Krajewski Ism Ch15
Short Description
Download Krajewski Ism Ch15...
Description
Chapter
15
Resource Planning
DISCUSSION QUESTIONS 1. The purpose of this exercise is to get the students to think about the usefulness of ERP for each of their major areas of interest. Because groups consist of different functional area representatives, the discussion is intended to emphasize the cross-functional needs that are satisfied with an information system such as ERP. Some responses to this exercise include: Marketing—information about the availability of finished products that can be promised for delivery; finished goods inventory performance (service levels, stockouts). Finance—short-term financing needs for production plans, developed from the order releases and projected inventory levels. Accounting—billing invoices for products shipped to customers; payments to suppliers of raw materials and purchased components, developed from the schedule of orders actually received. Operations—the schedule of order releases to support the master schedule; estimates of capacity requirements at critical work centers. 2. Some responses from each functional area could include: Marketing: The available-to-promise quantities because they determine when orders can be promised to customers, the history of orders accepted for each product by time period because this information can be useful in projecting future demand patterns. Finance: The projected MPS quantities and inventory levels because they will indicate cash needs. Operations: The MPS start quantities because they indicate when production of products must begin to meet customer promises and because they provide the basis for estimating capacity needs at critical workstations. 3. A master flight schedule specifies the arrival and departure times for all the flights an airline must produce to meet customer demands. Here, the lead time is the time between departure and arrival, which is similar to the lead time in producing a quantity of a product. The passenger size of the aircraft is analogous to a production quantity, and the available-to-promise quantity in manufacturing bears similarity to the seats available on a given flight. In general, the flight schedule can be used to estimate the needs for resources such as pilots, flight attendants, airport slots, and aircraft.
Resource Planning
z
CHAPTER 15
z
431
4. The principles of MRP can be used for UPS by identifying bills of resources for resources such as employees, trucks, planes, and equipment. Forecasts of delivery requirements and the BORs can be used to estimate resource needs and project the loads on critical sorting operations. PROBLEMS 1. Bill of materials, Fig. 15.26 a. Item I has only one parent (E). However, item E has two parents (B and C). b. Item A has 10 unique components (B, C, D, E, F, G, H, I, J, and K). c. Item A has five purchased items (I, F, G, H, and K). These are the items without components. d. Item A has five intermediate items (B, C, D, E, and J). These items have both parents and components. e. The longest path is I–E–C–A at 11 weeks. 2. Item A. The bill of materials for item A is shown following. A
B(2)
C(2)
C(2)
E(1)
D(2)
F(2)
3. Lead time is determined by the longest path, C–B–A, at 13 weeks. 4. The bill of materials for item A with lead times is shown following. a. Lead time is determined by the longest path G-E-B-A = 12 weeks. b. If purchased items D, F, G, and H are already in inventory, the lead time is reduced to: A–B–E = 8 weeks. c. Item G with the longest lead time.
