Labor and material productivity

1

Labor and material productivity Labor and material productivity, including labor output and material output norms, is about standard output norms related to building construction precisely for labor and material. This article is useful for construction/project manager, planning engineer and all those related directly or indirectly to project planning and management. These norms are calculated and referred from below mentioned reliable sources. As output of Labor and material varies with geographical locations across globe, these norms are more suitable for Indian scenario. These norms can certainly prove handy to project planning and management (PPM) personnel as they can use it for performing Labor requirement calculation, material requirement calculation (of building projects) and for cross checking the existing daily progress report (DPR) of their site to know how good the Labor and material is performing. How to use these norms? As the existing page layout allows only vertical typing, sorting of norms are done with each head in bold letters and then subsequently its related data. The norms are mentioned below: Oct, 2009 I] FORMWORK / SHUTTERING Activity

TASKS

Task – UOM Labor (L) – Carpenter (Mandays)

Labor (L) – Helper (Mandays)

Material (M)

Material (M)

Material (M)

Footing formwork

Footing – Shuttering & Providing Support

Sqm

0.8 Mandays/10Sqm

1.5 Mandays/10Sqm

MS Wall Form Panel – 1250 x 500 : 16Nos/10Sqm

Props – 2m to 3m Long : 2 Nos/Rm

Shuttering Oil : 4Ltr/10Sqm

Footing – Deshuttering & insitu Stacking

Sqm

0.48 Mandays/10Sqm

0.9 Mandays/10Sqm

Raft – Shuttering & Providing Support

Sqm

0.71 Mandays/10Sqm

1.41 Mandays/10Sqm

MS Wall Form Panel – 1250 x 500 : 16Nos/10Sqm

Props – 2m to 3m Long : 2 Nos/Rm

Shuttering Oil : 4Ltr/10Sqm

Raft – Deshuttering & insitu Stacking

Sqm

0.42 Mandays/10Sqm

0.84 Mandays/10Sqm

Walls (Any Thickness), Including Buttresses – Shuttering & Providing Support – Up to 3.5m Height

Sqm

2.22 2.64 MS Wall Form Panel Mandays/10Sqm(Including Mandays/10Sqm(Including – 1250 x 500 – 32 Both Sides) Both Sides) Nos/10Sqm(Including Both Sides)

Walls – Deshuttering & insitu Stacking

Sqm

1.32 1.76 Mandays/10Sqm(Including Mandays/10Sqm(Including Both Sides) Both Sides)

Raft formwork

Walls formwork

Props – 2m to 3m Shuttering Oil : Long : 5Ltr/10Sqm(On 4Nos/Rm(Including One Side) Both Sides)

Labor and material productivity

Staircase formwork

Staircase (Excluding Spiral Staircase) – Shuttering & Providing Support

2

Sqm

0.23 Mandays/Sqm

0.46 Mandays/Sqm

Staircase Sqm (Excluding Spiral Staircase) – Deshuttering & Stacking Appropriately at Same Location

0.14 Mandays/Sqm

0.28 Mandays/Sqm

Ramp formwork

Ramp – Shuttering & Providing Support

Sqm

0.22 Mandays/Sqm

0.44 Mandays/Sqm

MS Floor Form Panel MS Floor Form Adjustable – 750 x 600 – Panel – 1250 x 500 Props – 2.02m 13.3Nos/10Sqm : 6.4Nos/10Sqm to 3.75 m : 2Nos/Sqm and Shuttering Oil : 5Ltr/10Sqm

Ramp – Deshuttering & Stacking Appropriately at Same Location

Sqm

0.13 0.26 Mandays/Sqm Mandays/Sqm

Shades Formwork

Weather Shade, Chajjas, Corbels Shuttering (Including Propping)

Sqm

0.14 Mandays/Sqm

MS Floor Form Panel Adjustable Props – – 750 x 600 – 2.02m to 3.75 m : 2.2Nos/Sqm 2Nos/Sqm

Weather Shade, Sqm Chajjas, Corbels – Deshuttering & Stacking Appropriately at Same Location

0.12 Mandays/Sqm

0.07 0.08 Mandays/Sqm Mandays/Sqm

MS Floor Form Panel Adjustable Props – – 750 x 600 – 2.02m to 3.75 m : 2.2Nos/Sqm 2Nos/Sqm

Shuttering Oil : 5Ltr/10Sqm

Shuttering Oil : 0.3Ltr/Sqm

Labor and material productivity

3

II] Reinforcement Activity

TASKS

Footing Reinforcement

Foot Rein – Placing in Position Mt & Binding – Using TMT Bars, Mild Steel, Tor Steel

