LECTURE 8 - Bond Development Length and Splices

April 11, 2018 | Author: Howell Tungol | Category: Bending, Stress (Mechanics), Beam (Structure), Strength Of Materials, Tension (Physics)
Share Embed Donate


Short Description

Bond Development Length and Splices according to NSCP 2010...

Description

Bond Development Length and Splices Lecture #8 References:

UP – Institute of Civil Engineering

Summary

Keyword 1.

Flexure consideration

2.

Development length

Lecture #8 Objectives Bond Stress Dev’t Length Tension Bundled Compression

Hooks Cut-Off 1. Flexure 2. Dev’t length 3. Shear Effects 4. Construction Req'ts 5. Other Req'ts

3.

2a. Tension

412.3

2b. Development length check

412.12.3

2c. Compression

412.4

2d. Bundled

412.5, 407.7.6

2e. Hooks

412.6, 407.2

Shear effect 3a. Shear effect

412.11.3

3b. Shear capacity check

412.11.5

4.

Construction

5.

Other requirements

Lap Splice Summary

6.

NSCP 2010

5a. Support and inflection point (tension, compression)

412.13.1, 412.13.3

5b. Structural integrity*

407.14

Lap Splice 6a. Tension

412.16

6b. Compression

412.17 3

IHST

UP – Institute of Civil Engineering

Bond Stress Lecture #8 Objectives Bond Stress Dev’t Length Tension Bundled Compression

Hooks Cut-Off 1. Flexure 2. Dev’t length 3. Shear Effects 4. Construction Req'ts 5. Other Req'ts



 

One assumption in flexural design: No slippage of the bars in relation to the surrounding concrete If bond doesn't exist, unreinforced concrete If bond do exist, bond stresses should also exist to maintain equilibrium

Lap Splice Summary

4

IHST

UP – Institute of Civil Engineering

Bond Stress Lecture #8 Objectives Bond Stress Dev’t Length Tension Bundled Compression

Hooks Cut-Off 1. Flexure 2. Dev’t length 3. Shear Effects 4. Construction Req'ts 5. Other Req'ts

∑𝐹 = 0;

𝜋𝑑𝑏2 𝑓𝑠2 − 𝑓𝑠1 = 𝜇𝑎𝑣𝑔 𝜋𝑑𝑏 𝑙 4 Let 𝑓𝑠2 − 𝑓𝑠1 = 𝛥𝑓𝑠 gives Δ𝑓𝑠 𝑑𝑏 1 𝜇𝑎𝑣𝑔 = 4𝑙

Lap Splice Summary

5

IHST

UP – Institute of Civil Engineering

Mechanism of Bond Transfer

Adhesion and Friction

Lecture #8 Objectives Bond Stress Dev’t Length Tension Bundled Compression

Hooks Cut-Off 1. Flexure 2. Dev’t length 3. Shear Effects 4. Construction Req'ts 5. Other Req'ts Lap Splice Summary

7

IHST

UP – Institute of Civil Engineering

Mechanism of Bond Transfer Lecture #8 Objectives Bond Stress Dev’t Length Tension Bundled Compression

Hooks Cut-Off 1. Flexure 2. Dev’t length 3. Shear Effects 4. Construction Req'ts 5. Other Req'ts Lap Splice Summary

If splitting occurs, the yield strength of the bars assumed to be part of equilibrium equations will not be developed 8

IHST

UP – Institute of Civil Engineering

Development Length Lecture #8 Objectives



Bond Stress Dev’t Length Tension Bundled Compression

Hooks Cut-Off 1. Flexure 2. Dev’t length 3. Shear Effects 4. Construction Req'ts 5. Other Req'ts



Because the actual bond stresses varies along the length of the bar, the ACI Code uses the concept of development length rather than bond stresses The development length, 𝑙𝑑 , is the shortest length of bar in which the bar stress increase from zero to the yield strength 𝑓𝑦

Lap Splice Summary

9

IHST

UP – Institute of Civil Engineering

Development Length Lecture #8 Objectives Bond Stress Dev’t Length Tension Bundled Compression

Hooks Cut-Off 1. Flexure 2. Dev’t length 3. Shear Effects 4. Construction Req'ts 5. Other Req'ts Lap Splice Summary

𝑙𝑑

not be less than 𝑙𝑑

Region of maximum bar stress

10

IHST

UP – Institute of Civil Engineering

Development Length – ACI 12.1

NSCP 412

Lecture #8 Objectives Bond Stress Dev’t Length Tension Bundled Compression

Hooks Cut-Off 1. Flexure 2. Dev’t length 3. Shear Effects 4. Construction Req'ts 5. Other Req'ts Lap Splice Summary

