Lecture 18

May 3, 2017 | Author: Priyanka | Category: N/A
Share Embed Donate


Short Description

vjvj...

Description

NPTEL - ADVANCED FOUNDATION ENGINEERING-1

Module 5

(Lecture 18) MAT FOUNDATIONS

Topics 1.1 FIELD SETTLEMENT OBSERVATIONS FOR MAT FOUNDATIONS 1.2 COMPENSATED FOUNDATIONS 1.3 Example

FIELD SETTLEMENT OBSERVATIONS FOR MAT FOUNDATIONS Several field settlement observations for mat foundations are currently available in the literature. In this section we compare the observed settlements for some mat foundations constructed over granular soil deposits with those obtained from equations (12 and 13). Meyerhof (1965) compiled the observed maximum settlements for mat foundations constructed on sand and gravel, as listed in table 1. In equation (13) if the depth factor, 1 + 0.33(๐ท๐ท๐‘“๐‘“ /๐ต๐ต), is assumed to be approximately 1, ๐‘ž๐‘ž all (net )

๐‘†๐‘†๐‘’๐‘’ = 0.25๐‘๐‘

cor

[5.19]

Table 2 shows a comparison of the observed maximum settlements in table 1 and the settlements obtained from equation (19). For the cases considered the ratio of ๐‘†๐‘†๐‘’๐‘’ calculated /๐‘†๐‘†๐‘’๐‘’ observed varies from 0.84 to 3.6. Thus calculation of the net allowable bearing capacity with equation (12 or 13) will yield a safe and conservative value. Stuart and Graham (1975) reported the case history of the 13-story Ashby Institute building of Queens University, Belfast, Ireland, construction of which began in August 1960. It was supported by at foundation 180 ft (length)ร— 65 ft (width). Figure 5.5a shows a schematic diagram of the building cross section. The nature of the subsoil along with the field standard penetration resistance values at the south end of the building are shown in figure 5.5b. The base of the mat was constructed about 20 ft below the ground surface.

NPTEL - ADVANCED FOUNDATION ENGINEERING-1

Figure 5.5 Ashby Institute Building of Queens University, as reported by Stuart and Graham (1975); (a) building cross section; (b) subsoil conditions at south end The variation of the corrected standard penetration number with depth is shown in table 3. Note that the average ๐‘๐‘cor value between the bottom of the mat and a depth of 30 ft (โ‰ˆ ๐ต๐ต/2) is about 17. The engineers estimated the average net dead and live load [equation (16)] at the level of the mat foundation to be about 3360 lb/ft 2 . From equation (13) ๐‘†๐‘†๐‘’๐‘’ =

๐‘ž๐‘ž all (net )

๐ท๐ท ๐‘“๐‘“

0.25๐‘๐‘cor ๏ฟฝ1+0.33๏ฟฝ

๐ต๐ต

๏ฟฝ๏ฟฝ

[5.20]

Substituting appropriate values into equation (20) yield the settlement at the south end of the building: (3360 /1000 )

๐‘†๐‘†๐‘’๐‘’ = (0.25)(17)[1+0.33(20/65)] = 0.72 in.

The construction of the building was completed in February 1964. Figure 5.6 shows the variation of the mean settlement of the mat at the south end. In 1972 (eight years after completion of the building) the mean settlement was about 0.55 in. Thus the estimated settlement of 0.72 in. is about 30% higher than that actually observed.

NPTEL - ADVANCED FOUNDATION ENGINEERING-1 Table 1 Observed Maximum Settlement of Mat Foundations on Sand and Gravel Reference

๐ต๐ต(ft)

Case no.

Structure

1

T. Edison

Rios and Silva Sao Paulo, (1948) Brazil

60

2

Banco Brasil

do Rios and Silva (1948); Sao Paulo, Vargas Brazil (1961)

3

Iparanga

๐‘๐‘cor (๐‘Ž๐‘Ž๐‘Ž๐‘Ž๐‘Ž๐‘Ž) ๐‘ž๐‘žall (net ) (kip/ Observed maximum settlement, ๐‘†๐‘†๐‘’๐‘’ (in. ) ft 2 ) 15

4.8

0.6

75

18

5.0

1.1

Vargas (1948)

30

9

6.4

1.4

C. B. I. Vargas Esplanada (1961)

48

22

8.0

1.1

Vargas (1948)

13

20

4.8

0.5

Schultze (1962)

74

25

5.0

0.95

Schultze (1962)

52

20

4.6

0.8

Schultze (1962)

67

10

3.6

0.4

Sao Paulo, Brazil 4

Sao Paulo, Brazil 5

Riscala Sao Paulo, Brazil

6

Thyssen Dusseldorf, Germany

7

Ministry Dusseldorf, Germany

8

Chimney Cologne, Germany

NPTEL - ADVANCED FOUNDATION ENGINEERING-1 Table 2 Comparison of Settlements Observed and Calculated Case 1

๐‘†๐‘†๐‘’๐‘’calculated ๐‘†๐‘†๐‘’๐‘’observed

1

Maximum observed settlement, ๐‘†๐‘†๐‘’๐‘’ (in. ) 0.6

Calculated settlement, ๐‘†๐‘†๐‘’๐‘’ [equation (19)]

