Labor and Material Productivity
Short Description
Labor and material productivity...
Description
Labor and material productivity
1
Labor and material productivity Labor and material productivity, including labor output and material output norms, is about standard output norms related to building construction precisely for labor and material. This article is useful for construction/project manager, planning engineer and all those related directly or indirectly to project planning and management. These norms are calculated and referred from below mentioned reliable sources. As output of Labor and material varies with geographical locations across globe, these norms are more suitable for Indian scenario. These norms can certainly prove handy to project planning and management (PPM) personnel as they can use it for performing Labor requirement calculation, material requirement calculation (of building projects) and for cross checking the existing daily progress report (DPR) of their site to know how good the Labor and material is performing. How to use these norms? As the existing page layout allows only vertical typing, sorting of norms are done with each head in bold letters and then subsequently its related data. The norms are mentioned below: Oct, 2009 I] FORMWORK / SHUTTERING Activity
TASKS
Task – UOM Labor (L) – Carpenter (Mandays)
Labor (L) – Helper (Mandays)
Material (M)
Material (M)
Material (M)
Footing formwork
Footing – Shuttering & Providing Support
Sqm
0.8 Mandays/10Sqm
1.5 Mandays/10Sqm
MS Wall Form Panel – 1250 x 500 : 16Nos/10Sqm
Props – 2m to 3m Long : 2 Nos/Rm
Shuttering Oil : 4Ltr/10Sqm
Footing – Deshuttering & insitu Stacking
Sqm
0.48 Mandays/10Sqm
0.9 Mandays/10Sqm
Raft – Shuttering & Providing Support
Sqm
0.71 Mandays/10Sqm
1.41 Mandays/10Sqm
MS Wall Form Panel – 1250 x 500 : 16Nos/10Sqm
Props – 2m to 3m Long : 2 Nos/Rm
Shuttering Oil : 4Ltr/10Sqm
Raft – Deshuttering & insitu Stacking
Sqm
0.42 Mandays/10Sqm
0.84 Mandays/10Sqm
Walls (Any Thickness), Including Buttresses – Shuttering & Providing Support – Up to 3.5m Height
Sqm
2.22 2.64 MS Wall Form Panel Mandays/10Sqm(Including Mandays/10Sqm(Including – 1250 x 500 – 32 Both Sides) Both Sides) Nos/10Sqm(Including Both Sides)
Walls – Deshuttering & insitu Stacking
Sqm
1.32 1.76 Mandays/10Sqm(Including Mandays/10Sqm(Including Both Sides) Both Sides)
Raft formwork
Walls formwork
Props – 2m to 3m Shuttering Oil : Long : 5Ltr/10Sqm(On 4Nos/Rm(Including One Side) Both Sides)
Labor and material productivity
Staircase formwork
Staircase (Excluding Spiral Staircase) – Shuttering & Providing Support
2
Sqm
0.23 Mandays/Sqm
0.46 Mandays/Sqm
Staircase Sqm (Excluding Spiral Staircase) – Deshuttering & Stacking Appropriately at Same Location
0.14 Mandays/Sqm
0.28 Mandays/Sqm
Ramp formwork
Ramp – Shuttering & Providing Support
Sqm
0.22 Mandays/Sqm
0.44 Mandays/Sqm
MS Floor Form Panel MS Floor Form Adjustable – 750 x 600 – Panel – 1250 x 500 Props – 2.02m 13.3Nos/10Sqm : 6.4Nos/10Sqm to 3.75 m : 2Nos/Sqm and Shuttering Oil : 5Ltr/10Sqm
Ramp – Deshuttering & Stacking Appropriately at Same Location
Sqm
0.13 0.26 Mandays/Sqm Mandays/Sqm
Shades Formwork
Weather Shade, Chajjas, Corbels Shuttering (Including Propping)
Sqm
0.14 Mandays/Sqm
MS Floor Form Panel Adjustable Props – – 750 x 600 – 2.02m to 3.75 m : 2.2Nos/Sqm 2Nos/Sqm
Weather Shade, Sqm Chajjas, Corbels – Deshuttering & Stacking Appropriately at Same Location
0.12 Mandays/Sqm
0.07 0.08 Mandays/Sqm Mandays/Sqm
