Lf Cue Cost 3 Seattle
Short Description
lo...
Description
CUECost - Air Pollution Control Systems Economics Spreadsheet
Economic Inputs Cost Basis -Year Dollars Sevice Life (levelization period) Inflation Rate After Tax Discount Rate (current $'s) AFDC Rate (current $'s) First-year Carrying Charge (current $'s) Levelized Carrying Charge (current $'s) First-year Carrying Charge (constant $'s) Levelized Carrying Charge (constant $'s) Sales Tax Escalation Rates: Consumables (O&M) Capital Costs: Is Chem. Eng. Cost Index available? If "Yes" input cost basis CE Plant Index. If "No" input escalation rate. Construction Labor Rate Prime Contractor's Markup Operating Labor Rate Power Cost Steam Cost
254276149.xls.ms_office, User Input Sheet
Year Years % % % % % % % %
1998 30 3.00% 9.20% 10.80% 22.30% 16.90% 15.70% 11.70% 6%
2009 20 3.00% 9.20% 10.80% 22.30% 16.90% 15.70% 11.70% 6.5%
2009 20 3.00% 9.20% 10.80% 22.30% 16.90% 15.70% 11.70% 6.5%
2009 20 3.00% 9.20% 10.80% 22.30% 16.90% 15.70% 11.70% 6.5%
2009 20 3.00% 9.20% 10.80% 22.30% 16.90% 15.70% 11.70% 6.5%
2009 20 3.00% 9.20% 10.80% 22.30% 16.90% 15.70% 11.70% 6.5%
%
3%
3%
3%
3%
3%
3%
Yes / No Integer % $/hr % $/hr Mills/kWh $/1000 lbs
Yes 388 3% $35 3% $30 25 3.5
Yes 561 3% $35 3% $35 53.3 3.5
Yes 561 3% $35 3% $35 53.3 3.5
Yes 561 3% $35 3% $35 53.5 3.5
Yes 561 3% $35 3% $35 53.3 3.5
Yes 561 3% $35 3% $35 53.3 3.5
1
12/9/2014, 12:59 PM
CUECost - Air Pollution Control Systems Economics Spreadsheet
APC Technology Choices Description
Units
Input 1
Input 2
Input 3
Input 4
Input 5
FGD Process (1 = LSFO, 2 = LSD) Particulate Control (1 = Fabric Filter, 2 = ESP) NOx Control (1 = SCR, 2 = SNCR, 3 = LNBs, 4 = NGR)
Integer
1
1
2
2
2
Integer
2
2
2
2
2
Integer
1
2
1
2
4
Units
Input 1
Input 2
Input 3
Input 4
Input 5
Abbrev. MW Btu/kWhr % % % °F °F In. of Hg In. of H2O lb/lb dry air
WA 22.5 10,500 95% 120% 12% 300 55 29.4 -12 0.013
WA 22.5 10,500 95% 120% 12% 300 55 29.4 -12 0.013
WA 22.5 10,500 95% 120% 12% 300 55 29.4 -12 0.013
WA 22.5 10,500 95% 120% 12% 300 55 29.4 -12 0.013
Wa 22.5 10,500 95% 120% 12% 300 55 29.4 -12 0.013
% % Integer Integer
80% 20% 3 1.6
80% 20% 3 1.6
80% 20% 3 1.6
80% 20% 3 1.6
80% 20% 3 1.6
Integer Yes / No
6 Yes
6 yes
6 Yes
6 Yes
8 yes
Year Years % % % % % % % %
2009 20 3% 9% 11% 22% 17% 16% 12% 7%
2009 20 3% 9% 11% 22% 17% 16% 12% 7%
2009 20 3% 9% 11% 22% 17% 16% 12% 7%
2009 20 3% 9% 11% 22% 17% 16% 12% 7%
2009 20 3% 9% 11% 22% 17% 16% 12% 7%
%
3%
3%
3%
3%
3%
Yes / No Integer % $/hr % $/hr Mills/kWh $/1000 lbs
Yes 561 3% $35 3% $35 53.3 3.5
Yes 561 3% $35 3% $35 53.3 3.5
Yes 561 3% $35 3% $35 53.5 3.5
Yes 561 3% $35 3% $35 53.3 3.5
Yes 561 3% $35 3% $35 53.3 3.5
95% 125 2
95% 125 1
95% 125 2
95% 125 2
95% 125 2
INPUTS Description
General Plant Technical Inputs Location - State MW Equivalent of Flue Gas to Control System Net Plant Heat Rate Plant Capacity Factor Total Air Downstream of Economizer Air Heater Leakage Air Heater Outlet Gas Temperature Inlet Air Temperature Ambient Absolute Pressure Pressure After Air Heater Moisture in Air Ash Split: Fly Ash Bottom Ash Seismic Zone Retrofit Factor (1.0 = new, 1.3 = medium, 1.6 = difficult) Select Coal Is Selected Coal a Powder River Basin Coal?
Economic Inputs Cost Basis -Year Dollars Sevice Life (levelization period) Inflation Rate After Tax Discount Rate (current $'s) AFDC Rate (current $'s) First-year Carrying Charge (current $'s) Levelized Carrying Charge (current $'s) First-year Carrying Charge (constant $'s) Levelized Carrying Charge (constant $'s) Sales Tax Escalation Rates: Consumables (O&M) Capital Costs: Is Chem. Eng. Cost Index available? If "Yes" input cost basis CE Plant Index. If "No" input escalation rate. Construction Labor Rate Prime Contractor's Markup Operating Labor Rate Power Cost Steam Cost
Limestone Forced Oxidation (LSFO) Inputs SO2 Removal Required L/G Ratio Design Scrubber with Dibasic Acid Addition? (1 = yes, 2 = no)
% gal / 1000 acf Integer
254276149.xls.ms_office, Input & Calculation Summary
2
12/9/2014, 12:59 PM
CUECost - Air Pollution Control Systems Economics Spreadsheet Adiabatic Saturation Temperature Reagent Feed Ratio (Mole CaCO3 / Mole SO2 removed) Scrubber Slurry Solids Concentration Stacking, Landfill, Wallboard (1 = stacking, 2 = lanfill, 3 = wallboard) Number of Absorbers (Max. Capacity = 700 MW per absorber) Absorber Material (1 = alloy, 2 = RLCS) Absorber Pressure Drop Reheat Required ? (1 = yes, 2 = no) Amount of Reheat Reagent Bulk Storage Reagent Cost (delivered) Landfill Disposal Cost Stacking Disposal Cost Credit for Gypsum Byproduct Maintenance Factors by Area (% of Installed Cost) Reagent Feed SO2 Removal Flue Gas Handling Waste / Byproduct Support Equipment Contingency by Area (% of Installed Cost) Reagent Feed SO2 Removal Flue Gas Handling Waste / Byproduct Support Equipment General Facilities by Area (% of Installed Cost) Reagent Feed SO2 Removal Flue Gas Handling Waste / Byproduct Support Equipment Engineering Fees by Area (% of Installed Cost) Reagent Feed SO2 Removal Flue Gas Handling Waste / Byproduct Support Equipment
°F Factor
127 1.05
127 1.05
127 1.05
127 1.05
127 1.05
Wt. % Integer
15% 1
15% 1
15% 1
15% 1
15% 1
Integer
1
1
1
1
1
Integer
1
1
1
1
1
in. H2O Integer
6 2
6 2
6 2
6 2
6 2
°F Days $/ton $/ton $/ton $/ton
0 60 $15 $30 $6 $2
0 60 $15 $30 $6 $2
0 60 $15 $30 $6 $2
0 60 $15 $30 $6 $2
0 60 $15 $30 $6 $2
% % % % %
5% 5% 5% 5% 5%
5% 5% 5% 5% 5%
5% 5% 5% 5% 5%
5% 5% 5% 5% 5%
5% 5% 5% 5% 5%
% % % % %
20% 20% 20% 20% 20%
20% 20% 20% 20% 20%
20% 20% 20% 20% 20%
20% 20% 20% 20% 20%
20% 20% 20% 20% 20%
% % % % %
10% 10% 10% 10% 10%
10% 10% 10% 10% 10%
10% 10% 10% 10% 10%
10% 10% 10% 10% 10%
10% 10% 10% 10% 10%
% % % % %
10% 10% 10% 10% 10%
10% 10% 10% 10% 10%
10% 10% 10% 10% 10%
10% 10% 10% 10% 10%
10% 10% 10% 10% 10%
% °F °F °F Factor
30% 127 20 147 0.31
30% 127 20 147 0.31
30% 127 20 147 0.31
30% 127 20 147 0.31
25% 127 20 147 0.26
Factor
19.5
19.5
19.5
19.5
30
Wt. % Integer
50% 1
50% 1
50% 1
50% 1
50% 1
Integer
1
1
1
1
1
in. H2O Days $/ton $/ton
5 60 $0 $0
5 60 $0 $0
5 60 $0 $0
5 60 $0 $0
1 60 $0 $0
% % % % %
5% 5% 5% 5% 5%
5% 5% 5% 5% 5%
5% 5% 5% 5% 5%
5% 5% 5% 5% 5%
5% 5% 0% 0% 5%
Lime Spray Dryer (LSD) Inputs SO2 Removal Required Adiabatic Saturation Temperature Flue Gas Approach to Saturation Spray Dryer Outlet Temperature Reagent Feed Ratio (Mole CaO / Mole Inlet SO2) Recycle Rate (lb recycle / lb lime feed) Recycle Slurry Solids Concentration Number of Absorbers (Max. Capacity = 300 MW per spray dryer) Absorber Material (1 = alloy, 2 = RLCS) Spray Dryer Pressure Drop Reagent Bulk Storage Reagent Cost (delivered) Dry Waste Disposal Cost Maintenance Factors by Area (% of Installed Cost) Reagent Feed SO2 Removal Flue Gas Handling Waste / Byproduct Support Equipment Contingency by Area (% of Installed Cost) 254276149.xls.ms_office, Input & Calculation Summary
3
12/9/2014, 12:59 PM
CUECost - Air Pollution Control Systems Economics Spreadsheet Reagent Feed SO2 Removal Flue Gas Handling Waste / Byproduct Support Equipment General Facilities by Area (% of Installed Cost) Reagent Feed SO2 Removal Flue Gas Handling Waste / Byproduct Support Equipment Engineering Fees by Area (% of Installed Cost) Reagent Feed SO2 Removal Flue Gas Handling Waste / Byproduct Support Equipment
% % % % %
20% 20% 20% 20% 20%
20% 20% 20% 20% 20%
20% 20% 20% 20% 20%
20% 20% 20% 20% 20%
20% 20% 0% 0% 20%
% % % % %
10% 10% 10% 10% 10%
10% 10% 10% 10% 10%
10% 10% 10% 10% 10%
10% 10% 10% 10% 10%
10% 0% 0% 10% 10%
% % % % %
10% 10% 10% 10% 10%
10% 10% 10% 10% 10%
10% 10% 10% 10% 10%
10% 10% 10% 10% 10%
10% 10% 10% 10% 10%
lbs/MMBtu
0.001
0.001
0.001
0.001
0.001
in. H2O Integer
6 2
6 2
6 2
6 2
6 2
ACFM/ft2 Integer
3.5 2
3.5 2
3.5 2
3.5 2
3.5 2
inches feet % Years % % % %
6 20 3 10% 5 5% 20% 10% 10%
6 20 3 10% 5 5% 20% 10% 10%
6 20 3 10% 5 5% 20% 10% 10%
6 20 3 10% 5 5% 20% 10% 10%
6 20 3 10% 5 5% 20% 10% 10%
kV/cm in. ft. in. H2O % % % %
10.0 12 36 3 5% 20% 10% 10%
10.0 12 36 3 5% 20% 10% 10%
10.0 12 36 3 5% 20% 10% 10%
10.0 12 36 3 5% 20% 10% 10%
10.0 12 36 3 5% 20% 10% 10%
NH3/NOX Fraction lbs/MMBtu 1/hr years $/ton $/ft3 $/ton % % % % integer integer
0.9 0.90 6.93 0 3 280 356.34 11.48 1.5% 20% 5% 10% 2 1
0.9 0.90 6.93 0 3 280 356.34 11.48 1.5% 20% 5% 10% 2 1
0.9 0.90 6.93 0 3 280 356.34 11.48 1.5% 20% 5% 10% 2 1
0.9 0.90 6.93 0 3 280 356.34 11.48 1.5% 20% 5% 10% 2 1
0.9 0.90 6.93 0 3 282 356.34 11.48 1.5% 20% 5% 10% 2 1
1:Urea 2:Ammonia integer
2 3
2 3
2 3
2 3
2 3
Particulate Control Inputs Outlet Particulate Emission Limit Fabric Filter: Pressure Drop Type (1 = Reverse Gas, 2 = Pulse Jet) Gas-to-Cloth Ratio Bag Material (RGFF fiberglass only) (1 = Fiberglass, 2 = Nomex, 3 = Ryton) Bag Diameter Bag Length Bag Reach Compartments out of Service Bag Life Maintenance (% of installed cost) Contingency (% of installed cost) General Facilities (% of installed cost) Engineering Fees (% of installed cost) ESP: Strength of the electric field in the ESP = E Plate Spacing Plate Height Pressure Drop Maintenance (% of installed cost) Contingency (% of installed cost) General Facilities (% of installed cost) Engineering Fees (% of installed cost)