2

1.1

1.11

1.0

3

1.4

2.84

2.03

4

1.1

1.45

1.32

5

0.5

0.96

1.92

6

0.95

0.8

0.84

7

0.8

0.92

1.15

8

0.4

1.44

3.6

1.28

2.1

Refer to table 1

Table 3 Determination of Corrected Standard Penetration Resistance Depth ground (ft) 20

below Field standard ๐œŽ๐œŽ๐‘ฃ๐‘ฃโ€ฒ๐‘Ž๐‘Ž (ton/ft 2 ) surface penetration number, ๐‘๐‘๐น๐น 21

1.2

25

22

30

1 ๐ถ๐ถ๐‘๐‘ = ๏ฟฝ โ€ฒ ๐œŽ๐œŽ ๐›พ๐›พ

(๐‘๐‘)

๐‘๐‘๐‘๐‘๐‘๐‘๐‘๐‘ [equation chapter 2)]

0.91

19

1.5

0.82

18

21

1.8

0.75

16

35

15

2.1

0.69

10

40

20

2.4

0.65

13

45

18

2.7

0.61

11

50

50

3.0

0.58

29

๐œŽ๐œŽโ€ฒ๐‘ฃ๐‘ฃ = (depth); ๐›พ๐›พ = 120 lb/ft 3 (assumed) Table 4 from chapter 2

7

NPTEL - ADVANCED FOUNDATION ENGINEERING-1

Figure 5.6 Mean settlement at the south end of the mat foundation, as reported by Stuart and Graham (1975) COMPENSATED FOUNDATIONS The settlement of a mat foundation can be reduced by decreasing the net pressure increase on soil, which can be done by increasing the depth of embedment, ๐ท๐ท๐‘“๐‘“ . This increase is particularly important for mats on soft clays, where large consolidation settlements are expected. From equation (16), the net average applied pressure on soil is ๐‘„๐‘„

๐‘ž๐‘ž = ๐ด๐ด โˆ’ ๐›พ๐›พ๐ท๐ท๐‘“๐‘“

For no increase of the net soil pressure on soil below a raft foundation, ๐‘ž๐‘ž should be zero. Thus ๐‘„๐‘„

๐ท๐ท๐‘“๐‘“ = ๐ด๐ด๐ด๐ด

[5.21]

This relation for ๐ท๐ท๐‘“๐‘“ is usually referred to as the depth of a fully compensated foundation.

The factor of safety against bearing capacity failure for partially compensated foundations (that is, ๐ท๐ท๐‘“๐‘“ < ๐‘„๐‘„/๐ด๐ด๐ด๐ด) may be given as ๐น๐น๐น๐น =

๐‘ž๐‘ž net (๐ฎ๐ฎ) ๐‘ž๐‘ž

=

๐‘ž๐‘ž net (๐‘ข๐‘ข ) ๐‘„๐‘„ โˆ’๐›พ๐›พ๐ท๐ท๐‘“๐‘“ ๐ด๐ด

[5.22]

For saturated clays, the factor of safety against bearing capacity failure can thus be obtained by substituting equation (10) into equation (22): ๐น๐น๐น๐น =

๐ท๐ท ๐‘“๐‘“ 0.195 ๐ต๐ต ๏ฟฝ๏ฟฝ1+0.4 ๏ฟฝ ๐ฟ๐ฟ ๐ต๐ต ๐‘„๐‘„ โˆ’๐›พ๐›พ๐ท๐ท๐‘“๐‘“ ๐ด๐ด

5.14๏ฟฝ1+

[5.23]

NPTEL - ADVANCED FOUNDATION ENGINEERING-1 Example 3 Refer to figure 5.4. The mat has dimensions of 60 ft ร— 100 ft. The total dead and live load on the mat is 25 ร— 103 kip. The mat is placed over a saturated clay having a unit weight of 120 lb/ft 3 and ๐‘๐‘๐‘ข๐‘ข = 2800 lb/ft 2 . Given ๐ท๐ท๐‘“๐‘“ = 5 ft, determine the factor of safety against bearing capacity failure. Solution From equation (23), the factor of safety ๐น๐น๐น๐น =

๐ท๐ท ๐‘“๐‘“ 0.195 ๐ต๐ต ๏ฟฝ๏ฟฝ1+0.4 ๏ฟฝ ๐ฟ๐ฟ ๐ต๐ต ๐‘„๐‘„ โˆ’๐›พ๐›พ๐ท๐ท๐‘“๐‘“ ๐ด๐ด

5.14๐‘๐‘๐‘ข๐‘ข ๏ฟฝ1+

Given: ๐‘๐‘๐‘ข๐‘ข = 2800 lb/ft 2 , ๐ท๐ท๐‘“๐‘“ = 5 ft, ๐ต๐ต = 60 ft, ๐ฟ๐ฟ = 100 ft, and ๐›พ๐›พ = 120 lb/ft 3 . Hence ๐น๐น๐น๐น =

(0.195 )(60) 5 ๏ฟฝ๏ฟฝ1+0.4๏ฟฝ ๏ฟฝ๏ฟฝ 100 60 25 ร—10 6 lb ๏ฟฝ ๏ฟฝโˆ’(120)(5) 60 ร—100

(5.14)(2800 )๏ฟฝ1+

Example 4

= 4.66

Consider a mat foundation 90 ft ร— 120 ft in plan, as shown in figure 5.7. The total dead load and live load on the raft is 45 ร— 103 kip. Estimate the consolidation settlement at the center of the foundation.