11

IHST

UP – Institute of Civil Engineering

Development Length – ACI 12.3

NSCP 412.3.3

Lecture #8 Objectives Bond Stress Dev’t Length Tension Bundled Compression

𝑓𝑐𝑡

𝑓𝑐𝑡

Hooks Cut-Off 1. Flexure 2. Dev’t length 3. Shear Effects 4. Construction Req'ts 5. Other Req'ts

Properties

Actual

Idealized

Major factors affecting the development length ▪ Bar properties (𝑓𝑦 and 𝑑𝑏 ) ▪ Bar spacing, 𝑐𝑏 (discussion later) ▪ Concrete strength

Lap Splice Summary

ACI 𝒍𝒅 full equation 12

IHST

UP – Institute of Civil Engineering

Development Length – ACI 12.2.4NSCP 412.3.4 Lecture #8 Objectives

1.

Location of Reinforcement (𝜓𝑡 )

2.

Coating of bars(𝜓𝑒 )

Bond Stress Dev’t Length Tension Bundled Compression

Hooks Cut-Off 1. Flexure 2. Dev’t length 3. Shear Effects 4. Construction Req'ts 5. Other Req'ts Lap Splice Summary

13

IHST

UP – Institute of Civil Engineering

Development Length – ACI 12.2.4NSCP 412.3.4 Lecture #8 Objectives Bond Stress Dev’t Length Tension Bundled Compression

Hooks

3.

Sizes of Reinforcing Bars (𝜓𝑠 )

4.

Lightweight Aggregates (𝜆)

Cut-Off 1. Flexure 2. Dev’t length 3. Shear Effects 4. Construction Req'ts 5. Other Req'ts Lap Splice Summary

14

IHST

UP – Institute of Civil Engineering

Development Length – ACI 12.2.4NSCP 412.3.4 Lecture #8 Objectives

5.

Confinement term

Bond Stress Dev’t Length Tension Bundled Compression

Hooks Cut-Off 1. Flexure 2. Dev’t length 3. Shear Effects 4. Construction Req'ts 5. Other Req'ts Lap Splice Summary

where 𝑐𝑏 = represents the smaller of the distance from the center of the tension bar or wire to the nearest concrete surface, or one half the center-to-center spacing of reinforcement 𝐾𝑡𝑟 = transverse reinforcement index. Used to account for the contribution of confining reinforcement across possible splitting planes 𝐴𝑡𝑟 = the total cross-sectional area of all transverse reinforcement having the center-to-center spacing, 𝑠, and a yield strength, 𝑓𝑦𝑡 . 𝑛 = number of bars or wires being developed along the plane of splitting

15

IHST

UP – Institute of Civil Engineering

𝑨𝐯,𝒎𝒊𝒏 =

𝒇′𝒄

𝒃𝒘 𝒔 𝒃𝒘 𝒔 ≥ 𝟏𝟔𝒇𝒚𝒕 𝟑𝒇𝒚𝒕

Development Length – simplified NSCP 412.3.2 Lecture #8 Objectives Bond Stress Dev’t Length Tension Bundled Compression

Substituting lower limit values of 𝑐𝑏 and 𝐾𝑡𝑟 for common design cases:

Hooks Cut-Off 1. Flexure 2. Dev’t length 3. Shear Effects 4. Construction Req'ts 5. Other Req'ts Lap Splice

Case 1

Case 2

Summary

ACI 𝒍𝒅 full equation

ACI 𝒍𝒅 simplified equations

16

IHST

UP – Institute of Civil Engineering

Development Length – simplified Lecture #8 Objectives Bond Stress Dev’t Length Tension Bundled Compression

Hooks Cut-Off 1. Flexure 2. Dev’t length 3. Shear Effects 4. Construction Req'ts 5. Other Req'ts Lap Splice Summary

17

IHST

UP – Institute of Civil Engineering

Problem 8.1 Lecture #8 Objectives Bond Stress Dev’t Length Tension Bundled Compression

Hooks Cut-Off 1. Flexure 2. Dev’t length 3. Shear Effects 4. Construction Req'ts 5. Other Req'ts Lap Splice

A 400-mm-wide cantilever beam frames into the edge of a 400-mm-thick wall as shown. To reach Mn, the 3-25mm bars at the top of the beam are stressed to their yield strength at point A at the face of the wall. Compute the minimum embedment of the bars into the wall and the development length in the beam. The concrete is sand/low density concrete with a strength of 25 MPa. The yield strength of the flexural reinforcement is 420 MPa. Construction joints are located at the top and bottom of the beam. The beam has closed 10mm stirrups with fyt = 420 MPa at a spacing of 180 mm throughout its length (the stirrups are not shown). The cover is 40-mm to the stirrups. The three No. 25 bars are inside the 13mm vertical steel in each face of the wall.

