Laporan Mingguan Projek Pembinaan

April 23, 2017 | Author: Muhammad Farezon | Category: N/A
Share Embed Donate


Short Description

Contoh Laporan Pembinaan Mingguan untuk pelajar IPT...

Description

CADANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM BAHAGIAN PENCEGAHAN DAN PERUMAHAN DI TG. DAWAI, MERBOK, KEDAH

25 OKTOBER 2011 AGENSI PELAKSANA :

JABATAN KERJA RAYA MALAYSIA CAWANGAN PANGKALAN UDARA DAN MARITIM

PELANGGAN :

KEMENTERIAN KEWANGAN MALAYSIA

PENGGUNA :

JABATAN KASTAM DIRAJA MALAYSIA

CADANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM BAHAGIAN PENCEGAHAN DAN PERUMAHAN DI TG. DAWAI , MERBOK, KEDAH

KANDUNGAN LAPORAN MAKLUMAT KONTRAK STATUS KEMAJUAN FIZIKAL & KEWANGAN - SEHINGGA 25 OKTOBER 2011 S-CURVE FIZIKAL S-CURVE KEWANGAN KEMAJUAN KERJA SEHINGGA 25 OKTOBER 2011 KEMAJUAN KERJA SEHINGGA AKHIR OKTOBER 2011 BUTIRAN BAYARAN KEMAJUAN KEPADA KONTRAKTOR ISU / MASALAH & CADANGAN TINDAKAN PENYELESAIAN

KOS KERUGIAN & BAYARAN TAMBAHAN DISEBABKAN LANJUTAN MASA (EOT) GAMBAR KEMAJUAN

CADANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM BAHAGIAN PENCEGAHAN DAN PERUMAHAN DI TG. DAWAI , MERBOK, KEDAH

MAKLUMAT KONTRAK NAMA KONTRAKTOR

:

WIDAD BUILDERS SDN. BHD.

KELAS KONTRAKTOR

:

KELAS ‘A’ (BUMIPUTERA)

HARGA KONTRAK ASAL

:

RM 12,137,667.00

HARGA KONTRAK TERKINI

:

RM 11,853,377.70

TARIKH MILIK TAPAK

:

12 APRIL 2010

TARIKH SIAP KERJA

:

06 JUN 2011

TARIKH SIAP SEMASA

:

04 MAC 2012

TEMPOH LM NO. 2

:

13 MINGGU (90 hari) [Klausa 43.1 (e) Kelewatan memberi sebahagian milik Tapak Bina kepada kontraktor]

TEMPOH KONTRAK

:

99 MINGGU

TEMPOH LIABILITI KECACATAN

:

12 BULAN

CADANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM BAHAGIAN PENCEGAHAN DAN PERUMAHAN DI TG. DAWAI , MERBOK, 3 KEDAH

STATUS KEMAJUAN SEHINGGA 25 OKTOBER 2011 (Berdasarkan Revised CPM-EOT No.2)

KEMAJUAN FIZIKAL (KONTRAKTOR)

Jadual

52 %

Sebenar

55%

Kemajuan

+3%

CADANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM BAHAGIAN PENCEGAHAN DAN PERUMAHAN DI TG. DAWAI , MERBOK, KEDAH

S-CURVE FIZIKAL PEMBINAAN KOMPLEKS PENGKALAN KASTAM, TANJUNG DAWAI Physical S - Curve 100% 90% 80%

Percentage (%)

70% 60%

50% 40% 30% 20% 10% 0%

April

Mei

Jun

Julai

Ogos

Sep

Okt

Nov

Dis

Jan

Feb

Mac

April

Mei

Jun

Julai

Ogos

Sept

Okt

Nov

Dis

Jan

Feb

March

Kemajuan Jadual

0%

2%

4%

6%

8%

11%

13%

14%

16%

19%

21%

24%

26%

30%

33%

37%

42%

47%

54%

63%

78%

93%

99%

100%

Kemajuan Sebenar

0%

1%

2%

3%

3%

4%

6%

8%

11%

12%

16%

17%

20%

23%

27%

36%

43%

53%

Time/Month

CADANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM BAHAGIAN PENCEGAHAN DAN PERUMAHAN DI TG. DAWAI , MERBOK,

S-CURVE KEWANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM , TANJUNG DAWAI FINANCIAL S-CURVE 14,000,000.00 12,137,667.00 12,124,029.20 12,000,000.00 10,793,524.97 10,000,000.00

COST (RM)

