Method Statement for a construction project
Short Description
Method statement for a construction project...
Description
The Public Authority For Applied Education & Training
Construction, Completion, Operation & Maintenance of the Nursing Institute at PAEET Shuwaikh Campus Contract No. PA/AFA/112-2008/2009
Project Method Statement
Dar Al Hadiah Consultant Engineer
Real Estate Construction & Fabrication Co.
Contents 1.
Introduction 1.1
Project Parties
1.2
Project Information
1.3
Project Components
1.4
Site Location
1.5
Site Staff Organization Chart 1.5a Organization Chart 1.5 b Job Description
2.
Project Obstacles
3.
Construction Strategy
4.
1.
Zoning Plans
2.
Project Milestones & Constrains
3.
Project Priorities
Construction Methodology 1.
Methodology flow Chart
2.
Procurement
3.
Excavation, Shoring & Dewatering
4.
Foundation
5.
Basement walls & columns
6.
Slab formwork circulation
7.
Roofing system
8.
Façade Finishes
9.
Finishing Works & Electromechanical works
10.
External Works
11.
Authorities Approval, Testing & Commissioning
5.
Site Logistics
6.
Activity Coding & ID System
7.
Productivity Rates
Real Estate Construction & Fabrication Co.
1-Introduction
1
Real Estate Construction & Fabrication Co.
1.1- Project Parties
Owner
Public Authority for Applied Education & Training
Construction Manager
Turner Projacs
Consultant
Dar Al Hadiah Consultant Engineers
Contractor
Real Estate Construction & Fabrication Co.
2
Real Estate Construction & Fabrication Co.
1.2- Project Information
Project
Nursing Institute
Project Location
PAAET Campus, Shuwaikh
Project Duration
730 Calendar days including all holidays from date of enterprise
Project Value
KD 6,930,000.000
3
Real Estate Construction & Fabrication Co.
1.3-Project Component The project comprises the construction, completion & maintenance of the Nursing Institute for The Public Authority For Applied Education & Training. The Project is located at the south west side of PAAET Campus, Shuwaikh. The project includes one building and external landscape, the Building consists of Basement, Ground Floor, 1st Floor, 2nd Floor & Roof. The area of each project component is as follows: •Basement area : Total area 8136.64 m2 •Ground Floor Area : 8009.54 m2 •First Floor Area : 7040 m2 •Second Floor Area : 7040 m2 •Roof Floor Area : 204 m2 The Basement will include the following: •Car park with a capacity of 104 cars. •A shelter area for peace time & war time. Upon completion it will be ready to accommodate 100 person •Electric & Mechanical rooms for the pumps, generators, transformers, water tanks and all major electromechanical equipments The Ground Floor will include the Following: •Registration & students waiting area •Class rooms with capacity for 600 students •2 nos of Auditorium rooms for 240 students •Examination halls •Students book store •Studio •Dinning halls & central kitchen unit •2nos prayer rooms
4
Real Estate Construction & Fabrication Co.
The First & Second Floor will include the Following : •Staff rooms •Conference room •Technical Director Office •Class rooms for 860 students •Computer Class rooms •Nursing labs •Physics labs •Language labs •Biology labs •pharmacology labs •Chemistry labs. •General study halls with library •Instruction technology support unit •Research rooms •Video conference •Media presentation labs. A Roof floor that will include 4 mechanical rooms. External area that will include Infrastructure and landscape works such as pavement tiles as well as parking lot area for 150 car and 12 busses
5
Real Estate Construction & Fabrication Co.
The Major Activities The construction of the Nursing Institute Building, will generally comprises of the following : 1.
Site Clearance
2.
Excavation, Shoring / Dewatering & Termite Control
3.
Complete Structure works
4.
Waterproofing works
5.
Masonry works
6.
Finishing works including interior & exterior finishes for floors, walls, ceiling and wall partitions
7.
Steel, wood & aluminum doors & windows frames, leaves and hardware.
8.
Metal works
9.
All MEP works
10. LPG Works 11. Electrical Equipment (Smart sys) 12. Kitchen Equipment 13. Furnishing 14. Signage (External & Internal) 15. Shelter works 16. Elevators 17. Façade (Concrete panels cladding, curtain wall) 18. External Works (Infrastructure services, Landscapes)
6
Real Estate Construction & Fabrication Co.
1.4- Site Location Location of the Project •The Project (Nursing Institute) owned by the Public Authority of Applied Education & Training (PAAET). The site is located at south western corner of PAAET Shuwaikh campus. The campus resides between Jamal abdul Nasser street from north, Al Jahra road from south, Al Jahez street from the west and Al-Ghazali street from the east. a plan is attached to indicate the location of the project.
7
Real Estate Construction & Fabrication Co.
N
STC Building
MEW Substation
Figure 1.1 8
Real Estate Construction & Fabrication Co.
1.5- Site Staff Organization Chart
9
Real Estate Construction & Fabrication Co.
Project Manager Secretary Messenger
Safety
Quality Control Engineer
Officer
Document Controller
Senior
Planning
Quantity
Arch.Coord
Project Engineer
Engineer
Surveyor
Engineer
MEP Subcontractor
Subcontractors
Civil Engineer
Lab Tech.
Structure Engineer
MEP Coordinator General Forman
Land Surveyor
Draftsmen Elec Engineer
PL & FF Engineer
HVAC Engineer
Elec Foreman
PL & FF Foreman
HVAC Foreman
Civil Forman
Waterproofing subcontractor
Dewatering subcontractor
Shoring subcontractor
Carpentry subcont.
Alum. Works Subcontractor
Precast Concrete. Subcontractor
Shelter Equip. Subcontractor
Elevator Subcontractor
Waterproofing Foreman
Dewatering Foreman
Shoring works Foreman
Carpentry Foreman
Alum. Works Foreman
Precast Concrete Foreman
Shelter Equip. Foreman
Elev Foreman
Lab Furniture subcontractor
Decoration works subcontractor
Metal works subcontractor
Kitchen Equip subcontractor
Decoration works Foreman
Decoration works Foreman
Metal Works Foreman
Waterproofing Foreman
Key Legend Required Contractually
Not Required Contractually Responsibility Line Coordination Line
10
Ready mix conc Supplier
Draftsmen
1.5b- Job Description •Project Manager : •Overall project policy and monitoring relations with consultant and clients team. •Conducting daily / weekly meetings with all staff / subcontractors to point out the difficulties in work activities, requirement of resources, order/ direct material and equipment at site with maximum efficiency, find solutions and taking immediate actions •Review correspondence for proper action •Financial follow up and control the cost of project duration execution, follow up monthly payment certificates, variation orders in co-ordination with Q.S/Planner •He will be directing the Senior Project Engineer, Architectural engineer, Planning Engineer, Quality Control engineer, Quantity Surveyor and the Safety Officer •Senior Project Engineer: •Overall area activities directing, monitoring and controlling the productivity of all staff. •He will determine possible critical areas and activities have to be improved for the successful completion of project in time •Find solutions and taking immediate action required to push the work in proper coordination with project manager •He will be assisted by the site engineer, foreman, safety officer and services/finishing works engineers •He will be directing the Subcontractors, Site Engineer, General foreman and Land Surveyor and reporting to the Project Manager •Architectural Coordination Engineer: •Overall technical coordination, preparation of architectural drawing, composite drawings. •He will be responsible for the coordination between subcontractors for the preparation of shop drawings. •Find technical solutions with consultants and subcontractors and taking immediate action required •He will be reporting directly to the Project Manager, and will be directing the structural engineer and the architectural draftsmen.
11
Real Estate Construction & Fabrication Co.
•Planning Engineer : •Preparation, submission, approval of the project schedule, updates, revisions, adjustments and monitor the construction progress, identify/initiate potential variance and delays, follow up resource assignment. He will be reporting directly to the Project manager and will coordinate with Senior Project Engineer to follow up and monitor construction activities and the Q.S for the preparation of CLS, as well the subcontractors. •Preparation, submission, approval of cost loaded schedule in coordination with Q.S •Prepare the monthly / fortnightly work programmes including values of work done vs planned values •Prepare monthly progress reports •Follow up the updates of material / drawing submittal logs & procurement of material •Preparation & submittal of Pre-meeting submittals •Quantity surveyor: •Preparation of Cost load values for all activities as per Project construction schedule in coordination with planning engineer •Check quantities, preparation of payment application under the supervision of the project manager and in co-ordination with the Planning engineer / Senior project engineer •Preparation of Subcontractors payments, analyzing variations, claims and all other contractual issues in coordination with planning engineer
•Safety Officer : Establish and follow up safety procedures all in accordance with the safety manual prepared by him. He will be reporting to Project Manager, and will be coordinating with the Senior Project Engineer to ensure safety control at site. •Quality Control Engineer : •All the aspects of materials / quality control of site works, and site laboratory functioning. •Review preparation of all submittals of subcontractors, supplier’s materials, samples to provide continuous flow of procurements as per the requirement of Project Programme. As well as E1 & E2 logs •Responsible for all technical aspects regarding shop drawings preparation and coordination between different subcontractors. •Preparation of Method statements and follow up procurement of materials and equipment. •Supervise Quaility control procedures and will follow up all types of submittals such as Subcontractors, suppliers shop drawings, materials, etc.
12
Real Estate Construction & Fabrication Co.
