Laporan Mingguan Projek Pembinaan
April 23, 2017 | Author: Muhammad Farezon | Category: N/A
Short Description
Contoh Laporan Pembinaan Mingguan untuk pelajar IPT...
Description
CADANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM BAHAGIAN PENCEGAHAN DAN PERUMAHAN DI TG. DAWAI, MERBOK, KEDAH
25 OKTOBER 2011 AGENSI PELAKSANA :
JABATAN KERJA RAYA MALAYSIA CAWANGAN PANGKALAN UDARA DAN MARITIM
PELANGGAN :
KEMENTERIAN KEWANGAN MALAYSIA
PENGGUNA :
JABATAN KASTAM DIRAJA MALAYSIA
CADANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM BAHAGIAN PENCEGAHAN DAN PERUMAHAN DI TG. DAWAI , MERBOK, KEDAH
KANDUNGAN LAPORAN MAKLUMAT KONTRAK STATUS KEMAJUAN FIZIKAL & KEWANGAN - SEHINGGA 25 OKTOBER 2011 S-CURVE FIZIKAL S-CURVE KEWANGAN KEMAJUAN KERJA SEHINGGA 25 OKTOBER 2011 KEMAJUAN KERJA SEHINGGA AKHIR OKTOBER 2011 BUTIRAN BAYARAN KEMAJUAN KEPADA KONTRAKTOR ISU / MASALAH & CADANGAN TINDAKAN PENYELESAIAN
KOS KERUGIAN & BAYARAN TAMBAHAN DISEBABKAN LANJUTAN MASA (EOT) GAMBAR KEMAJUAN
CADANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM BAHAGIAN PENCEGAHAN DAN PERUMAHAN DI TG. DAWAI , MERBOK, KEDAH
MAKLUMAT KONTRAK NAMA KONTRAKTOR
:
WIDAD BUILDERS SDN. BHD.
KELAS KONTRAKTOR
:
KELAS ‘A’ (BUMIPUTERA)
HARGA KONTRAK ASAL
:
RM 12,137,667.00
HARGA KONTRAK TERKINI
:
RM 11,853,377.70
TARIKH MILIK TAPAK
:
12 APRIL 2010
TARIKH SIAP KERJA
:
06 JUN 2011
TARIKH SIAP SEMASA
:
04 MAC 2012
TEMPOH LM NO. 2
:
13 MINGGU (90 hari) [Klausa 43.1 (e) Kelewatan memberi sebahagian milik Tapak Bina kepada kontraktor]
TEMPOH KONTRAK
:
99 MINGGU
TEMPOH LIABILITI KECACATAN
:
12 BULAN
CADANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM BAHAGIAN PENCEGAHAN DAN PERUMAHAN DI TG. DAWAI , MERBOK, 3 KEDAH
STATUS KEMAJUAN SEHINGGA 25 OKTOBER 2011 (Berdasarkan Revised CPM-EOT No.2)
KEMAJUAN FIZIKAL (KONTRAKTOR)
Jadual
52 %
Sebenar
55%
Kemajuan
+3%
CADANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM BAHAGIAN PENCEGAHAN DAN PERUMAHAN DI TG. DAWAI , MERBOK, KEDAH
S-CURVE FIZIKAL PEMBINAAN KOMPLEKS PENGKALAN KASTAM, TANJUNG DAWAI Physical S - Curve 100% 90% 80%
Percentage (%)
70% 60%
50% 40% 30% 20% 10% 0%
April
Mei
Jun
Julai
Ogos
Sep
Okt
Nov
Dis
Jan
Feb
Mac
April
Mei
Jun
Julai
Ogos
Sept
Okt
Nov
Dis
Jan
Feb
March
Kemajuan Jadual
0%
2%
4%
6%
8%
11%
13%
14%
16%
19%
21%
24%
26%
30%
33%
37%
42%
47%
54%
63%
78%
93%
99%
100%
Kemajuan Sebenar
0%
1%
2%
3%
3%
4%
6%
8%
11%
12%
16%
17%
20%
23%
27%
36%
43%
53%
Time/Month
CADANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM BAHAGIAN PENCEGAHAN DAN PERUMAHAN DI TG. DAWAI , MERBOK,
S-CURVE KEWANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM , TANJUNG DAWAI FINANCIAL S-CURVE 14,000,000.00 12,137,667.00 12,124,029.20 12,000,000.00 10,793,524.97 10,000,000.00
COST (RM)
8,409,877.32 8,000,000.00 6,645,541.76 5,954,523.99 6,000,000.00
4,000,000.00
2,000,000.00
-
Kemajuan Jadual Kemajuan Sebenar
