MCM3320 Application Training Switchgear Engineer Training 083006 Rev4 New Cummins Template
Short Description
Download MCM3320 Application Training Switchgear Engineer Training 083006 Rev4 New Cummins Template...
Description
MCM3320 QTQ Training
Rev 1.5 prd June 13, 2006
Presentation Outline
Introduction Features Hardware Operation System Setup and Simulator (HANDS ON) Operation (continued) Variables Interconnect HMI & Simulator (HANDS ON) InPower Applications (GROUP) Control and Component Mode Panels New Discussion/Questions/Comments
2
Rev 1.5 prd June 13, 2006
Presentation Goals
What are the capabilities of the MCM3320? What are the board connections? How does it operate? How do I apply it? How do I set it up?
3
Rev 1.5 prd June 13, 2006
MCM3320 Information
Lotus Notes Database “Commercial ESB Controls” Sort by “Category” Look for “MCM3320” This presentation and other technical information located there An Application Guide is in the works to provide a one-stop document
4
Rev 1.5 prd June 13, 2006
MCM3320 Technical Support
Documentation PGA Controls Engineering: 1. 2. 3.
5
Rev 1.5 prd June 13, 2006
Kevin Aufderhar Paul Dahlen Rich Scroggins
FEATURES One-Line Feature Summary (Q2 2006)
MCM3320
Customer I/O
AC Metering Source Failure Gensets Start/Stop Main Breaker Control Sync/Volt Match Open/Closed Transition Load Ramping Extended Paralleling kW and kVAR Control Load Demand Load Add / Shed Scheduler Modbus Diagnostics
HMI211 Operator Panel #1
HMI112 Gensets Bargraph
HMI211 Operator Panel #2
HMI211 Utility Bargraph
G1 GM
UM
G2 G3 G4
Breakers or ATS
Load1
6
Rev 1.5 prd June 13, 2006
AUX101 AUX102
Load2
Load3
Load4
Load5
Load6
FEATURES Feature Validation
All available features have been tested Firmware test Bench test w/simulator Live test at Fridley Endurance Pad test facility Live test at Fridley with real Utility Source (transfers, sync, base load / peak shave)
7
Rev 1.5 prd June 13, 2006
FEATURES
AC Metering
3 Phase metering of genset bus and utility bus simultaneously Phase and Total/avg metering of V, A, kW, kVAR, kVA, PF, Hz Phase and total metering of +kWh, -kWh, +kVARh, kVARh, kVAh for each source CT secondaries of 1A or 5A PT accepts 0-480VLL directly; external PT for higher voltages (up to 35000V) PT and CT inputs pre-calibrated
8
Rev 1.5 prd June 13, 2006
FEATURES
Master Sync / Volt Match
both phase synchronization and voltage matching 20 genset limit for synchronizer frequency offset range: +/- 1.0 Hz min; up to +/- 3.0Hz output voltage offset range: +/- 6% min; up to +/- 10% offset range generally independent of gen bus load
9
Rev 1.5 prd June 13, 2006
FEATURES
Master Sync / Volt Match
controls frequency and voltage via PCC kW and kVAR load share lines selectable phase synchronization (default) or slip frequency synchronization sync enable input for manual control mode option to invert synchronizer polarity if genset and utility swap positions in synchronizer only application (via Modbus)
10
Rev 1.5 prd June 13, 2006
FEATURES
Permissive Sync Check
sync check function is independent of synchronizer adjustable frequency window, phase window, voltage window, and window time for permissive check includes configurable dead bus logic sync check output fail to synchronize diagnostic phase rotation mismatch diagnostic
11
Rev 1.5 prd June 13, 2006
FEATURES
Breaker Control
interface for both genset main and utility main close and open control – momentary energization until desired position is achieved a/b and tripped breaker position inputs adjustable breaker recharge time delay to prevent fail to close due to inadequate charge time
12
Rev 1.5 prd June 13, 2006
FEATURES
Breaker Control
utility paralleling enable output breaker inhibit control input breaker diagnostics with appropriate system control reaction adjustable fail to close and fail to open time delays paralleling fail to disconnect diagnostic with configurable system control reaction
13
Rev 1.5 prd June 13, 2006
FEATURES
Breaker Control
anti-pump avoidance logic – external breaker position contacts not required in series with trip coil breaker inhibit output to control individual genset paralleling breakers in applications with no gen main, and for backup disconnect protection capability
14
Rev 1.5 prd June 13, 2006
FEATURES
Power Transfer Control
open transition w/pgm transition delay, hard closed transition (