•Structural Engineer : •Structural shop drawings preparation. •Coordination between the different subcontractors •Prepare, submit and get approval of structural As-Built drawings. •To coordinate with the Project Manager / MEP Coordinator for the progress priority of shop drawings submittal and to solve site structural problems on daily basis •He will be assisted by the draftsmen. •Civil Engineer : •Work under the directives of the Project Engineer and will be responsible to carry out the works as site directly, and to arrange laborers, materials, equipment, machine etc. •To supervise the work of subcontractors and arrange their responsibility •To report for any material or other requirements well in time and report to the Project Engineer in case of expected shortage. •To supervise the foremen and advise him to carry out the work according to drawings, specification. •To get the work inspection of A/E and follow up with checklists in co-ordination with QC Engineer •To follow up the works progress under the responsibility of Project Manager and Project Engineer and ensure that CCS is followed. •Land Surveyor : Assisting Site Engineers, Foremen with all levels, coordination information. He will be reporting to the Civil Engineer. General Foreman : Proper execution of Daily work / weekly work program as provided by the Civil Engineer and proper distribution of resources. He will reporting to the Civil Engineer and will be managing the labors at site. Electrical Engineer : •Follow up the execution of electrical works at site •Follow up all electrical materials submittal and approvals as well as procurement and delivery of these materials to the site. •Find solutions take immediate actions •Testing and commissioning of all electrical works prior handing over the project •Mechanical Engineer: •Follow up the execution of mechanical works at site •Follow up all mechanical materials submittal and approvals as well as procurement and delivery of these materials to the site. •Find solutions take immediate actions •Testing and commissiong of all mechanical works prior handing over the project 13
Real Estate Construction & Fabrication Co.
2- Project Obstacles 1- Time milestones & constraints. The contractor is obliged to plan and execute the works within the contractual milestones and constraints. Accordingly, the contractor will provide the adequate resources to execute the construction activities to fulfil the contract milestone. 2- Site Accessibility limitation The contractor shall have only one side for site access, due to the site location. Accordingly, only one side will be utilized, and the contractor shall plan for the execution of the works accordingly 3- Tightness of location Major project obstacle is the tightness of the location, where there is no enough space for the A/E & contractors offices, store, labour rest shed steel yard, etc
14
Real Estate Construction & Fabrication Co.
3- Construction Strategy 3.1 Project Zoning : For more control & closer follow up of the project, buildings are divided into different zones, this is based on different functions, structural nature such as expansion joints, or volume of work The following presents the project elements and the number of zones for each: •The Nursing college : Divided to 3 zones •The External Works : Divided to 3 Zones These Zones will include the structural, finishes and electromechanical works. To further meet the requirement and needs of the project, those zones were developed into smaller sub zones as follows : •For the structural purpose and requirements each zone will be divided to 2 sub zones: •Sub zone A1, Sub zone A2 for Zone A •Sub zone B1, Sub zone B2 for Zone B •Sub zone C1, Sub zone C2 for Zone C •For the Finishing & electromechanical purpose each zone will be divided to the following : •Class rooms/Corridors Sub zone •Shelter area sub zone (at basement only) •Transformer room sub zone (at basement only) •Mechanical room sub zone (at basement only) •Ramps Sub zone (at basement only) •Wet area sub zone •Stair case sub zone •Open court area 1 •Open court area 2 •Open court area 3 •For External works Zones will be divided as follows: •Zone 1 •Zone 2 •Zone 3 Detailed sketched are attached to illustrate the Zoning system of the project
15
Real Estate Construction & Fabrication Co.
N
16
Figure 3.1
17
N
Sub Zone C1
Sub Zone B1 Sub Zone A1
Sub Zone C2
Sub Zone B2
18 Basement
Figure 3.2
Sub Zone A2
N
Sub Zone C1
Sub Zone B1 Sub Zone A1
Sub Zone C2
Sub Zone B2
19
Ground Floor Figure 3.3
Sub Zone A2
N
Sub Zone C1
Sub Zone B1 Sub Zone A1
Sub Zone B2
Sub Zone C2
20
1st
Floor Floor Figure 3.4
Sub Zone A2
N
Sub Zone C1
Sub Zone B1 Sub Zone A1
Sub Zone C2
Sub Zone B2
21
2nd Floor Floor Figure 3.5
Sub Zone A2
N
Sub Zone C1
Sub Zone B1 Sub Zone A1
Sub Zone C2
Sub Zone B2
22
Roof Figure 3.6
Sub Zone A2
23
N
24
Figure 3.7
N
25 Figure
3.8
Figure 3.9 26
N
27
Figure 3.10
N
28 Figure
3.11
29
N North Elevation
Sub Zone O2
Sub Zone O3
30
Figure 3.12
South Elevation
Sub Zone O1
East Elevation
West Elevation
Elevations Zoning System
Elevations Zoning System
Zone A
Zone B
Zone C
North Elevation
East Elevation (Zone A) 31
Figure 3.13
Elevations Zoning System
Zone C
Zone B
South Elevation
West Elevation (Zone C) 32
Figure 3.14
Zone A
3.2- Project Milestones & Constraints 33
Real Estate Construction & Fabrication Co.
Activity ID
Activity Description
Duration Days 1
2
3
4
5
6
7
8
9
10
11
12
Months 13 14 15
16
17
18
19
20
21
22
23
24
25
26
Nursing Institute Subtotal
731
Start milestone 10
0
Start Milestone of the Project
Mobilization 20
45
Contractor's Mobilization
Engineering 30
Shopdrawings,Materials Submittals & Approvals
365
Procurement & Delivery 40
440
Materials Procurement & Delivery
Sub-Structure 50 60
75
Excavation & Backfilling Foundations & Sub-Structure
120
Super-Structure 70
330
Super Structure Works
E/M Works 80
595
Electrical & Mechanical Works
Finishing Works 90
390
Masonary & Finishing Works
Elevation Works 100
180
Elevations Works
Roofing Works 110
90
Roofing System
Furniture 130
75
Fixed Furniture & Equipment
External Works 120
150
External Works
Testing & Commissioning 140 150
1
Power On Testing & Commissioning
60
Substantial Completion 160
0
Project Substantial Completion 11JAN09 13:35 NURI
Run Date
© Primavera Systems, Inc.
Sheet 1 of 1
DAR AL34 HADIAH Nursing Institute Construction Master Schedule
Date
Revision
Checked
Approved
2
3.3 The Project Priority The Project priorities will be for the main building. After excavation the concrete skeleton works, will take place. As explained previously, the main building will be consisting of 3 zone (A, B & C), and accordingly, the sequence of work will start from Zone A to B to C as will be explained in detail in the construction methodology. The next priority will be for the façade work. The last stage will be for the external works.
35
Real Estate Construction & Fabrication Co.
4-Construction Methodology 36
Real Estate Construction & Fabrication Co.
4.1- Methodology Flow Chart
37
Layout Excavation Dewatering, Excavation (2nd Stage), anti-termite
S U
Blinding : Casting + Curing
B S
Waterproofing + Screed
T R
Raft Foundation Raft Foundation
U Formwork + Reinf 1st Layer
C T
Drainage + Pipelines + other MEP Services
U e
Col.& Walls : Formwork + Shelter Equip + MEP + Reinf + Casting + curing
Slab : Formwork + Fix Reinforcement + MEP + Concrete + Curing
Basement Floor
Reinforcement 2nd Layer + Casting concrete
R
S U P
G.F, 1st 2nd, Roof Col: Formwork + Fix Shutter + MEP Service + Concrete + Curing
E R S T
G.F, 1st, 2nd, Roof & Upper Roof Slab : Formwork + Fix Reinforcement + MEP + Concrete + Curing
U
Attic Slab
C T
Activity Sequence up to Upper Roof
U R e
Precast Concrete Cladding
Curtain wall works
External Works & Landscape 38
Int. & Ext Block works + Finishing & MEP
4.2- Procurement
39
Procurement •Long lead items are the materials that are specified to be delivered from abroad (such as diesel generator, AHUs, Ceramic tiles, marble tiles, etc) or materials that needs a period for fabrication (such as doors, windows, etc) therefore, it requires a long duration to arrive to the site and might affect the installation works if not properly planned and tracked. •The material will be procured by the contractor and his subcontractor but all procurement will be through the main contractor only, since its his responsibility as per contract conditions to review and make necessary coordination for his subcontractor’s procurement after the material samples and catalogues are approved by the engineers. •Critical materials such as concrete, reinforcement and waterproofing, water stop, termite control as well as the shelter equipment are affecting the early activities of the project. The related submittals and approvals of these types of materials will be finalized as early as possible. •Other long lead materials will be existing in our project, all these long lead materials will be elaborated in the CCS and the material / procurement log, to monitor and control its delivery on time and to ensure no delays will occur.
40
List of Early Critical Material No 1 2 3 4 5 6 7 8 9 10
CSI Division Div 02 Div 02 Div 02 Div 03 Div 03 Div 03 Div 03 Div 07 Div 13 Div 15
Description Termite Control Dewatering system Shoring system Steel Reinforcement Form Work Concrete Ready Mix Water Stop Waterproofing Material Shelter Equipment Drainage Pipes
List of Long Lead Items No
CSI Division
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34
Div 03 Div 04 Div 05 Div 05 Div 07 Div 08 Div 08 Div 08 Div 08 Div 08 Div 08 Div 09 Div 09 Div 09 Div 09 Div 09 Div 09 Div 09 Div 09 Div 09 Div 09 Div 11 Div 12 Div 13 Div 14 Div 15 Div 15 Div 15 Div 15 Div 16 Div 16 Div 16 Div 16 Div 16
Description Precast Concrete Panels Glass Masonry Block Pipe Tube Railing Arch Metal Building Insulation Steel Doors Flush Wooden doors Aluminium doors Curtain walls + Alum Windows Doors Hardware Glazing Ceramic Tiles Acoustical Suspended Ceiling Metal Ceiling Stone Flooring Stone Flooring Adhesive Grouts Reselient Flooring & accessories Vinyl coverings Wooden Flooring Rubber Flooring Carpet Flooring Unit Kitchen Fixed Furniture Shelter Equipment Elevators HVAC Pumps AHUS Plumbing Equipmemt Ducts Diesel Generator Switch Baords Distribution Boards Trunking Light fittings
41
Lead Time
Source
6 month 6 month 6 month 6 month 3 month 6 month 6 month 6-10 month 6-10 month 6-10 month 6-10 month 6-10 month 6-10 month 6-10 month 3-4 month 6-10 month 6-10 month 6-10 month 6-10 month 6-10 month 6-10 month 6-10 month 6-10 month 3-4 month 8-10 month 8-10 month 8-10 month 8 month 2month 12 month 10-12 month 4 month 4 month 10-12 month
Local Overseas Local Local Local Local Local Overseas Overseas Overseas Overseas Overseas Overseas Overseas Local Overseas Overseas Overseas Overseas Overseas Overseas Overseas Overseas Overseas Overseas Overseas Overseas Overseas Local Overseas Overseas Overseas Overseas Overseas
4.3- Excavation, Shoring & Dewatering
42
Survey mark up and Layout Necessary bench mark and grid layout are established by the contractor’s land surveyor (Recafco), and cross checked by consultant’s land surveyor (Hadiya) for acceptance before starting the works.