5,172,354.58 5,568,215.08 4,768,216.07 4,752,397.79 3,994,612.86 4,030,559.49 2,962,872.50 2,766,522.86 2,633,381.01 2,575,800.78 3,224,489.49 2,518,587.60 2,461,613.70 2,398,950.63 2,257,141.23 2,047,837.68 1,513,170.25 2,137,380.30 1,862,070.30 1,835,070.30 1,829,220.30 1,821,920.30 1,815,020.30 1,802,420.30 923,532.07 481,844.47 1,042,220.30 264,891.44 - 91,594.59 649,320.30 462,320.00 227,920.00 159,420.30 4 5 85,820.00 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 -
10
11
12
1
2
3
91,59 264,8 481,8 923,5 1,513 2,047 2,257 2,398 2,461 2,518 2,575 2,633 2,766 2,962 3,994 4,768 5,172 5,954 6,645 8,409 10,79 12,12 12,13 85,82 159,4 227,9 462,3 649,3 1,042 1,802 1,815 1,821 1,829 1,835 1,862 2,137 3,224 4,030 4,752 5,568 TIME (MONTHS)
CADANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM BAHAGIAN PENCEGAHAN DAN PERUMAHAN DI TG. DAWAI , MERBOK, KEDAH
KEMAJUAN KERJA SEHINGGA 27 OKTOBER 2011 % Jadual (CPM)
% Sebenar
52%
55%
Kerja Cerucuk (Bangunan) Bangunan Pentadbiran TNB ‘Sub – station’ Rumah Pam Pondok Keselamatan
100% 100% 100% 100% 100%
100% 100% 100% 100% 100%
Kerja Bangunan Bangunan Pentadbiran TNB ‘Sub – station’ Rumah Pam Pondok Keselamatan
26% 21% 64% 30% 0%
25% 20% 62% 34% 1%
Jeti Jambatan Penghubung Kepala Jeti Production of Precast Component
69% 46% 26% 100%
71% 65% 22% 100%
Aktiviti
CADANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM BAHAGIAN PENCEGAHAN DAN PERUMAHAN DI TG. DAWAI , MERBOK, KEDAH
KEMAJUAN KERJA SEHINGGA 27 OKTOBER 2011 % Jadual (CPM)
% Sebenar
55%
52%
Revetment
22%
30%
Kerja Luar Surface water drainage Sewerage External Water Reticulation Roads and Car Park Underground Fuel Tank Turfing Fencing and Gates
6% 14% 0% 0% 0% 17% 0% 8%
18% 32% 27% 0% 0% 13% 15% 25%
Provisional Sum Prime Cost Sum
0% 1%
0% 8%
Aktiviti
CADANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM BAHAGIAN PENCEGAHAN DAN PERUMAHAN DI TG. DAWAI , MERBOK, KEDAH
KEMAJUAN KERJA SEHINGGA 31 OKTOBER 2011 % Jadual (CPM)
% Sasaran
54%
56%
Kerja Cerucuk (Bangunan) Bangunan Pentadbiran TNB ‘Sub – station’ Rumah Pam Pondok Keselamatan
100% 100% 100% 100% 100%
100% 100% 100% 100% 100%
Kerja Bangunan Bangunan Pentadbiran TNB ‘Sub – station’ Rumah Pam Pondok Keselamatan
29% 22% 76% 34% 4%
35% 22% 80% 50% 9%
Jeti Jambatan Penghubung Kepala Jeti Production of Precast Component
71% 51% 28% 100%
75% 70% 36% 100%
Aktiviti
CADANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM BAHAGIAN PENCEGAHAN DAN PERUMAHAN DI TG. DAWAI , MERBOK, KEDAH
KEMAJUAN KERJA SEHINGGA 31 OKTOBER 2011 % Jadual (CPM)
% Sasaran
54%
56%
Revetment
25%
50%
Kerja Luar Surface water drainage Sewerage External Water Reticulation Roads and Car Park Underground Fuel Tank Turfing Fencing and Gates
8% 14% 0% 0% 0% 30% 0% 12%
19% 30% 27% 0% 0% 55% 13% 23%
Provisional Sum Prime Cost Sum
0% 2%
0% 9%
Aktiviti
CADANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM BAHAGIAN PENCEGAHAN DAN PERUMAHAN DI TG. DAWAI , MERBOK, KEDAH
BUTIRAN BAYARAN KEMAJUAN KEPADA KONTRAKTOR No
Tarikh
Interim
Penilaian
Nilai Kerja Yang Dilaksanakan (RM) Nilai Kerja Dilaksanakan
%
Nilai Kerja Dilaksanakan
Bayaran Pendahuluan
Yang Perlu Dibayar Semasa Kumulatif (RM) (RM) (RM)
(RM)
LAD
Disyorkan
(RM)
Amaun Yang Diperakui
Bayaran
(RM)
Wang Tahanan 10% Semasa Kumulatif (RM)
(RM)
Kontraktor
(RM)
NSC
etc.
