Contract No.

Document No.

CONSTRUCTION PROCEDURE FOR ROAD AND PAVEMENT  Doc Type: Procedure

Discipline: Construction

LTJ-PGAS-0000-CN-PR-004   LTJ-PGAS-0000-CN-PR-004 Revision: 1

Status: IFC

Revision Date: 15/08/2019  Page 1 of 13

PEKERJAA N PEMBANGUN PEKERJAAN PEMBANGUNAN AN FASILITAS LNG L NG TER TERMIN MINAL AL JAWA JA WA TIMUR This document has been generated by an Electronic Document Management System. When it its printed, it shall be considered as “For information only copy”. “For The controlled copy is the screen version, and thus, it is the holder’s responsibility to make sure that he/she holds the latest valid version.  

CONSTRUCTION PROCEDURE FOR ROAD AND PAVEMENT 

1

15/08/2019

IFC

Re-Issued for Construction

Rev Re v

Date Date

Status

Descrip Descrip tion

FDN

ANS

EFC

FAP

Issued

Checked Checked

Appr oved

Acknow ledge

PGAS SOLUTION

PGN LNG

This document is the property of PGN-LNG and it shall not be disclosed to third parties or reproduced without permission of the COMPANY.  

 

Contract No.

Document No.

CONSTRUCTION PROCEDURE FOR ROAD AND PAVEMENT  Doc Type: Procedure

Discipline: Construction

LTJ-PGAS-0000-CN-PR-004   LTJ-PGAS-0000-CN-PR-004 Revision: 1

Status: IFC

Revision Date: 15/08/2019  Page 2 of 13

REVISION HISTORICAL SHEET Rev. Re v.

Date Date

Page

1

15/08/2019

-

Descrip tio n Re-Issued For Construction

This document is the property of PGN-LNG and it shall not be disclosed to third parties or reproduced without permission of the COMPANY.  

 

Contract No.

Document No.

CONSTRUCTION PROCEDURE FOR ROAD AND PAVEMENT  Doc Type: Procedure

Discipline: Construction

LTJ-PGAS-0000-CN-PR-004   LTJ-PGAS-0000-CN-PR-004 Revision: 1

Status: IFC

Revision Date: 15/08/2019  Page 3 of 13

TABL E OF CONTENT CONTENT

 

TABL E OF CONTENT CONTENT........................................... ............................................................ ................................. ................................. .................................. .............................. .............3  1.  INTRO INTRODUC DUCTION TION ................................. .................................................. ................................. ................................. .................................. .................................. ........................ .......4  2.  DEFIN DEFINITION ITION AND AB BREVIATION ............................. .............................................. ................................. ................................. ................................. ................4  2.1.  2.2. 

Definition Definiti on ................................. ................................................. ................................. .................................. ................................. ................................. ................................. ................4   Abbreviations................... ......... ................... .................. ................... ................... .................. ................... ................... ................... ................... .................. ................... .............. .... 4 

3.  CODE AND STANDARD.............................................. .............................................................. ................................. .................................. ................................. ................4  4.  SUB GRADE .................................. .................................................. ................................. ................................. ................................. ................................. .............................. ..............5  4.1.  4.2. 

Material................................. Material .................................................. ................................. ................................. ................................. ................................. .................................. ................... ..5  Sub Grade Preparation ............................................................................................................... 6  

5.  SUB BA SE .................................. .................................................. ................................. .................................. ................................. ................................. ................................. ................6  5.1.  5.2. 

Material................................. Material .................................................. ................................. ................................. ................................. ................................. .................................. ................... ..6  Sub Base Preparation.................. ......... .................. ................... ................... ................... ................... .................. ................... ................... .................. ................... ............7 

6.  BA SE COURSE COURSE................................ ................................................. .................................. ................................. ................................. .................................. ........................... ..........7  6.1.  Mate Material rial................................. .................................................. ................................. ................................. ................................. ................................. .................................. ................... ..7  6.2.  Base Course Course Preparation: Preparation: .................. ......... ................... ................... ................... ................... .................. ................... ................... ................... ................... ............. .... 8  7.  ROAD AND PAVEMENT PAVEMENT WORKS ............................... ................................................ .................................. ................................. ................................ ................8  7.1.  7.2. 

Material................................. Material .................................................. ................................. ................................. ................................. ................................. .................................. ................... ..8  Construct Cons truction ion ................................. .................................................. .................................. ................................. ................................. .................................. ........................... ..........9 

8.  TEST AND INSPECTIO INSPECTION N ............................... ................................................ ................................. ................................. .................................. ............................ ........... 11  8.1.  8.2. 