Marking Foundation The Marking and layout of foundations will be done by site engineer / foreman and cross checked by land surveyor. The level and the co-ordinates will be carried out from the approved Grid Line and Bench mark Excavation After establishing bench marks and grid lines, excavation works will take place, 2nos of loaders will start excavating 1m depth at Zone A. After that, the same will take place at Zone B then Zone C with the same sequence shown in the attached plan. After excavation of 1m in each zone, shoring H-Beams will be installed, and excavation works will proceed till 0.5m above water table while installing shoring timbers every 2m of excavation. After reaching 0.5m above water table level the dewatering system will be installed and operated. After installation & operation of dewatering system, excavation and shoring works will proceed till the level of anchors. Shoring anchors will be installed and tested, and excavation & shoring works will proceed till the bottom of foundation level. Note: Only 3 sides will include shoring works, there will be no shoring works for the side at Axis Z. For curved parts, the shoring works will be segmented. The temporary access ramp will be made as indicated in the attached plan, and will be removed while casting the last part of raft foundation. The expected completion of the excavation works will be on the 5th month from the date of enterprise 43
N
Ramp
Start
Zone C
Zone B
Zone A Start
Figure 4.1
•The sequence of work for the stages of excavation, shoring and dewatering will be as shown in the above plan 44
Excavation Plan
Shoring Plan
45 Figure 4.2
4.4- Foundation
46
Termite Control •For the raft foundation area, the leveled surface will be treated with antitermite treatment before casting blinding concrete. •Subcontractor as well as the material used, will be submitted to the consultant for approval prior to execution of works
Foundation •After termite control, a 10cm thick blinding will be casted & after curing the water proofing will proceed as per specified layers and drawings and then will be protected with 5cm screed layer. •After completion of water proofing works and screed protection, raft foundation work shall be carried out by fixing rebars and shuttering for the sides of the raft. After completion of rebars fixation for bottom and top layers, shuttering the sides and installing the utilities pipes, casting preparation will take place and the raft foundation will be poured using the adequate number of tansmixers and concrete pumps. The execution of raft foundation will be as per the zoning strategy, 2 crews will be available for executing the foundation works and will be working in parallel. he sequence of works and movement of crews will be illustrated in the attached plans. •Ramp Footings will be carried out later on after completion of waterproofing for basement walls and backfilling till the bottom of ramps foundation level. After casting the ramp foundations the walls will be casted and then water proofing will be carried out. After waterproofing is completed, backfilling under ramp S.O.G will start till the bottom of slab level and then the concrete works for the S.O.G will take place. •After casting of raft foundation the Tower cranes will be installed as will be explained in the site logistic plan.
47
N
Zone C1
Zone B1
Zone A1 Crew no 1
C2
Zone B2
Zone A2
Crew no 2
48
Raft Foundation Figure 4.3
4.5- Walls & Columns
49
•
Basement Walls
•
After the raft foundation is hardened enough, installation of rebars for walls shall start and the Doka formwork will be lifted and fixed in position using a crane. The available formwork for the walls will be enough to cast 45 mr (3 sets each 15m with 4.50m height) The walls will be casted in 17 cycles as shown in the attached plan with an expected date of 5 days for each cycle. The wall shutter will be dismantled after the specified duration of casting each wall, and will be used again for the next cycle. Shelter Equipments will be embedded in the concrete as it will be fixed prior casting of concrete. Shelter equipments (valves and blast doors) will installed using cranes
•
Form work System
•
The formwork system that will be used will be Doka large-area formwork Top 50
•
The major components of the system will be: 1.
Doka Timber H-Beam
2.
Doka steel waling
3.
Plywood
4.
Supporting Props
5.
Tie Rods
Doka formwork Top 50 50
•Columns •10 nos of column sets will be used for casting the columns. •Each cycle will take 2 days (1 day for steel reinforcement fixation + 1 day for shuttering & casting) For example, sub zone C2 contains a number of 53 columns, 10 columns will be casted in1 cycles so the total number of cycles will be 6 cycles, each cycle requires 2 days so the total duration of casting the columns for sub zone C2 will be 12 days.
Columns Formworks Doka Formwork Top 50 will be used for casting the columns The components of the System will be: •Doka timber H-Beam •Steel Waling •Plywood •Tie rods •Props for Supporting sides of formwork
Column Formwork Detail 51
14
N
6
1
4
5
6
Walls Formwork Circulation
Total of Formwork Available = 45 mr
8
9
8
2 8
7 9 10
14
15
11
13 13
13
12
52
15
5
Figure 4.4
4
3
N 1
Total of Formwork Available = 45 mr
2
Casted Walls Under Construction
53
Figure 4.5
N 4
Total of Formwork Available = 45 mr
Casted Walls Under Construction
54
Figure 4.6
4
3
N 6
5
6
Total of Formwork Available = 45 mr
Casted Walls Under Construction
55
5
Figure 4.7
N
Total of Formwork Available = 45 mr
8
9
8
9
7 9 10 17
11
13 13
13
12 Casted Walls Under Construction
56
17 Figure 4.8
14
N
Total of Formwork Available = 45 mr
14 15
Casted Walls Under Construction
57
15 Figure 4.9
4.6- Slabs Formwork Circulation
58
•Slab formwork circulation •After completion of walls and columns, formwork for slabs shall start. 3 formwork sets (Doka) will be available to execute and cast the slabs with total area of 4,360m2. each formwork set will be as the following : •Formwork set 1 = 979m2 and will be used for sub zones A1 & B1 •Formwork set 2 = 2160m2 and will be used for sub zones A2 & C2 •Formwork set 3 = 1225m2 and will be used for sub zones B2 & C1 •Each formwork of the above will be used in 8 cycles, each of different durations as for formwork set 1 will have 27 days duration for each cycle, Formwork set 2 will have 33 days for each cycle and Formwork set 3 will have 32 days for each cycle •The expected finish date of the superstructure works will be at the 17 month from the date of enterprise •Plans illustrating each formwork set utilization are attached
•Scaffolding System •The Scaffolding system that will be used for the concrete slabs will be the Dokaflex floor formworks system . The system will be containing of 3 components •Floor Prop Eco 20 •Doka Timber H-Beam (H20) •Plywood
59
N
Total of Formwork Available = 4360m2 Sub Zone C1 Formwork Set 3 = 1225 m2
Sub Zone B1 Formwork Set 1 = 979 m2
Area = 1255m2
Sub Zone A1 Formwork Set 1 = 979 m2
Area = 979m2 Area = 822m2
Sub Zone C2
Sub Zone B2
Formwork Set 2 = 2160 m2
Sub Zone A2
Formwork Set 2 = 2160 m2 Formwork Set 3 = 1225 m2
Area = 2160m2
Area = 1255m2
There will be 3 sets of Formwork available for casting all concrete slabs, as illustrated in plan 60 Figure 4.10
Ground Floor Plan
Area = 1730m2
Formwork Set 1 Circulation
Formwork Set 2 Circulation
Formwork Set 3 Circulation
Area of formwork set is 979m2
Area of formwork set is 2160m2
Area of formwork set is 1225 m2
The formwork will be moving between Sub zone A1 & B1 horizontally & vertically as shown below
The formwork will be moving between Sub zone A2 & C2 horizontally & vertically as shown below
The formwork will be moving between Sub zone B2 & C1 horizontally & vertically as shown below
SF
SF
SF
FF
FF
FF
GF
GF
GF
BF
BF
BF
Sub Zone B1
Sub Zone A1
Sub Zone C2
Sub Zone A1
Sub Zone C1
Sub Zone B2
Area of Sub zone slab A1 = 979m2
Area of Sub zone slab A2 = 1730m2
Area of Sub zone slab B2 = 1255m2
Area of Sub zone slab B1 = 822m2
Area of Sub zone slab C2 = 2160m2
Area of Sub zone slab C1 = 1235m2
The Cycle of each movement will take 27 days
61
The Cycle of each movement will take 33 days
The Cycle of each movement will take 32 days
Formwork Circulation Bar Chart Formwork Set 1 (979m2) Activity
1
2
3
4
5
6
7
8
Days 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
1
2
3
4
5
6
7
8
Days 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
1
2
3
4
5
6
7
8
Days 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35
Formwork Shuttering fixing Steel Reinforcement Installation of services pipes Concrete Casting Curing & Dismantling formwork
Formwork Set 2 (2160m2) Activity Formwork Shuttering fixing Steel Reinforcement Installation of services pipes Concrete Casting Curing & Dismantling formwork
Formwork Set 3 (1225 m2) Activity Formwork Shuttering fixing Steel Reinforcement Installation of services pipes Concrete Casting Curing & Dismantling formwork
62
Cycles of Concrete Slabs Cycle 1 Floor
Zone A1
Zone A2
FW Set 1
FW Set 2
Zone B1
Zone B2
Zone C1
Zone C2
Zone B1
Zone B2
Zone C1
Zone C2
FW Set 1
FW Set 3
Zone C1
Zone C2
FW Set 3
FW Set 2
Zone C1
Zone C2
Zone C1
Zone C2
FW Set 3
FW Set 2
Roof Slab Second Floor Slab First Floor Slab Ground Floor Slab
Cycle 2 Floor
Zone A1
Zone A2
Roof Slab Second Floor Slab First Floor Slab Ground Floor Slab
Cycle 3 Floor
Zone A1
Zone A2
Zone B1
Zone B2
Roof Slab Second Floor Slab First Floor Slab
FW Set 1
Ground Floor Slab
Cycle 4 Floor
Zone A1
Zone A2
Zone B1
Zone B2
FW Set 2
FW Set 1
FW Set 3
Roof Slab Second Floor Slab First Floor Slab Ground Floor Slab
Cycle 5 Floor
Zone A1
Zone A2
Zone B1
Zone B2
Roof Slab Second Floor Slab
FW Set 1
First Floor Slab Ground Floor Slab 63
Cycle 5 Floor
Zone A1
Zone A2
Zone B1
Zone B2
FW Set 2
FW Set 1
FW Set 3
Zone C1
Zone C2
Zone C1
Zone C2
FW Set 3
FW Set 2
Zone C1
Zone C2
Zone C1
Zone C2
FW Set 3
FW Set 2
Roof Slab Second Floor Slab First Floor Slab Ground Floor Slab
Cycle 6 Floor
Zone A1
Roof Slab
FW Set 1
Zone A2
Zone B1
Zone B2
Second Floor Slab First Floor Slab Ground Floor Slab
Cycle 7 Floor
Zone A1
Roof Slab
Zone A2
Zone B1
Zone B2
FW Set 2
FW Set 1
FW Set 3
Second Floor Slab First Floor Slab Ground Floor Slab
Cycle 8 Floor
Zone A1
Zone A2
Zone B1
Roof Slab Second Floor Slab First Floor Slab Ground Floor Slab
64
Zone B2
4.7- Roofing System
65
Roofing system •Once all heavy works are completed on roof, and drainage and other inserts are fixed in place, the area will be cleaned and roofing works starts. All roofing layers shall be as per drawings / specifications / manufacturer recommendations. After each layer is completed, it will be inspected / approved by the engineer before applying the next layer. After roof work works are completed, flash up and rain water outlets and other roof fixtures shall be erected. A section detail is attached below to illustrate the roofing system layers.