Bayaran
Bayaran
Date &
Bayaran
Yang Diperakukan
Diperakukan (Kumulatif)
Voucher No
Diterima
(RM)
(RM)
14.7.2010
77,238.27
1
27.5.2010
85,820.30 0.41%
85,820.30
85,820.30
8,582.03 8,582.03
77,238.27
85,820.30
85,820.30
2
21.6.2010
159,516.00 0.77%
82,277.73
73,695.70
7,360.00 15,942.03
66,240.00
73,600.00
159,420.30
17.7.2010 66,240.00
3
27.7.2010
227,957.90 1.10%
84,479.63
68,537.60
6,850.00 22,792.03
61,650.00
68,500.00
227,920.30
4.3.2010
61,650.00
4
9.8.2010
338,247.26
1.63%
133,118.99
110,326.96
11,030.00 33,822.03
99,270.00
110,300.00
338,220.30
1.9.2010
99,270.00
5
23.8.2010
473,404.01
2.29%
157,975.74
124,153.71
12,410.00 46,232.03
111,690.00
124,100.00
462,320.30
7.9.2010
111,690.00
6
27.9.2010
672,859.70
3.25%
245,741.43
199,509.40
18,700.00 64,932.03
168,300.00
187,000.00
649,320.30
15.10.2010
168,300.00
7
25.10.2010
1,053,329.14
5.09%
468,940.87
404,008.84
39,290.00 104,222.03
353,610.00
392,900.00
1,042,220.30
18.11.2010
353,610.00
8
14.11.2010
1,473,580.58
7.12%
535,582.31
431,360.28
43,130.00 147,352.03
388,170.00
431,300.00
1,473,520.30
1.12.2010
388,170.00
9
24.11.2010
1,802,512.58
8.71%
476,344.31
328,992.28
32,890.00 180,242.03
296,010.00
328,900.00
1,802,420.30
9.12.2010
296,010.00
10
22.12.2010
1,815,084.02
8.77%
192,905.75
12,663.72
1,260.00 181,502.03
11,340.00
12,600.00
1,815,020.30
26.1.2011
11,340.00
11
24.1.2011
1,821,985.46
8.80%
188,467.19
6,965.16
690.00 182,192.03
6,210.00
6,900.00
1,821,920.30
17.03.2011
6,210.00
12
22.2.2011
1,829,306.90
8.84%
189,578.63
7,386.60
730.00 182,922.03
6,570.00
7,300.00
1,829,220.30
17.3.2011
6,570.00
13
25.3.2011
1,881,590.09
9.09%
235,291.82
52,369.79
650.00 183,572.03
5,850.00
6,500.00
1,835,720.30
25.4.2011
5,850.00
14
21.4.2011
1,996,032.59
9.64%
343,884.32
160,312.29
3,000.00
186,572.03
27,000.00
30,000.00
1,865,720.30
04.05.2011
27,000.00
15
23.5.2011
2,171,669.35
10.49%
492,521.08
305,949.05
30,590.00
217,162.03
275,310.00
305,900.00
2,171,620.30
15.04.2011
275,310.00
16
20.06.2011
2,557,403.90 12.35%
602,945.63
385,783.60
38,570.00
255,732.03
347,130.00
385,700.00
2,557,320.30
11.07.2011
347,130.00
17
06.07.2011
3,229,962.88 15.60%
928,374.61
672,642.58
67,260.00
322,992.03
605,340.00
672,600.00
3,229,920.30
19.07.2011
605,340.00
18
27.07.2011
19.50%
1,129,142.82
806,150.79
80,610.00
403,602.03
725,490.00
806,100.00
4,036,020.30
08.08.2011
725,490.00
19
15.08.2011
4,752,397.79 22.96%
1,119,979.52
716,377.49
71,630.00
475,232.03
644,670.00
716,300.00
4,752,320.30
25.08.2011
644,670.00
20
26.09.2011
1,291,126.81
815,894.78
81,580.00
734,220.00
815,800.00
5,568,120.30
12.10.2011
734,220.00
4,036,071.09
5,568,215.08
26.90%
556,812.03
556,812.03
5,011,308.27
5,568,120.30
5,011,308.27
CADANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM BAHAGIAN PENCEGAHAN DAN PERUMAHAN DI TG. DAWAI , MERBOK, KEDAH
ISU & MASALAH Kelewatan Pemilikan Sepenuhnya Tapak Bina (Pemindahan Jeti Nelayan) • Terdapat sembilan (9) buah jeti nelayan sedia ada di tapak cadangan jeti yang menghalang kerja pembinaan • Pembayaran Pampasan kepada pemilik jeti nelayan diselesaikan pada bulan April 2011. Namun terdapat sebuah jeti yang tetap tidak memindahkan operasi. • Pemindahan sepenuhnya jeti nelayan hanya berlaku dalam bulan Jun 2011. • Kerja – kerja jeti dan ‘revetment’ hanya dapat dimulakan pada bulan Jun 2011. Jadual sebenar (LM 01) kerja tersebut bermula pada 24 Feb. 2011
TINDAKAN/ PENYELESAIAN Perakuan Kelambatan dan Lanjutan Masa
• Lanjutan masa 01 telah diberikan selama 182 hari dan lanjutan masa 02 selama 90 hari berdasarkan klausa 43.1(e).
CADANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM BAHAGIAN PENCEGAHAN DAN PERUMAHAN DI TG. DAWAI , MERBOK, KEDAH
KOS KERUGIAN & BAYARAN TAMBAHAN DISEBABKAN LANJUTAN MASA (EOT) JKR Kedah (P.P) telah terima Notis Niat Menuntut Kos Kerugian dan Bayaran (Claim for Loss and Expenses) dari pihak kontraktor dan tuntutan tersebut di dalam semakan Bahagian Kontrak dan Ukur Bahan JKR Negeri Kedah.
CADANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM BAHAGIAN PENCEGAHAN DAN PERUMAHAN DI TG. DAWAI , MERBOK, KEDAH
GAMBAR KEMAJUAN
BANGUNAN PENTADBIRAN
12 OKTOBER 2011
25 OKTOBER 2011
CADANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM BAHAGIAN PENCEGAHAN DAN PERUMAHAN DI TG. DAWAI , MERBOK, 14 KEDAH
GAMBAR KEMAJUAN
TNB SUB STATION
07 SEPTEMBER 2011
25 OKTOBER 2011
CADANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM BAHAGIAN PENCEGAHAN DAN PERUMAHAN DI TG. DAWAI , MERBOK, KEDAH
GAMBAR KEMAJUAN
RUMAH PAM
13 OKTOBER 2011
25 OKTOBER 2011
CADANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM BAHAGIAN PENCEGAHAN DAN PERUMAHAN DI TG. DAWAI , MERBOK, 16 KEDAH
GAMBAR KEMAJUAN
JETI
10 SEPTEMBER 2011
25 OKTOBER 2011
CADANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM BAHAGIAN PENCEGAHAN DAN PERUMAHAN DI TG. DAWAI , MERBOK, 17 KEDAH
GAMBAR KEMAJUAN
LONGKANG
01 OKTOBER 2011
25 OKTOBER 2011
CADANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM BAHAGIAN PENCEGAHAN DAN PERUMAHAN DI TG. DAWAI , MERBOK, KEDAH
18
GAMBAR KEMAJUAN
DETENTION PONDS
12 OKTOBER 2011
25 OKTOBER 2011
CADANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM BAHAGIAN PENCEGAHAN DAN PERUMAHAN DI TG. DAWAI , MERBOK, KEDAH
19
GAMBAR KEMAJUAN
SEWERAGE
12 OKTOBER 2011
25 OKTOBER 2011
CADANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM BAHAGIAN PENCEGAHAN DAN PERUMAHAN DI TG. DAWAI , MERBOK, KEDAH
20
GAMBAR KEMAJUAN
FENCING & GATES
12 OKTOBER 2011
25 OKTOBER 2011
CADANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM BAHAGIAN PENCEGAHAN DAN PERUMAHAN DI TG. DAWAI , MERBOK, KEDAH
21
GAMBAR KEMAJUAN
FUEL DISPENSER
25 OKTOBER 2011
CADANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM BAHAGIAN PENCEGAHAN DAN PERUMAHAN DI TG. DAWAI , MERBOK, KEDAH
22
CADANGAN PEMBINAAN KOMPLEKS PANGKALAN KASTAM BAHAGIAN PENCEGAHAN DAN PERUMAHAN DI TG. DAWAI , MERBOK, 23 KEDAH
View more...