Subgrade and Base Course ...................................................................................................... 11   Concrete Conc rete .................................. .................................................. ................................. .................................. ................................. ................................. ............................... ..............11 

This document is the property of PGN-LNG and it shall not be disclosed to third parties or reproduced without permission of the COMPANY.  

 

Contract No.

Document No.

CONSTRUCTION PROCEDURE FOR ROAD AND PAVEMENT  Doc Type: Procedure

1.

Discipline: Construction

LTJ-PGAS-0000-CN-PR-004   LTJ-PGAS-0000-CN-PR-004 Revision: 1

Status: IFC

Revision Date: 15/08/2019  Page 4 of 13

INTRODUCTION This procedure covers the minimum requirement of road and pavement for Pekerjaan Pembangunan Fasilitas LNG Terminal Jawa Timur   Project Project owned by PT PGN LNG Indonesia.

2.

DEFINITION DEFINITION AND AB BREVIATION

2.1.

Definition PROJECT NAME

“Pekerjaan Pembangunan Fasilitas LNG Terminal Jawa Timur”  

PROJECT SITE LOCATION

Teluk Lamong, Surabaya, Surabaya, East Java, Indonesia

CLIENT/OWNER

PT PGN LNG Indonesia

CONTRACTOR

PT PGAS Solution

SUB-CONTRACTOR SUB-CONTRAC TOR

The party(ies) that carry(ies) out all or part of the design, procurement, installation and testing of the system(s) as specified by the CONTRACTOR

VENDOR/SUPPLIER VENDOR/SUPPL IER

Refers to the company selected by CONTRACTOR, CONTRACTOR, which is responsible for the purchase agreement or purchase order of the goods/services specified in this t his document

2.2. Abbreviations  AASHTO

American Association of State Highway and Transportation Official

3.

 ACI

American Concrete Concrete Institute

 AISC

American Institute of Steel construction

 ASCE

American Society Society of Civil Engineers Engineers

 ASTM

American Society Society of Testing and Material Material

JIS

Japan Industrial Standard

SNI

Standar Nasional Indonesia  Indonesia 

CODE AND STANDARD STANDA RD This procedure is prepared based on code and standard. Unless otherwise noted, this reference is made based on the latest code, standard, and specification. Codes, standards, and specifications that are listed in the t he basic design consist of:  AASHTO 1993

Standard Guide for Design of R Road oad and Pavement Pavement

 ASTM A615

Standard Specification Specification for Deformed and Plain Carbon Steel Bars for Concrete Reinforcement Reinforcement

This document is the property of PGN-LNG and it shall not be disclosed to third parties or reproduced without permission of the COMPANY.  

 

Contract No.

Document No.

LTJ-PGAS-0000-CN-PR-004   LTJ-PGAS-0000-CN-PR-004

CONSTRUCTION PROCEDURE FOR ROAD AND PAVEMENT  Doc Type: Procedure

Revision: 1

Status: IFC

Revision Date: 15/08/2019 

Discipline: Construction

Page 5 of 13

 ASTM C33

Standard Specification Specification for Concrete Concrete Aggregate

 ASTM C39

Standard Test Method for Compressive Strength of Cylindrical Concrete Specimens

 ASTM C150  ASTM C494

Standard Specification Specification for Portland Portland Cement Standard Specification Specification for Chemical Chemical Admixture Admixture for Concrete

 ASTM D136

Standard Test Method for Sieve Analysis of Fine and Course  Aggregate.

 ASTM D553

Methods of Test for Viscosity and Total Solids Content of Rubber Cements

 ASTM D792

Standard Test Methods for Density and Specific Gravity of Plastics by Displacement. Displacement.

 ASTM D698

Standard

Test

Methods

for

Laboratory

Compaction

Characteristics Characteristic s of Soil Using Standard Effort  ASTM D1241

Standard Specification Specification for Materials for Soil-Aggregate Soil-Aggregate Sub base, Base, and Surface Courses

 ASTM D1556

Standard Test Method for Density and Unit Weight of Soil in Place by the SandCone Method

 ASTM D1557

Standard

Test

Methods

for

Laboratory

Compaction

Characteristics Characteristic s of Soil Using Modified Effort  ASTM D2628

Standard

Specification Specification

for

Preformed

Polychloroprene Polychloroprene

Elastomeric Joint Seals for Concrete Pavements  ASTM D4492

Test Method for CBR CBR of Soil in Place Place

JIS G 3112.87

Reinforce Steel Bar

PU Bina Marga 2012

Manual Desain Perkerasan Jalan

SNI 07-2052-2002

Baja Tulangan Beton  Beton 

SNI 15-2049-2004

Semen Portland  Portland 

 All deviations from the requirements of this specification, specification, its attachments and the referenced codes and standards shall shall be stated in the quotation. quotation. In the absence of such a statement, statement, full compliance shall be assumed

4.