66
4.8- Façade Works
67
Façade works •The façade works will include installation of concrete panel cladding as well as curtain wall works. Sigma paint shall be applied in the elevations of open court areas. •After completion of concrete works in each zone, block works shall be carried out, for both external and internal once the external block works are completed insulation works will take place and after completion of insulation works on external block works concrete precast panel cladding works shall start. Opening in block works will be provided to receive precast support ribs without causing damages to the adjacent works. •Curtain wall works shall proceed immediately after the completion of concrete works. After completion of concrete works, Curtain wall brackets will be fixed and aligned, after completion of brackets, aluminium frames will be installed and then the glass will be erected after installation of aluminium frames. •The windows will be fixed after the completion of external cladding as it will rest on the precast panels. •The sequence of works and crews movement shall be as per the zoning strategy. The crews movement will be from Zone A to Zone B to Zone C. 2 crews will be provided for the installation of Concrete precast cladding. Tower cranes and mobile cranes will be used for the installation of the precast panels •Plaster and sigma works are also included in the internal façade works in the open court area, completion of these activities will be depending on dismantling the tower cranes and clearing the area to enable the erection of scaffolding. The tower crane will be dismantled after the completion of roofing system works as well as uploading the required materials to its locations in the floors. However, 3 sides can be carried out prior the dismantling of tower cranes to expedite the works.
68
Elevation 1
Sequence of Work
Zone B
Zone A
Sub Zone O2
Sub Zone O1
Crews Movement
Sub Zone O3
Elevation 2
Elevation 4
Crews Movement
Zone C
69
Figure 4.11
Elevation 3
4.9- Finishing & Electromechanical Works
70
Finishing & Electromechanical works •Finishing works will include the following: •Masonry block works & gypsum board partitions •Wall finishes such as plaster, painting & ceramic tiles for wet area •Ceiling works such as gypsum board and tiles, metal ceiling •Flooring works such as terrazzo tiles, marble tiles, resilient flooring, carpet tiles, carpet roles for prayer rooms, rubber tiles, raised flooring, ceramic flooring for wet areas as well as epoxy paints for the car park area at the basement. •Electromechanical works shall include the following : •Water supply & drainage piping •HVAC ducting & piping •Electrical conduiting and wiring •Equipments such as generators, pumps, AHUs and exhaust fans •Sanitary fixtures & toilet accessories •Electrical accessories
71
Finishing Strategy •The finishing works shall start with the masonry works. The masonry works will be externally & internally., internal & external masonry can be carried out once the site is ready and the slabs scaffolding are removed. Simultaneously fire fighting pipes, chilled water pipes, HVAC ducting, drainage and water supply H/L pipes shall start. •Wall finishes will consist of sand cement plaster & paint while in wet areas ceramic tiles. The plaster works will be carried out after completion of first fix electromechanical works such as electrical conduits, and plumbing pipes at wet areas. Paint works & ceramic works shall follow up once plaster work is completed, as for painting works will be on stages (Paint preparation, 2nd Painting coat, and Final painting coat which will be carried out at the final stage of the project) •Ceilings will be consisting of gypsum boards and tiles, metal false ceiling as well as plaster and paint for wet area and stair cases. False ceiling works shall take place after the completion of all MEP works above false ceiling and the completion of the paint putty & first coat. •Floor finishes will consist of various materials such as terrazzo tiles, vinyl tiles, marble tiles, carpet tiles, etc. all materials will be applied on the prepared beds after wall plastering and fixation of the door frames and all other interior finishes on the walls and ceiling will be done afterwards. In case of carpet tiles & roles, flooring works will be done after completion of other finishing works. Electromechanical works will be divided to three items: •First fix items such as piping, ducting, cable trays, etc works at high level, will be carried out after removal of slab formwork, while conduits will be carried out after the completion of block works. •Second Fix items such as equipments, pumps, elect panels shall be carried out after completion of second painting coats and flooring. •Third Fix items such as elect accessories, sanitary fixtures, toilet accessories, etc shall be carried out after installation of doors leaves and hardware as well as 2nd painting coats.
72
Finishing & Electromechanical works strategy As per the Zoning strategy of the finishing works, the execution of works will be carried out as follows: •
Dry Areas
The finishing works will include the following:
•
•
•
Plaster & Paint for wall.
•
Gypsum Board & Tiles for false ceiling.
•
Marble tiles, Vinyl tiles, Terrazzo Tiles, Ceramic Tiles and Carpet tiles for Flooring.
The sequence of works are planned to be carried out as follows: 1.
Block works & First fix electromechanical works such as elec conduits, ducting & piping
2.
Installation of door frames
3.
Plaster works
4.
Paint preparation & Putty
5.
Window frames
6.
Screed for flooring (vinyl and carpet tiles)
7.
First fix gypsum board partition + door frames + First fix Electromechanical
8.
Insulation & closing gypsum board partition + Paint preparation & Putty
9.
Installation of HVAC ducts, FF pipes, elec conduits above ceiling
10.
False ceiling suspension system
11.
Installation of false ceiling services tiles
12.
KFD visual inspection prior closing false ceiling
13.
Painting of ceiling
14.
Flooring tiles (Marble, Terrazzo, Ceramic)
15.
Fixing door leaves & window glazing
16.
Doors & windows hardware
17.
Painting Coats
18.
Final fix electromechanical
19.
Final painting coat
20.
Installation of carpet & vinyl tiles
The above mentioned activities will be added in more details in the CCS
73
•
Corridors
The finishing works will include the following:
•
•
•
Plaster & Paint for walls
•
Gypsum Board & Tiles for false ceiling
•
Marble tiles & Vinyl Tiles for First & second floors
The sequence of works are planned to be carried out as follows: 1.
Block works & First fix electromechanical works such as elec conduits, ducting & piping
2.
Installation of door frames
3.
Plaster works
4.
Paint preparation & Putty
5.
Screed for flooring (Vinyl or carpet)
6.
False ceiling suspension system
7.
Installation of false ceiling services tiles
8.
KFD visual inspection prior closing false ceiling
9.
Painting of ceiling
10.
Installation of Marble tiles
11.
Fixing door leaves & window glazing
12.
Doors & windows hardware
13.
Final fix electromechanical
14.
Final painting coat
15.
Installation of vinyl tiles
The above mentioned activities will be added in more details in the CCS
74
•
Wet areas
The finishing works will include the following:
•
•
•
Ceramic walls
•
Plaster & Paint for ceiling
•
Ceramic Flooring
•
Sanitary fixtures & Toilet accessories
The sequence of works are planned to be carried out as follows: 1.
Block works & First fix electromechanical works such as elec conduits, water supply & drainage pipes at low level
2.
Waterproofing works
3.
Installation of door frames
4.
Plaster works
5.
Steel frame for marble counters
6.
Ceramic tiles for walls
7.
Ceramic for floors
8.
Doors Leaves
9.
Doors & windows hardware
10.
Installation of marble counter
11.
Installation of Sanitary fixtures and toilet accessories
12.
Painting of ceiling
13.
Final fix electromechanical
•
Air Handling Units Installation: •
The Air Handling Units will be kept in the stores once arrived to the site
•
The maximum dimensions of the AHUs will be 1.60mX1.00m X0.55m and will have a weight of 100kg
•
The air handling units will be lifted by 4 labors through the staircases to reach the required floors and will be installed above the attic slab after the completion of attic slab water proofing works and prior completion of block work above attic slab so that enough space will be available to install the AHU.
The above mentioned activities will be added in more details in the CCS
75
•
Staircase area
The finishing works will include the following:
•
•
•
Plaster & Paint for walls
•
Plaster & Paint for ceiling
•
Marble tiles Flooring
•
Handrails
The sequence of works are planned to be carried out as follows: 1.
Block works & First fix electromechanical works such as elec conduits
2.
Installation of door frames
3.
Plaster works
4.
Paint preparation & putty
5.
2nd coat painting
6.
Marble tiles and skirting
7.
Doors Leaves
8.
Doors & windows hardware
9.
Fixing handrails
10.
Final fix electromechanical
11.
Final Painting coats
Sequence of Work & Crews movement One crew for each trade will start in execution as soon as the finishing works are ready, the movement of each crew will be zone wise. Once the finishing works at Zone C is ready to start, another crew will be added to have a total of two crews working together. The first crew (Crew 1) will be moving horizontally and vertically between Zones A & B, while the second crew (Crew 2) will be moving vertically in Zone C. A diagram is attached to illustrate the crews movement for execution of Finishing works.
