Method of Statement for Electrical Work

June 23, 2019 | Author: Kg Chit Zaw | Category: Waste Management, Excavation (Archaeology), Trench, Waste, Nature
Share Embed Donate


Short Description

Method...

Description

GFMP

KABLE MYANMAR FACTORY PROJECT

METHOD OF STATEMENT FOR ELECTRICAL WORK

PRESENTED BY GOLDEN FUTURE MYANMAR POWER April 4th 2019

GFMP

1. Introduction 2. Scope of Work 3. Method of Statement for Excavation, Pipe Laying and Back Filling 4. Method of Statement for Manhole Casting 5. Method of Statement for Lamp post Erection 6. Method of Statement for Cabling 7. Method of Statement for Transformer Installation 8. Method of Statement for MV/LV Panel Installation 9. Method of Statement for Termination of MV Cable 10.Method 10.Method of Statement for Lighting Fixture Installation 11.Method 11.Method of Statement for Fabrication of Support

GFMP

1. INTRODUCTION This Method of Statement is issued as a confidential document and at all times remains the property of GFMP. This MOS is a live document and will be updated from time to time to incorporate changing site circumstance and client’s recommendations. Copies of this plan will be provi ded to subcontractors and other parties working under GFMP.

2. SCOPE OF WORK Supply, Delivery and Installation of Electrical System.

3. METHOD OF STATEMENT FOR EXCAVATION, PIPE LAYING AND BACK FI LLING 1.1 Scope of Activity The Scope of Method of Statement is to describe the method of excavation for HDPE Flexible pipe laying for the proposed KALBE Project, Thilawa SEZ A, Yangon, Myanmar. 1.2 Site Observation Before Commencement of the planned work, carry out examination of the physical condition of the area for ongoing activities, blockages of Ingress/ Egress and the weather condition. 1.3 Method of Statement Preparation 

Load all equipment required for Job



Report to KDK and received approval



Put on personal protective equipment



Inform all other contractors in the area of start to work



 

Liaise with Main contractor and other contractor to be ensure safe operation Cordon of work area Ensure the area to be worked and exit points are clear of obstruction

GFMP



Ensure that safe access and egress is maintained



Determine location of underground services

Producer 

 





 





Provide copies of the shop drawings, copy of the permit to work & necessary instructions. Briefly introduce the workers on the safety aspects & safe work procedures. Barricade the area of working. Mark out area to be excavated with marker paint Bring excavator onto site following safety procedures listed above Ensure trained banksman is available to watch excavation work Dig out ground as per contract drawings to required size and depth All excavations must be left safe at the end of each day The bottom of trench will be compacted prior to installation of sand bedding for the pipe pipe The pipe will be laydown as indicated on the approved shop drawings and according to manufacturer’s manufacturer’s writing instruction After pipe laying, back fill will start step by step.

1.4 Waste Management All waste materials to be removed from site on a daily basis. Trash collecting bags are to be provided at the working areas. All general waste to be thrown into the provided trash bags according to the type of garbage (Segregate waste before disposal) and should be disposed in to the relevant metal waste bins provided. Wooden crates or palettes must be dismembered before disposal

GFMP

To perform general housekeeping every day after the work Mass housekeeping exercise to be performed on weekly basis

4. METHOD OF STATEMENT FOR MANHOLE CASTING 1.1 Scope of Activity The Scope of Method of Statement is to describe the method of excavation and electrical manhole casting for propose KALBE Project, Thilawa SEZ A, Yangon, Myanmar. 1.2 Site Observation Before Commencement of the planned work, carry out examination of the physical condition of the area for ongoing activities, blockages of Ingress/ Egress and the weather condition. 1.3 Method of Statement Preparation 

Load all equipment required for Job



Report to KDK and received approval



Put on personal protective equipment



Inform all other contractors in the area of start to work



 

Liaise with Main contractor and other contractor to be ensure safe operation Cordon of work area Ensure the area to be worked and exit points are clear of obstruction



Ensure that safe access and egress is maintained



Determine location of underground services

Producer 

Provide copies of the shop drawings, copy of the permit to work & necessary instructions. Briefly introduce the

GFMP

workers on the safety aspects & safe work procedures. Barricade the area of working.  





 





Mark out area to be excavated with marker paint Bring excavator onto site following safety procedures listed above Ensure trained banksman is available to watch excavation work Dig out ground as per contract drawings to required size and depth All excavations must be left safe at the end of each day The bottom of trench will be compacted prior to installation of sand bedding for the pipe pipe Start fabricating rebar work at the work shop and Install rebar at designated manhole. After finished rebar rebar work, pour concrete concrete step by step.

1.4 Waste Management All waste materials to be removed from site on a daily basis. Trash collecting bags are to be provided at the working areas. All general waste to be thrown into the provided trash bags according to the type of garbage (Segregate waste before disposal) and should be disposed in to the relevant metal waste bins provided. Wooden crates or palettes must be dismembered before disposal

GFMP

5. METHOD OF STATEMENT FOR LAMP POST Erection. 1.1 Scope of Activity The Scope of Method of Statement is to describe the method of erection for the proposed KALBE Project, Thilawa SEZ A, Yangon, Myanmar. 1.2 Site Observation Before Commencement of the planned work, carry out examination of the physical condition of the area for ongoing activities, blockages of Ingress/ Egress and the weather condition. 1.3 Method of Statement Preparation 

Load all equipment required for Job



Report to KDK and received approval



Put on personal protective equipment



Inform all other contractors in the area of start to work



 

Liaise with Main contractor and other contractor to be ensure safe operation Cordon of work area Ensure the area to be worked and exit points are clear of obstruction



Ensure that safe access and egress is maintained



Determine location of underground services

Producer 

 

Provide copies of the shop drawings, copy of the permit to work & necessary instructions. Briefly introduce the workers on the safety aspects & safe work procedures. Barricade the area of working. Mark out area to be excavated with marker paint After excavation put precast base at excavated area and back filling.

GFMP

 









Ensure the pole is correctly assemble prior to lifting. Ensure all lifting tackle is check for its capacity and adequacy for the weight of pole being lifted. Attached a single loop sling around the pole at approximately two third of overall height, taking care not to damage the pole finish. The slings shall not be wrapped tight around the pole On the opposite side of the lifting side attached the safety rope from the sling and attached the other end to hook which is to be hooked into the access door. Ensure the safety rope is taught at all time Began lifting the pole. After lifting the top of the pole approximately After pipe laying, back fill will start step by step.

1.4 Waste Management All waste materials to be removed from site on a daily basis. Trash collecting bags are to be provided at the working areas. All general waste to be thrown into the provided trash bags according to the type of garbage (Segregate waste before disposal) and should be disposed in to the relevant metal waste bins provided. Wooden crates or palettes must be dismembered before disposal