MS Floor Form Panel Adjustable Props – – 750 x 600 – 2.02m to 3.75 m : 2.2Nos/Sqm 2Nos/Sqm
Shuttering Oil : 5Ltr/10Sqm
Shuttering Oil : 0.3Ltr/Sqm
Labor and material productivity
3
II] Reinforcement Activity
TASKS
Footing Reinforcement
Foot Rein – Placing in Position Mt & Binding – Using TMT Bars, Mild Steel, Tor Steel
0.28 Mandays/0.1Mt 0.38 Mandays/0.1Mt
Bars – Binding Wire Cover Blocks Include 5% : 5 kg/0.1Mt – 10No/0.1Mt Wastage
Foot Rein – Straightening, Cutting (With Machine Cutting), bending – Using TMT Bars, Mild Steel, Tor Steel
Mt
0.2 Mandays/0.1Mt
0.28 Mandays/0.1Mt
Bars – Include 5% Wastage
Foot Rein – Straightening, Cutting (With Manual Cutting), bending – Using TMT Bars, Mild Steel, Tor Steel
Mt
0.29 Mandays/0.1Mt 0.32 Mandays/0.1Mt
Bars – Include 5% Wastage
Walls Rein – Placing in Position & Binding – Using TMT Bars, Mild Steel, Tor Steel
Mt
0.41 Mandays/0.1Mt 0.45 Mandays/0.1Mt
Bars – Binding Wire Cover Blocks Include 5% : 5 kg/0.1Mt – 10No/0.1Mt Wastage
Walls Rein – Straightening, Cutting (With Machine Cutting), bending – Using TMT Bars, Mild Steel, Tor Steel.
Mt
0.2 Mandays/0.1Mt
0.28 Mandays/0.1Mt
Bars – Include 5% Wastage
Walls Rein – Straightening, Cutting (With Manual Cutting), bending – Using TMT Bars, Mild Steel, Tor Steel.
Mt
0.39 Mandays/0.1Mt 0.43 Mandays/0.1Mt
Bars – Include 5% Wastage
Walls Rein – Stirrups Cutting and Bending
Mt
0.47 Mandays/0.1Mt 0.5 Mandays/0.1Mt
Bars – Include 5% Wastage
Walls Rein – Stirrups Teing
Mt
0.55 Mandays/0.1Mt 0.57 Mandays/0.1Mt
Bars – Include 5% Wastage
Staircase Rein – Placing in Position & Binding – Using TMT Bars, Mild Steel, Tor Steel
Mt
0.32 Mandays/0.1Mt 0.34 Mandays/0.1Mt
Bars – Binding Wire Cover Blocks Include 5% : 5 kg/0.1Mt – 10No/0.1Mt Wastage
Staircase Rein – Straightening, Mt Cutting (With Machine Cutting), bending – Using TMT Bars, Mild Steel, Tor Steel.
0.2 Mandays/0.1Mt
0.28 Mandays/0.1Mt
Bars – Include 5% Wastage
Staircase Rein- Straightening, Cutting (With Manual Cutting), bending – Using TMT Bars, Mild Steel, Tor Steel.
0.29 Mandays/0.1Mt 0.32 Mandays/0.1Mt
Bars – Include 5% Wastage
Walls Reinforcement
Staircase Reinforcement
Task – L – UOM Barbender/Fitter (Mandays)
Mt
L – Helper (Mandays)
M
M
M
Labor and material productivity Further details of labor and material output norms of formwork, reinforcement and other important works like earthwork, concreting, brickwork, blockwork, plastering, pointing, painting, flooring, stone work, marble work, wood work and dismantling works are being calculated and will be posted here very soon.
References • • • •
Practical Information for Quantity Surveyors – By Late P. T. Joglekar (Edition: May, 2007) CPWD – Analysis of Rates – Vol II – Sub-Head 04 and 05 – By CPWD (Edition:1997) Estimation and Costing – By B. N. Dutta (Edition:2004) A to Z of Civil Engineering – Theory & Practice – By Mantri (Edition:2005)
External links • www.planningplanet.com [1]
References [1] http:/ / www. planningplanet. com/ index. asp
4
Article Sources and Contributors
Article Sources and Contributors Labor and material productivity Source: http://en.wikipedia.org/w/index.php?oldid=518534727 Contributors: Autoerrant, Ben Ben, DoctorKubla, Ekabhishek, Fabrictramp, Katharineamy, Malcolma, Nihiltres, RHaworth, RJFJR, Rich Farmbrough, Saini.sukh, Signalhead, Tony1, Topbanana, Woohookitty
License Creative Commons Attribution-Share Alike 3.0 Unported //creativecommons.org/licenses/by-sa/3.0/
5
View more...
Comments