Figure 5.7

NPTEL - ADVANCED FOUNDATION ENGINEERING-1

Solution From equation (64 from chapter 1) ๐ถ๐ถ ๐ป๐ป

๐‘๐‘ ๐‘œ๐‘œ +โˆ†๐‘๐‘ ๐‘Ž๐‘Ž๐‘Ž๐‘Ž

๐‘๐‘ ๐‘๐‘ ๐‘†๐‘†๐‘๐‘ = 1+๐‘’๐‘’ log ๏ฟฝ ๐‘œ๐‘œ

๐‘๐‘ ๐‘œ๐‘œ

๏ฟฝ

๐‘๐‘๐‘œ๐‘œ = (11)(100) + (40)(121.5 โˆ’ 62.4) + ๐ป๐ป๐‘๐‘ = 18 ร— 12 in.

18 2

(118 โˆ’ 62.4) โ‰ˆ 3964lb/ft 2

๐ถ๐ถ๐‘๐‘ = 0.28 ๐‘’๐‘’๐‘œ๐‘œ = 0.9

For ๐‘„๐‘„ = 45 ร— 106 lb, the net load per unit area 45ร—10 6

๐‘„๐‘„

๐‘ž๐‘ž = ๐ด๐ด โˆ’ ๐›พ๐›พ๐ท๐ท๐‘“๐‘“ = 90ร—120 โˆ’ (100)(6) โ‰ˆ 3567lb/ft 2

In order to calculate โˆ†๐‘๐‘๐‘Ž๐‘Ž๐‘Ž๐‘Ž , we refer to section 5. The loaded area can be divided into four areas, each measuring45 ft ร— 60 ft. Now using equation (19 from chapter 4), we can calculate the average stress increase in the clay layer below the corner of each rectangular area, or โˆ†๐‘๐‘๐‘Ž๐‘Ž๐‘Ž๐‘Ž(๐ป๐ป2 /๐ป๐ป1 ) = ๐‘ž๐‘ž ๏ฟฝ = 3567 ๏ฟฝ

๐ป๐ป2 ๐ผ๐ผ๐‘Ž๐‘Ž (๐ป๐ป 2 ) โˆ’๐ป๐ป1 ๐ผ๐ผ๐‘Ž๐‘Ž (๐ป๐ป 1 ) ๐ป๐ป2 โˆ’๐ป๐ป1

๏ฟฝ

(5+40+18)๐ผ๐ผ๐‘Ž๐‘Ž (๐ป๐ป 2 ) โˆ’(5+40)๐ผ๐ผ๐‘Ž๐‘Ž (๐ป๐ป 1 )

For ๐ผ๐ผ๐‘Ž๐‘Ž(๐ป๐ป2 ) , ๐ต๐ต

18

๏ฟฝ

45

๐‘š๐‘š = ๐ป๐ป = 5+40+18 = 0.71 ๐ฟ๐ฟ

2

60

๐‘›๐‘› = ๐ป๐ป = 63 = 0.95 2

From figure 5.8, for ๐‘š๐‘š = 0.71 and ๐‘›๐‘› = 0.95, the value of ๐ผ๐ผ๐‘Ž๐‘Ž(๐ป๐ป2 ) is 0.21. Again, for ๐ผ๐ผ๐‘Ž๐‘Ž(๐ป๐ป1 ) ,

NPTEL - ADVANCED FOUNDATION ENGINEERING-1

Figure 5.8 Conventional rigid mat foundation design

Fig 5.9 (Continued)

NPTEL - ADVANCED FOUNDATION ENGINEERING-1 ๐ต๐ต

45

๐‘š๐‘š = ๐ป๐ป = 45 = 1 ๐ฟ๐ฟ

1

60

๐‘›๐‘› = ๐ป๐ป = 45 = 1.33 1

From figure 5.8, ๐ผ๐ผ๐‘Ž๐‘Ž(๐ป๐ป1 ) = 0.225, so โˆ†๐‘๐‘๐‘Ž๐‘Ž๐‘Ž๐‘Ž(๐ป๐ป2 /๐ป๐ป1 ) = 3567 ๏ฟฝ

(63)(0.21)โˆ’(45)(0.225) 18

๏ฟฝ = 615.3 lb/ft 2

So, the stress increase below the center of the 90 ft ร— 120 ft area is (4)(615.3) = 2461.2 lb/ft 2 . Thus ๐‘†๐‘†๐‘๐‘ =

(0.28)(18ร—12) 1+0.9

3964+2461 .2

log ๏ฟฝ

3964

๏ฟฝ = 6.68 in.

View more...

Comments

Copyright ©2017 KUPDF Inc.
SUPPORT KUPDF