76
Internal Block Works
MEP First Fixation
Internal Block Works
Internal Block Works
Attic Slab Installation
Plaster
of Door frames
Works
MEP First Fixation
Screed for Flooring
Paint Prep. & Putty
Waterproofing works
First Fix Gypsum Board partition
First Fix MEP For G.B Partitions
Insulation & gypsum board partition closing
Paint Preparation & Putty for G.B Partitions
Door Leaves, window glazing & Hardware
Painting Coats
Carpet & Vinyl
MEP above false ceiling
Installation of Door frames Plaster Works Paint preparation & Putty
Installation of Door frames
Installation of False ceiling suspension sys
2nd Painting Stage
Plaster Works
Steel frame for marble counter
Marble tiles & Skirting
Installation of False ceiling service tiles
Ceramic tiles for Walls
Painting of G.B Ceiling
Ceramic Tiles for Floors
Doors Leaves
Doors & windows Hardware
Flooring
Installation of Marble Counter
Doors Hardware
Fixing Handrail
tiles Final Fix electromechanical
Final Painting Coats
Doors Leaves
MEP Final fixation
Installation of Sanitary Fixtures & Toilet access Painting of ceiling
77
Final Fix electromechanical
Final Painting coat
Finishing & electromechanical works sequence & crews movement
SF
Crew 2
Crew 1
4
FF
GF
BF
8
Crew 1 7
Crew 2
Crew 1
Crew 1
3
6
5
Crew 2
Crew 1
Crew 1
4
3
Crew 2
Crew 1
Crew 1
1
2
1
Zone C
Zone B
Zone A
2
Figure 4.12
Two crews will be provided to execute the works, the number below the crew indicates the movement sequence of the crew
78
4.10- External Works
79
External works After completion of concrete skeleton and most of the façade works ( Elevations 1,2 & 3) the external works shall be carried out. The execution of external works will be in two stages as follows :
Infrastructure Services The infrastructure service should start with the lower network (storm work network + sanitary network) we will locate all pipe lines & manhole as per approved shop drawings & coordination drawings. We will excavate for pipelines and manhole location. After fixing installing & fixing all manholes and pipelines in the approved levels and locations, we will backfill the pipe lines in layers as specified. The network of fresh water, brackish, fire protection and LPG will be done as per approved drawings and method statement All the external services such as laying of cables, installation of street lights, communication network etc. will be carried out as per the approved shop drawings and contract specification. For all infrastructure piping works, the concrete encasement will be done as per approved shop drawings & specifications Hard Landscape •General method for all the hard landscape elements is the same, it will be carried out after completion of infrastructure services. It will begin with site measurements and placement of the precasted concrete curb stones along their specified path. This will form the area for developing the asphalt roads as per contract specifications. •Development of the pavements, paths and paved areas will be done on compacted soil, by placing the polythene sheet if needed, concrete slabs and mortar or sand beds for the specified finishes (precast concrete tiles, precast concrete interlocking pavers)
80
As per the construction strategy and methodology, the external works will be divided to 4 Zones as follows : •Zone 1 •Zone 2 •Zone 3 The sequence of work for the external works will be related to the site logistics as well as the concrete and cladding works. The execution of works will be planned to take place in four stages as explained in the following: Stage 1 Once the concrete works are completed, the steel reinforcement workshop will be no longer required and will be removed from the site. In addition the cladding works for the east elevation will be completed. Accordingly, the site will be ready for the external works at Zone 1 to be carried out. Such works will include all infrastructure works as well as the landscaping works. The material store will be one of the main obstacle in execution of the external works, therefore its is planned to be relocated in the basement at Zone C (A plan for the new stores location is attached). In addition, the temporary vehicle road will be rerouted as illustrated on the attached plans. The works that will take place in this stage are the following: •Infrastructure works •Kerbstone works •Sub grade for asphalt Stage 2 After completion of stage 1. Cladding works at the south and west elevations is expected to be completed. Accordingly, external works at Zone 2 will be carried out. Rerouting of the temporary vehicle road will be taken into consideration. The works that will take place in this stage are as follows: •Infrastructure Works •Kerbstone works •Sub grade for asphalt Stage 3 After completion of stage 2. Cladding works at the north elevation is expected to be completed. Accordingly, external works at Zone 3 will be carried out. Rerouting of the temporary vehicle road will be taken into consideration. The works that will take place in this stage are as follows: •Infrastructure Works •Kerbstone Works •Sub grade for Asphalt 81
After completion of all above mentioned stages, final asphalt layers and interlock tiling works shall be carried out. The sequence of these works shall be as per construction strategy.
The existing external services near the shelter escape will be studied and relocated and will be assured to stay fully operating and maintained.
82
N
83
Figure 4.13
N
84
Figure 4.14
N
85
Figure 4.15
Level formation
Excavation for Lower network (Storm & Drainage pipes)
Installation of Pipes & Manholes Encasement & Backfilling Excavation of higher network pipes
Installation of pipes & manholes
Encasement & Backfilling
Completion of Infrastructure works
Landscape Works Fixing Curbstone
Laying Asphalt Layers
Interlock Tiles paving 86
4.11- Authority Approvals, Testing & Commissioning
87
Authority Approvals, testing & commissioning Authority approvals , testing and commissioning are all linked to the completion of respective works and are included in the schedule under a separate section A diagram is attached to clarify the procedure followed in order to complete the project Testing & Commissioning •Plumbing system A. During the manufacture (at Contractor's premises only), installation and after completion of works; the system, sections of the system or its components shall be tested by the Contractor / specialist Subcontractor in the presence of the Engineer’s representative, as directed below or elsewhere. The Contractor shall procure all testing instruments and accessories and bear all costs in connection with the same: 1. Basic materials for conformity with the specified standards. 2. Supports and anchors for ability to withstand required loads. 3. Wall mounted sanitary fixtures with a dead weight of 100 kgs. 4. Pumping equipment for the specified flow, head, controls, safety interlocks and alarms; noise criteria, etc. 5. Heat transfer equipment for full load capability, controls, safety interlocks, and alarms and operation of safety valves. 6. Filtration equipment for flow, head loss, filtration fineness, controls alarms, regeneration etc. 7. Control system for operating ranges, tolerances, cutout, alarms 8. Water supply systems for required flow and pressure at simulated peak flow conditions (open sectional control valves estimated no. of outlets in open condition, in series). 9. Drainage systems for simulated peak flow conditions and performance of trap seals (by simultaneous discharge of all water closets stack or groups). 10. Piping in general for line, level and slopes. 11. Sanitary fixtures for operation of fittings and proper fixation. 88
B. Balance and regulate the following items, systems. 1. Globe valves on pump discharge for design flow. 2. Balancing valves in circulating systems for equal or proportionate flow. 3. Thermostats for cut in cut out temperatures or range. 4. Angle valves on fixture supply for regulated flow. TESTING OF PRESSURIZED PIPING A. The pipes shall be jointed, plugged and shall have been in position for at least 24 hours, before the tests are carried out. B. The piping shall be tested for line, gradient and water tightness. The Contractor shall furnish all labour, and necessary testing instruments such as gauges, pumps etc. as directed by the Engineer’s representative. A minimum of two (2) nos identical pressure gauges shall be installed at extremities of the piping circuit to be tested. C. Fill the piping with clean fresh water, leaving all high points open to allow for purging of air. Allow a soaking period of at least 24 hours for cement lined or concrete pipes. D. Pressurize the system using manual pumps in increments of 25 percent of the test pressure. Allow a standing period of 10 minutes after each pressure increment. Pressure testing using motor driven pump is not permitted. E. Do not over pressurize the system under any circumstance. If the test pressure is close to the maximum permissible pressure of any of the system components, install calibrated pressure relief valves in the tested circuit. F. Prior to testing keep all valves and control devices in open position. After completion of pressure test, close each valve one at a time starting from the pressure release end, so as to ensure tightness of the valve. G. The piping shall be hydrostatically tested at a pressure of 690 Kpa (100 psig) or 1.5 times the system working pressure, whichever is greater, but limited to 1379 Kpa (200 psig) for copper and steel piping and 1034 Kpa (150 psig) for UPVC piping. The pressure shall be maintained for at least 4 hours. In metallic piping, allow for pressure fluctuations due to ambient temperature variations. Record the circuit temperature along with the pressure readings. H. Check for leaks by swabbing with a dry tissue. Drop in pressure to the order of 10 Kpa (1.5 psig) per hour shall be considered as acceptable. I. Do not subject sanitary fixture chrome fittings to the test pressure. J. Piping shall be tested in segments during the progress of the work. Maintain an official log book for recording the tests carried out on sections of piping, including test pressure, date of test 89
TESTING OF DRAIN, WASTE AND VENT PIPING A. The pipes shall be joined, plugged and shall have been in position for at least 24 hours before the tests are carried out. B. The piping shall be tested for line, gradient and water tightness. Furnish all labour and necessary testing instruments as directed by the Engineer’s representative. C. Install compression type rubber plugs with bleeding caps to plug branch risers in horizontal piping. Install inflatable pneumatic rubber plugs for vertical risers and other inaccessible areas. D. Fill the piping with clean fresh water, leaving all the high points open to allow purging of air. E. All soil, waste, vent and storm piping shall be tested by filling entire system with water to a minimum head of 3 Ms (10 feet) minimum at any part of the system. The system shall hold the water level to within 100 mm (4 inch) drop in 8 hours. Vertical piping shall be tested in sections of two or three floors at a time. F. Check for leaks by swabbing with a dry tissue. G. Test completed piping by simultaneous flushing of all water closets. Test drainage branches by simultaneous discharge of filled bath tubs, washbasins etc.