432
z
PART 3
z
Managing Value Chains
A LT = 1 B(1) LT = 2
C(1) LT = 2
D(1) E(1) F(1) H(1) LT = 6 LT = 5 LT = 6 LT = 3 G(1) LT = 4
H(1) LT = 3
5. Refer to Figure 15.21 and Solved Problem 1. FIGURE 15.21
A LT = 1 B(3) LT = 2
C(1) LT = 3
D(1) E(2) F(1) D(1) LT = 3 LT = 6 LT = 1 LT = 3 G(1) LT = 3
Material requirement to produce 5 units of end-item A: ( 5 A × 3B per A ) = 15B − 2 B on hand = 13B
( 5 A ×1C per A) = 5C
Material requirement to produce 13B: (13B ×1D per B ) = 13D
(13B × 2 E per B ) = 26E
Material requirement to produce 5C:
Resource Planning
( 5C ×1D per C ) = 5D ( 5C ×1F per C ) = 5F − 1F
z
CHAPTER 15
z
433
on hand = 4F
Material requirement to produce 4F: ( 4 F ×1G per F ) = 4G – 3G on hand = 1G Purchased material requirements net of on-hand inventory: 13 + 5 = 18D , 26E, and 1G. 6. MPS record in Fig. 15.28. The following table is from the Master Production Scheduling Solver in OM Explorer. The ATP row is not required for this problem. Solver Master Production Scheduling Enter data in yellow shaded areas. Lot Size Lead Time
60 1
Quantity on Hand
35 1
2
3
4
5
6
7
8
Forecast
20 18 28 28 23 30 33 38
Customer Orders (Booked)
15 17
Projected On-Hand Inventory
15 57 29
MPS Quantity 60
Available-to-Promise Inv (ATP)
9
8 35 57
60
60 60
60
20 20
10 11 12 13 14 15
7
1 38
60
MPS start
Override Formulas
9 14
9
60 60 51
53 60
Restore Formulas
7. MPS record in Fig. 15.29 Lot Size: 100 Quantity on Hand: 75 Forecast Customer orders (booked) Projected on-hand inventory MPS quantity MPS start
1 65 40 10 100
January 2 3 65 65 10 85 45 60 100 100 100
4 45 0 15 100
5 50 35 65 100 100
February 6 7 50 50 70 0 95 45 100 100
8 50 0 95 100
434
z
PART 3
z
Managing Value Chains
8. An end-item Lot Size: 100 Quantity on Hand: 80 Forecast Customer orders (booked) Projected on-hand inventory MPS quantity MPS start
1 30 22 50
2 20 30 20
3 35 15 85 100
100
Week 5 6 25 25 0 0 10 85 100
4 50 9 35
7
8 40 3 40
0 5 80
100
9 0 7 33
10 50 0 83 100
100
9. Ball Bearings Prospective MPS a. Solver Master Production Scheduling Enter data in yellow shaded areas. Lot Size Lead Time
500 1
Quantity on Hand
400 1
2
3
4
5
6
7
8
9
10 11 12 13 14 15
Forecast
550 300 400 450 300 350 200 300 450 400
Customer Orders (Booked)
300 350 250 250 200 150 100 100 100 100
Projected On-Hand Inventory
350
100 150 350
300
50 150
MPS Quantity
500
500 500 500
500
500 500
MPS start Available-to-Promise Inv (ATP)
500 500 500 500 500 500 250 250 250 150 300 400 400
Override Formulas
Restore Formulas
The first order for 500 (in week 4) should be accepted. Through week 4, on hand (400) plus three MPS quantities of 500 each = 1900. Of those, (300 + 350 + 250 + 250) = 1150 have been sold, leaving 750 available (250 after this commitment). b. The second order for 400 (in week 5) should be accepted. Through week 5, the 250 remaining after the first order plus one more MPS quantity of 500 = 750. Of those, 200 have been sold in the 5th week and 150 in the 6th week. Therefore, (250 + 500 – 200 – 150) = 400 are still available. There will be zero units remaining for sale even after accepting this order. c. The third order for 300 units (in week 1) should not be accepted. At that time, of the 400 on hand, plus 500 MPS quantity to arrive in the first week, a total of 300 plus 350 has been sold. Note that because no MPS is scheduled for the 2nd week,
Resource Planning
z
CHAPTER 15
z
435
the 350 ordered for the 2nd week must come from those on hand or those arriving in the 1st week. In total [(400 + 500) – (300 + 350)] = 250 remaining, which will not cover the order for 300. d. The fourth order for 300 units (in week 7) should be accepted. After accepting the second order (part ii), zero units remain. In the 7th week 500 units arrive. Of those, demands of 100 in each of weeks 7 and 8 have been promised, leaving (500 – 200) = 300. This order of 300 units would reduce the quantity available to promise to zero units. 10. Morrison Electronics a. Prospective MPS Quantity on Hand: 100
1
2
3
4
5
6
7
8
Forecast Customer orders (booked) Projected on-hand inventory MPS quantity MPS start
70 50 30
70 60 110 150
65 55 45
60 40 135 150
55 35 80
85 0 145 150
75 0 70
85 0 135 150
150
150
150
150
b. Revised forecast Quantity on Hand: 100
1
2
3
4
5
6
7
8
Forecast Customer orders (booked) Projected on-hand inventory MPS quantity MPS start
70 50 30
70 60 110 150
75 55 35
70 40 115 150
70 35 45
100 0 95 150
100 0 –5
110 0 35 150
150
150
150
150
Although the projected on-hand row indicates a negative balance, this difficulty will occur only if the actual orders meet the new forecast. If the new forecasts are “solid,” we should consider revising the master production schedule or shifting demand to avoid stockouts in week 7.