SUB GRADE

4.1. Material a. All materials used for subgrade shall be free from organic matter, refuse rubbish, broken pieces of concrete, and other foreign substances substances and shall be ap approved proved by CLIENT prior to This document is the property of PGN-LNG and it shall not be disclosed to third parties or reproduced without permission of the COMPANY.  

 

Contract No.

Document No.

LTJ-PGAS-0000-CN-PR-004   LTJ-PGAS-0000-CN-PR-004

CONSTRUCTION PROCEDURE FOR ROAD AND PAVEMENT  Doc Type: Procedure

Revision: 1

Status: IFC

Revision Date: 15/08/2019 

Discipline: Construction

Page 6 of 13

use. Grubbing and stripping shall be done in 10 cm below ground surface or depend on site condition until all foreign substance can be removed (Conform to “Construction Procedure for Site Preparation (Earth Works)” Works)” (Doc. LTJ-PGAS-0000-CN-PR-002 LTJ-PGAS-0000-CN-PR-002-A4) -A4) b. Material for subgrade shall not include high plasticity soil, which is classified as A7-6 according to AASHTO M145 and shall not include very expansive soil which classified on  AASHTO T258. c. SUB-CONTRACTOR SUB-CONTRACTOR

shall

propose

quarry

area

with

laboratory

test

report

for

CONTRACTOR review and CLIENT approval. If SUB-CONTRACTOR changes quarry area, new quarry laboratory test shall be submitted to CONTRACTOR review and CLIENT approval. d. All materials for subgrade shall comply with Construction Procedure for Site Preparation (Earth Works) (Doc. LTJ-PGAS-0000-CN-PR-002-A4). LTJ-PGAS-0000-CN-PR-002-A4).

4.2.. Sub Grade Preparation 4.2 a.

Soft soil and and obstacles encountered in the sub sub grade shall be removed and and replaced replaced with suitable material as approved by CLIENT.

b.

CBR test on finished level of sub grade shall have a minimum value of 10% CBR field test and minimum 95% dry density by modified proctor, as per ASTM D 1557 Standard Test Methods for Laboratory Compaction Characteristics of Soil Using Modified Effort.

c.

The elevation elevation of top subgrade finish shall shall refer to engineering engineering drawing. drawing. The tolerance tolerance of elevation subgrade shall refer to Section 8.0 of this document.

d.

If required, surface of of subgrade may be marked and covered by plastic sheet or other suitable material after final compaction to ensure there are no changes and damages.

5.

SUB BA SE

5.1. Material a.

The sub-base shall consist consist of hard hard durable particles gravel or crushed stone stone aggregates. aggregates. All sub-base material shall be free from organic matter and deleterious substances, and shall be of such quality that it will bind readily to form a firm stable base. Material shall comply with requirement of ASTM D1241 class B as shown in Table 1

b.

Sub-base material shall be compacted to not less than 95% of maximum dry density at optimum moisture as determined in accordance with ASTM D1557.

c.

Minimum thickness of sub base course shall be 300 mm.

This document is the property of PGN-LNG and it shall not be disclosed to third parties or reproduced without permission of the COMPANY.  

 

Contract No.

Document No.

CONSTRUCTION PROCEDURE FOR ROAD AND PAVEMENT  Doc Type: Procedure

Discipline: Construction

LTJ-PGAS-0000-CN-PR-004   LTJ-PGAS-0000-CN-PR-004 Revision: 1

Status: IFC

Revision Date: 15/08/2019  Page 7 of 13

5.2.. Sub Base Preparation 5.2 a.

Sub Base course course shall be excavated or filled, as as required, and and then shall shall be graded graded and compacted to provide a firm foundation of uniform density throughout.

b.

CBR test on finished level level of complete complete sub base course shall have a minimum value value of 30 % CBR field test (refers to Manual Desain Perkerasan Jalan, Jalan, Dirjen Bina Marga, 2012).

c.