NOx Control Inputs Selective Catalytic Reduction (SCR) Inputs NH3/NOX Stoichiometric Ratio NOX Reduction Efficiency Inlet NOx Space Velocity (Calculated if zero) Overall Catalyst Life Ammonia Cost Catalyst Cost Solid Waste Disposal Cost Maintenance (% of installed cost) Contingency (% of installed cost) General Facilities (% of installed cost) Engineering Fees (% of installed cost) Number of Reactors Number of Air Preheaters Selective NonCatalytic Reduction (SNCR) Inputs Reagent Number of Injector Levels
254276149.xls.ms_office, Input & Calculation Summary
4
12/9/2014, 12:59 PM
CUECost - Air Pollution Control Systems Economics Spreadsheet Number of Injectors Number of Lance Levels Number of Lances Steam or Air Injection for Ammonia NOX Reduction Efficiency Inlet NOx NH3/NOX Stoichiometric Ratio Urea/NOX Stoichiometric Ratio Urea Cost Ammonia Cost Water Cost Maintenance (% of installed cost) Contingency (% of installed cost) General Facilities (% of installed cost) Engineering Fees (% of installed cost)
integer integer integer integer Fraction lbs/MMBtu NH3/NOX Urea/NOX $/ton $/ton $/1,000 gal % % % %
18 0 0 2 0.40 6.93 1.2 1.2 225 280 0.407 1.5% 20% 5% 10%
18 0 0 2 0.40 6.93 1.2 1.2 224.95 280 0.407 1.5% 20% 5% 10%
18 0 0 2 0.40 6.93 1.2 1.2 224.95 280 0.407 1.5% 20% 5% 10%
18 0 0 2 0.40 6.93 1.2 1.2 224.95 280 0.407 1.5% 20% 5% 10%
18 0 0 2 0.40 6.93 1.2 1.2 224.95 280 0.407 1.5% 20% 5% 10%
fraction T:T-fired, W:Wall
0.35 T
0.35 T
0.35 T
0.35 T
0.35 T
L:Low, A:Average, H:High % %
A 0.8% 1.2%
A 0.8% 1.2%
A 0.8% 1.2%
A 0.8% 1.2%
A 0.8% 1.2%
fraction fraction $/ton $/MMBtu % % % %
0.61 0.15 11.48 1.04 1.5% 20% 2% 10%
0.61 0.15 11.48 1.04 1.5% 20% 2% 10%
0.61 0.15 11.48 1.04 1.5% 20% 2% 10%
0.61 0.15 11.48 1.04 1.5% 20% 2% 10%
0.61 0.15 11.48 1.04 1.5% 20% 2% 10%
Low NOX Burner Technology Inputs NOX Reduction Efficiency Boiler Type
Retrofit Difficulty Maintenance Labor (% of installed cost) Maintenance Materials (% of installed cost) Natural Gas Reburning Inputs NOX Reduction Efficiency Gas Reburn Fraction Waste Disposal Cost Natural Gas Cost Maintenance (% of installed cost) Contingency (% of installed cost) General Facilities (% of installed cost) Engineering Fees (% of installed cost)
254276149.xls.ms_office, Input & Calculation Summary
5
12/9/2014, 12:59 PM
CUECost - Air Pollution Control Systems Economics Spreadsheet
SCR (high-dust) - Preliminary
Case1
Case2
Case3
Case4
Case5
Ammonia Injection Rate
lb/hr
545
545
545
545
545
Space Velocity
1/hr ft3
2,673
2,673
2,673
2,673
2,673
1,163
1,163
1,163
1,163
1,163
Gross Catalyst Volume
SCR Capital Costs Cost Basis (Year)
Case1
Case2
Case3
Case4
Case5
2009
2009
2009
2009
2009
Reactor Housing and Installation Ammonia Handling and Injection
$ $
1,316,707 1,663,119
1,316,707 1,663,119
1,316,707 1,663,119
1,316,707 1,663,119
1,316,485 1,663,119
Flue Gas Handling:Ductwork and Fans
$
851,019
851,019
851,019
851,019
850,815
Air Preheater Modifications Misc. Other Direct Capital Costs Equipment Capital Cost Subtotal Instruments & Controls Taxes Freight Total Direct Cost
$ $ $ $ $ $
145,068 226,217 $4,202,130 $84,043 $273,138 $210,107 $4,769,418
145,068 226,217 $4,202,130 $84,043 $273,138 $210,107 $4,769,418
145,068 226,217 $4,202,130 $84,043 $273,138 $210,107 $4,769,418
145,068 226,217 $4,202,130 $84,043 $273,138 $210,107 $4,769,418
145,028 226,217 $4,201,664 $84,033 $273,108 $210,083 $4,768,888
Total Direct Cost with Retrofit Factor General Facilities Engineering Fees Contingency Total Plant Cost (TPC) Total Plant Cost (TPC) w/ Prime Contractor's Markup
$ $ $ $ $ $
$7,631,069 $381,553 $763,107 $1,526,214 $10,301,943 $10,611,001
$7,631,069 $381,553 $763,107 $1,526,214 $10,301,943 $10,611,001
$7,631,069 $381,553 $763,107 $1,526,214 $10,301,943 $10,611,001
$7,631,069 $381,553 $763,107 $1,526,214 $10,301,943 $10,611,001
$7,630,221 $381,511 $763,022 $1,526,044 $10,300,799 $10,609,823
Total Cash Expended (TCE)
$
$10,611,001
$10,611,001
$10,611,001
$10,611,001
$10,609,823
Allow. for Funds During Constr. (AFDC)
$
$0
$0
$0
$0
$0
Total Plant Investment (TPI) Preproduction Costs Inventory Capital Initial Ammonia(60 days) Initial Catalyst
$ $
$10,611,001 $285,109
$10,611,001 $285,109
$10,611,001 $285,109
$10,611,001 $285,109
$10,609,823 $285,483
$ $
$104,472 $414,396
$104,472 $414,396
$104,472 $414,396
$104,472 $414,396
$105,218 $414,252
$ $/kW
$11,414,978 $507
$11,414,978 $507
$11,414,978 $507
$11,414,978 $507
$11,414,776 $507
Case1
Case2
Case3
Case4
Case5
2009
2009
2009
2009
2009
Total Capital Requirement (TCR)
SCR O&M Costs Cost Basis (Year) Ammonia
$/yr
635,535
635,535
635,535
635,535
640,075
Catalyst Replacement
$/yr
138,132
138,132
138,132
138,132
138,084
Catalyst Disposal
$/yr
107
107
107
107
107
Electricity High-dust SCR Steam Operating Labor Maintenance Total O&M Costs
$/yr $/yr $/yr $/yr $/yr
(2,342) 60,327 51,158 154,529 1,037,447
SNCR - Preliminary Number of Wall Injectors Number of Lances Urea Injection Rate Ammonia Injection Rate
integer integer lb/hr lb/hr
SNCR Capital Costs Cost Basis (Year)
254276149.xls.ms_office, NOX Cost & Tech. Results
6
(2,342) 60,327 51,158 154,529 1,037,447
(2,351) 60,327 51,158 154,529 1,037,438
(2,342) 60,327 51,158 154,529 1,037,447
(2,356) 60,327 51,158 154,512 1,041,907
Case1
Case2
Case3
Case4
Case5
18 0 1277 727
18 0 1277 727
18 0 1277 727
18 0 1277 727
18 0 1277 727
Case1
Case2
Case3
Case4
Case5
2009
2009
2009
2009
2009
12/9/2014, 12:59 PM
CUECost - Air Pollution Control Systems Economics Spreadsheet Urea Based SNCR Costs Urea Storage & Handling Urea Injection
$ $
$0 $0
$0 $0
$0 $0
$0 $0
$0 $0
Controls/Miscellaneous
$
$0
$0
$0
$0
$0
Air Heater Modifications Ammonia Based SNCR Costs Ammonia Storage, Handling, Injection, Controls
$
$0
$0
$0
$0
$0
$
$424,704
$424,704
$424,704
$424,704
$424,704
Air Heater Modifications Total Direct Cost
$ $
$92,417 $517,121
$92,417 $517,121
$92,417 $517,121
$92,417 $517,121
$92,378 $517,082
Total Direct Cost with Retrofit Factor General Facilities Engineering Fees Contingency Total Plant Cost (TPC) Total Plant Cost (TPC) w/ Prime Contractor's Markup
$ $ $ $ $ $
$827,394 $41,370 $82,739 $165,479 $1,116,982 $1,150,492
$827,394 $41,370 $82,739 $165,479 $1,116,982 $1,150,492
$827,394 $41,370 $82,739 $165,479 $1,116,982 $1,150,492
$827,394 $41,370 $82,739 $165,479 $1,116,982 $1,150,492
$827,331 $41,367 $82,733 $165,466 $1,116,897 $1,150,404
Total Cash Expended (TCE)
$
$1,150,492
$1,150,492
$1,150,492
$1,150,492
$1,150,404
Allow. for Funds During Constr. (AFDC)
$
$0
$0
$0
$0
$0
Total Plant Investment (TPI) Preproduction Costs
$ $
$1,150,492 $105,125
$1,150,492 $105,125
$1,150,492 $105,125
$1,150,492 $105,125
$1,150,404 $105,123
$
$139,295
$139,295
$139,295
$139,295
$139,295
$ $/kW
$1,394,913 $62.0
$1,394,913 $62.0
$1,394,913 $62.0
$1,394,913 $62.0
$1,394,822 $62.0
Case1
Case2
Case3
Case4
Case5
2009
2009
2009
2009
2009
Inventory Capital
Total Capital Requirement (TCR)
SNCR O&M Costs Cost Basis (Year) Operating and Supervisory Labor Maintenance Labor and Materials
$/yr $/yr
76,650 16,755
76,650 16,755
76,650 16,755
76,650 16,755
76,650 16,753
Reagent
$/yr
847,380
847,380
847,380
847,380
847,380
Electricity
$/yr
42,216
42,216
42,374
42,216
42,216
Water
$/yr
-
-
-
-
-
Steam (for steam atomization) Total O&M Costs
$/yr $/yr
983,001
Low NOX Burner Technology Capital Costs Cost Basis (Year)
Total Capital Requirement with Retrofit (TCR)
$ $/kW
Low NOX Burner Technology O&M Costs Cost Basis (Year) Maintenance Labor Maintenance Materials Control, Administration, Overhead Total O&M Costs
254276149.xls.ms_office, NOX Cost & Tech. Results
7
983,160
983,001
983,000
Case1
Case2
Case3
Case4
Case5
2009
2009
2009
2009
2009
$1,852,731 $82.3
$1,852,731 $82.3
$1,852,731 $82.3
$1,852,731 $82.3
$1,852,731 $82.3
Case1
Case2
Case3
Case4
Case5
2009 14,822 22,233 4,447 41,501
$/yr $/yr $/yr $/yr
983,001
2009 14,822 22,233 4,447 41,501
2009 14,822 22,233 4,447 41,501
2009 14,822 22,233 4,447 41,501
2009 14,822 22,233 4,447 41,501
12/9/2014, 12:59 PM
CUECost - Air Pollution Control Systems Economics Spreadsheet
Natural Gas Reburning - Preliminary
Case1
Case2
Case3
Case4
Case5
Fraction of heat input as reburn fuel
fraction
0.15
0.15
0.15
0.15
0.15
Bottom Ash Rate
tons/yr
91
91
91
91
94
Case1
Case2
Case3
Case4
Case5
2009
2009
2009
2009
2009
Natural Gas Reburning Capital Costs Cost Basis (Year) Gas Pipeline from Fenceline to Boiler Fuel Injectors, Overfire Air Ports and Associated Piping, Valves, Windbox and Control Dampers Total Direct Cost
$
$501,678
$501,678
$501,678
$501,678
$501,678
$ $
$1,274,466 $1,776,145
$1,274,466 $1,776,145
$1,274,466 $1,776,145
$1,274,466 $1,776,145
$1,274,466 $1,776,145
Total Direct Cost with Retrofit Factor General Facilities Engineering Fees Contingency Total Plant Cost (TPC) Total Plant Cost (TPC) w/ Prime Contractor's Markup
$ $ $ $ $ $
$2,841,832 $56,837 $284,183 $568,366 $3,751,218 $3,863,754
$2,841,832 $56,837 $284,183 $568,366 $3,751,218 $3,863,754
$2,841,832 $56,837 $284,183 $568,366 $3,751,218 $3,863,754
$2,841,832 $56,837 $284,183 $568,366 $3,751,218 $3,863,754
$2,841,832 $56,837 $284,183 $568,366 $3,751,218 $3,863,754
Total Cash Expended (TCE)
$
$3,863,754
$3,863,754
$3,863,754
$3,863,754
$3,863,754
Allow. for Funds During Constr. (AFDC)
$
$0
$0
$0
$0
$0
Total Plant Investment (TPI) Preproduction Costs Inventory Capital
$ $ $
$3,863,754 $80,823 $0
$3,863,754 $80,823 $0
$3,863,754 $80,823 $0
$3,863,754 $80,823 $0
$3,863,754 $80,793 $0