436
z
PART 3
z
Managing Value Chains
11. Completed MPS Record ITEM: 2" Pneumatic Control Valve LEAD TIME: 1 week
ORDER POLICY: 75 units QUANTITY ON HAND: 10 units Week
1 Forecast requirements Customer orders (booked) Projected on-hand inventory MPS quantity MPS start Available-to-promise (ATP) inventory
40 60 25 75 75 25
2
3
40 45 55 75
4
40 30 15
5
40 35 50 75
6
30 10 20
75
7
30 5 65 75
8
50 5 15
75
50 0 40 75
75
30
65
75
Decisions on the arriving orders: Order 1 for 15 units in week 2 should be accepted because there are 25 units ATP from week 1. After this order is accepted 10 units remain in ATP from Week 1. Order 2 for 30 units in week 5 should be accepted because there are 30 units ATP from week 4. After this order is accepted 10 units still remain in ATP from week 1 and zero units from week 4. Order 3 for 25 units in week 3 should NOT be accepted because there are only 10 units remaining in ATP from week 1 and this is not adequate to fill the order completely. After this order is rejected 10 units continue to remain in ATP from week 1. Order 4 for 75 units in week 7 should be accepted because there will be 65 units in ATP from week 6, which, along with the 10 units that continue to remain in ATP from week 1, will be adequate to fill the order completely. 12. a. Completed MPS Record ITEM: Electric Hand Drill LEAD TIME: 1 week
ORDER POLICY: 60 units QUANTITY ON HAND: 30 units Week 1
Forecast requirements Customer orders (booked) Projected on-hand inventory MPS quantity MPS start Available-to-promise (ATP) inventory
15 20 10 60 10
2
3
40 25 30 60
10 10 20
4 20 20
60 5
5
6
50
30
10 60 60 60
40 60 60
b. The shipping date would be week 2 because we will have 10 units from week 1 and 5 units from week 2 available-to-promise inventory to fill this order.