DISINFECTION AND FLUSHING OF FRESH WATER PIPING SYSTEM A. Prior to starting work, verify that system is complete, flushed and clean. B. Ensure pH of water to be treated is between 7.4 and 7.6 by adding alkali (caustic soda or soda ash) or acid (hydrochloric acid). C. Add disinfectant, free chlorine in liquid, powder or tablet form to obtain 50 to 80 mg/L residual. D. Fill the system piping with chlorinated water and bleed water from outlets to ensure distribution and test for disinfectant residual at minimum 15 percent of outlets. E. Maintain disinfectant in system for 24 hours. F. During the disinfections period install temporary warning signs in both Arabic and English at conspicuous places throughout the Project against using the chlorinated water. G. If final disinfectant residual tests less than 25 mg/L, at any outlet, repeat treatment. H. Flush disinfectant from system until residual equal to that of incoming water or 1.0 mg/L. I. Take samples no sooner than 24 hours after flushing, from remote outlet of each riser and from water entry, and analyse in accordance with AWWA C601. Submit result of analysis to Engineer’s representative for approval. 90
•INSPECTION, TESTS AND ADJUSTMENTS OF FIRE PUMPS A. Prior to Start Up. 1. The pump motor assembly alignment shall be checked and adjusted, if necessary. Steel cleats shall be welded on pump and motor bases to lock them in aligned position. 2. Foundation and coupling bolts shall be tightened and locked. 3. Pump shaft shall be checked for free rotation. 4. Electrical continuity and insulation of motor and the control panel shall be checked by meggering. 5. The calibration of the relief valve opening and its installation shall be checked and corrected if necessary. 6. The system isolating valve/s shall be shut-off and the test line opened. 7. The tripping element of the circuit breaker shall be checked for correct selection and proper installation. The star-delta change over timing shall be adjusted to the period recommended by the motor manufacturer. 8. System power supply voltage shall be checked and all other checks outlined in the controller operation manual performed, before energizing the controller. 9. The suction lines and the pump casing shall be checked for proper filling with water. B. The following shall be executed to start the system up: 1. The direction of rotation of the pump shall be checked and corrected, if necessary, by momentary operation of the emergency start lever. 2. The valve on the test line shall be partially closed to avoid the operation of the pump at high discharge rates. 3. The pump shall be started on manual mode. 4. The motor full load current shall be checked by manipulating the flow. 5. The pressure relief valve shall be checked for proper operation by gradually closing the test valve. 6. The pump and motor bearings shall be checked for signs of overheating. 7. The suction line shall be checked for signs for entry of air and proper suction intake flow. C. The pump performance shall be verified as follows: 1. The pump head shall be checked at 10091 % and 150 % of nominal flow and
D. The following shall be executed to put the system into Service: 1. Isolate the fire pump controllers. 2. Close the test line and open the system isolating valve. Ensure that the system outlets are closed. 3. Fill the system with the jockey pump. Maintain pressure for 24 hours and ensure that there are no leaks. 4. Energize fire pump controllers and ensure that the system is in automatic mode. •HVAC Systems During the manufacture (in Contractors premises only) and installation and after completion of works; the system, sections of the system or its components shall be tested by the Contractor/Specialist Subcontractor in the presence of the Engineer’s Representative as directed below or elsewhere. The Contractor shall procure all testing instruments and accessories and bear all costs in connection with the same: 1. Basic materials for conformity with the specified standards. 2. Supports and anchors for ability to withstand required loads. 3. Pumping equipment for the specified flow, head, controls, safety interlocks and alarms; noise criteria, etc. 4. Heat transfer equipment for full load capability, controls, safety interlocks, and alarms and operation of safety valves. 5. Control system for operating ranges, tolerances, cutout, alarms etc.
•Electrical works Testing & Commissioning Wiring Devices A. Test all switches, socket outlets etc., for correct polarity and continuity of conductors in the presence of and to the entire satisfaction of the Engineer. B. Carry out live phase to earth loop impedance tests at all switches and socket outlets with an approved earth loop impedance tester to the entire satisfaction of the Engineer. Ensure that all device plates have satisfactory earth continuity to the protective conductor system. C. Test all 13 Amp. socket outlets for instantaneous tripping of associated distribution board current operated earth leakage circuit breaker using testing equipment, approved by the Engineer. 92
Diesel Generator Testing shall be carried out at full load after completion of installation by the Engine manufacturer's qualified representation by the Engine manufacturer's qualified representative in the presence of the Engineer. 2. If the above cannot be done then testing shall be done at the manufacturer/supplier's premises at full load in the presence of the Engineer. All arrangements and costs incurred by such a test shall be responsibility of the Contractor.
Switch Boards Test shall be performed at the manufacturer’s plant in accordance with BS-5486. The manufacturer shall submit the test reports to the purchaser for approval. Inspection shall be carried out at the manufacturer’s plant and test witnessed by the Engineer before delivery of equipment to site.
UPS 1. Routine tests shall be carried out at the manufacturer’s works on each completed unit and witnessed by the Purchaser and Owner or his appointed representatives. These tests shall include: a. Insulation resistance test b. Dielectric strength test c. Operational and sequence test d. Performance test e. Transient response test The transient response should record the results with oscillograms. These tests shall include: - Simulation of an inverter failure which would cause the full load to transfer from the inverter to standby power. - Manual return of the full load from standby power to the inverter. - Simulation of failure of the AC power input of the battery charger. - Simulation of battery charger failure. - Measurement of the inverter output voltage when the input voltage is varied between ± 10 percent and the frequency, between ± 2 Hz. f. Short circuit tests - Short the inverter output circuit to record the current limiting effect of the inverter. - Short the output of one of the branch circuits to ensure clearing of the fault. g. Temperature rise test h. Noise level test i. Measurement of dimensions j. Visual check of workmanship and finish 2. The manufacture shall submit these test reports for Owner’s approval. 3. Approval by the purchaser/Owner shall not relieve the manufacturer of his commitments under the terms of the purchase order and this specifications. 93
•Telecommunication System Testing shall conform to TIA/EIA TSB-67 Transmission Performance Specifications for Field Testing of Unshielded Twisted Cabling Systems and ANSI/TIA/EIA-568-A-1, Propagation Delay and Delay Skew Specification for 100-ohm 4-pair cable. Testing shall be accomplished using level III field testers. Test each pair of each cable for opens, shorts, grounds, and pair reversal. Correct grounded and reversed pairs. Examine open and shorted pairs to determine if problem is caused by improper termination. If termination is proper, tag bad pairs at both ends and note on termination sheets. 1) Perform testing of copper cables with tester meeting TIA/EIA TSB-67 and ANSI/TIA/EIA-568-A-1 requirements. 2) If horizontal cable contains bad conductors or shield, remove and replace cable.
Fire Alarm & Detection System A. After the installation is complete, the contractor shall conduct operating commissioning tests. The system installation, testing and commissioning shall be as per Kuwait Fire Brigade approval and requirements. B. The Fire Alarm System shall be completely programmed in accordance with Kuwait Fire Brigade requirement and a specialist from the manufacturer shall attend and demonstrate the complete system.
Public Address System A. The completed public address system shall be fully tested and adjusted the transformer taps for appropriate sound level by the contractor in the presence of the owners representative. B. Measure and record sound pressure levels at designated locations. C. Upon completion of a successful test, the Contractor shall so certify in writing to the Owner and provide detailed, demonstration and training. D. Submit all shop drawings indicating installation details, cable routing and system configuration and technical catalogue for each component.
94
KFB Submit fire alarm, fire protection, smoke ventilation system shop drawing & materials to KFB Approval of fire alarm, fire protection, smoke ventilation system shop drawing & materials by KFB
Inspection of Installation prior ceiling closing
Final Installation & Arch. Visual inspection by KFB
MOE
KM
Submit of Substation shop dwg
Submit HVAC as built & load calculation to MOE
Approval of Substation shop dwgs
Approval of HVAC as built & load calculation by MOE
Checking of site issuance of clearing certificate by KM
MEW
MOC
MEW Site inspection & Approval
Submit MOC intake dwgs for approval
Payment of Fee by the owner
Inspection of Intake By MOC
Approval by MOC Substation Civil works inspection
Submit elec as built & all loads to MOE
Approval of Civil works inspection
Approve elec as built & all loads by MOE
Fix Transformer, HT Panel & connection by MOE
Physical installation, inspection approval by MOC Payment of fees by owner
Inspection of site
Connection, activation of telephone lines by MOC
MOE Approval
Approval by KFB Payment of fee to MOE by owner Letter to KM for Power connection KFB Final operation
Civil Defense
Issuance of letter of Power connection to MOE by KM
Third Party inspection
Electrical Connection to site Civil Defense inspection
Final certification of acceptance
Testing & commissioning 95
Project Complete
5-Site Logistics 96
Real Estate Construction & Fabrication Co.
5 - Site Logistics Plan •The Site Logistic Plan includes the temporary fences, sign boards, Consultant site offices, Contractors site offices, subcontractors site offices, consultant and contractor’s car park shed, workshops for cutting & bending steel, stores for keeping materials, labors toilets & rest sheds. Temporary access routes are taken in consideration to allow equipments & machines movement around the construction site facilities. For further illustrations, refer to the attached plan •Two Tower cranes (TC-1 and TC-2) will be erected as shown in the attached plans. The first Tower Crane TC-1 will be located at the open court area between axis (H & S) and axis (21 & 28). The second Tower crane TC-2 will be located at the open court area between axis (H & S) and axis (6 & 12). Both Tower cranes will have radius of 55 m and lifting capacity of 52.6 KN and will be installed after casting the raft foundation. A plan is attached to indicate the proposed foundation of the tower crane which will be submitted for approval to the consultant. •Impact of Tower Crane (TC-1) •Due to the tower crane location in the open court area between axis (21 & 28). Some construction activities will be on hold till dismantling the tower crane, such as the following: •Part of the concrete slab in the ground floor (tower crane location) •Cast in situ terrazzo tiles •Flooring works at the basement. •External Plaster works •Impact of Tower Crane (TC-2) •Due to the tower crane location in the open court area between axis (6 & 12). Some construction activities will be on hold till dismantling the tower crane, such as the following: •Part of the concrete slab in the ground floor (tower crane location) •Cast in situ terrazzo tiles •Flooring works at the basement. •External Plaster works •Tower Crane Dismantling •2 mobile cranes will be used for dismantling the tower crane, the tower crane boom and the counter jib will first be dismantled. •After dismantling the boom and counter jib, the operator cabin will be dismantled. •After dismantling the operator cabin, the tower crane section will be dismantled one by one till all sections are dismantled
97
Real Estate Construction & Fabrication Co.