The material used for sub base course should be durable and strong and has a CBR value of 30% and Plasticity Index (PI) 4 % (usually used crushed stone class A, B, or C, Lapen or the stability of the aggregates aggregates with cement or asphalt).

d.

Drainage culvert under the sub base course shall have been constructed before the sub base course work is carried out.

e.

The SUB-CONTRACTOR SUB-CONTRACTOR shall provide temporary temporary drainage drainage as required required to facilitate facilitate the work activities during wet/rainy season and keep sub base course material in dry condition.

f.

If required, surface of sub base course may be marked and covered by plastic sheet or other suitable material after final compaction to ensure there are no changes and damages.

6.

BA SE COURSE

6.1. Material a.

Granular of material shall be used as base course under concrete pavement. Such material shall consist of sand, sand-gravel, crushed stone, crushed or granulated slag or combination of this material.

b.

Material for sub sub base shall meet the following requirements: requirements: -

Material gradation shall meet with the minimum class B ASTM D 1241 Standard Specification for Materials for Soil-Aggregate Sub base, Base, and Surface Courses, as shown on Table 1 and ASTM D 136 Standard Test Method for Sieve Analysis of Fine and Course Aggregate.

-

Material shall free from organic matter, refuse rubbish, broken pieces of concrete, and and other foreign substances. Table 1 Material Gradation Class B Sieve Size Weight Percent Passing 2-in. (50-mm) 100 1-in. (25.0-mm) 75 - 95 1-B-in. (9.5-mm) 40 - 75 No. 4 (4.75-mm) 30 - 60 No. 10 (2.00-mm) 20 - 45 No. 40 (425-µm) 15 - 30 No. 200 (75-µm) 5 - 15

This document is the property of PGN-LNG and it shall not be disclosed to third parties or reproduced without permission of the COMPANY.  

 

Contract No.

Document No.

CONSTRUCTION PROCEDURE FOR ROAD AND PAVEMENT  Doc Type: Procedure

Discipline: Construction

LTJ-PGAS-0000-CN-PR-004   LTJ-PGAS-0000-CN-PR-004 Revision: 1

Status: IFC

Revision Date: 15/08/2019  Page 8 of 13

6.2.. Base Cours e Preparation: 6.2 a.

Base course shall be excavated or filled, as required, and then shall be graded and compacted to provide a firm foundation of uniform density throughout.

b.

CBR test on finished level of complete base course shall have a minimum value of 70 % CBR field test (refers to Manual Desain Perkerasan Jalan, Jalan, Dirjen Bina Marga, 2012).

c.

The material used for base course should be durable durable and strong and has a CBR value of 70% and Plasticity Index (PI) 4 % (usually used crushed stone class A, B, or C, Lapen or the stability of the aggregates aggregates with cement or asphalt).

d.

Drainage culvert under the base course shall have been constructed construct ed before the base course work is carried out.

e.

The SUB-CONTRACTOR SUB-CONTRACTOR shall provide temporary temporary drainage drainage as required required to facilitate facilitate the work activities during wet/rainy season and keep base course material in dry condition.

f.

If required, surface of base course may be marked and covered by plastic sheet or other suitable material after final compaction to ensure there are no changes and damages.

7.

ROAD AND PAVEMENT WORKS

7.1. Material a.

Concrete The concrete mix proportions shall be designed to conform to the compressive strength or flexural strength specified on the drawings, or which shall have a minimum compressive str ength, ength, fc’ = 30 MPa at 28 days. The slump shall not exceed 75 mm for paving subject to normal plant vehicular traffic, and 100 mm for paving subject to zero or occasional traffic.

b.

Reinforcement -

The material for concrete concrete reinforcement reinforcement shall shall be of w welded elded steel wire wire fabric conforming to ASTM A 185, or steel reinforcing bars conforming to ASTM A 615 and SNl-07-20522002 BJTD 40 or SNl-07- 2053-2002 BJTP 24.

-

Construction Construct ion joint bars shall use deformed bar and shall conform to ASTM A 615 grade 60, minimum yield strength is 60000 psi (420 MPa) or equal to SNl-07-2052-2002 BJTS 40.

-

Expansion, isolation, and contraction contract ion joint dowel shall use plain/round plain/roun d bar conform and shall conform to AASHTO M-31 or equivalent.

c.

All reinforcement shall be free from rust, dirt, oil, paint and other materials.

Expansion joint filler fille r and sealer Material for joint sealer shall be polyurethane sealant, non-bituminous/asphal non-bituminous/asphalt, t, and for filler shall be flexible foam, soft board or equivalent.