8,409,877.32 8,000,000.00 6,645,541.76 5,954,523.99 6,000,000.00

4,000,000.00

2,000,000.00

-

Kemajuan Jadual Kemajuan Sebenar

5,172,354.58 5,568,215.08 4,768,216.07 4,752,397.79 3,994,612.86 4,030,559.49 2,962,872.50 2,766,522.86 2,633,381.01 2,575,800.78 3,224,489.49 2,518,587.60 2,461,613.70 2,398,950.63 2,257,141.23 2,047,837.68 1,513,170.25 2,137,380.30 1,862,070.30 1,835,070.30 1,829,220.30 1,821,920.30 1,815,020.30 1,802,420.30 923,532.07 481,844.47 1,042,220.30 264,891.44 - 91,594.59 649,320.30 462,320.00 227,920.00 159,420.30 4 5 85,820.00 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 -

10

11

12

1

2

3

91,59 264,8 481,8 923,5 1,513 2,047 2,257 2,398 2,461 2,518 2,575 2,633 2,766 2,962 3,994 4,768 5,172 5,954 6,645 8,409 10,79 12,12 12,13 85,82 159,4 227,9 462,3 649,3 1,042 1,802 1,815 1,821 1,829 1,835 1,862 2,137 3,224 4,030 4,752 5,568 TIME (MONTHS)

CADANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM BAHAGIAN PENCEGAHAN DAN PERUMAHAN DI TG. DAWAI , MERBOK, KEDAH

KEMAJUAN KERJA SEHINGGA 27 OKTOBER 2011 % Jadual (CPM)

% Sebenar

52%

55%

 Kerja Cerucuk (Bangunan)  Bangunan Pentadbiran  TNB ‘Sub – station’  Rumah Pam  Pondok Keselamatan

100% 100% 100% 100% 100%

100% 100% 100% 100% 100%

 Kerja Bangunan  Bangunan Pentadbiran  TNB ‘Sub – station’  Rumah Pam  Pondok Keselamatan

26% 21% 64% 30% 0%

25% 20% 62% 34% 1%

 Jeti  Jambatan Penghubung  Kepala Jeti  Production of Precast Component

69% 46% 26% 100%

71% 65% 22% 100%

Aktiviti

CADANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM BAHAGIAN PENCEGAHAN DAN PERUMAHAN DI TG. DAWAI , MERBOK, KEDAH

KEMAJUAN KERJA SEHINGGA 27 OKTOBER 2011 % Jadual (CPM)

% Sebenar

55%

52%

 Revetment

22%

30%

 Kerja Luar  Surface water drainage  Sewerage  External Water Reticulation  Roads and Car Park  Underground Fuel Tank  Turfing  Fencing and Gates

6% 14% 0% 0% 0% 17% 0% 8%

18% 32% 27% 0% 0% 13% 15% 25%

 Provisional Sum  Prime Cost Sum

0% 1%

0% 8%

Aktiviti

CADANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM BAHAGIAN PENCEGAHAN DAN PERUMAHAN DI TG. DAWAI , MERBOK, KEDAH

KEMAJUAN KERJA SEHINGGA 31 OKTOBER 2011 % Jadual (CPM)

% Sasaran

54%

56%

 Kerja Cerucuk (Bangunan)  Bangunan Pentadbiran  TNB ‘Sub – station’  Rumah Pam  Pondok Keselamatan

100% 100% 100% 100% 100%

100% 100% 100% 100% 100%

 Kerja Bangunan  Bangunan Pentadbiran  TNB ‘Sub – station’  Rumah Pam  Pondok Keselamatan

29% 22% 76% 34% 4%

35% 22% 80% 50% 9%

 Jeti  Jambatan Penghubung  Kepala Jeti  Production of Precast Component

71% 51% 28% 100%

75% 70% 36% 100%

Aktiviti

CADANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM BAHAGIAN PENCEGAHAN DAN PERUMAHAN DI TG. DAWAI , MERBOK, KEDAH

KEMAJUAN KERJA SEHINGGA 31 OKTOBER 2011 % Jadual (CPM)

% Sasaran

54%

56%

 Revetment

25%

50%

 Kerja Luar  Surface water drainage  Sewerage  External Water Reticulation  Roads and Car Park  Underground Fuel Tank  Turfing  Fencing and Gates

8% 14% 0% 0% 0% 30% 0% 12%

19% 30% 27% 0% 0% 55% 13% 23%

 Provisional Sum  Prime Cost Sum

0% 2%

0% 9%

Aktiviti

CADANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM BAHAGIAN PENCEGAHAN DAN PERUMAHAN DI TG. DAWAI , MERBOK, KEDAH

BUTIRAN BAYARAN KEMAJUAN KEPADA KONTRAKTOR No

Tarikh

Interim

Penilaian

Nilai Kerja Yang Dilaksanakan (RM) Nilai Kerja Dilaksanakan

%

Nilai Kerja Dilaksanakan

Bayaran Pendahuluan

Yang Perlu Dibayar Semasa Kumulatif (RM) (RM) (RM)

(RM)

LAD

Disyorkan

(RM)

Amaun Yang Diperakui

Bayaran

(RM)

Wang Tahanan 10% Semasa Kumulatif (RM)

(RM)

Kontraktor

(RM)

NSC

etc.