Mobilization •The construction phase shall commence upon receiving the handing over of the site from the municipality. Accordingly, mobilization works shall start. The mobilization will be in accordance with the proposed time schedule and contract milestones and within this period all requirements mentioned in the specifications and other contract documents will be followed and coordinated with the municipality and other authorities for all related approvals and permits. •The mobilization works shall include the following: •Consultant & Contractor/ Subcontractors site offices A/E site offices will be erected by a professional subcontractor, while main contractor staff office will be constructed by our carpentry workshop, and will be sited as approved by the engineer, In addition to all the site temporary services such as fire fighting, water supply, drainage, electric HVAC, telephone network, etc. The offices will be furnished and equipped as required. Suitable paved temporary site access roads as per standard. Detailed shop drawing for the above will be submitted for consultants review and approval prior execution. •Consultant & Contractor car park sheds Consultant and main contractor car park shed will be erected by a professional subcontractor to allow adequate number of cars, and will be sited as approved by the engineer. Detailed Shop drawing will be submitted for review and approval prior the execution. •Temporary fence A complete fence will be executed as specified in tender documents, with the relevant approved shop drawings. All Client, CM and consultant requirements shall be taken into consideration •Sign Boards Shop drawings will be submitted in due time for the same for approval prior fixation, as well as all calculations required. Necessary electrical supply to sign board lighting shall be provided. •Stores Covered storage area for different type of materials will be provided, and will be sited as approved by the engineer. •Work shops •The site will be provided with work shops for steel reinforcement preparation, cutting and bending, as well as formwork and shutter assembling
98
Real Estate Construction & Fabrication Co.
•Labors rest sheds & toilets •Labors rest sheds, drinking fountains, guard house, etc shall be provided, and will be located as approved by the engineer. •Temporary Lighting & Power Adequate lighting and power shall be provided for all construction tools and equipment without overloading the temporary facilities, and shall be made available for construction operations of all trades . •Construction debris removal The debris will be removed as required to maintain the site tidy and accessible all the time, and the same will be transported to the offsite dumping area. Temporary Controls Temporary controls shall be taken in consideration as specified during the construction period, such as noise control, dust control, water control , fire fighting control, etc. First Aid Facilities First aid Facilities shall be provided as per the safety program
99
Real Estate Construction & Fabrication Co.
Site Logistic Plan
100
Figure 5.1
Real Estate Construction & Fabrication Co.
Tower Cranes Locations
Tower Crane (TC2)
Tower Crane (TC1)
Figure 5.2 101
Real Estate Construction & Fabrication Co.
102
Real Estate Construction & Fabrication Co. Figure 5.3
6- Activity Coding & ID System 103
Real Estate Construction & Fabrication Co.
Nursing Institute - PAAET RECAFCO Activity Coding System No 1 2 3 4 5 6 7 8
No 1 2 3 4
Description
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Notes
Location
Description General Subcontractors/Sppliers Shop Drawings Materials Main Building External Works Testing & Commissioning Authorities Approvals Close Out Provisional Items
Notes
Floor
Description General Submittal & Approvals Mock Ups Procurement Foundation Basement Ground Floor First Floor Second Floor Roof Upper Roof Elevators Staircases Elevations External Works
Notes
Description
Notes
GN SA MU PR FD BF GF FF SF RF UR EV ST EL EX
No 1 2 3 4 5 6 7 8 9 10 11 12
Description General Engineering Phase Construction Phase Project Closure
G C S M B X T A O P
No
Zone G A B C S N O W E 1 2 3
Notes
1 1 2 1 2 2 3 5
Type G E C S
No 1 2 3 4 5 6 7 8 9 10
Number of characters
Phase Building Floor Zone Sub Zone Subcontractor Division Sub Division
General Zone A Zone B Zone C Shelter Area North Elevation South Elevation West Elevation East Ealevation Zone 1 Zone 2 Zone 3
only in basement
for external works for external works for external works
104
No
Sub Zone
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
GN A1 A2 B1 B2 C1 C2 DR WT CO S1 S2 S3 S4 S5 S6 S7 S8 S9 MA TR O1 O2 O3 IS LS
No
Subcontractor 1 2 3 5 6 7 8 9
RC DS JN KF AL BD KZ ET
No 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 No 1 2 3 4 5 6 7 8 9 10 11 12 13
Description General Zone A1 Zone A2 Zone B1 Zone B2 Zone C1 Zone C2 Dry Areas Wet Areas Corridors Stair Case 1 Stair Case 2 Stair Case 3 Stair Case 4 Stair Case 5 Stair Case 6 Stair Case 7 Stair Case 8 Stair Case 9 Mechanical Area Transformer Room Open Court Area 1 Open Court Area 2 Open Court Area 3 Infrastructure works Landscape works
Division
Notes For Concrete works only For Concrete works only For Concrete works only For Concrete works only For Concrete works only For Concrete works only
Description Recafco Drake & Skull Jassim Al-Nisf Kuwait Foundation Alico Kuwait Boodai Trading Co KZ Pest Control ETA Engineering & Elevator Co
Notes Main Contractor Electormechanical Subcontractor Waterproofing Subcontractor Shoring works subcontractor Aluminium Works subcont. Shelter Equip. subcontractor Anti Termite Subcontractor Elevator works subcontractor
Description General Division 02 - Earth Works Division 03 - Concrete Works Division 04 - Masonry Works Division 05 - Metal Works Division 07 - Thermal & Moisture Protection Division 08 - Doors & Windows Division 09 - Finishes Division 10 - Specialities Division 11 - Equipment Division 12 - Furinture Division 13 - Special Construction Division 14 - Conveying System Division 15 - Mechanical Works (Plumbing) Division 15 - Mechanical Works (Fire Fighting) Division 15 - Mechanical Works (HVAC) Division 15 - Mechanical Works (LPG) Division 16 - Electrical works
Notes
GN0 020 030 040 050 070 080 090 100 110 120 130 140 15P 15F 15H 15L 160 CSI Subdivision 01110 01250 01290 01311 01312 01313 01321 01322 01330 01333 01400 01420 01455
Description SUMMARY OF WORKS CONTRACT MODIFICATION PROCEDURE PAYMENT PROCEDURES PROJECT COORDINATION MECHANICAL AND ELECTRICAL COORDINATION PROJECT MEETINGS NETWORK ANALYSIS SCHEDULES CONSTRUCTION PHOTOGRAPHS SUBMITTAL PROCEDURES DOCUMENT PRODUCT DATA AND SAMPLES QUALITY REQUIREMENTS REFERENCE STANDARDS AND DEFINATIONS MOCK UP REQUIREMENTS
Notes
105
No CSI Subdivision 14 01458 15 01505 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72
01521 01555 01561 01562 01580 01600 01632 01722 01732 01741 01742 01750 01770 01783 01785 01787 01789 02210 02330 02240 02260 02300 02362 02510 02580 02772 02783 02890 03100 03200 03300 03480 03550 03520 03535 04050 04815 05500 05521 05580 07110 07120 07160 07210 07320 07551 07620 07920 07840 08110 08120 08210 08310 08520 08710 08800 08900
Description TESTING LABORATORY SERVICES CONSTRUCTION FACILITIES AND TEMPORARY CONTROL FIELD OFFICE AND SHEDS TRAFFIC CONTROL SAFETY MEASURES AND STANDARD TEMPORARY BARRIERS AND ENCLOSURES PROJECT IDENTIFICATION AND SIGNS PRODUCT REQUIREMENT ALTERNATIVES AND SUBSTITUTES FIELD ENGINEERING CUTTING AND PATCHING FINAL CLEANING PROGRESS CLEANING STARTING AND ADJUSTING CLOSEOUT PROCEDURES OPERATION AND MAINTENANCE DUTIES DURING MAINTENANCE PERIOD PROJECT WARRANTIES PROJECT RECORD DOCUMENTS SUBSURFACE INVESTIGATION SITE CLEARING DEWATERING EXCAVATION SUPPORT & PROTECTION EARTH WORK TERMITE CONTROL ASPHALT WORK ROADWAY AND PARKING MARKINGS PRECAST CONCRETE CURBS INTERLOCK PRECAST CONCRETE PAVERS TRAFIC SIGN AND SIGNALS CONCRETE FORMWORK STEEL REINFORCEMENT CAST IN-PLACE CONCRETE PLANT PRECAST ARCH. CONCRETE CONCRETE TOPPING & FLOOR FINISH LIGHTWEIGHT CONCRETE FILL SAN CEMENT SCREED CONC. UNIT MASONRY GLASS UNIT MASONARY METAL FABRICATIONS METAL RAILINGS ARCHITECTURAL METAL MEMBRANE WATERPROOFING FLUID APPLIED W/P BITOMINIOUS WATERPROOFING BUILDING INSULATION PRECAST CONC. ROOF TILES MODIFIED BITUMINIOUS PROOFING SHEET METAL FLASHING & TRIM JOINT SEALANT FIRESTOPPING STEEL DOORS AND FRAMES ALUMINIUM WORKS (DOORS) FLUSH WOOD DOOR ACCESS DOORS & PANELS ALUMINIUM DOORS & WINDOWS DOOR HARDWARE GLAZING GLAZED CURTAIN WALL