$ $/kW
$3,944,577 $175.3
$3,944,577 $175.3
$3,944,577 $175.3
$3,944,577 $175.3
$3,944,547 $175.3
Case1
Case2
Case3
Case4
Case5
2009
2009
2009
2009
2009
Total Capital Requirement (TCR)
Natural Gas Reburning O&M Costs Cost Basis (Year)
Electrical Consumption Savings
$/yr
(19,416)
(19,416)
(19,489)
(19,416)
(19,433)
Maintenance
$/yr
56,236
56,236
56,236
56,236
56,236
Waste Disposal Savings
$/yr
(12,981)
(12,981)
(12,981)
(12,981)
(13,318)
Natural Gas Consumption Total O&M Costs
$/yr
(134,479) (110,641)
(134,479) (110,641)
(134,479) (110,714)
(134,479) (110,641)
(134,479) (110,995)
254276149.xls.ms_office, NOX Cost & Tech. Results
8
12/9/2014, 12:59 PM
CUECost - Air Pollution Control Systems Economics Spreadsheet
LSFO Material Balance - Preliminary
Case1
Case 2
Case 3
Case 4
Case 5
°F in. H2O SCFM ACFM lb/hr lb/hr lb/hr lb/hr lb/hr lb/hr lb/hr lb/hr lb/hr
295 10 58,015 83,634 50,489 184,042 301 14,693 28 66 17,793 0 267,412
295 10 58,015 83,634 50,489 184,042 301 14,693 28 66 17,793 0 267,412
295 10 58,015 83,634 50,489 184,042 301 14,693 28 66 17,793 0 267,412
295 10 58,015 83,634 50,489 184,042 301 14,693 28 66 17,793 0 267,412
295 10 57,995 83,605 50,535 183,960 188 14,687 28 66 17,805 0 267,269
°F in. H2O SCFM ACFM lb/hr lb/hr lb/hr lb/hr lb/hr lb/hr lb/hr lb/hr lb/hr
295 10 58,015 83,634 50,489 184,042 301 14,693 28 66 17,793 0 267,412
295 10 58,015 83,634 50,489 184,042 301 14,693 28 66 17,793 0 267,412
295 10 58,015 83,634 50,489 184,042 301 14,693 28 66 17,793 0 267,412
295 10 58,015 83,634 50,489 184,042 301 14,693 28 66 17,793 0 267,412
295 10 57,995 83,605 50,535 183,960 188 14,687 28 66 17,805 0 267,269
°F in. H2O SCFM ACFM lb/hr lb/hr lb/hr lb/hr lb/hr lb/hr lb/hr lb/hr lb/hr
127 4 60,374 68,672 50,702 184,988 15 14,907 0 66 23,773 0 274,451
127 4 60,374 68,672 50,702 184,988 15 14,907 0 66 23,773 0 274,451
127 4 60,374 68,672 50,702 184,988 15 14,907 0 66 23,773 0 274,451
127 4 60,374 68,672 50,702 184,988 15 14,907 0 66 23,773 0 274,451
127 4 60,249 68,531 50,675 184,552 9 14,821 0 66 23,762 0 273,884
Btu/lbmol°F Btu/lbmol°F Btu/lbmol°F Btu/lbmol°F Btu/lbmol°F Btu/lbmol°F Btu/lbmol°F Btu/lb°F Btu/lb°F Btu/lb°F Btu/lb°F Btu/lb°F Btu/lb°F Btu/lb°F °C K °C K Btu/hr
7.203 9.263 6.990 8.048 7.151 9.771 6.951 0.225 0.210 0.249 0.447 0.238 0.153 0.191 52.8 325.8 52.8 325.8 0
7.203 9.263 6.990 8.048 7.151 9.771 6.951 0.225 0.210 0.249 0.447 0.238 0.153 0.191 52.8 325.8 52.8 325.8 0
7.203 9.263 6.990 8.048 7.151 9.771 6.951 0.225 0.210 0.249 0.447 0.238 0.153 0.191 52.8 325.8 52.8 325.8 0
7.203 9.263 6.990 8.048 7.151 9.771 6.951 0.225 0.210 0.249 0.447 0.238 0.153 0.191 52.8 325.8 52.8 325.8 0
7.203 9.263 6.990 8.048 7.151 9.771 6.951 0.225 0.210 0.249 0.447 0.238 0.153 0.191 52.8 325.8 52.8 325.8 0
°F in. H2O SCFM ACFM lb/hr lb/hr
440 1 0 0 0 0
440 1 0 0 0 0
440 1 0 0 0 0
440 1 0 0 0 0
440 1 0 0 0 0
Flue Gas, Downstream of ID Fans Temperature Pressure Flow Rate Flow Rate CO2 N2 SO2 O2 HCl Other Gases H2O Fly Ash Total (gas only)
Flue Gas, to Absorber Temperature Pressure Flow Rate Flow Rate CO2 N2 SO2 O2 HCl Other Gases H2O Fly Ash Total (gas only)
Flue Gas, from Absorbers (total) Temperature Pressure Flow Rate Flow Rate CO2 N2 SO2 O2 HCl Other Gases H2O Fly Ash Total (gas only) Heat Capacities O2 CO2 N2 H2O NO SO2 HCl O2 CO2 N2 H2O NO SO2 HCl Reheated Gas Temperature: FGD Outlet Temperature: Total Btu/hr
Hot Reheat Air Temperature Pressure Flow Rate Flow Rate N2 O2
254276149.xls.ms_office, LSFO Cost & Tech. Results
9
12/9/2014, 12:59 PM
CUECost - Air Pollution Control Systems Economics Spreadsheet H2O Total Heat Capacities of Hot Reheat Air O2 N2 H2O O2 N2 H2O Heated Temperature: FGD Outlet Temperature: Heat Capacities of Inlet Reheat Air O2 N2 H2O O2 N2 H2O Heated Temperature: Inlet Air Temperature: Required Heat
lb/hr lb/hr
0 0
0 0
0 0
0 0
0 0
Btu/lbmol°F Btu/lbmol°F Btu/lbmol°F Btu/lb°F Btu/lb°F Btu/lb°F °C K °C K
7.322 7.104 8.316 0.229 0.254 0.462 226.7 499.7 52.8 325.8
7.322 7.104 8.316 0.229 0.254 0.462 226.7 499.7 52.8 325.8
7.322 7.104 8.316 0.229 0.254 0.462 226.7 499.7 52.8 325.8
7.322 7.104 8.316 0.229 0.254 0.462 226.7 499.7 52.8 325.8
7.322 7.104 8.316 0.229 0.254 0.462 226.7 499.7 52.8 325.8
Btu/lbmol°F Btu/lbmol°F Btu/lbmol°F Btu/lb°F Btu/lb°F Btu/lb°F °C K °C K Btu/hr
7.295 7.077 8.254 0.228 0.253 0.458 226.7 499.7 12.8 285.8 0
7.295 7.077 8.254 0.228 0.253 0.458 226.7 499.7 12.8 285.8 0
7.295 7.077 8.254 0.228 0.253 0.458 226.7 499.7 12.8 285.8 0
7.295 7.077 8.254 0.228 0.253 0.458 226.7 499.7 12.8 285.8 0
7.295 7.077 8.254 0.228 0.253 0.458 226.7 499.7 12.8 285.8 0
°F in. H2O SCFM ACFM lb/hr lb/hr lb/hr lb/hr
60 0 276 281 946 285 16 1,248
60 0 276 281 946 285 16 1,248
60 0 276 281 946 285 16 1,248
60 0 276 281 946 285 16 1,248
60 0 173 176 592 179 10 781
°F wt. % lb/hr lb/hr lb/hr
55 100% 25 507 532
55 100% 25 507 532
55 100% 25 507 532
55 100% 25 507 532
55 100% 16 331 348
°F GPM wt. % lb/hr lb/hr lb/hr lb/hr
90 1.9 40% 25 507 797 1,329
90 1.9 40% 25 507 797 1,329
90 1.9 40% 25 507 797 1,329
90 1.9 40% 25 507 797 1,329
90 1.2 40% 16 331 521 869
°F GPM wt. % lb/hr lb/hr lb/hr lb/hr
68 4.4 20% 25 507 2,127 2,658
68 4.4 20% 25 507 2,127 2,658
68 4.4 20% 25 507 2,127 2,658
68 4.4 20% 25 507 2,127 2,658
68 2.9 20% 16 331 1,390 1,738
°F GPM wt. % lb/hr lb/hr lb/hr lb/hr lb/hr lb/hr lb/hr
126 8,479 15% 0 655,593 21,333 35,923 19,056 4,147,468 4,879,374
126 4,748 15% 0 367,132 11,947 20,117 10,671 2,322,582 2,732,449
126 8,479 15% 0 655,593 21,333 35,923 19,056 4,147,468 4,879,374
126 8,479 15% 0 655,593 21,333 35,923 19,056 4,147,468 4,879,374
126 8,462 15% 0 634,723 21,582 55,648 18,449 4,138,947 4,869,350
°F
126
126
126
126
126
Oxidation Air (total) Temperature Pressure Flow Rate Flow Rate N2 O2 H2O Total (gas only)
Limestone to Ball Mill Temperature Wt.% Solids Inerts CaCO3 Total
Limestone Slurry to Limestone Slurry Tank Temperature Flow Rate Wt.% Solids Inerts CaCO3 H2O Total
Limestone Slurry to Reaction Mix Tank (total) Temperature Flow Rate Wt.% Solids Inerts CaCO3 H2O Total
Slurry to Absorber Temperature Flow Rate Wt.% Solids CaSO3*1/2H2O CaSO4*2H2O Inerts CaCl2 CaCO3 H2O Total
Slurry from Rxn Tank to Thickener Temperature
254276149.xls.ms_office, LSFO Cost & Tech. Results
10
12/9/2014, 12:59 PM
CUECost - Air Pollution Control Systems Economics Spreadsheet Flow Rate Wt.% Solids CaSO3*1/2H2O CaSO4*2H2O Inerts CaCl2 CaCO3 H2O Total
GPM wt. % lb/hr lb/hr lb/hr lb/hr lb/hr lb/hr lb/hr
9.9 15% 0 768 25 42 22 4,858 5,715
9.9 15% 0 768 25 42 22 4,858 5,715
9.9 15% 0 768 25 42 22 4,858 5,715
9.9 15% 0 768 25 42 22 4,858 5,715
6.4 15% 0 480 16 42 14 3,132 3,685
Case1
Case 2
Case 3
Case 4
Case 5
2009
2009
2009
2009
2009
$ $ $ $
Sizing Criteria kpph Reag. TPH Reag. gpm DBA kpph SO2
$10,344,623 $2,690,576 $0 $2,769,943
$10,344,623 $2,690,576 $108,960 $2,769,943
$10,344,623 $2,690,576 $0 $2,769,943
$10,344,623 $2,690,576 $0 $2,769,943
$10,326,592 $2,687,591 $0 $2,764,290
$ $
kACFM slurry gpm
$4,034,765 $287,420
$4,034,765 $203,511
$4,034,765 $287,420
$4,034,765 $287,420
$4,033,979 $287,068
$
*
$2,132,534
$2,132,534
$2,132,534
$2,132,534
$2,132,196
$ $ $
ACFM kpph SO2 TPH solids
$397,788 $117,459 $171,232
$397,788 $117,459 $171,232
$397,788 $117,459 $171,232
$397,788 $117,459 $171,232
$397,694 $117,168 $169,247
$ $ $
MW ACFM
$1,766,858 $2,624,233 $27,337,430
$1,766,858 $2,624,233 $27,362,481
$1,766,858 $2,624,233 $27,337,430
$1,766,858 $2,624,233 $27,337,430
$1,766,858 $2,622,125 $27,304,808
$ $ $ $ $ $ $ $ $ $ $ $ $
$16,551,396 $4,304,922 $0 $4,431,909 $6,455,625 $459,872 $3,412,054 $636,460 $187,935 $273,971 $2,826,972 $4,198,773 $43,739,888
$16,551,396 $4,304,922 $174,336 $4,431,909 $6,455,625 $325,618 $3,412,054 $636,460 $187,935 $273,971 $2,826,972 $4,198,773 $43,779,970
$16,551,396 $4,304,922 $0 $4,431,909 $6,455,625 $459,872 $3,412,054 $636,460 $187,935 $273,971 $2,826,972 $4,198,773 $43,739,888
$16,551,396 $4,304,922 $0 $4,431,909 $6,455,625 $459,872 $3,412,054 $636,460 $187,935 $273,971 $2,826,972 $4,198,773 $43,739,888
$16,522,547 $4,300,146 $0 $4,422,865 $6,454,367 $459,309 $3,411,514 $636,310 $187,469 $270,794 $2,826,972 $4,195,400 $43,687,693
$ $ $ $ $ $ $ $ $ $ $ $ $
$1,655,140 $430,492 $0 $443,191 $645,562 $45,987 $341,205 $63,646 $18,793 $27,397 $282,697 $419,877 $4,373,989
$1,655,140 $430,492 $17,434 $443,191 $645,562 $32,562 $341,205 $63,646 $18,793 $27,397 $282,697 $419,877 $4,377,997
$1,655,140 $430,492 $0 $443,191 $645,562 $45,987 $341,205 $63,646 $18,793 $27,397 $282,697 $419,877 $4,373,989
$1,655,140 $430,492 $0 $443,191 $645,562 $45,987 $341,205 $63,646 $18,793 $27,397 $282,697 $419,877 $4,373,989
$1,652,255 $430,015 $0 $442,286 $645,437 $45,931 $341,151 $63,631 $18,747 $27,079 $282,697 $419,540 $4,368,769
$ $ $ $ $
$1,655,140 $430,492 $0 $443,191 $645,562
$1,655,140 $430,492 $17,434 $443,191 $645,562
$1,655,140 $430,492 $0 $443,191 $645,562
$1,655,140 $430,492 $0 $443,191 $645,562
$1,652,255 $430,015 $0 $442,286 $645,437
LSFO Equipment Capital Costs Cost Basis (Year)
Reagent Feed System Ball Mill & Hydroclone System DBA Acid Tank (pump, heater, agitator) SO2 Removal System Absorber Tower Spray Pumps Flue Gas Handling System ID Fans Waste / Byproduct Handling System Thickener System Support Equipment Chimney TOTAL * Based on flue gas flow and reheat temperature.
