Method Statement for Cable Laying

March 14, 2017 | Author: pandan27 | Category: N/A
Share Embed Donate


Short Description

A preliminary method statement for cable laying...

Description

`

CLIENT

PROJECT / CONTRACT

Construction of Permanent Backwash System for PWWT unit Multimedia filters CONTRACT NO RL/TC/T/15/13A Dated 23 Feb 2014 DOCUMENT TITLE:

METHOD STATEMENT FOR CABLE INSTALLATION, TERMINATION AND TESTING

DANEM ENGINEERING WORKS

P.O BOX: 7408, DOHA-QATAR, TEL.: 4601006 FAX: 4606969

05 March

0

ISSUED FOR REVIEW AND APPROVAL

PDD

PDD

PKP

2014 DATE

REV. NO.

REASON FOR REVISION

DOCUMENT NUMBER:

PREPA RED

1

4472-1009 REV 0

CHECKED

SHEET.

OF

APPD. Q.CHEM

APPD.

14

REV.

0

METHOD STATEMENT FOR CABLE INSTALLATION AND TERMINATION

CONTRACT NO RL/TC/T/15/13A

DOC NO : DEW/RLOC/E /002

REV. 0

Dated 23 Feb 2014

PROJECT : Construction of Permanent Backwash System for PWWT unit Multimedia filters

INDEX 1. PURPOSE 2. SCOPE 3. ABBREVIATIONS 4. REFERENCE DOCUMENTS 5.

EQUIPMENTS / VEHICLES /TOOLS

6. RESPONSIBILITIES 7.

PROCEDURE

8. HEALTH, SAFETY AND ENVIRONMENT 9. JOB SAFETY ANALYSIS (JSA)

Page 2 of 9

METHOD STATEMENT FOR CABLE INSTALLATION AND TERMINATION

CONTRACT NO RL/TC/T/15/13A

DOC NO : DEW/RLOC/E /002

REV. 0

Dated 23 Feb 2014

PROJECT : Construction of Permanent Backwash System for PWWT unit Multimedia filters

1. PURPOSE The intention of this document is to describe the methodology we are adopting during the execution of the scope. Further to ensure the execution will be done in controlled and safe manner as per project scope complying with RLOC Specifications, Standards and procedures. 2. SCOPE To install and terminate power, instrumentation and earthing cables for the Permanent Backwash system for PWWT unit Multimedia filters. 3. Abbreviations 1) IFC: Issued For Construction 2)

JSA: Job Safety Analysis

3)

PPE: Personal Protective Equipment

4)

PTW: Permit To Work

5)

QCS: Qatar Construction Standards

6)

Q-Chem: Qatar Chemical Company Ltd.

7)

QA/QC: Quality Assurance /Quality Control

8)

RFI: Request For Inspection

9)

MSDS: Material Safety Data Sheets

4. REFERENCE DOCUMENTS 1)

Scope of Work TE-PRJ-SOW-31-0012

2)

Annexure 4 Rev1 for TE-PRJ-SOW-31-0012

5. EQUIPMENTS / VEHICLES / TOOLS

Page 3 of 9

METHOD STATEMENT FOR CABLE INSTALLATION AND TERMINATION

CONTRACT NO RL/TC/T/15/13A

DOC NO : DEW/RLOC/E /002

REV. 0

Dated 23 Feb 2014

PROJECT : Construction of Permanent Backwash System for PWWT unit Multimedia filters

1)

Hydraulic jack / cable jack

2)

Rollers

3)

Compactor

4)

Shovel

5)

Trucks

6)

Cable Reel Stand

7)

Puller Machine

8)

End Tying Basket

9)

Megger (0 – 5 KV)

10)Continuity Tester

6. RESPONSIBILITIES 1) Construction Manager and Project Engineer will be responsible for all the activities. 2)

Surveyor will be responsible for the setting out as well as the elevations.

3)

Safety Officers and Site Supervisors will be responsible for all the related activities and the personnel working at site.

7. Procedure: 1.

General a.

Cable Installation shall comply with reference codes and design documents

b.

All cable drums shall be checked with packing lists and confirmation of mechanical damage will be done

c.

During cable drum shifting ;check mechanical damage ,nameplate with cable schedule and drum list and phase rotation of the cable

Page 4 of 9

METHOD STATEMENT FOR CABLE INSTALLATION AND TERMINATION

CONTRACT NO RL/TC/T/15/13A

DOC NO : DEW/RLOC/E /002

REV. 0

Dated 23 Feb 2014

PROJECT : Construction of Permanent Backwash System for PWWT unit Multimedia filters

d.

Assure necessary PPE ,tools and equipment for cable pulling. Check the latest cable drum list and cable schedule. Check if all cable supports are installed and fixed.

e.

All wires and cables shall be megaohm meter tested

f.

Cables to be buried or used externally will be steel wire armoured.

g.

Cables will be directly buries, laid in concrete trenches, fastened to cable trays rack, or in underground ducts

h.