This document is the property of PGN-LNG and it shall not be disclosed to third parties or reproduced without permission of the COMPANY.  

 

Contract No.

Document No.

CONSTRUCTION PROCEDURE FOR ROAD AND PAVEMENT  Doc Type: Procedure

d.

Discipline: Construction

LTJ-PGAS-0000-CN-PR-004   LTJ-PGAS-0000-CN-PR-004 Revision: 1

Status: IFC

Revision Date: 15/08/2019  Page 9 of 13

Polyethylene I plastic sheet or equivalent. equivalent. Polyethylene sheeting or plastic sheeting applied for covering the base shall be capable of withstanding impact during the placing and consolidation of the concrete without tearing.

e.

Minimum overlap for polyethylene I plastic sheet shall be 100 mm. Curing material The curing materials shall be of wet burlap, polyethylene sheeting, waterproof paper or a liquid membrane-forming compound. Burlap containing sugar shall not be used.

7.2. Construction a.

Forms -

The granular granular base under form shall shall be compacted compacted and graded so that form, when when set, are uniformly supported for their entire length and are at the correct elevation.

-

The form shall be of wood wood or steel and shall be cleaned and oiled before used. Bent, twisted or broken forms shall not be used.

-

The form shall be so aligned and secure positioned when the concrete is place and finished.

-

The form form shall shall remain in place for 10 hours if the ambient ambient temperature after placing placing the concrete is more than 10°C. When the ambient temperature is below 10°C, the forms shall remain in position until the pavement edges have hardened sufficiently for the forms to be removed without damage to the pavement.

b.

Joints -

Expansion, isolation, construction, and contraction joints shall be provided in concrete pavements at the locations indicated on the drawing road and pavement.

-

The joint filler shall be straight and perpendicular to the pavement.

-

The top of the expansion joint shall be sealed sealed with sealing sealing material according to the specifications. Before the sealing material is installed the joint opening shall be thoroughly cleaned of all foreign matter. Any excess material spilled over the concrete surface shall be immediately removed.

c.

Reinforcement -

Welded steel wire fabric or steel steel reinforcing bars shall be installed installed in the positions and with the cover of concrete shown on the engineering drawings.

-

Lap length for welded steel wire fabric or steel reinforcing reinforcin g bars and The locations and details of reinforcement for joints shown on the engineering drawings.

This document is the property of PGN-LNG and it shall not be disclosed to third parties or reproduced without permission of the COMPANY.  

 

Contract No.

Document No.

CONSTRUCTION PROCEDURE FOR ROAD AND PAVEMENT  Doc Type: Procedure

d.

Discipline: Construction

LTJ-PGAS-0000-CN-PR-004   LTJ-PGAS-0000-CN-PR-004 Revision: 1

Status: IFC

Revision Date: 15/08/2019  Page 10 of 13

Placing of Concrete -

Prior to placing concrete, SUB-CONTRACTOR SUB-CONTRACTOR shall be notified to CONTRACTOR CONTRACTOR at least 24 hours in advance.

-

Concrete shall be mixed & transported transport ed according accordin g to “Construction Procedure  Procedure  for Concrete Work” (Doc. No. LTJ-PGAS-0000-CN-PR-003). LTJ-PGAS-0000-CN-PR-003).

-

Before the concrete is placed, the granular base base shall be moistened. Polyethylene sheeting shall be laid over the moist granular base. Polyethylene sheeting shall be overlapped at minimum 10 cm.

-

Concrete shall be placed carefully to prevent segregation and displacement of the reinforcement or form work. After spreading, the concrete shall be thoroughly consolidated with vibrators or other approved means.

e.

Finishing of Concrete -

The concrete shall be tamped and consolidated by mechanical or vibro machine.

-

All excess water and laitance shall be removed removed from the surface of the concrete by scraping. Bleeding water shall not be mixed into the concrete.

-

The surface of the concrete shall be sloped, grooved and carefully finished to prevent future pounding use suitable tools/equipment.

f.

Slope of road surface shall refer to engineering drawing for road and pavement section.

Curing -

Curing shall commence immediately immediatel y after the concrete surface is finished. Concrete surface, including the vertical sides, shall be completely covered with curing material.

-

Burlap shall be kept continually moistened during the curing period. Polyethylene Polyet hylene sheeting or waterproof paper shall be overlapped to prevent moisture loss from concrete. A curing compound may be applied after approval by CLIENT.