Capital Costs with Retrofit Factors Reagent Feed System Ball Mill & Hydroclone System DBA Acid Tank (pump, heater, agitator) SO2 Removal System Absorber Tower Spray Pumps Flue Gas Handling System ID Fans Waste / Byproduct Handling System Thickener System Support Equipment Chimney TOTAL
General Facilities Reagent Feed System Ball Mill & Hydroclone System DBA Acid Tank (pump, heater, agitator) SO2 Removal System Absorber Tower Spray Pumps Flue Gas Handling System ID Fans Waste / Byproduct Handling System Thickener System Support Equipment Chimney TOTAL
Engineering Fees Reagent Feed System Ball Mill & Hydroclone System DBA Acid Tank (pump, heater, agitator) SO2 Removal System Absorber Tower
254276149.xls.ms_office, LSFO Cost & Tech. Results
11
12/9/2014, 12:59 PM
CUECost - Air Pollution Control Systems Economics Spreadsheet Spray Pumps Flue Gas Handling System ID Fans Waste / Byproduct Handling System Thickener System Support Equipment Chimney TOTAL
$ $ $ $ $ $ $ $
$45,987 $341,205 $63,646 $18,793 $27,397 $282,697 $419,877 $4,373,989
$32,562 $341,205 $63,646 $18,793 $27,397 $282,697 $419,877 $4,377,997
$45,987 $341,205 $63,646 $18,793 $27,397 $282,697 $419,877 $4,373,989
$45,987 $341,205 $63,646 $18,793 $27,397 $282,697 $419,877 $4,373,989
$45,931 $341,151 $63,631 $18,747 $27,079 $282,697 $419,540 $4,368,769
Reagent Feed System Ball Mill & Hydroclone System DBA Acid Tank (pump, heater, agitator) SO2 Removal System Absorber Tower Spray Pumps Flue Gas Handling System ID Fans Waste / Byproduct Handling System Thickener System Support Equipment Chimney TOTAL
$ $ $ $ $ $ $ $ $ $ $ $ $
$3,310,279 $860,984 $0 $886,382 $1,291,125 $91,974 $682,411 $127,292 $37,587 $54,794 $565,394 $839,755 $8,747,978
$3,310,279 $860,984 $34,867 $886,382 $1,291,125 $65,124 $682,411 $127,292 $37,587 $54,794 $565,394 $839,755 $8,755,994
$3,310,279 $860,984 $0 $886,382 $1,291,125 $91,974 $682,411 $127,292 $37,587 $54,794 $565,394 $839,755 $8,747,978
$3,310,279 $860,984 $0 $886,382 $1,291,125 $91,974 $682,411 $127,292 $37,587 $54,794 $565,394 $839,755 $8,747,978
$3,304,509 $860,029 $0 $884,573 $1,290,873 $91,862 $682,303 $127,262 $37,494 $54,159 $565,394 $839,080 $8,737,539
Total Plant Cost (TPC) Total Plant Cost (TPC) w/ Prime Contractor's Markup
$ $
$61,235,843 $63,072,918
$61,291,958 $63,130,717
$61,235,843 $63,072,918
$61,235,843 $63,072,918
$61,162,771 $62,997,654
Total Cash Expended (TCE)
$
$63,072,918
$63,130,717
$63,072,918
$63,072,918
$62,997,654
Allow. for Funds During Constr. (AFDC)
$
$0
$0
$0
$0
$0
Total Plant Investment (TPI)
$
$63,072,918
$63,130,717
$63,072,918
$63,072,918
$62,997,654
$ $
$1,494,583 $5,742
$1,490,904 $5,742
$1,494,649 $5,742
$1,494,583 $5,742
$1,491,184 $3,753
$
$64,573,243
$64,627,363
$64,573,309
$64,573,243
$64,492,591
$/kW
$2,870
$2,872
$2,870
$2,870
$2,866
Case1
Case 2
Case 3
Case 4
Case 5
Contingency
Preproduction Costs Inventory Capital
Total Capital Requirement (TCR)
Maintenance Cost by Area TPC w/o Retrofit Factor Reagent Feed System Ball Mill & Hydroclone System DBA Acid Tank (pump, heater, agitator) SO2 Removal System Absorber Tower Spray Pumps Flue Gas Handling System ID Fans Waste / Byproduct Handling System Thickener System Support Equipment Chimney TOTAL
$ $ $ $ $ $ $ $ $ $ $ $ $
$14,896,256 $3,874,430 $0 $3,988,718 $5,810,062 $413,885 $3,070,848 $572,814 $169,141 $246,574 $2,544,275 $3,778,895 $39,365,899
$14,896,256 $3,874,430 $156,903 $3,988,718 $5,810,062 $293,056 $3,070,848 $572,814 $169,141 $246,574 $2,544,275 $3,778,895 $39,401,973
$14,896,256 $3,874,430 $0 $3,988,718 $5,810,062 $413,885 $3,070,848 $572,814 $169,141 $246,574 $2,544,275 $3,778,895 $39,365,899
$14,896,256 $3,874,430 $0 $3,988,718 $5,810,062 $413,885 $3,070,848 $572,814 $169,141 $246,574 $2,544,275 $3,778,895 $39,365,899
$14,870,292 $3,870,131 $0 $3,980,578 $5,808,930 $413,378 $3,070,363 $572,679 $168,722 $243,715 $2,544,275 $3,775,860 $39,318,924
First Year Maintenance Costs Reagent Feed System Ball Mill & Hydroclone System DBA Acid Tank (pump, heater, agitator) SO2 Removal System Absorber Tower Spray Pumps Flue Gas Handling System ID Fans Waste / Byproduct Handling System
$ $ $ $ $ $ $ $ $
$744,813 $193,721 $0 $199,436 $290,503 $20,694 $153,542 $28,641 $8,457
$744,813 $193,721 $7,845 $189,464 $275,978 $13,920 $153,542 $28,641 $8,457
$744,813 $193,721 $0 $199,436 $290,503 $20,694 $153,542 $28,641 $8,457
$744,813 $193,721 $0 $199,436 $290,503 $20,694 $153,542 $28,641 $8,457
$743,515 $193,507 $0 $199,029 $290,447 $20,669 $153,518 $28,634 $8,436
254276149.xls.ms_office, LSFO Cost & Tech. Results
12
12/9/2014, 12:59 PM
CUECost - Air Pollution Control Systems Economics Spreadsheet Thickener System Support Equipment Chimney TOTAL
$ $ $ $
LSFO O&M Data and Costs Cost Basis (Year)
Parameters Reagent Required DBA Required Percent SO2 Removal FGD Sludge to Disposal Steam to FGD System Total FGD Power Consumption FGD Byproduct
lbs/hr lbs/MMBtu lbs/hr % lbs/hr, dry lbs/hr kW lbs/hr
$12,329 $127,214 $188,945 $1,968,295
$12,329 $127,214 $188,945 $1,944,869
$12,329 $127,214 $188,945 $1,968,295
$12,329 $127,214 $188,945 $1,968,295
$12,186 $127,214 $188,793 $1,965,946
Case1
Case 2
Case 3
Case 4
Case 5
2009
2009
2009
2009
2009
532 2.250 0.0 95% 857 0 450 0
532 2.250 2.9 95% 857 0 370 0
532 2.250 0.0 95% 857 0 450 0
532 2.250 0.0 95% 857 0 450 0
348 1.471 0.0 95% 553 0 450 0
3
3
3
3
3
Fixed O&M Costs Number of Operators (40 hrs/week) Operating Labor Cost ** Maint. Labor & Matls. Cost Admin. & Support Labor TOTAL
$/yr $/yr $/yr $/yr
$250,341 $1,968,295 $311,298 $2,529,934
$250,341 $1,944,869 $308,487 $2,503,697
$250,341 $1,968,295 $311,298 $2,529,934
$250,341 $1,968,295 $311,298 $2,529,934
$250,341 $1,965,946 $311,016 $2,527,303
Variable Operating Costs ** Reagent Costs DBA Costs Disposal Costs Credit for Byproduct Steam Costs Power Costs TOTAL