Cantilever beam

Summary

18

IHST

UP – Institute of Civil Engineering

Problem 8.2 – Group Seatwork Lecture #8 Objectives Bond Stress Dev’t Length Tension Bundled Compression

The required reinforcing steel area for the lightweight concrete (fc’ = 21MPa) beam in the figure is given below. The 25-mm top bars (fy = 420MPa) shown are uncoated. Use fyt = 270 MPa. Compute the development lengths using a.) simplified equation (assume stirrup is code compliant) b.) the full equation of ACI equation 12-1 with calculated value of Ktr c.) ACI equation 12-1 with Ktr = 0

40

Hooks Cut-Off 1. Flexure 2. Dev’t length 3. Shear Effects 4. Construction Req'ts 5. Other Req'ts Lap Splice

420 4-25 mm

10 mm stirrups spaced at 200 mm

40 40 mm

750 mm 710 mm

Summary

500 mm 19

IHST

UP – Institute of Civil Engineering

Development Length – Bundled bars Lecture #8 Objectives Bond Stress Dev’t Length Tension Bundled Compression



Greater development lengths are needed when bundled bars are used since part of the surface area of one bar will not be in contact with the concrete

Hooks Cut-Off 1. Flexure 2. Dev’t length 3. Shear Effects 4. Construction Req'ts 5. Other Req'ts Lap Splice Summary

20

IHST

UP – Institute of Civil Engineering

Problem 8.3 Lecture #8 Objectives Bond Stress Dev’t Length Tension Bundled Compression

Compute the development length required for the uncoated bundled bars shown in the figure. Assume fy = 414 MPa, fc’ = 21 MPa and fyt = 270 MPa.

Hooks Cut-Off 1. Flexure 2. Dev’t length 3. Shear Effects 4. Construction Req'ts 5. Other Req'ts

50

50

10mm stirrup at 200mm 500 mm

Lap Splice Summary

250

3 – 25 mm bars 50 mm 21

IHST

UP – Institute of Civil Engineering

Development Length –

Tension ACI 12.11

Lecture #8 Objectives Bond Stress Dev’t Length Tension Bundled Compression

Moment Capacity 𝜙𝑀𝑛

ACI 𝒍𝒅 full equation Hooks Cut-Off 1. Flexure 2. Dev’t length 3. Shear Effects 4. Construction Req'ts 5. Other Req'ts

Required Moment 𝑀𝑢 O

𝒍𝒅

𝝓𝑴𝒏 < 𝑴𝒖

Lap Splice Summary

22

IHST

UP – Institute of Civil Engineering

Development Length –

Tension ACI 12.11

Lecture #8 Objectives Bond Stress Dev’t Length Tension Bundled Compression

Moment Capacity 𝜙𝑀𝑛

ACI 𝒍𝒅 full equation Hooks Cut-Off 1. Flexure 2. Dev’t length 3. Shear Effects 4. Construction Req'ts 5. Other Req'ts Lap Splice Summary

Required Moment 𝑀𝑢 O

𝒍𝒅

𝝓𝑴𝒏 < 𝑴𝒖

To maintain 𝜙𝑀𝑛 > 𝑀𝑢 the slope of the momentcapacity diagram (line OB) cannot be less than the slope of the moment-load diagram (line OA)

23

IHST

UP – Institute of Civil Engineering

Development Length –

NSCP 412.12.3

Tension ACI 12.11

Lecture #8 Objectives Bond Stress Dev’t Length Tension Bundled Compression

Hooks Cut-Off 1. Flexure 2. Dev’t length 3. Shear Effects 4. Construction Req'ts 5. Other Req'ts Lap Splice Summary

24

IHST

UP – Institute of Civil Engineering

Development Length –

NSCP 412.12.3

Tension ACI 12.11

Lecture #8 Objectives Bond Stress Dev’t Length Tension Bundled Compression

Hooks Cut-Off 1. Flexure 2. Dev’t length 3. Shear Effects 4. Construction Req'ts 5. Other Req'ts Lap Splice Summary