106
Notes
No 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103 104 105 106 107 108 109 110 111 112 113 114 115 116 117 118 119 120 121 122 123 124 125 126 127 128 129 130 131 132 133
CSI Subdivision 09220 09250 09260 09310 09420 09440 09505 09510 09546 09638 09651 09653 09671 09680 09910 10265 10270 10400 10810 11460 12566 13036 14210 15050 15060 15070 15075 15080 15100 15121 15122 15123 15140 15181 15183 15185 15190 15300 15310 15320 15325 15330 15355 15375 15400 15410 15450 15500 15725 15731 15734 15738 15761 15763 15785 15810 15820 15837 15838 15841 15855
Description PORTLAND CEMENT PLASTER GYPSUM BOARD GYPSUM BOARD ASSEMBLIES CERAMIC TILE PRECAST TERRAZZO CAST IN SITU TERRAZZO GYP.BOARD SUSP.CEILING SUSPENDED CEILING METAL CEILINGS STONE FLOORING RESILIENT BASE AND ACCESSORIES SHEET VINYL FLOOR COVERING EPOXY FLOORING CARPET TILES PAINTING IMPACT RESISTANT WALL PROTECTION ACCESS FLOORING IDENTIFICATION SIGNS TOILET ACCESSORIES UNIT KITCHENS LABORATORY FURNITURE PUBLIC SHELTER ELECTRIC TRACTION ELEVATORS PLUMBING SYSTEM HANGERS AND SUPPORTS MECHANICAL SOUND & VIBRATION CONTROL MECHANICAL IDENTIFICATION MECHANICAL INSULATION PLUMBING PIPING EXPANSION COMPENSATION METERS AND GUAGES PIPING SPECIALITIES PLUMBING SPECIALITIES HYDRONIC PIPING AND VALVES REFRIGERANT PIPING HVAC PUMPS FUEL PIPING FIRE PROTECTION SYSTEM FIRE PROTECTION PIPING FIRE PUMPS & ACCESSORIES SPRINKLERS SYSTEM FIRE PROTECTION SPECIALITIES FOAM EXISTING SYSTEM STAND PIPE AND HOSE SYSTEM PLUMBING EQUIPMENT PLUMBING FIXTURES WATER STORAGE TANKS AND ACCESSORIES HVAC SYSTEM AIR HANDLING UNITS PACKAGED AIR HANDLING UNITS COMPUTER ROOM AIR CONDITIONING UNIT SPLIT SYSTEM AIR CONDITIONING UNIT AIR COILS FAN COIL UNITS AIR TO AIR ENERGY RECOVERY UNITS DUCTS (DUCT WORK) DUCT ACCESSORIES CENTRIFUGAL FANS AND AXIAL FANS POWER ROOF VENTILATORS BYPASS VARIABLE AIR VOLUME TERMINALS DIFFUSERS, REGISTER AND GRILLS
107
Notes
No 134 135 136 137 138 139 140 141 142 143 144 145 146 147 148 149 150 151 152 153 154 155 156 157 158 159 160 161 162 163 164
CSI Subdivision 15900 15860 15950 15900 15400 15500 16050 16060 16075 16123 16130 16133 16134 16140 16210 16235 16441 16442 16443 16500 16611 16640 16670 16710 16721 16725 16771 16800 16821 16850 16860
Description BUILDING AUTOMATION SYSTEM AIR CLEANING DEVICES TESTING ADJUSTING & BALANCES OF HVAC BUILDING AUTOMATION SYSTEM PLUMBING SYSTEMS HVAC SYSTEMS BASIC ELECTRICAL MATERIALS & METHODS GROUNDING & BONDING ELECTRICAL IDENTIFICATION BUILDING WIRES & CABLES RACEWAY & BOXES CABLE TRAYS UNDERFLOOR RACEWAY ASSEMBLIES WIRING DEVICES ELECTRICAL WORKS FOR SUBSTATION DIESEL GENERATOR SWITCHING BOARDS PANEL BOARDS MOTOR CONTROL CENTERS LIGHTING FIXTURES UNINTERRUPTIBLE POWER SUPPLY SYSTEM AUTOMATIC TRANSFER SWUTCH LIGHTING PROTECTION SYSTEM TELECOMMUNICATION SYSTEM INTEGERATED FIRE ALARM SECURITY AND CCTV SYSTEM AUDIO VISUAL SYSTEM CLOCK SYSTEM PUBLIC ADDRESS SYSTEM TV AND SATELITE SYSTEM INTERACTIVE ELECTRONIC SMART BOARD
108
Notes
Activity ID System 20 characters will be used for the Activity ID 1
.
Phase
3
.
Location
5
6
Floor
.
8
Zone
.
10 11
Sub Zone
.
13 14 15 16 17
Subdivision
.
19 20
Number
Example C.B.GF.A.WT.09310.01 = Ceramic Flooring for wet areas at Ground floor Zone A
109
7- Productivity Rates 110
Real Estate Construction & Fabrication Co.
Productivity Rates No. of working days : 6 days/ week (Saturday to Thursday, Friday is day off) Working shifts : one shift / day Working hours : 8 hours / day Over time and Fridays shall be used if necessary to keep on schedule or to compensate for any unexpected events.
No
Division
Productivity Rate per day
Item Describtion
Crew (Manpower/Equipment)
1
Div 02
Excavation Works
350 m³
1nos Loader
2
Div 02
Shoring
50 m²
4 shoring labours
3
Div 02
Backfilling
80 m³
2 Roller + 2 compactor + 4 labors
4
Div 02
Preparation of blinding
200 m²
3 Labours + 1 Compactor
5
Div 02
Anti Termite Control
600 m²
1 labour
6
Div 02
Kerbstones
75m
3 Masons
7
Div 02
Inerlock Tiles
30m²
8
Div 02
Asphalt
9
Div 03
Concrete Slab
30m²
4 Masons 1 Asphalt paver + Roller + Pnuematic wheel + compacter & compressor 4 carpenters + 2 labour + 4 Steel Fixers
10
Div 03
Concrete Columns
5 nos
2 carpenters + 2 steel Fixers + 2 Labours
11
Div 03
Precast Concrete Cladding
60m²
6 mason + 1 crane
12
Div 03
Concrete Topping / Screed
40m³
5 concreter + 1 finisher
13
Div 03
Leight weight concrete
60m³
6 concreter + 1 finisher
14
Div 04
Block Works
15m²
1 Block work mason + 1 Labour
15
Div 04
Glass Block Works
5m²
1 Mason + 1 Helper
16
Div 05
Handrails
10m
1 Handrail mason + 1 helper
17
Div 07
Waterproofing membrane
60m²
1 WP mason
18
Div 07
Protection Board
60m²
1 WP mason
19
Div 07
Building Insulation
100m²
1 Mason + 1 Helper
20
Div 07
Concrete Pavers for Roof
30m²
1 Tile Layer + 1 Helper
21
Div 07
Metal panels cladding
30m²
1 Cladding Mason + 1 Helper
22
Div 07
Aluminium Flashing
60m²
1 Mason + 1 Helper
23
Div 07
Fire Stop
40mr
1 Mason + 1 Helper
24
Div 08
Door Frames
5 Nos
1 Doors carpenters + 1 helper
25
Div 08
Door Leaves
5 Nos
1 Doors carpenters + 1 helper
26
Div 08
Door Hardware
5 Nos
1 Doors carpenters + 1 helper
27
Div 08
Frameless Glass panels
30m²
2 Metal Masons + 1 helper
28
Div 09
Cement plaster 1st stage
60m²
1 Plaster mason + 1 Helper
29
Div 09
Cement plaster 2nd stage
30m²
1 Plaster mason + 1 Helper
30
Div 09
Ceramic walls for wet areas
12m²
1 ceramic mason + 1 helper
31
Div 09
Ceramic Skirting
30mr
1 ceramic mason + 1 helper
32
Div 09
G.B partition Studs+1st Layer +Insulation
20m²
2 mason + 1 Helper
33
Div 09
G.B parititions Closing
50m²
2 mason + 1 Helper
34
Div 09
Gypsum false ceiling
20m²
1 Mason + 1 Helper
35
Div 09
Metal false ceiling
30m²
1 Mason + 1 Helper
36
Div 09
Paint preparation
40m²
1 Painter
37
Div 09
Painting Coats
40m²
1 Painter
38
Div 09
Vinyl Tiles
25m²
1 Tile Layer + 1 Helper
2000m²
111
Productivity Rate per day
No
Division
Item Describtion
39
Div 09
Rubber Tiles
25m²
1 Tile Layer + 1 Helper
40
Div 09
Marble Tiles
12m²
1 Tile Layer + 1 Helper
41
Div 09
Marble Skirting
30mr
1 Tile Layer + 1 Helper
42
Div 09
Marble Threshold
20mr
1 Tile Layer + 1 Helper
43
Div 09
Marble Counter
15mr
1 Tile Layer + 1 Helper
44
Div 09
Granite Flooring
12m²
1 Tile Layer + 1 Helper
45
Div 09
Terrazzo Tiles
15m²
1 Tile Layer + 1 Helper
46
Div 09
Insitu Terrazo tiles
5m²
1 Tile Layer + 1 Helper
47
Div 09
Carpet Tiles
40m²
1 Tile Layer + 1 Helper
48
Div 09
Wood Flooring
10m²
1 Mason + 1 Helper
49
Div 10
Wall & Corner guards
7 nos
1 Mason + 1 Helper
50
Div 10
Toilet Accessories
5 nos
1 Mason + 1 Helper
51
Div 10
Access Flooring
20m²
1 Mason + 1 Helper
52
Div 10
Internal Signage
12 Nos
53
Div 12
Lab Furnitures
10 seats
54
Div 13
Shelter Doors
1 nos
3 Mason + 1 Helper
55
Div 15
Laying Water supply pipes
30m
1 plumber + 1 helper
56
Div 15
Laying Drainage pipes
24m
1 plumber + 1 helper
57
Div 15
Laying Fire Fighting Pipes
24m
1 FF Pipe Fitter + helper
58
Div 15
Laying HVAC Ducts
70 kg
1 Duct Fitter + 1 helper
59
Div 15
Duct Insulation
20 m
1 Duct Fitter + 1 helper
60
Div 15
HVAC Piping
20m
1 Pipe Fitter + 1 helper
61
Div 16
Installing Cable Trays
15m
1 Electrician + Helper
62
Div 16
Electrian Conduiting
24m
1 Electrician + Helper
63
Div 16
Wiring Works
400m
3 Electricians + 3 helpers
64
Div 16
Laying Cables
20m
3 Electricians + 3 helpers
112
Crew (Manpower/Equipment)
1 Signage Mason 1 Finishing Carp. + 1 helper
View more...
Comments