$/yr $/yr $/yr $/yr $/yr $/yr $/yr
$33,182 $0 $21,402 $0 $0 $199,603 $254,188
$33,182 $5,112 $21,402 $0 $0 $164,293 $223,990
$33,182 $0 $21,402 $0 $0 $200,352 $254,937
$33,182 $0 $21,402 $0 $0 $199,603 $254,188
$21,691 $0 $13,800 $0 $0 $199,603 $235,094
Case1
Case 2
Case 3
Case 4
Case 5
lbmole/hr lbmole/hr lbmole/hr lbmole/hr lbmole/hr lb/hr lb/hr lb/hr lb/hr lb/hr
4.46 4.46 2.23 4.46 4.46 286 446 40 576 196
4.46 4.46 2.23 4.46 4.46 286 446 40 576 196
4.46 4.46 2.23 4.46 4.46 286 446 40 576 196
4.46 4.46 2.23 4.46 4.46 286 446 40 576 196
2.79 2.79 1.39 2.79 2.79 179 279 25 360 123
lbmole/hr lbmole/hr lbmole/hr lbmole/hr lb/hr lb/hr lb/hr lb/hr
4.46 2.23 6.69 4.46 576 71 121 768
4.46 2.23 6.69 4.46 576 71 121 768
4.46 2.23 6.69 4.46 576 71 121 768
4.46 2.23 6.69 4.46 576 71 121 768
2.79 1.39 4.18 2.79 360 45 75 480
% lbmole
0.1389 1,319.20
0.1389 1,319.20
0.1389 1,319.20
0.1389 1,319.20
0.1389 1,318.58
lbs/hr
286
286
286
286
179
** These costs assume inputs are in current dollars (no escalation included).
Intermediate Material Balance Calcs. Sulfite Reaction SO2 CaCO3 H2O CaSO3*1/2H2O CO2 SO2 CaCO3 H2O CaSO3*1/2H2O CO2
Sulfate Reaction CaSO3*1/2H2O O2 H2O CaSO4*2H2O CaSO3*1/2H2O O2 H2O CaSO4*2H2O
Water in Absorber Mole Fraction H2O in Absorber Moles H2O in Absorber
DBA Feed Calculations SO2 Removed
254276149.xls.ms_office, LSFO Cost & Tech. Results
13
12/9/2014, 12:59 PM
CUECost - Air Pollution Control Systems Economics Spreadsheet DBA Added DBA Added
254276149.xls.ms_office, LSFO Cost & Tech. Results
lbs/hr GPM
0.00 0.00
14
2.86 0.00
0.00 0.00
0.00 0.00
0.00 0.00
12/9/2014, 12:59 PM
CUECost - Air Pollution Control Systems Economics Spreadsheet
LSD Material Balance - Preliminary
Case1
Case 2
Case 3
Case 4
Case 5
°F in. H2O SCFM ACFM lb/hr lb/hr lb/hr lb/hr lb/hr lb/hr lb/hr lb/hr lb/hr
300 -12 58,015 88,958 50,489 184,042 301 14,693 28 66 17,793 1,808 267,412
300 -12 58,015 88,958 50,489 184,042 301 14,693 28 66 17,793 1,808 267,412
300 -12 58,015 88,958 50,489 184,042 301 14,693 28 66 17,793 1,808 267,412
300 -12 58,015 88,958 50,489 184,042 301 14,693 28 66 17,793 1,808 267,412
300 -12 57,995 88,927 50,535 183,960 188 14,687 28 66 17,805 1,855 267,269
°F in. H2O SCFM ACFM lb/hr lb/hr lb/hr lb/hr lb/hr lb/hr lb/hr lb/hr lb/hr
300 -12 58,015 88,958 50,489 184,042 301 14,693 28 66 17,793 1,808 267,412
300 -12 58,015 88,958 50,489 184,042 301 14,693 28 66 17,793 1,808 267,412
300 -12 58,015 88,958 50,489 184,042 301 14,693 28 66 17,793 1,808 267,412
300 -12 58,015 88,958 50,489 184,042 301 14,693 28 66 17,793 1,808 267,412
300 -12 57,995 88,927 50,535 183,960 188 14,687 28 66 17,805 1,855 267,269
°F in. H2O SCFM ACFM lb/hr lb/hr lb/hr lb/hr lb/hr lb/hr lb/hr lb/hr lb/hr
147 -17 63,810 79,166 50,489 184,042 229 14,689 0 66 34,317 3,356 283,831
147 -17 63,810 79,166 50,489 184,042 229 14,689 0 66 34,317 3,356 283,831
147 -17 63,810 79,166 50,489 184,042 229 14,689 0 66 34,317 3,356 283,831
147 -17 63,810 79,166 50,489 184,042 229 14,689 0 66 34,317 3,356 283,831
147 -13 63,627 78,124 50,535 183,960 151 14,685 0 66 33,854 3,006 283,250
°F in. H2O SCFM ACFM lb/hr lb/hr lb/hr lb/hr lb/hr lb/hr lb/hr lb/hr lb/hr
147 -20 63,784 79,758 50,489 184,042 211 14,688 0 66 34,248 0 283,744
147 -20 63,784 79,758 50,489 184,042 211 14,688 0 66 34,248 0 283,744
147 -20 63,784 79,758 50,489 184,042 211 14,688 0 66 34,248 0 283,744
147 -20 63,784 79,758 50,489 184,042 211 14,688 0 66 34,248 0 283,744
147 -16 63,605 78,706 50,535 183,960 141 14,684 0 66 33,793 0 283,179
°F in. H2O SCFM ACFM lb/hr lb/hr lb/hr lb/hr lb/hr lb/hr lb/hr
152 1 63,784 76,207 50,489 184,042 211 14,688 0 66 34,248
152 1 63,784 76,207 50,489 184,042 211 14,688 0 66 34,248
152 1 63,784 76,207 50,489 184,042 211 14,688 0 66 34,248
152 1 63,784 76,207 50,489 184,042 211 14,688 0 66 34,248
152 1 63,605 75,992 50,535 183,960 141 14,684 0 66 33,793
Flue Gas, Downstream of Air Heater Temperature Pressure Flow Rate Flow Rate CO2 N2 SO2 O2 HCl Other Gases H2O Fly Ash Total (gas only)
Flue Gas, to Spray Dryer Temperature Pressure Flow Rate Flow Rate CO2 N2 SO2 O2 HCl Other Gases H2O Fly Ash Total (gas only)
Flue Gas, from Spray Dryers (total) Temperature Pressure Flow Rate Flow Rate CO2 N2 SO2 O2 HCl Other Gases H2O Fly Ash Total (gas only)
Flue Gas Downstream of Particulate Control Device Temperature Pressure Flow Rate Flow Rate CO2 N2 SO2 O2 HCl Other Gases H2O Fly Ash Total (gas only)
Flue Gas Downstream of ID Fans Temperature Pressure Flow Rate Flow Rate CO2 N2 SO2 O2 HCl Other Gases H2O
254276149.xls.ms_office, LSD Cost & Tech. Results
15
12/9/2014, 12:59 PM
CUECost - Air Pollution Control Systems Economics Spreadsheet Fly Ash Total (gas only)
lb/hr lb/hr
0 283,744
0 283,744
0 283,744
0 283,744
0 283,179
°F wt. % lb/hr lb/hr lb/hr
60 100% 9 81 90
60 100% 9 81 90
60 100% 9 81 90
60 100% 9 81 90
60 100% 5 42 47
°F GPM wt. % lb/hr lb/hr
60 1 0% 296 296
60 1 0% 296 296
60 1 0% 296 296
60 1 0% 296 296
60 0 0% 154 154
°F GPM wt. % lb/hr lb/hr lb/hr lb/hr
110 1 30% 107 9 270 386
110 1 30% 107 9 270 386
110 1 30% 107 9 270 386
110 1 30% 107 9 270 386
110 0 30% 56 5 140 201
°F GPM wt. % lb/hr lb/hr lb/hr lb/hr lb/hr lb/hr lb/hr
110 5 49% 112 50 1,541 87 82 1,945 3,818
110 5 49% 112 50 1,541 87 82 1,945 3,818
110 5 49% 112 50 1,541 87 82 1,945 3,818
110 5 49% 112 50 1,541 87 82 1,945 3,818
110 4 50% 48 21 1,283 38 59 1,471 2,920
°F GPM wt. % lb/hr lb/hr lb/hr lb/hr lb/hr lb/hr lb/hr
104 33 10% 112 50 1,541 87 82 16,515 18,388
104 33 10% 112 50 1,541 87 82 16,515 18,388
104 33 10% 112 50 1,541 87 82 16,515 18,388
104 33 10% 112 50 1,541 87 82 16,515 18,388
104 32 8% 48 21 1,283 38 59 16,041 17,490
°F wt. % lb/hr lb/hr lb/hr lb/hr lb/hr lb/hr lb/hr
150 98% 22 10 301 -2 42 8 380
150 98% 22 10 301 -2 42 8 380
150 98% 22 10 301 -2 42 8 380
150 98% 22 10 301 -2 42 8 380
150 98% 10 5 280 -3 42 7 341
% °F wt. % lb/hr lb/hr lb/hr lb/hr lb/hr lb/hr lb/hr
99.99% 150 98% 90 40 1,230 -17 40 27 1,371
99.99% 150 98% 90 40 1,230 -17 40 27 1,371
99.99% 150 98% 90 40 1,230 -17 40 27 1,371
99.99% 150 98% 90 40 1,230 -17 40 27 1,371
99.99% 150 98% 37 17 999 -14 17 21 1,060
°F
150
150
150
150
150
Lime to Ball Mill Temperature Wt.% Solids Inerts CaO Total
Water to Ball Mill Temperature Flow Rate Wt.% Solids H2O Total
Lime Slurry to Head Tanks (Total) Temperature Flow Rate Wt.% Solids Ca(OH)2 Inerts H2O Total
Lime Slurry from Head Tank Temperature Flow Rate Wt.% Solids CaSO3*1/2H2O CaSO4*2H2O Flyash / Inerts Ca(OH)2 CaCl2 H2O Total
Lime Slurry to Atomizer Temperature Flow Rate Wt.% Solids CaSO3*1/2H2O CaSO4*2H2O Flyash / Inerts Ca(OH)2 CaCl2 H2O Total
Solids from Spray Dryers (Total) Temperature Wt.% Solids CaSO3*1/2H2O CaSO4*2H2O Flyash / Inerts Ca(OH)2 CaCl2 H2O Total
Baghouse/ESP Solids to Recycle Particulate Removal Efficiency Temperature Wt.% Solids CaSO3*1/2H2O CaSO4*2H2O Flyash / Inerts Ca(OH)2 CaCl2 H2O Total
Recycle Solids to Slurry Tank Temperature 254276149.xls.ms_office, LSD Cost & Tech. Results
16
12/9/2014, 12:59 PM
CUECost - Air Pollution Control Systems Economics Spreadsheet Wt.% Solids CaSO3*1/2H2O CaSO4*2H2O Flyash / Inerts Ca(OH)2 CaCl2 H2O Total
wt. % lb/hr lb/hr lb/hr lb/hr lb/hr lb/hr lb/hr
98% 112 50 1,532 -19 82 35 1,792
98% 112 50 1,532 -19 82 35 1,792
98% 112 50 1,532 -19 82 35 1,792
98% 112 50 1,532 -19 82 35 1,792
98% 48 21 1,279 -18 59 28 1,417
°F GPM wt. % lb/hr lb/hr
60 3 0% 1,640 1,640
60 3 0% 1,640 1,640
60 3 0% 1,640 1,640
60 3 0% 1,640 1,640
60 3 0% 1,302 1,302
°F GPM wt. % lb/hr lb/hr lb/hr lb/hr lb/hr lb/hr lb/hr
110 5 50% 112 50 1,532 -19 82 1,675 3,432
110 5 50% 112 50 1,532 -19 82 1,675 3,432
110 5 50% 112 50 1,532 -19 82 1,675 3,432
110 5 50% 112 50 1,532 -19 82 1,675 3,432
110 4 50% 48 21 1,279 -18 59 1,330 2,719
°F wt. % lb/hr lb/hr lb/hr lb/hr lb/hr lb/hr lb/hr
100 98% 136 61 1,817 -26 84 41 2,114
100 98% 136 61 1,817 -26 84 41 2,114
100 98% 136 61 1,817 -26 84 41 2,114
100 98% 136 61 1,817 -26 84 41 2,114
100 98% 71 32 1,859 -27 84 40 2,060
°F wt. % lb/hr lb/hr lb/hr lb/hr lb/hr lb/hr lb/hr
100 80% 136 61 1,817 -26 84 518 2,590
100 80% 136 61 1,817 -26 84 518 2,590
100 80% 136 61 1,817 -26 84 518 2,590
100 80% 136 61 1,817 -26 84 518 2,590
100 80% 71 32 1,859 -27 84 505 2,524
Case1
Case 2
Case 3
Case 4
Case 5
2009
2009
2009
2009
2009
$ $ $
Sizing Criteria * Wt. % S kACFM
$5,553,775 $1,834,342 $3,120,143
$5,553,775 $1,834,342 $3,120,143
$5,553,775 $1,834,342 $3,120,143
$5,553,775 $1,834,342 $3,120,143
$5,526,459 $1,907,952 $3,119,624
$ $ $
kACFM ACFM kpph SO2
$834,503 $297,927 $1,565,513
$834,503 $297,927 $1,565,513
$834,503 $297,927 $1,565,513
$834,503 $297,927 $1,565,513
$829,836 $295,232 $1,513,201
$ $ $
MW ACFM
$2,045,839 $2,733,206 $17,985,249
$2,045,839 $2,733,206 $17,985,249
$2,045,839 $2,733,206 $17,985,249
$2,045,839 $2,733,206 $17,985,249
$2,045,839 $2,730,198 $17,968,343
$8,886,041 $2,934,947 $4,992,229 $1,335,206 $476,683
$8,886,041 $2,934,947 $4,992,229 $1,335,206 $476,683
$8,886,041 $2,934,947 $4,992,229 $1,335,206 $476,683
$8,886,041 $2,934,947 $4,992,229 $1,335,206 $476,683
$8,842,335 $3,052,724 $4,991,399 $1,327,738 $472,371
Blowdown Water to Recycle Solids Tank Temperature Flow Rate Wt.% Solids H2O Total
Recycle Slurry to Head Tanks (Total) Temperature Flow Rate Wt.% Solids CaSO3*1/2H2O CaSO4*2H2O Flyash / Inerts Ca(OH)2 CaCl2 H2O Total
Dry Solids Temperature Wt.% Solids CaSO3*1/2H2O CaSO4*2H2O Flyash / Inerts Ca(OH)2 CaCl2 H2O Total
Solids to Landfill Temperature Wt.% Solids CaSO3*1/2H2O CaSO4*2H2O Flyash / Inerts Ca(OH)2 CaCl2 H2O Total
LSD Equipment Capital Costs Cost Basis (Year)
Reagent Feed System SO2 Removal System Spray Dryers Flue Gas Handling System ID Fans Waste / Byproduct Handling System Support Equipment Chimney TOTAL * Based on lbs/hr of lime feed and GPM of lime slurry.