Bayaran

Bayaran

Date &

Bayaran

Yang Diperakukan

Diperakukan (Kumulatif)

Voucher No

Diterima

(RM)

(RM)

14.7.2010

77,238.27

1

27.5.2010

85,820.30 0.41%

85,820.30

85,820.30

8,582.03 8,582.03

77,238.27

85,820.30

85,820.30

2

21.6.2010

159,516.00 0.77%

82,277.73

73,695.70

7,360.00 15,942.03

66,240.00

73,600.00

159,420.30

17.7.2010 66,240.00

3

27.7.2010

227,957.90 1.10%

84,479.63

68,537.60

6,850.00 22,792.03

61,650.00

68,500.00

227,920.30

4.3.2010

61,650.00

4

9.8.2010

338,247.26

1.63%

133,118.99

110,326.96

11,030.00 33,822.03

99,270.00

110,300.00

338,220.30

1.9.2010

99,270.00

5

23.8.2010

473,404.01

2.29%

157,975.74

124,153.71

12,410.00 46,232.03

111,690.00

124,100.00

462,320.30

7.9.2010

111,690.00

6

27.9.2010

672,859.70

3.25%

245,741.43

199,509.40

18,700.00 64,932.03

168,300.00

187,000.00

649,320.30

15.10.2010

168,300.00

7

25.10.2010

1,053,329.14

5.09%

468,940.87

404,008.84

39,290.00 104,222.03

353,610.00

392,900.00

1,042,220.30

18.11.2010

353,610.00

8

14.11.2010

1,473,580.58

7.12%

535,582.31

431,360.28

43,130.00 147,352.03

388,170.00

431,300.00

1,473,520.30

1.12.2010

388,170.00

9

24.11.2010

1,802,512.58

8.71%

476,344.31

328,992.28

32,890.00 180,242.03

296,010.00

328,900.00

1,802,420.30

9.12.2010

296,010.00

10

22.12.2010

1,815,084.02

8.77%

192,905.75

12,663.72

1,260.00 181,502.03

11,340.00

12,600.00

1,815,020.30

26.1.2011

11,340.00

11

24.1.2011

1,821,985.46

8.80%

188,467.19

6,965.16

690.00 182,192.03

6,210.00

6,900.00

1,821,920.30

17.03.2011

6,210.00

12

22.2.2011

1,829,306.90

8.84%

189,578.63

7,386.60

730.00 182,922.03

6,570.00

7,300.00

1,829,220.30

17.3.2011

6,570.00

13

25.3.2011

1,881,590.09

9.09%

235,291.82

52,369.79

650.00 183,572.03

5,850.00

6,500.00

1,835,720.30

25.4.2011

5,850.00

14

21.4.2011

1,996,032.59

9.64%

343,884.32

160,312.29

3,000.00

186,572.03

27,000.00

30,000.00

1,865,720.30

04.05.2011

27,000.00

15

23.5.2011

2,171,669.35

10.49%

492,521.08

305,949.05

30,590.00

217,162.03

275,310.00

305,900.00

2,171,620.30

15.04.2011

275,310.00

16

20.06.2011

2,557,403.90 12.35%

602,945.63

385,783.60

38,570.00

255,732.03

347,130.00

385,700.00

2,557,320.30

11.07.2011

347,130.00

17

06.07.2011

3,229,962.88 15.60%

928,374.61

672,642.58

67,260.00

322,992.03

605,340.00

672,600.00

3,229,920.30

19.07.2011

605,340.00

18

27.07.2011

19.50%

1,129,142.82

806,150.79

80,610.00

403,602.03

725,490.00

806,100.00

4,036,020.30

08.08.2011

725,490.00

19

15.08.2011

4,752,397.79 22.96%

1,119,979.52

716,377.49

71,630.00

475,232.03

644,670.00

716,300.00

4,752,320.30

25.08.2011

644,670.00

20

26.09.2011

1,291,126.81

815,894.78

81,580.00

734,220.00

815,800.00

5,568,120.30

12.10.2011

734,220.00

4,036,071.09

5,568,215.08

26.90%

556,812.03

556,812.03

5,011,308.27

5,568,120.30

5,011,308.27

CADANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM BAHAGIAN PENCEGAHAN DAN PERUMAHAN DI TG. DAWAI , MERBOK, KEDAH