-

Curing shall be continued for at least 5 days when the temperature temperatu re is 21°C or higher or for at least 7 days when the temperature is less than 21°C. If the concrete contains high early strength Portland cement, the curing period shall be reduced to at least 3 days.

-

The finished pavement shall be closed to pedestrian traffic for a minimum of 3 days and strictly prohibited to vehicular traffic until the concrete has attained its designed compressive strength.

This document is the property of PGN-LNG and it shall not be disclosed to third parties or reproduced without permission of the COMPANY.  

 

Contract No.

Document No.

LTJ-PGAS-0000-CN-PR-004   LTJ-PGAS-0000-CN-PR-004

CONSTRUCTION PROCEDURE FOR ROAD AND PAVEMENT  Doc Type: Procedure

8.

Revision: 1

Status: IFC

Revision Date: 15/08/2019 

Discipline: Construction

Page 11 of 13

TEST AND INSPECTION

8.1.. Subgr ade and Base Cours e 8.1 a.

b.

Inspection -

Surface condition with visual inspection.

-

Tolerance of level (common practice in inspection for surface):  Allowable  Allowabl e deviation

: + 20 mm

Frequency of inspection

: every 50 m at center and both sides.

Testing Test method to be applied: -

ASTM D 1556, Density of Soil in Place by Sand Cone Method.

-

ASTM D 1557, Standard Test Methods for Laboratory Compaction Characteristics of Soil Using Modified Effort

-

ASTM D 1883, CBR Test

Frequency of testing Item

Frequency

Test

Pavement

Every 1000 m2 on Subgrade

Sand Cone + CBR

Every 100 m2 on Subgrade

Sand Cone + CBR

Every 100 m2 on Subbase

Sand Cone + CBR

Every 100 m2 on Base Course

Sand Cone + CBR

Road

8.2. Concrete a.

Inspection Surface condition with visual inspection. -

Tolerance of inspection (common practice):  Allowable  Allowabl e deviation of level

: + 10 mm

Frequency of level inspection

: every 20 m at center and both sides

Maximum allowance allowance width for for crack : + 2 mm b.

Testing The CONTRACTOR shall employ an independent third party testing laboratory and furnish all equipment facilities and labor required for field sampling, curing, transporting test sampling, field and laboratory test, recording of test result and preparing necessary report.  All test report copy shall shall be sent to Engineer Engineer as each is is completed, for review review and appro approval. val.

This document is the property of PGN-LNG and it shall not be disclosed to third parties or reproduced without permission of the COMPANY.  

 

Contract No.

Document No.

CONSTRUCTION PROCEDURE FOR ROAD AND PAVEMENT  Doc Type: Procedure

-

Discipline: Construction

LTJ-PGAS-0000-CN-PR-004   LTJ-PGAS-0000-CN-PR-004 Revision: 1

Status: IFC

Revision Date: 15/08/2019  Page 12 of 13

Mix Proportion Test Prior to the commencement of concrete work, SUB-CONTRACTOR shall perform mix proportion test to determine the kinds and mix proportion of cement, coarse aggregate, fine aggregate, water and admixtures. Result of the mix proportion test shall be reported in the prescribed form shown in table herewith:

-

Compressive Strength Test Compressive strengths of concrete at 28 days monitored by cylinder test, a minimum of four concrete mix samples shall be taken from each batch of concrete. Speciments shall be obtained in accordance with ASTM C172. The minimum compressive strength evaluation of all compressive strength data shall be done in accordance with ACI-214.

-

Slump test. Slump test shall be made in accordance with ASTM C 143 unless otherwise specified. Frequency of slump test shall be determined based on the weather conditions and on the operating condition of the mixer, however, the slump tests shall be made at least once for each set of specimen. Slump range for various types types of construction shown in table herewith (References: ACI 211.1-91 Table 9-6):

This document is the property of PGN-LNG and it shall not be disclosed to third parties or reproduced without permission of the COMPANY.  

 

Contract No.

Document No.

CONSTRUCTION PROCEDURE FOR ROAD AND PAVEMENT  Doc Type: Procedure

-

Discipline: Construction

LTJ-PGAS-0000-CN-PR-004   LTJ-PGAS-0000-CN-PR-004 Revision: 1

Status: IFC

Revision Date: 15/08/2019  Page 13 of 13

Air content test  Air content test shall be carried out if requested by CONTRACTOR, and in accordance with the requirements given in ASTM C 138, ASTM C 173, or ASTM C 231.

This document is the property of PGN-LNG and it shall not be disclosed to third parties or reproduced without permission of the COMPANY.  