Capital Costs with Retrofit Factors Reagent Feed System SO2 Removal System Spray Dryers Flue Gas Handling System ID Fans 254276149.xls.ms_office, LSD Cost & Tech. Results
$ $ $ $ $
17
12/9/2014, 12:59 PM
CUECost - Air Pollution Control Systems Economics Spreadsheet Waste / Byproduct Handling System Support Equipment Chimney TOTAL
$ $ $ $
$2,504,820 $3,273,343 $4,373,130 $28,776,398
$2,504,820 $3,273,343 $4,373,130 $28,776,398
$2,504,820 $3,273,343 $4,373,130 $28,776,398
$2,504,820 $3,273,343 $4,373,130 $28,776,398
$2,421,121 $3,273,343 $4,368,317 $28,749,348
$ $ $ $ $ $ $ $ $
$888,604 $293,495 $499,223 $133,521 $47,668 $250,482 $327,334 $437,313 $2,877,640
$888,604 $293,495 $499,223 $133,521 $47,668 $250,482 $327,334 $437,313 $2,877,640
$888,604 $293,495 $499,223 $133,521 $47,668 $250,482 $327,334 $437,313 $2,877,640
$888,604 $293,495 $499,223 $133,521 $47,668 $250,482 $327,334 $437,313 $2,877,640
$884,233 $0 $0 $0 $0 $242,112 $327,334 $436,832 $1,890,512
$ $ $ $ $ $ $ $ $
$888,604 $293,495 $499,223 $133,521 $47,668 $250,482 $327,334 $437,313 $2,877,640
$888,604 $293,495 $499,223 $133,521 $47,668 $250,482 $327,334 $437,313 $2,877,640
$888,604 $293,495 $499,223 $133,521 $47,668 $250,482 $327,334 $437,313 $2,877,640
$888,604 $293,495 $499,223 $133,521 $47,668 $250,482 $327,334 $437,313 $2,877,640
$884,233 $305,272 $499,140 $132,774 $47,237 $242,112 $327,334 $436,832 $2,874,935
$ $ $ $ $ $ $ $ $
$1,777,208 $586,989 $998,446 $267,041 $95,337 $500,964 $654,669 $874,626 $5,755,280
$1,777,208 $586,989 $998,446 $267,041 $95,337 $500,964 $654,669 $874,626 $5,755,280
$1,777,208 $586,989 $998,446 $267,041 $95,337 $500,964 $654,669 $874,626 $5,755,280
$1,777,208 $586,989 $998,446 $267,041 $95,337 $500,964 $654,669 $874,626 $5,755,280
$1,768,467 $610,545 $998,280 $0 $0 $0 $654,669 $873,663 $4,905,624
Total Plant Cost (TPC) $ Total Plant Cost (TPC) w/ Prime Contractor's Markup$
$40,286,957 $41,495,566
$40,286,957 $41,495,566
$40,286,957 $41,495,566
$40,286,957 $41,495,566
$38,420,418 $39,573,031
Total Cash Expended (TCE)
$
$41,495,566
$41,495,566
$41,495,566
$41,495,566
$39,573,031
Allow. for Funds During Constr. (AFDC)
$
$0
$0
$0
$0
$0
Total Plant Investment (TPI)
$
$41,495,566
$41,495,566
$41,495,566
$41,495,566
$39,573,031
$ $
$976,715 $0
$976,715 $0
$976,738 $0
$976,715 $0
$917,598 $0
$
$42,472,280
$42,472,280
$42,472,303
$42,472,280
$40,490,629
$/kW
$1,888
$1,888
$1,888
$1,888
$1,800
Case1
Case 2
Case 3
Case 4
Case 5
$7,997,437 $2,641,452 $4,493,006 $1,201,685 $429,015 $2,254,338 $2,946,008 $3,935,817 $25,898,758
$7,997,437 $2,641,452 $4,493,006 $1,201,685 $429,015 $2,254,338 $2,946,008 $3,935,817 $25,898,758
$7,997,437 $2,641,452 $4,493,006 $1,201,685 $429,015 $2,254,338 $2,946,008 $3,935,817 $25,898,758
$7,997,437 $2,641,452 $4,493,006 $1,201,685 $429,015 $2,254,338 $2,946,008 $3,935,817 $25,898,758
$7,958,101 $2,518,497 $4,117,904 $912,820 $324,755 $1,815,841 $2,946,008 $3,931,486 $24,525,413
General Facilities Reagent Feed System SO2 Removal System Spray Dryers Flue Gas Handling System ID Fans Waste / Byproduct Handling System Support Equipment Chimney TOTAL
Engineering Fees Reagent Feed System SO2 Removal System Spray Dryers Flue Gas Handling System ID Fans Waste / Byproduct Handling System Support Equipment Chimney TOTAL
Contingency Reagent Feed System SO2 Removal System Spray Dryers Flue Gas Handling System ID Fans Waste / Byproduct Handling System Support Equipment Chimney TOTAL
Preproduction Costs Inventory Capital
Total Capital Requirement (TCR)
Maintenance Cost by Area TPC w/o Retrofit Factor Reagent Feed System SO2 Removal System Spray Dryers Flue Gas Handling System ID Fans Waste / Byproduct Handling System Support Equipment Chimney TOTAL
254276149.xls.ms_office, LSD Cost & Tech. Results
$ $ $ $ $ $ $ $ $
18
12/9/2014, 12:59 PM
CUECost - Air Pollution Control Systems Economics Spreadsheet First Year Maintenance Costs Reagent Feed System SO2 Removal System Spray Dryers Flue Gas Handling System ID Fans Waste / Byproduct Handling System Support Equipment Chimney TOTAL
$ $ $ $ $ $ $ $ $
LSD O&M Data and Costs Cost Basis (Year)
Parameters Reagent Required Percent SO2 Removal FGD Solids - dry - wetted Fresh Water to FGD Blowdown Water to FGD Total FGD Power Consumption
lbs/hr lbs/MMBtu % lbs/hr lbs/hr gpm gpm kW
Fixed O&M Costs Number of Operators (40 hrs/week) Operating Labor Cost ** Maint. Labor & Matls. Cost Admin. & Support Labor TOTAL Variable Operating Costs ** Reagent Costs Disposal Costs Credit for Byproduct Steam Costs Fresh Water Costs Power Costs TOTAL
$/yr $/yr $/yr $/yr
$/yr $/yr $/yr $/yr $/yr $/yr $/yr ** These costs assume inputs are in current dollars (no escalation included).
254276149.xls.ms_office, LSD Cost & Tech. Results
$399,872 $132,073 $224,650 $60,084 $21,451 $112,717 $147,300 $196,791 $1,294,938
$399,872 $132,073 $224,650 $60,084 $21,451 $112,717 $147,300 $196,791 $1,294,938
$399,872 $132,073 $224,650 $60,084 $21,451 $112,717 $147,300 $196,791 $1,294,938
$399,872 $132,073 $224,650 $60,084 $21,451 $112,717 $147,300 $196,791 $1,294,938
$397,905 $125,925 $205,895 $0 $0 $0 $147,300 $196,574 $1,073,600
Case1
Case 2
Case 3
Case 4
Case 5
2009
2009
2009
2009
2009
90 0.380 30% 2,072 2,590 1 33 158
90 0.380 30% 2,072 2,590 1 33 158
90 0.380 30% 2,072 2,590 1 33 158
90 0.380 30% 2,072 2,590 1 33 158
47 0.198 25% 2,019 2,524 0 33 158
3
3
3
3
3
$182,758 $1,294,938 $210,220.07 $1,687,916
$182,758 $1,294,938 $210,220 $1,687,916
$182,758 $1,294,938 $210,220 $1,687,916
$182,758 $1,294,938 $210,220 $1,687,916
$182,758 $1,073,600 $183,660 $1,440,018
$0 $0 $0 $0 $177 $69,861 $70,038
$0 $0 $0 $0 $177 $69,861 $70,038
$0 $0 $0 $0 $177 $70,123 $70,301
$0 $0 $0 $0 $177 $69,861 $70,038
$0 $0 $0 $0 $92 $69,861 $69,953
19
12/9/2014, 12:59 PM
CUECost - Air Pollution Control Systems Economics Spreadsheet
Fabric Filter - Preliminary
Case1
Case 2
Case 3
Case 4
Case 5
°F in. H2O SCFM ACFM lb/hr lb/hr lb/hr lb/hr lb/hr lb/hr lb/hr lb/hr lb/hr
300 -12 58,015 88,958 50,489 184,042 301 14,693 28 66 17,793 1,808 267,412
300 -12 58,015 88,958 50,489 184,042 301 14,693 28 66 17,793 1,808 267,412
147 -17 63,810 79,166 50,489 184,042 229 14,689 0 66 34,317 3,356 283,831
147 -17 63,810 79,166 50,489 184,042 229 14,689 0 66 34,317 3,356 283,831
147 -13 63,627 78,124 50,535 183,960 151 14,685 0 66 33,854 3,006 283,250
Total Fabric Required
Ft2
25,416
25,416
22,619
22,619
22,321
Surface Area per Bag
Ft2
31.4
31.4
31.4
31.4
31.4
Required No. of Bags (no spare compartments)
809
809
720
720
710
Final No. of Bags
890
890
792
792
782
1
1
1
1
1
874 42 21
874 42 21
778 39 20
778 39 20
767 39 20
Case1
Case 2
Case 3
Case 4
Case 5
2009
2009
2009
2009
2009
$ $ $ $ $ $ $ $ $ $ $
$1,098,464 $67,784 $346,222 $176,894 $1,689,364 $33,787 $109,809 $84,468 $1,917,429 $1,284,677 $3,202,106
$1,098,464 $67,784 $346,222 $176,894 $1,689,364 $33,787 $109,809 $84,468 $1,917,429 $1,284,677 $3,202,106
$1,011,319 $60,323 $372,812 $164,575 $1,609,030 $32,181 $104,587 $80,451 $1,826,249 $1,223,587 $3,049,835
$1,011,319 $60,323 $372,812 $164,575 $1,609,030 $32,181 $104,587 $80,451 $1,826,249 $1,223,587 $3,049,835
$1,001,864 $59,529 $366,805 $163,230 $1,591,428 $31,829 $103,443 $79,571 $1,806,271 $1,210,202 $3,016,473
Total Direct Cost with Retrofit Factor $ General Facilities $ Engineering Fees $ Contingency $ Total Plant Cost (TPC) $ Total Plant Cost (TPC) w/ Prime Contractor's Markup $ Total Cash Expended (TCE) $
$5,123,369 $512,337 $512,337 $1,024,674 $7,172,717 $7,387,898 $7,280,307
$5,123,369 $512,337 $512,337 $1,024,674 $7,172,717 $7,387,898 $7,280,307
$4,879,736 $487,974 $487,974 $975,947 $6,831,631 $7,036,579 $6,934,105
$4,879,736 $487,974 $487,974 $975,947 $6,831,631 $7,036,579 $6,934,105
$4,826,356 $482,636 $482,636 $965,271 $6,756,899 $6,959,606 $6,858,252
Flue Gas, Upstream of Fabric Filter Temperature Pressure Flow Rate Flow Rate CO2 N2 SO2 O2 HCl Other Gases H2O Fly Ash Total (gas only)
No. of Casings Ft2 Ft Ft
Fabric Filter Dimensions (per Casing) Length Width
Capital Cost Cost Basis (Year) Fabric Filter Bags Ash Handling System ID Fan(s) Equipment Cost Subtotal Instruments & Controls Taxes Freight Purchased Equipment Cost Subtotal Installation Total Direct Cost
Allow. for Funds During Constr. (AFDC)
$
$387,327
$387,327
$368,908
$368,908
$364,873
Total Plant Investment (TPI) Preproduction Costs Inventory Capital
$ $ $
$7,667,634 $153,353 $0
$7,667,634 $153,353 $0
$7,303,013 $146,060 $0
$7,303,013 $146,060 $0
$7,223,125 $144,462 $0
$ $/kW
$7,820,987 $347.6
$7,820,987 $347.6
$7,449,073 $331.1
$7,449,073 $331.1
$7,367,587 $327.4
Case1
Case 2
Case 3
Case 4
Case 5
2009
2009
2009
2009
2009
42 90 132
42 90 132
38 80 118
38 80 118
37 79 116
Total Capital Requirement (TCR)
O&M Data and Costs Cost Basis (Year) Power Required Excluding ID Fan(s) ID Fan Power for FF Delta P Total Power
254276149.xls.ms_office, FF ESP Cost & Tech. Results
kW kW kW
20
12/9/2014, 12:59 PM
CUECost - Air Pollution Control Systems Economics Spreadsheet Power Cost ** Maintenance Costs Periodic Replacement Items