ISU & MASALAH Kelewatan Pemilikan Sepenuhnya Tapak Bina (Pemindahan Jeti Nelayan) • Terdapat sembilan (9) buah jeti nelayan sedia ada di tapak cadangan jeti yang menghalang kerja pembinaan • Pembayaran Pampasan kepada pemilik jeti nelayan diselesaikan pada bulan April 2011. Namun terdapat sebuah jeti yang tetap tidak memindahkan operasi. • Pemindahan sepenuhnya jeti nelayan hanya berlaku dalam bulan Jun 2011. • Kerja – kerja jeti dan ‘revetment’ hanya dapat dimulakan pada bulan Jun 2011. Jadual sebenar (LM 01) kerja tersebut bermula pada 24 Feb. 2011

TINDAKAN/ PENYELESAIAN Perakuan Kelambatan dan Lanjutan Masa

• Lanjutan masa 01 telah diberikan selama 182 hari dan lanjutan masa 02 selama 90 hari berdasarkan klausa 43.1(e).

CADANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM BAHAGIAN PENCEGAHAN DAN PERUMAHAN DI TG. DAWAI , MERBOK, KEDAH

KOS KERUGIAN & BAYARAN TAMBAHAN DISEBABKAN LANJUTAN MASA (EOT)  JKR Kedah (P.P) telah terima Notis Niat Menuntut Kos Kerugian dan Bayaran (Claim for Loss and Expenses) dari pihak kontraktor dan tuntutan tersebut di dalam semakan Bahagian Kontrak dan Ukur Bahan JKR Negeri Kedah.

CADANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM BAHAGIAN PENCEGAHAN DAN PERUMAHAN DI TG. DAWAI , MERBOK, KEDAH

GAMBAR KEMAJUAN

BANGUNAN PENTADBIRAN

12 OKTOBER 2011

25 OKTOBER 2011

CADANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM BAHAGIAN PENCEGAHAN DAN PERUMAHAN DI TG. DAWAI , MERBOK, 14 KEDAH

GAMBAR KEMAJUAN

TNB SUB STATION

07 SEPTEMBER 2011

25 OKTOBER 2011

CADANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM BAHAGIAN PENCEGAHAN DAN PERUMAHAN DI TG. DAWAI , MERBOK, KEDAH

GAMBAR KEMAJUAN

RUMAH PAM

13 OKTOBER 2011

25 OKTOBER 2011

CADANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM BAHAGIAN PENCEGAHAN DAN PERUMAHAN DI TG. DAWAI , MERBOK, 16 KEDAH

GAMBAR KEMAJUAN

JETI

10 SEPTEMBER 2011

25 OKTOBER 2011

CADANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM BAHAGIAN PENCEGAHAN DAN PERUMAHAN DI TG. DAWAI , MERBOK, 17 KEDAH

GAMBAR KEMAJUAN

LONGKANG

01 OKTOBER 2011

25 OKTOBER 2011

CADANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM BAHAGIAN PENCEGAHAN DAN PERUMAHAN DI TG. DAWAI , MERBOK, KEDAH

18

GAMBAR KEMAJUAN

DETENTION PONDS

12 OKTOBER 2011

25 OKTOBER 2011

CADANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM BAHAGIAN PENCEGAHAN DAN PERUMAHAN DI TG. DAWAI , MERBOK, KEDAH

19

GAMBAR KEMAJUAN

SEWERAGE

12 OKTOBER 2011

25 OKTOBER 2011

CADANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM BAHAGIAN PENCEGAHAN DAN PERUMAHAN DI TG. DAWAI , MERBOK, KEDAH

20

GAMBAR KEMAJUAN

FENCING & GATES

12 OKTOBER 2011

25 OKTOBER 2011

CADANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM BAHAGIAN PENCEGAHAN DAN PERUMAHAN DI TG. DAWAI , MERBOK, KEDAH

21

GAMBAR KEMAJUAN

FUEL DISPENSER

25 OKTOBER 2011

CADANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM BAHAGIAN PENCEGAHAN DAN PERUMAHAN DI TG. DAWAI , MERBOK, KEDAH

22

CADANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM BAHAGIAN PENCEGAHAN DAN PERUMAHAN DI TG. DAWAI , MERBOK, 23 KEDAH

View more...