25

IHST

UP – Institute of Civil Engineering

NSCP 412.4

Development Length –

Compression ACI 12.3

Lecture #8 Objectives Bond Stress Dev’t Length Tension Bundled Compression

Hooks Cut-Off 1. Flexure 2. Dev’t length 3. Shear Effects 4. Construction Req'ts 5. Other Req'ts Lap Splice Summary

𝑙𝑑𝑐 =

0.24𝑓𝑦 𝜆

𝑓𝑐′

≥ 0.043𝑓𝑦 𝑑𝑏

Note: 𝑙𝑑𝑐 is considerably shorter than 𝑙𝑑

26

IHST

UP – Institute of Civil Engineering

Development Length – Lecture #8 Objectives



NSCP 412.4

Compression ACI 12.3

Modification factors for Compression bars

Bond Stress Dev’t Length Tension Bundled Compression

Hooks Cut-Off 1. Flexure 2. Dev’t length 3. Shear Effects 4. Construction Req'ts 5. Other Req'ts Lap Splice Summary

27

IHST

UP – Institute of Civil Engineering

Development Length –

Compression ACI 12.3

Lecture #8 Objectives Bond Stress Dev’t Length Tension Bundled Compression

Hooks Cut-Off 1. Flexure 2. Dev’t length 3. Shear Effects 4. Construction Req'ts 5. Other Req'ts Lap Splice Summary

28

IHST

UP – Institute of Civil Engineering

Problem 8.4 Lecture #8 Objectives Bond Stress Dev’t Length Tension Bundled Compression

The forces in the column bars in the figure are to be transferred into the 500-mm thick footing with 32 mm dowels. Determine the development lengths needed for the dowels (a) down into the footing and (b) up into the column fy = 414 MPa and fc’ = 21 MPa (for footing) fc’ = 35 MPa (for column)

Hooks Cut-Off 1. Flexure 2. Dev’t length 3. Shear Effects 4. Construction Req'ts 5. Other Req'ts Lap Splice Summary

ld into column ld into footing

29

IHST

UP – Institute of Civil Engineering

Hooks Lecture #8 Objectives Bond Stress Dev’t Length Tension Bundled Compression

Hooks Cut-Off 1. Flexure 2. Dev’t length 3. Shear Effects 4. Construction Req'ts 5. Other Req'ts Lap Splice Summary

30

IHST

UP – Institute of Civil Engineering

Hooks – Mechanism(FBD) Lecture #8 Objectives Bond Stress Dev’t Length Tension Bundled Compression

Hooks Cut-Off 1. Flexure 2. Dev’t length 3. Shear Effects 4. Construction Req'ts 5. Other Req'ts Lap Splice Summary

31

IHST

UP – Institute of Civil Engineering

Hooks – Mechanism(Stresses) Lecture #8 Objectives Bond Stress Dev’t Length Tension Bundled Compression



Decrease in axial stress is due to bond and friction



Slip measured is relative to the axial stress (180° has a maximum slip 1.75 times the 90°)

Hooks Cut-Off 1. Flexure 2. Dev’t length 3. Shear Effects 4. Construction Req'ts 5. Other Req'ts Lap Splice Summary

Stress diagram and slip measured at points along a hook at a bar stress of 1.25𝑓𝑦 in tests of 90 and 180 degree hooks in No.7 bars

32

IHST

UP – Institute of Civil Engineering

NSCP 412.6

ACI Requirement Lecture #8 Objectives



For standard hooks, the development length is

Bond Stress Dev’t Length Tension Bundled Compression

Hooks Cut-Off 1. Flexure 2. Dev’t length 3. Shear Effects 4. Construction Req'ts 5. Other Req'ts Lap Splice Summary

𝑙𝑑ℎ = 0.24

𝜓𝑒 𝜆𝑓𝑦 𝑓𝑐′

𝑑𝑏 ≥ 8𝑑𝑏 𝑜𝑟 150𝑚𝑚

33

IHST

UP – Institute of Civil Engineering

NSCP 412.6

ACI Requirement - ACI 12.5.3 & …4 Lecture #8 Objectives Bond Stress Dev’t Length Tension Bundled Compression

Hooks Cut-Off 1. Flexure 2. Dev’t length 3. Shear Effects 4. Construction Req'ts 5. Other Req'ts Lap Splice Summary

34

IHST

UP – Institute of Civil Engineering

ACI Requirement - ACI 12.5.3a & …3b Lecture #8 Objectives Bond Stress Dev’t Length Tension Bundled Compression