$/yr $/yr $/yr
$58,563 $224,147 $67,784
$81,065 $224,147 $67,784
$72,526 $213,488 $60,323
$72,255 $213,488 $60,323
$71,317 $211,153 $59,529
5 Years
5 Years
5 Years
5 Years
5 Years
Case1
Case 2
Case 3
Case 4
Case 5
°F in. H2O SCFM ACFM lb/hr lb/hr lb/hr lb/hr lb/hr lb/hr lb/hr lb/hr lb/hr
300 -12 58,015 88,958 50,489 184,042 301 14,693 28 66 17,793 1,808 267,412
300 -12 58,015 88,958 50,489 184,042 301 14,693 28 66 17,793 1,808 267,412
147 -17 63,810 79,166 50,489 184,042 229 14,689 0 66 34,317 3,356 283,831
147 -17 63,810 79,166 50,489 184,042 229 14,689 0 66 34,317 3,356 283,831
147 -13 63,627 78,124 50,535 183,960 151 14,685 0 66 33,854 3,006 283,250
lb/hr gr/ft3
1,808 2.37
1,808 2.37
3,356 4.95
3,356 4.95
3,006 4.49
100.0%
100.0%
100.0%
100.0%
100.0%
First Year Cost. Bags Replaced Every
** These costs assume inputs are in current dollars (no escalation included).
ESP Flue Gas, Upstream of ESP Temperature Pressure Flow Rate Flow Rate CO2 N2 SO2 O2 HCl Other Gases H2O Fly Ash Total (gas only) Inlet Particulate Loading
Overall PM Collection Efficiency
%
h
ESP Requirements k E
dimensionless kV/cm
0.451 10.0
0.451 10.0
0.451 10.0
0.451 10.0
0.451 10.0
Na2O Fe MgO CaO
wt% in Ash wt% in Ash wt% in Ash wt% in Ash
2.80 9 20.90 0.00
2.80 9 20.90 0.00
2.80 9.00 20.90 0.00
2.80 9.00 20.90 0.00
2.80 9.00 20.90 0.00
Flue Gas Composition H2O SO2 SO3
Vol% ppm ppm
10.77 512 3.8
10.77 512 3.8
19.57 367 2.7
19.57 367 2.7
19.34 242 1.8
Flue Gas Temperature TF TC TK
°F °C Kelvin
300 149 422
300 149 422
147 64 337
147 64 337
147 64 337
Log10(ohm-cm) Log10(ohm-cm) Log10(ohm-cm) Log10(ohm-cm) Log10(ohm-cm) ohm-cm
8.31 8.07 1.14 11.41 11.54 2.5602E+11
8.31 8.07 1.14 11.41 11.54 2.5602E+11
8.31 8.07 1.14 14.00 11.54 9.9638E+13
8.31 8.07 1.14 14.00 11.54 9.9638E+13
8.31 8.07 1.14 14.00 11.54 9.9638E+13
rs1 rs2 rs3 rs4 rs4(with E=12) rs0 rs Surface Resistivity
Log10(ohm-cm) Log10(ohm-cm) Log10(ohm-cm) Log10(ohm-cm) Log10(ohm-cm) Log10(ohm-cm) Log10(ohm-cm) ohm-cm
9.78 9.55 8.94 8.70 8.64 10.01 9.20 1.5767E+09
9.78 9.55 8.94 8.70 8.64 10.01 9.20 1.5767E+09
9.78 8.42 7.81 7.57 7.51 10.00 4.17 1.4717E+04
9.78 8.42 7.81 7.57 7.51 10.00 4.17 1.4717E+04
9.78 8.45 7.84 7.60 7.54 10.00 4.24 1.7216E+04
rvs1 rs2(with H2O=10) rs3(with H2O=10) rs4(with H2O = 10) rs4(with H2O = 10, E = 12) rs0(with H2O = 10)
ohm-cm Log10(ohm-cm) Log10(ohm-cm) Log10(ohm-cm) Log10(ohm-cm) Log10(ohm-cm)
1.5670E+09 9.65E+00 9.04 8.80 8.74 10.01
1.5670E+09 9.65E+00 9.04 8.80 8.74 10.01
1.4717E+04 9.65E+00 9.04 8.80 8.74 10.01
1.4717E+04 9.65E+00 9.04 8.80 8.74 10.01
1.7216E+04 9.65E+00 9.04 8.80 8.74 10.01
Ash Composition
Resistivity Calculations Volume Resistivity rv1 rv2 iv rv rv(TK=1000/2.4) Volume Resistivity Surface Resistivity
254276149.xls.ms_office, FF ESP Cost & Tech. Results
21
12/9/2014, 12:59 PM
CUECost - Air Pollution Control Systems Economics Spreadsheet rs(with H2O = 10, TK = 1000/2.4) rvs1(with H2O=10, TK = 1000/2.4) rvs2
Log10(ohm-cm) ohm-cm Log10(ohm-cm)
9.20 1.5830E+09 9.44
9.20 1.5830E+09 9.44
9.20 1.5830E+09 9.44
9.20 1.5830E+09 9.44
9.20 1.5830E+09 9.44
Log10(ohm-cm) Log10(ohm-cm)
0.29 7.53 -2.05 8.76 7.58
0.29 7.53 -2.05 8.76 7.58
0.29 7.53 -2.05 8.76 7.88
0.29 7.53 -2.05 8.76 7.88
0.29 7.53 -2.05 8.76 8.25
Log10(ohm-cm) Log10(ohm-cm) Log10(ohm-cm) ohm-cm
2 1 -28.39 75.72 8.45 8.37 2.3400E+08
2 1 -28.39 75.72 8.45 8.37 2.3400E+08
1 1 -4.74 19.25 5.19 5.89 7.8246E+05
1 1 -4.74 19.25 5.19 5.89 7.8246E+05
1 1 -4.74 19.62 5.56 6.17 1.4960E+06
ohm-cm
2.0359E+08
2.0359E+08
1.4445E+04
1.4445E+04
1.7020E+04
1000ft/minute
0.060
0.060
0.091
0.091
0.091
ft2/1000acfm
2155
2155
1633
1633
1601
Acid Resistivity ia1 ra1 sa ia2 ra2
Log10(ohm-cm) Log10(ohm-cm)
acid_v atom_v sa1 ia3 ra3 ra Acid Resistivity
index value index value
Total Resistivity rvsa Migration Velocity wk Specific Collection Area SCA Total Collector Plate Area
ft2
191,669
191,669
129,297
129,297
125,105
ESP Footprint Area
ft2
5,324
5,324
3,592
3,592
3,475
Case1
Case 2
Case 3
Case 4
Case 5
2009
2009
2009
2009
2009
$ $ $ $ $ $ $ $ $ $
$763,689 $346,222 $176,894 $1,286,805 $25,736 $83,642 $64,340 $1,460,524 $1,183,024 $2,643,548
$763,689 $346,222 $176,894 $1,286,805 $25,736 $83,642 $64,340 $1,460,524 $1,183,024 $2,643,548
$687,816 $372,812 $164,575 $1,225,203 $24,504 $79,638 $61,260 $1,390,606 $1,126,391 $2,516,996
$687,816 $372,812 $164,575 $1,225,203 $24,504 $79,638 $61,260 $1,390,606 $1,126,391 $2,516,996
$679,686 $366,805 $163,230 $1,209,721 $24,194 $78,632 $60,486 $1,373,033 $1,112,157 $2,485,190
Total Direct Cost with Retrofit Factor $ General Facilities $ Engineering Fees $ Contingency $ Total Plant Cost (TPC) $ Total Plant Cost (TPC) w/ Prime Contractor's Markup $ Total Cash Expended (TCE) $
$4,229,677 $422,968 $422,968 $845,935 $5,921,548 $6,099,194 $6,010,371
$4,229,677 $422,968 $422,968 $845,935 $5,921,548 $6,099,194 $6,010,371
$4,027,194 $402,719 $402,719 $805,439 $5,638,072 $5,807,214 $5,722,643
$4,027,194 $402,719 $402,719 $805,439 $5,638,072 $5,807,214 $5,722,643
$3,976,303 $397,630 $397,630 $795,261 $5,566,825 $5,733,829 $5,650,327
Capital Cost Cost Basis (Year) ESP Ash Handling System ID Fan(s) Equipment Cost Subtotal Instruments & Controls Taxes Freight Purchased Equipment Cost Subtotal Installation Total Direct Cost
Allow. for Funds During Constr. (AFDC)
$
$319,764
$319,764
$304,456
$304,456
$300,609
Total Plant Investment (TPI) Preproduction Costs Inventory Capital
$ $ $
$6,330,135 $126,603 $0
$6,330,135 $126,603 $0
$6,027,099 $120,542 $0
$6,027,099 $120,542 $0
$5,950,936 $119,019 $0
$ $/kW
$6,456,737 $287.0
$6,456,737 $287.0
$6,147,641 $273.2
$6,147,641 $273.2
$6,069,954 $269.8
Case1
Case 2
Case 3
Case 4
Case 5
2009
2009
2009
2009
2009
-103 45 -58
-103 45 -58
-21 40 19
-21 40 19
-17 39 22
($25,649) $185,048
($35,505) $185,048
$11,709 $176,190
$11,665 $176,190
$13,515 $173,963
Total Capital Requirement (TCR)
O&M Data and Costs Cost Basis (Year) Power Required Excluding ID Fan(s) ID Fan Power for FF Delta P Total Power
kW kW kW
Power Cost ** $/yr Maintenance Costs $/yr ** These costs assume inputs are in current dollars (no escalation included).
