2015
Method Statement for Conduit Installation Including Accessories PVC & GI
6. Method Statement For Installation Of Emergency Lighting System The below method statement describes some standard operating steps to install the emergency lighting system for any kind of project the method statement can be modified as per different project...
7. Method Statement For Installation Of Electric Water Heaters The procedures for the installation and fixing of electric water heaters with supports and accessories shall be done as per the manufacturer’s recommended guidelines and installation instructions and as per...
8. METHOD STATEMENT FOR TESTING & COMMISSIONING OF PRESSURIZATION UNIT The purpose of this procedure is to define the step by step method to implement the correct practices for the precommissioning & commissioning of Pressurization Unit through the guidelines contained...
9. Method Of Statement For Installation of wires and cables – Wiring Below is the list of equipment / Tools required for installation of wires and cables, which cab be used for different projects after doing the customization as per the project...
10. METHOD STATEMENT FOR INSTALLATION OF MDB, SMDB, DB, MCC & CAPACITOR BANK 1.0 PURPOSE The purpose of generating this method statement is to define the procedure step by step to implement the correct practices for Installation of MDB, SMDB, DB, MCC &...
http://www.methodstatementhq.com/methodstatementinstallationgiconduitsaccessories.html
16/17
8/6/2015
Method Statement for Conduit Installation Including Accessories PVC & GI
Tags: architectural, GI Conduit, Installation of GI Conduits & Accessories, Method Statement, Method Statement For Conduit Installation, PVC Conduit, statement, works ◀ Installation & Leakage Testing Of Drainage Piping Method Of Statement for Testing & Commissioning Of Water Filtration System ▶
Copyright 2015. All Rights Reserved. Copying and republishing of our content is not allowed.
http://www.methodstatementhq.com/methodstatementinstallationgiconduitsaccessories.html
17/17
View more...
Comments