Hooks Cut-Off 1. Flexure 2. Dev’t length 3. Shear Effects 4. Construction Req'ts 5. Other Req'ts Lap Splice Summary

35

IHST

UP – Institute of Civil Engineering

Detailing dimension, 𝑙𝑑ℎ 𝜓𝑒 𝜆𝑓𝑦 𝑙𝑑ℎ = 0.24 𝑑𝑏 ′ 𝑓𝑐 Lecture ≥ 8𝑑#8 𝑏 𝑜𝑟 150𝑚𝑚 Objectives

Bond Stress Dev’t Length Tension Bundled Compression

Hooks Cut-Off 1. Flexure 2. Dev’t length 3. Shear Effects 4. Construction Req'ts 5. Other Req'ts Lap Splice Summary

36

IHST

UP – Institute of Civil Engineering

ACI Standard Hooks (Typical) Lecture #8 Objectives Bond Stress Dev’t Length Tension Bundled Compression

Hooks Cut-Off 1. Flexure 2. Dev’t length 3. Shear Effects 4. Construction Req'ts 5. Other Req'ts Lap Splice Summary

37

IHST

UP – Institute of Civil Engineering

Problem 8.5 The exterior Lecture #8 end 400x600mm continuous beam frames into a 650-mm square column. The column has 4-36M longitudinal bars. The negative moment reinforcement at the exterior end of the beam consists of 4-25M bars. The concrete is 25 MPa normal weight Objectives concrete. The steel strength is 420 MPa. Design the anchorage of the 4-25M bars into the column. Consider ACI 11.10.2 as well Bond Stress Dev’t Length Tension Bundled Compression

Hooks Cut-Off 1. Flexure 2. Dev’t length 3. Shear Effects 4. Construction Req'ts 5. Other Req'ts Lap Splice Summary

38

IHST

UP – Institute of Civil Engineering

Problem 8.6 Seatwork (Group) Lecture #8 Objectives Bond Stress Dev’t Length Tension Bundled Compression

Hooks



Determine the development or embedment length required for the epoxy-coated bars of the beam shown in the figure. fy = 414 MPa, fc’ = 28 MPa (a) if the bars are straight, assuming Ktr = 0 (b) if a 180-degree hook is used and (c) if a 90-degree hook is used. Assume 10M stirrups, db = 25M, concrete cover of 50mm 50

250

50 65 mm 115 mm

Cut-Off 1. Flexure 2. Dev’t length 3. Shear Effects 4. Construction Req'ts 5. Other Req'ts

325 mm

Lap Splice Summary

39

IHST

UP – Institute of Civil Engineering

Bar Cut-off Recall: Location of Reinforcement Lecture #8 Objectives Bond Stress Dev’t Length Tension Bundled Compression

Hooks Cut-Off 1. Flexure 2. Dev’t length 3. Shear Effects 4. Construction Req'ts 5. Other Req'ts Lap Splice Summary

40

IHST

UP – Institute of Civil Engineering

Bar Cut-off Lecture #8 Objectives Bond Stress Dev’t Length Tension Bundled Compression

Hooks Cut-Off 1. Flexure 2. Dev’t length 3. Shear Effects 4. Construction Req'ts 5. Other Req'ts

Four major factors affecting location of bar cut-offs: 1. When they are no longer needed 2. Development lengths 3. Location of moderately high shear force 4. Constructional requirements 5. Other requirements

Lap Splice Summary

42

IHST

UP – Institute of Civil Engineering

1

Problem 8.7 Illustration Lecture #8 Objectives Bond Stress Dev’t Length Tension Bundled Compression

Given the following parameters, f'c = 28 MPa, fy = 420 MPa with 100 kN/m load on a 6m (b = 400mm, d = 550mm) beam, the resulting design is 5-25M bars (design strength, 𝜙𝑀𝑛 is 465 kN/m).

Hooks Cut-Off 1. Flexure 2. Dev’t length 3. Shear Effects 4. Construction Req'ts 5. Other Req'ts Lap Splice Summary

43

IHST

UP – Institute of Civil Engineering

1

Bar Cut-off (Illustration) Lecture #8 Objectives Bond Stress Dev’t Length Tension Bundled Compression

Hooks Cut-Off 1. Flexure 2. Dev’t length 3. Shear Effects 4. Construction Req'ts 5. Other Req'ts Lap Splice Summary

44

IHST

UP – Institute of Civil Engineering

1

Problem 8.10 Flexure Lecture #8 Objectives Bond Stress Dev’t Length Tension Bundled Compression

Hooks

The beam shown is constructed of normal-weight, 21-MPa concrete and Grade-60 reinforcement. It supports the factored load as shown. Given the cross sections at the points of maximum positive and negative moment, determine the bar cut-off locations of 2-25M bars considering flexural capacities only.