254276149.xls.ms_office, FF ESP Cost & Tech. Results
22
12/9/2014, 12:59 PM
CUECost - Air Pollution Control Systems Economics Spreadsheet
FUEL AND COMBUSTION CALCULATIONS
Case1
Case 2
Case 3
Case 4
Case 5
FUEL ANALYSIS FOR SPECIFIED COALS PROXIMATE ANALYSIS (wt. %) Moisture Volatile Matter Fixed Carbon Ash TOTAL
wt% wt% wt% wt%
25.2 36.4 30.3 8.15 100.05
25.2 36.4 30.3 8.15 100.05
25.2 36.4 30.3 8.15 100.05
25.2 36.4 30.3 8.15 100.05
25.2 36.4 30.3 8.36 100.26
COAL ULTIMATE ANALYSIS (wt. %) Moisture Carbon Hydrogen Nitrogen Chlorine Sulfur Ash Oxygen TOTAL
wt% wt% wt% wt% wt% wt% wt% wt%
25.2 51.52 3.29 0.69 0.1 0.56 8.15 10.49 100
25.2 51.52 3.29 0.69 0.1 0.56 8.15 10.49 100
25.2 51.52 3.29 0.69 0.1 0.56 8.15 10.49 100
25.2 51.52 3.29 0.69 0.1 0.56 8.15 10.49 100
25.2 51.52 3.29 0.69 0.1 0.35 8.36 10.49 100
Btu/lb $/MMBtu
8789 1.50
8789 1.50
8789 1.50
8789 1.50
8781 1.50
wt% wt% wt% wt% wt% wt% wt% wt% wt% wt% wt% wt%
27.00 19.00 1.08 9.00 18.50 2.40 2.80 0.45 0.42 18.85 0.50 100.00
27.00 19.00 1.08 9.00 18.50 2.40 2.80 0.45 0.42 18.85 0.50 100.00
27.00 19.00 1.08 9.00 18.50 2.40 2.80 0.45 0.42 18.85 0.50 100.00
27.00 19.00 1.08 9.00 18.50 2.40 2.80 0.45 0.42 18.85 0.50 100.00
27.00 19.00 1.08 9.00 18.50 2.40 2.80 0.45 0.42 18.85 0.50 100.00
PROXIMATE ANALYSIS (lbs/MMBtu) Moisture Volatile Matter Fixed Carbon Ash TOTAL
lbs/MMBtu lbs/MMBtu lbs/MMBtu lbs/MMBtu lbs/MMBtu
28.67 41.42 34.47 9.27 113.84
28.67 41.42 34.47 9.27 113.84
28.67 41.42 34.47 9.27 113.84
28.67 41.42 34.47 9.27 113.84
28.70 41.45 34.51 9.52 114.18
COAL ULTIMATE ANALYSIS (lbs/MMBtu) Moisture Carbon Hydrogen Nitrogen Chlorine Sulfur Ash Oxygen TOTAL
lbs/MMBtu lbs/MMBtu lbs/MMBtu lbs/MMBtu lbs/MMBtu lbs/MMBtu lbs/MMBtu lbs/MMBtu lbs/MMBtu
28.67 58.62 3.74 0.79 0.11 0.64 9.27 11.94 113.78
28.67 58.62 3.74 0.79 0.11 0.64 9.27 11.94 113.78
28.67 58.62 3.74 0.79 0.11 0.64 9.27 11.94 113.78
28.67 58.62 3.74 0.79 0.11 0.64 9.27 11.94 113.78
28.70 58.67 3.75 0.79 0.11 0.40 9.52 11.95 113.88
lbmoles/MMBtu lbmoles/MMBtu lbmoles/MMBtu lbmoles/MMBtu lbmoles/MMBtu lbmoles/MMBtu lbmoles/MMBtu lbmoles/MMBtu
1.5915 4.8804 1.8569 0.0280 0.0016 0.0199 9.2730 0.3730
1.5915 4.8804 1.8569 0.0280 0.0016 0.0199 9.2730 0.3730
1.5915 4.8804 1.8569 0.0280 0.0016 0.0199 9.2730 0.3730
1.5915 4.8804 1.8569 0.0280 0.0016 0.0199 9.2730 0.3730
1.5930 4.8848 1.8586 0.0280 0.0016 0.0124 9.5206 0.3733
Flue Gas (lb-moles/MMBtu) CO2 NOx HCl SO2 Total O2 Req'd - * N2 O2 H20 Total Dry Total Wet
lbmoles/MMBtu lbmoles/MMBtu lbmoles/MMBtu lbmoles/MMBtu lbmoles/MMBtu lbmoles/MMBtu lbmoles/MMBtu lbmoles/MMBtu lbmoles/MMBtu lbmoles/MMBtu
4.856 0.009 0.003 0.020 6.529 24.584 1.088 4.096 30.560 34.656
4.856 0.009 0.003 0.020 6.529 24.584 1.088 4.096 30.560 34.656
4.856 0.009 0.003 0.020 6.529 24.584 1.088 4.096 30.560 34.656
4.856 0.009 0.003 0.020 6.529 24.584 1.088 4.096 30.560 34.656
4.860 0.009 0.003 0.012 6.526 24.572 1.088 4.099 30.545 34.644
Wet Flue Gas PPMV & % Vol % O2 % CO2 % N2 NOx HCL SO2 % H2O
% Vol % Vol % Vol ppmv ppmv ppmv % Vol
3.140 14.012 70.936 268.765 92.604 573.395 11.818
3.140 14.012 70.936 268.765 92.604 573.395 11.818
3.140 14.012 70.936 268.765 92.604 573.395 11.818
3.140 14.012 70.936 268.765 92.604 573.395 11.818
3.139 14.030 70.928 268.903 92.721 358.822 11.831
HIGHER HEATING VALUE (HHV) Modified Mott Spooner - calc COAL COST COAL ASH ANALYSIS (ASTM, as rec'd) SiO2 Al2O3 TiO2 Fe2O3 CaO MgO Na2O K2O P2O5 SO3 Other Unaccounted for TOTAL
COAL ULTIMATE ANALYSIS (lbmoles/MMBtu) Moisture Carbon Hydrogen Nitrogen Chlorine Sulfur Ash Oxygen
Flue Gas, Downstream Of Economizer
254276149.xls.ms_office, Constants_CC
23
12/9/2014, 12:59 PM
CUECost - Air Pollution Control Systems Economics Spreadsheet Dry Flue Gas PPMV & % Vol % O2 % CO2 % N2 NOx HCL SO2 % H2O
% Vol % Vol % Vol ppmv ppmv ppmv % Vol
3.561 15.890 80.444 304.786 105.015 650.243 0
3.561 15.890 80.444 304.786 105.015 650.243 0
3.561 15.890 80.444 304.786 105.015 650.243 0
3.561 15.890 80.444 304.786 105.015 650.243 0
3.561 15.912 80.446 304.985 105.162 406.969 0
lbs/MMBtu lbs/MMBtu lbs/MMBtu lbs/MMBtu lbs/MMBtu lbs/MMBtu lbs/MMBtu lbs/MMBtu lbs/MMBtu wt% lbs/MMBtu lbs/MMBtu lbs/lb-mole
34.818 213.711 688.834 0.280 0.117 1.273 73.786 939.033 1012.819 7.285 757.293 908.752 29.225
34.818 213.711 688.834 0.280 0.117 1.273 73.786 939.033 1012.819 7.285 757.293 908.752 29.225
34.818 213.711 688.834 0.280 0.117 1.273 73.786 939.033 1012.819 7.285 757.293 908.752 29.225
34.818 213.711 688.834 0.280 0.117 1.273 73.786 939.033 1012.819 7.285 757.293 908.752 29.225
34.802 213.905 688.517 0.280 0.117 0.796 73.838 938.418 1012.256 7.294 756.944 908.333 29.219
lbs/MMBtu lbs/MMBtu lbs/MMBtu
9.566 7.653 1.913
9.566 7.653 1.913
9.566 7.653 1.913
9.566 7.653 1.913
9.814 7.851 1.963
0.280 0.024
0.280 0.024
0.280 0.024
0.280 0.024
0.280 0.024
Flue Gas, Air & Ash Downstream Of Economizer Flue Gas (lbs/MMBtu) O2 CO2 N2 NOx HCl SO2 H2O Gas Dry Gas Wet % H2O Theoretical Wet Air Actual Total Wet Air Mol Wt Wet, Lb/Lb-Mol Total Ash Fly Ash Bottom Ash
NOx - Flue Gas lbs/MMBtu Carbon Loss lbmoles/MMBtu * - Theoretical + Excess O2 Required for Combustion, Not O2 in Flue Gas
Gases, Downstream Of Air Heater Flue Gas (lb-moles/MMBtu) CO2 NOx HCl SO2 N2 O2 H2O Total Dry Flue Gas Total Wet Flue Gas
lbmoles/MMBtu lbmoles/MMBtu lbmoles/MMBtu lbmoles/MMBtu lbmoles/MMBtu lbmoles/MMBtu lbmoles/MMBtu lbmoles/MMBtu lbmoles/MMBtu
4.856 0.009 0.003 0.020 27.802 1.944 4.181 34.634 38.815
4.856 0.009 0.003 0.020 27.802 1.944 4.181 34.634 38.815
4.856 0.009 0.003 0.020 27.802 1.944 4.181 34.634 38.815
4.856 0.009 0.003 0.020 27.802 1.944 4.181 34.634 38.815
4.860 0.009 0.003 0.012 27.790 1.943 4.183 34.618 38.801
Dry Air Addition Wet Air Addition
lbmoles/MMBtu lbmoles/MMBtu
4.074 4.159
4.074 4.159
4.074 4.159
4.074 4.159
4.072 4.157
Wet Flue Gas PPMV & % Vol % O2 % CO2 % N2 PPMV NOx PPMV HCL PPMV SO2 % H2O TOTAL
% Vol % Vol % Vol ppmv ppmv ppmv % Vol
5.01 12.51 71.63 239.97 82.68 511.96 10.77 100.00
5.01 12.51 71.63 239.97 82.68 511.96 10.77 100.00
5.01 12.51 71.63 239.97 82.68 511.96 10.77 100.00
5.01 12.51 71.63 239.97 82.68 511.96 10.77 100.00
5.01 12.53 71.62 240.09 82.79 320.38 10.78 100.00
Dry Flue Gas PPMV & % Vol % O2 % CO2 % N2 NOx HCL SO2 % H2O TOTAL
% Vol % Vol % Vol ppmv ppmv ppmv % Vol
5.61 14.02 80.27 268.93 92.66 573.76 0 100.00
5.61 14.02 80.27 268.93 92.66 573.76 0 100.00
5.61 14.02 80.27 268.93 92.66 573.76 0 100.00
5.61 14.02 80.27 268.93 92.66 573.76 0 100.00
5.61 14.04 80.28 269.11 92.79 359.09 0 100.00
lbs/MMBtu lbs/MMBtu lbs/MMBtu lbs/MMBtu lbs/MMBtu lbs/MMBtu lbs/MMBtu lbs/MMBtu lbs/MMBtu wt% lbs/MMBtu lbs/lb-mole
62.194 213.711 779.013 0.280 0.117 1.273 75.314 1056.587 1131.901 6.654 1027.834 29.162
62.194 213.711 779.013 0.280 0.117 1.273 75.314 1056.587 1131.901 6.654 1027.834 29.162
62.194 213.711 779.013 0.280 0.117 1.273 75.314 1056.587 1131.901 6.654 1027.834 29.162
62.194 213.711 779.013 0.280 0.117 1.273 75.314 1056.587 1131.901 6.654 1027.834 29.162
62.168 213.905 778.665 0.280 0.117 0.796 75.365 1055.931 1131.297 6.662 1027.374 29.156
% % % % % %
6.295 7.172 0.413 0.352 1.5 0
6.295 7.172 0.413 0.352 1.5 0
6.295 7.172 0.413 0.352 1.5 0
6.295 7.172 0.413 0.352 1.5 0
6.292 7.178 0.414 0.352 1.5 0
Flue Gas & Air Downstream Of Air Heater Flue Gas (lbs/MMBtu) O2 CO2 N2 NOx HCl SO2 H2O Gas Dry Gas Wet Wt % H2O Total Wet Air Mol Wt Wet, Lb/Lb-Mol
Boiler Losses & Efficiencies Dry Gas Moisture Carbon Radiation Manufacturers Margin Ash Losses
254276149.xls.ms_office, Constants_CC
24
12/9/2014, 12:59 PM
CUECost - Air Pollution Control Systems Economics Spreadsheet Total Losses Boiler Efficiency
%
15.732
15.732
15.732
15.732
15.736
%
84.268
84.268
84.268
84.268
84.264
MMBtu/hr tons/hr lbs/MMBtu
236.25 13.4 113.8
236.25 13.4 113.8
236.25 13.4 113.8
236.25 13.4 113.8
236.25 13.5 113.9
SCFM/MMBtu SCFM lb/hr SCFM lb/hr % %
13,156 51,803 239,278 47,076 214,693 120% 20%
13,156 51,803 239,278 47,076 214,693 120% 20%
13,156 51,803 239,278 47,076 214,693 120% 20%
13,156 51,803 239,278 47,076 214,693 120% 20%
13,152 51,785 239,145 47,054 214,594 120% 20%
SCFM/MMBtu SCFM lb/hr SCFM lb/hr SCFM lb/hr % % °F in. H2O ACFM
14,735 58,020 267,412 53,245 242,826 6,169 28,133 135.7% 35.7% 300 -12 88,965
14,735 58,020 267,412 53,245 242,826 6,169 28,133 135.7% 35.7% 300 -12 88,965
14,735 58,020 267,412 53,245 242,826 6,169 28,133 135.7% 35.7% 300 -12 88,965
14,735 58,020 267,412 53,245 242,826 6,169 28,133 135.7% 35.7% 300 -12 88,965
14,730 58,000 267,269 53,221 242,717 6,167 28,123 135.7% 35.7% 300 -12 88,934
tons/hr tons/hr tons/hr
0.90 0.23 1.13
0.90 0.23 1.13
0.90 0.23 1.13
0.90 0.23 1.13
0.93 0.23 1.16
Coal Flow Rates Btu Input Rate to Boiler Coal Input Rate to Boiler Coal Input Rate to Boiler
Economizer Outlet Flue Gas Flue Gas Wet Flue Gas Wet Air Wet Air Total Air Excess Air
Air Heater Outlet Flue Gas Flue Gas Wet Flue Gas Wet Air Wet Air Wet Air Leakage Wet Air Leakage Equivalent Total Air Equivalent Excess Air Flue Gas Temperature Pressure Flue Gas
Ash Parameters Fly Ash Bottom Ash Total Ash
254276149.xls.ms_office, Constants_CC
25
12/9/2014, 12:59 PM
View more...
Comments