Check for the following i. Proper type, size, color and number of the wires and cables are being installed ii. For long pulls the pull is performed as per required pulling tension iii. Cable is not pulled around too many bends and the radius is not too tight. iv. Ambient temperature is as per required by cable manufacturer v. Proper pulling compound is used vi. Wires/Cables

are

protected

from

mechanical

damage during pulling vii. Cable fill is as per the required standards viii. Minimum curve radius for cables ,where D is the overall diameter of the cable ,shall be 6D for unarmoured cable and 8D for armoured cable. ix. Junctions/slices where not removable ,shall be made using sleeves ,crimped or welded ,restoring the integrity of the line by appropriate heat shrinkable

sleeves

Page 5 of 9

.Cable

splicing

shall

be

METHOD STATEMENT FOR CABLE INSTALLATION AND TERMINATION

CONTRACT NO RL/TC/T/15/13A

DOC NO : DEW/RLOC/E /002

REV. 0

Dated 23 Feb 2014

PROJECT : Construction of Permanent Backwash System for PWWT unit Multimedia filters

prohibhited except in the case of cable length exceeding the supplied lengths 2) Cable Pulling works a.

Direct buried cables shall be taken to ensure that the laying area is not subject to landslide or cracking ,that there are no obstacles in the subsoil and there is no soil contamination

b.

The bottom of the trench shall be backfilled with a layer of fine sand as per the drawings.The fill material shall be tamped and any hard material which could damage the cable will be removed.

c.

Install

cables

on

layer

of

the

cleaned

and

tamped

sand.Ensure excessive force and twisting of cables is avoided d.

Cables shall be cut from the drums as per the actual cable length in accordance to the drum schedule and drum allocation sheets

e.

Cable drums shall be rotated in direction of the arrow

f.

Check Drum jacks provided are suitable for the cable drum loads

g.

Proper spacing will be maintained between the cables

h.

Protection shall be provided to the cables at crossings with pipes, civil works to prevent mechanical damage

i.

Both ends fo the cable to be firmly sealed with tape to prevent entry of water

j.

Intermediate cable markers to be firmly attached to the cables

k.

Control cables will be laid along the LV cables.HV cables to be laid in separate trays

l.

Cables shall be arranged to minimise crossovers,twists.

Page 6 of 9

METHOD STATEMENT FOR CABLE INSTALLATION AND TERMINATION

CONTRACT NO RL/TC/T/15/13A

DOC NO : DEW/RLOC/E /002

REV. 0

Dated 23 Feb 2014

PROJECT : Construction of Permanent Backwash System for PWWT unit Multimedia filters

m.

All cables will be secured to the trays by nylon fasteners

n.

Cables leaving the trays will be properly protected by pipes/channels

o.

All buried cables to be secured by covering with sand, tiles,warning tapes at specified depths

3) Marking of Cables a.

All cables will be marked as per cable schedule

b.

Buried cables will be tagged with corrosion resistant tags

c.

Cable marking shall be positioned properly to read and identify

4) Cable Termination and Connection work a.

High voltage cable termination work will be done by certified cable terminator.

b.

The cable to be checked as per the Check List A before cable termination work.

c.

Cable bends in the terminal boxes shall be big as possible.

d.

If cable glands are used cables will be checked as per Check List B before the work starts.

e.

Cable core markers to be firmly attached.

f.

Before termination, insulation resistance check will be done. Interphase continuity check will also be done

g.

Pressure and compression terminals to be used ,shall be of correct size for the cable.

h.

Terminals shall be connected.

i.

Cable arrangement after the termination shall be neat and tidy.

j.

After completion of termination, insulation resistance check will be done. Interphase continuity check will also be done.

Page 7 of 9

METHOD STATEMENT FOR CABLE INSTALLATION AND TERMINATION

CONTRACT NO RL/TC/T/15/13A

DOC NO : DEW/RLOC/E /002

REV. 0

Dated 23 Feb 2014

PROJECT : Construction of Permanent Backwash System for PWWT unit Multimedia filters

5) Testing and Records a.

Insulation resistance test will be carried out by approved calibrated equipment.

b.

Testing will be witnessed by QA/QC person

c.

DC high voltage test will be conducted after confirming the cables are properly laid as per schedule and specifications

Voltage Class

Test instrument

Acceptance Value

M/V Cable

5000 VDC

>100 Megaohm

L/V Cable

1000 VDC

>20 Megaohm

Control,Instrumentation,Commu

250 VDC

>1 Megaohm

nication cable

8. HEALTH, SAFETY AND ENVIRONMENT 2) Temporary barricades shall be provided around the working area prior to commencement of site work. 3)

Safety signboards, warning tape and signs, cones shall be provided

around the working area confirming the safety of personnel, RLOC assets 4)

Tool box meetings shall be conducted every week and the reports

shall be submitted to RLOC weekly/monthly.

Page 8 of 9

METHOD STATEMENT FOR CABLE INSTALLATION AND TERMINATION

CONTRACT NO RL/TC/T/15/13A

DOC NO : DEW/RLOC/E /002

REV. 0

Dated 23 Feb 2014

PROJECT : Construction of Permanent Backwash System for PWWT unit Multimedia filters

5)

The construction area shall be neat and tidy at all times and all

unwanted materials / debris shall be transported to RLOC approved dumping site on daily basis.

6)

Environmental assessment achieved from RLOC will be utilized.

9. Attachments 1. JSA 2. Check list A 3. Check List B 4. Field Installation Check List 5. Insulation and continuity test for LV Cable 6. Insulation and continuity test for Instrumentation/Communication Cable

Page 9 of 9