Cut-Off 1. Flexure 2. Dev’t length 3. Shear Effects 4. Construction Req'ts 5. Other Req'ts

1.2𝑤𝐷 = 6𝑘𝑁/𝑚 & 1.6𝑤𝐿 = 49𝑘𝑁/𝑚

Lap Splice Summary

𝟐 − 𝟑𝟎𝑴 section 𝜙𝑀𝑛 = 253 𝑘𝑁𝑚 𝟐 − 𝟐𝟓𝑴 and 𝟐 − 𝟑𝟎𝑴 section 𝜙𝑀𝑛 = 308 𝐾𝑁𝑚 47

IHST

UP – Institute of Civil Engineering

2

Problem 8.10 Dev’t Length Lecture #8 Objectives Bond Stress Dev’t Length Tension Bundled Compression

Hooks Cut-Off 1. Flexure 2. Dev’t length 3. Shear Effects 4. Construction Req'ts 5. Other Req'ts

The beam shown is constructed of normal-weight, 21-MPa concrete and Grade-60 reinforcement. It supports the factored load as shown. Given the cross sections at the points of maximum positive and negative moment, determine the bar cut-off locations considering development lengths only. 1.2𝑤𝐷 = 6𝑘𝑁/𝑚 & 1.6𝑤𝐿 = 49𝑘𝑁/𝑚

Lap Splice Summary

48

IHST

UP – Institute of Civil Engineering

3

Bar Cut-off Shear Effects Lecture #8 of Shear Objectives Bond Stress Dev’t Length Tension Bundled Compression

Hooks Cut-Off 1. Flexure 2. Dev’t length 3. Shear Effects 4.The Construction Req'tsbe bars should 5. Other Req'ts

anchored into the support Lap Splicefor at least 0.5𝑉𝑢, and Summary preferably 0.75𝑉𝑢. a.

Inclined cracking (shear force) increases the tension force in the flexural reinforcement 49

IHST

UP – Institute of Civil Engineering

Bar Cut-off Shear b. Lecture Stress #8

concentration ▪ Due to reduction of bars (𝐴𝑠 ↓), Bond Stress stresses in bars increases which can Dev’t Length Tension lead to major inclined cracks at the Bundled bar cut-off. (see Figure e) Compression 𝑀𝑢′ 𝑓𝑠 = Hooks 𝜙𝐴𝑠 𝑗𝑑 Objectives

Cut-Off 12.10.3 1. Flexure – Reinforcement shall extend 2. Dev’t length beyond the point at which it is no longer 3. Shear Effects required toReq'ts resist flexure for a distance 4. Construction 5. Other to Req'ts equal d or 12db whichever is greater,

except Lap Spliceat supports of simple spans and at free end of cantilevers Summary

In addition to shear effect, ACI 12.10.3 also accounts for the maximum moment shifts due to changes in loading and support settlement 50

IHST

UP – Institute of Civil Engineering

3

Bar Cut-off Shear c. Lecture Shear #8

strength reduction and loss of ductility ▪ Due to reduced reinforcement, flexure cracks tend to open early whenever any Bond Stress rebar is terminated in a tension zone. Objectives

Dev’t Length Tension Bundled Compression

Hooks Cut-Off 1. Flexure 2. Dev’t length 3. Shear Effects 4. Construction Req'ts 5. Other Req'ts Lap Splice

As a result of the difficulties in satisfying these sections, designers frequently will extend all bars into the supports in simple beams or past points of inflection in continuous beams.

Summary

51

IHST

UP – Institute of Civil Engineering

3

Problem 8.10 Shear Lecture #8 Objectives Bond Stress Dev’t Length Tension Bundled Compression

Hooks

The beam shown is constructed of normal-weight, 21-MPa concrete and Grade-60 reinforcement. It supports the factored load as shown. Given the cross sections at the points of maximum positive and negative moment, determine the bar cut-off locations considering shear effects only.