0.28 Mandays/0.1Mt 0.38 Mandays/0.1Mt

Bars – Binding Wire Cover Blocks Include 5% : 5 kg/0.1Mt – 10No/0.1Mt Wastage

Foot Rein – Straightening, Cutting (With Machine Cutting), bending – Using TMT Bars, Mild Steel, Tor Steel

Mt

0.2 Mandays/0.1Mt

0.28 Mandays/0.1Mt

Bars – Include 5% Wastage

Foot Rein – Straightening, Cutting (With Manual Cutting), bending – Using TMT Bars, Mild Steel, Tor Steel

Mt

0.29 Mandays/0.1Mt 0.32 Mandays/0.1Mt

Bars – Include 5% Wastage

Walls Rein – Placing in Position & Binding – Using TMT Bars, Mild Steel, Tor Steel

Mt

0.41 Mandays/0.1Mt 0.45 Mandays/0.1Mt

Bars – Binding Wire Cover Blocks Include 5% : 5 kg/0.1Mt – 10No/0.1Mt Wastage

Walls Rein – Straightening, Cutting (With Machine Cutting), bending – Using TMT Bars, Mild Steel, Tor Steel.

Mt

0.2 Mandays/0.1Mt

0.28 Mandays/0.1Mt

Bars – Include 5% Wastage

Walls Rein – Straightening, Cutting (With Manual Cutting), bending – Using TMT Bars, Mild Steel, Tor Steel.

Mt

0.39 Mandays/0.1Mt 0.43 Mandays/0.1Mt

Bars – Include 5% Wastage

Walls Rein – Stirrups Cutting and Bending

Mt

0.47 Mandays/0.1Mt 0.5 Mandays/0.1Mt

Bars – Include 5% Wastage

Walls Rein – Stirrups Teing

Mt

0.55 Mandays/0.1Mt 0.57 Mandays/0.1Mt

Bars – Include 5% Wastage

Staircase Rein – Placing in Position & Binding – Using TMT Bars, Mild Steel, Tor Steel

Mt

0.32 Mandays/0.1Mt 0.34 Mandays/0.1Mt

Bars – Binding Wire Cover Blocks Include 5% : 5 kg/0.1Mt – 10No/0.1Mt Wastage

Staircase Rein – Straightening, Mt Cutting (With Machine Cutting), bending – Using TMT Bars, Mild Steel, Tor Steel.

0.2 Mandays/0.1Mt

0.28 Mandays/0.1Mt

Bars – Include 5% Wastage

Staircase Rein- Straightening, Cutting (With Manual Cutting), bending – Using TMT Bars, Mild Steel, Tor Steel.

0.29 Mandays/0.1Mt 0.32 Mandays/0.1Mt

Bars – Include 5% Wastage

Walls Reinforcement

Staircase Reinforcement

Task – L – UOM Barbender/Fitter (Mandays)

Mt

L – Helper (Mandays)

M

M

M

Labor and material productivity Further details of labor and material output norms of formwork, reinforcement and other important works like earthwork, concreting, brickwork, blockwork, plastering, pointing, painting, flooring, stone work, marble work, wood work and dismantling works are being calculated and will be posted here very soon.

References • • • •

Practical Information for Quantity Surveyors – By Late P. T. Joglekar (Edition: May, 2007) CPWD – Analysis of Rates – Vol II – Sub-Head 04 and 05 – By CPWD (Edition:1997) Estimation and Costing – By B. N. Dutta (Edition:2004) A to Z of Civil Engineering – Theory & Practice – By Mantri (Edition:2005)

External links • www.planningplanet.com [1]

References [1] http:/ / www. planningplanet. com/ index. asp

4

Article Sources and Contributors

Article Sources and Contributors Labor and material productivity  Source: http://en.wikipedia.org/w/index.php?oldid=518534727  Contributors: Autoerrant, Ben Ben, DoctorKubla, Ekabhishek, Fabrictramp, Katharineamy, Malcolma, Nihiltres, RHaworth, RJFJR, Rich Farmbrough, Saini.sukh, Signalhead, Tony1, Topbanana, Woohookitty

License Creative Commons Attribution-Share Alike 3.0 Unported //creativecommons.org/licenses/by-sa/3.0/

5

View more...

Comments

Copyright ©2017 KUPDF Inc.
SUPPORT KUPDF