Cut-Off 1. Flexure 2. Dev’t length 3. Shear Effects 4. Construction Req'ts 5. Other Req'ts

1.2𝑤𝐷 = 6𝑘𝑁/𝑚 & 1.6𝑤𝐿 = 49𝑘𝑁/𝑚

Lap Splice Summary

𝟐 − 𝟑𝟎𝑴 section 𝜙𝑀𝑛 = 253 𝑘𝑁𝑚 𝟐 − 𝟐𝟓𝑴 and 𝟐 − 𝟑𝟎𝑴 section 𝜙𝑀𝑛 = 308 𝐾𝑁𝑚 52

IHST

UP – Institute of Civil Engineering

5

Bar Cut-off Code Requirements Lecture #8 Objectives Bond Stress Dev’t Length Tension Bundled Compression

Hooks Cut-Off 1. Flexure 2. Dev’t length 3. Shear Effects 4. Construction Req'ts 5. Other Req'ts Lap Splice Summary

Extension of tension bars Positive moment: at least 1/3 (simple) or 1/4 (continuous) the reinforcement shall be extended at least 150mm. Negative moment: (beyond pt. of inflection) at least 1/3 shall be extended either 𝑑, 12𝑑𝑏 or 𝑙𝑛 /16 (whichever is greater) 53

IHST

UP – Institute of Civil Engineering

5

Bar Cut-off Code Requirements Lecture #8 Objectives Bond Stress Dev’t Length Tension Bundled Compression

Hooks Cut-Off 1. Flexure 2. Dev’t length 3. Shear Effects 4. Construction Req'ts 5. Other Req'ts Lap Splice Summary

54

IHST

UP – Institute of Civil Engineering

Summary (ACI) 1. When they are no longer needed Lecture #8 Locate flexural cut-off points Objectives 2. Development lengths Bond Stress Apply development lengths past Dev’t Length Tension the points of maximum stress Bundled a. Compression

b.

Hooks

3.

Cut-Off a. 12.10.3 1. Flexure b. 12.10.5 2. Dev’t length 3. Shear Effects zone 4. Construction Req'ts 5.4. Other Req'ts

b.

6.

Flexure consideration

2.

Development length

12.11.1 or 12.12.3 Extension into the supports 7.13.2.2 Structural integrity

Lap splice

3.

Shear effect Termination at tension

Constructional requirements 5. Other requirements Lap Splice a.

1.

12.2 to 12.5 𝑙𝑑 formula 12.11.3 Tension bars: 𝑀𝑛 /𝑉𝑢

Shear effects

Summary

Keyword

2a.

Tension

12.2

2b.

Development length check

12.11.3

2c.

Compression

12.3

2d.

Bundled

12.4

2e.

Hooks

12.5

Shear effect 3a.

Shear effect

12.10.3

3b.

Shear capacity check

12.10.5

4.

Construction

5.

Other requirements

6.

ACI 318M (2011)

5a.

Support and inflection point (tension, compression)

12.11.1, 12.12.3

5b.

Structural integrity*

7.13.2.2

Lap Splice 6a.

Tension

12.15

6b.

Compression

12.16

55

IHST

UP – Institute of Civil Engineering

Summary (NSCP) 1. When they are no longer needed Lecture #8 Locate flexural cut-off points Objectives 2. Development lengths Bond Stress Apply development lengths past Dev’t Length Tension the points of maximum stress Bundled a. Compression

b.

Hooks

3.

Cut-Off a. 412.11.3 1. Flexure b. 412.11.5 2. Dev’t length 3. Shear Effects zone 4. Construction Req'ts 5.4. Other Req'ts

b.

6.

Flexure consideration

2.

Development length

3.

Shear effect Termination at tension

Constructional requirements 5. Other requirements Lap Splice a.

1.

412.3 to 412.6 𝑙𝑑 formula 412.12.3 Tension bars: 𝑀𝑛 /𝑉𝑢

Shear effects

Summary

Keyword

412.12.1 or 412.12.3 Extension into the supports 407.14 Structural integrity

Lap splice

2a.

Tension

412.3

2b.

Development length check

412.12.3

2c.

Compression

412.4

2d.

Bundled

412.5, 407.7.6

2e.

Hooks

412.6, 407.2

Shear effect 3a.

Shear effect

412.11.3

3b.

Shear capacity check

412.11.5

4.

Construction

5.

Other requirements

6.

NSCP 2010

5a.

Support and inflection point (tension, compression)

412.12.1, 412.12.3

5b.

Structural integrity*

407.14

Lap Splice 6a.

Tension

412.16

6b.

Compression

412.17

56

IHST

UP – Institute of Civil Engineering

Splices Lecture #8 Objectives Bond Stress Dev’t Length Tension Bundled Compression

Hooks Cut-Off 1. Flexure 2. Dev’t length 3. Shear Effects 4. Construction Req'ts 5. Other Req'ts Lap Splice Summary



Lapped splices, mechanical splices, welded splices, and end-bearing splices

Considerations  Limited bar lengths available and requirements at construction joints (6 m, 7.5 m, 9 m, 10.5 m, 12 m)  Reinforcement congestion  Laps will not be satisfactory for very long lengths (for 29 mm to 36 mm bars) 57

IHST

UP – Institute of Civil Engineering

Splices Lecture #8 Objectives Bond Stress Dev’t Length Tension Bundled Compression

Hooks Cut-Off 1. Flexure 2. Dev’t length 3. Shear Effects 4. Construction Req'ts 5. Other Req'ts Lap Splice Summary

Dywidag THREADBAR® reinforcing bar 58

IHST

UP – Institute of Civil Engineering

Tension Lap Splice Lecture #8 Objectives Bond Stress Dev’t Length Tension Bundled Compression

Hooks Cut-Off 1. Flexure 2. Dev’t length 3. Shear Effects 4. Construction Req'ts 5. Other Req'ts Lap Splice Summary

59

IHST

UP – Institute of Civil Engineering

Tension Lap Splice Lecture #8 Objectives Bond Stress Dev’t Length Tension Bundled Compression

Hooks Cut-Off 1. Flexure 2. Dev’t length 3. Shear Effects 4. Construction Req'ts 5. Other Req'ts Lap Splice Summary

Failure of a tension Lap Splice without stirrups enclosing the splice

60

IHST

UP – Institute of Civil Engineering

Tension Lap Splice Lecture #8 Objectives Bond Stress Dev’t Length Tension Bundled Compression

Hooks Cut-Off 1. Flexure 2. Dev’t length 3. Shear Effects 4. Construction Req'ts 5. Other Req'ts Lap Splice Summary

61

IHST

UP – Institute of Civil Engineering

Compression Splices Lecture #8 Objectives Bond Stress Dev’t Length Tension Bundled Compression

Hooks

Compression bars may be spliced by: ▪ Lapping ▪ End Bearing ▪ Welding or Mechanical Devices

Cut-Off 1. Flexure 2. Dev’t length 3. Shear Effects 4. Construction Req'ts 5. Other Req'ts Lap Splice Summary

62

IHST

UP – Institute of Civil Engineering

Problem 8.10 Lecture #8 Objectives Bond Stress Dev’t Length Tension Bundled Compression

Hooks

ALL

The beam shown is constructed of normal-weight, 21-MPa concrete and Grade-60 reinforcement. It supports the factored load as shown. Given the cross sections at the points of maximum positive and negative moment, determine the bar cut-off locations. Consider bar lengths to be 7.5m only. Use Class A splice.

Cut-Off 1. Flexure 2. Dev’t length 3. Shear Effects 4. Construction Req'ts 5. Other Req'ts

1.2𝑤𝐷 = 6𝑘𝑁/𝑚 & 1.6𝑤𝐿 = 49𝑘𝑁/𝑚

Lap Splice Summary

𝟐 − 𝟑𝟎𝑴 section 𝜙𝑀𝑛 = 253 𝑘𝑁𝑚 𝟐 − 𝟐𝟓𝑴 and 𝟐 − 𝟑𝟎𝑴 section 𝜙𝑀𝑛 = 308 𝐾𝑁𝑚 63

IHST

UP – Institute of Civil Engineering

Problem 8.10 Lecture #8 Objectives

Lap splice locations

Bond Stress Dev’t Length Tension Bundled Compression

Hooks Cut-Off 1. Flexure 2. Dev’t length 3. Shear Effects 4. Construction Req'ts 5. Other Req'ts Lap Splice Summary

64

IHST

UP – Institute of Civil (ACI Engineering Standard Bar Details 7.13)

Standard Bar Details (ACI 7.13) Lecture #8 Objectives Bond Stress Dev’t Length Tension Bundled Compression

Hooks Cut-Off 1. Flexure 2. Dev’t length 3. Shear Effects 4. Construction Req'ts 5. Other Req'ts Lap Splice Summary

65

IHST

UP – Institute of Civil Engineering

Standard Bar Details (ACI 7.13) Lecture #8 Objectives Bond Stress Dev’t Length Tension Bundled Compression

Hooks Cut-Off 1. Flexure 2. Dev’t length 3. Shear Effects 4. Construction Req'ts 5. Other Req'ts Lap Splice Summary

66

IHST

View more...

Comments

Copyright ©2017 KUPDF Inc.
SUPPORT KUPDF