Resource Planning
13. Completed MPS record ITEM: Product C LEAD TIME: 2 weeks
CHAPTER 15
z
437
ORDER POLICY: 40 units QUANTITY ON HAND: 10 units 1
Forecast requirements Customer orders (booked) Projected on-hand inventory MPS quantity MPS start Available-to-promise (ATP) inventory
z
2
3
4
Week 6 7
5
8
9
10
11
12
15 25
15 12
15 8
15 10
20 2
20 3
20 0
20 0
15 0
15 0
15 0
15 0
25
10
35
20
0
20
0
20
5
30
15
0
40 40 13
40
40 40 37
40 20
40 40 40
40 40
14. Inventory record. The tables following were generated with the Single-Item MRP solver from OM Explorer. a. Fixed order quantity = 110
Inputs Solver - Single-Item MRP Enter data in yellow shaded areas. Periods Item Description
8 M405-X Table Top Assemby
FOQ Rule
1
2
Gross Requirements
90
Scheduled Receipts
110
Projected On-Hand Inventory
40
60
Planned Receipts Planned Order Releases
Period (P) for POQ 3
4
5
85
60
85
Lot Size (FOQ) Lead Time Safety Stock 6 7 80
85
5
5
110 110
110
110
110 2 0 8 45
90
70
90
110
110
438
z
PART 3
z
Managing Value Chains
b. L4L
Inputs Solver - Single-Item MRP Enter data in yellow shaded areas. Periods Item Description
8 M405-X Table Top Assemby
L4L Rule
1
2
Gross Requirements
90
Scheduled Receipts
110
Projected On-Hand Inventory
40
Period (P) for POQ
60
3
5
2 0 8
85
80
45
90
25
80
45
90
80
45
60
Planned Receipts Planned Order Releases
4
Lot Size (FOQ) Lead Time Safety Stock 6 7
25
90
c. POQ, P = 2
Inputs Solver - Single-Item MRP Enter data in yellow shaded areas. Periods Item Description
8 M405-X Table Top Assemby
POQ Rule
1
2
Gross Requirements
90
Scheduled Receipts
110
Projected On-Hand Inventory
40
Period (P) for POQ
60
3
15.
5
85
80
25
2 0 8 45
60
Planned Receipts Planned Order Releases
4
2 Lot Size (FOQ) Lead Time Safety Stock 6 7
90 25
80
80
135
135
Completed inventory records a. FOQ of 150 units Item:
Rotor assembly
Week Gross requirements Scheduled receipts Projected on hand 20 Planned receipts Planned order releases
1 65 150 105
2 15
3 45
Lot Size: 150 units Lead Time: 2 weeks 4 5 6 7 40 80 80 80
90
45
5
150
150
75 150
145 150 150
65
8 80 135 150
90
Resource Planning
z
CHAPTER 15
b. L4L Item:
Rotor assembly
Week Gross requirements Scheduled receipts Projected on hand 20 Planned receipts Planned order releases
1 65 150 105
2 15
3 45
90
45
Lot Size: Lead Time: 4 5 6 40 80 80 5 75 80
0 80 80
75
80
2 15
3 45
Lot Size: Lead Time: 4 5 6 40 80 80
90
45
L4L 2 weeks 7 80 0 80
8 80 0 80
c. POQ with P = 2 Item:
Rotor assembly
Week Gross requirements Scheduled receipts Projected on hand 20 Planned receipts Planned order releases
1 65 150 105
5
155
80 155 160
0
2 25
3 15
Lot Size: Lead Time: 4 5 6 20 40 40
30
15
POQ, P = 2 2 weeks 7 8 80 80 80 160
0
16. Completed inventory records a. FOQ of 50 units Item:
Drive shaft
Week Gross requirements Scheduled receipts Projected on hand 10 Planned receipts Planned order releases
1 35 80 55 50
50
45 50 50
5
15 50
Lot Size: Lead Time: 4 5 6 20 40 40
50 units 3 weeks 7 50
8 50
15 50
15 50
50
b. L4L Item:
Drive shaft
Week Gross requirements Scheduled receipts Projected on hand 10 Planned receipts Planned order releases
1 35 80 55
2 25
3 15
30
15
5
40
40
0 5 50
0 40 50
0 40
L4L 3 weeks 7 50 0 50
8 50 0 50
z
439
440
z
PART 3
z
Managing Value Chains
c. POQ with P = 4 Item:
Drive shaft
Week Gross requirements Scheduled receipts Projected on hand 10 Planned receipts Planned order releases
17.
1 35 80 55
2 25
3 15
30
15
Lot Size: Lead Time: 4 5 6 20 40 40 130 135
135
90
50
POQ, P = 4 3 weeks 7 8 50 50 0
0 50
50
Rear wheel assembly, Fig. 15.35 a. Fixed order quantity = 300 Item: MQ—09 Description: Rear wheel assembly Week 1 2 Gross requirements 205 Scheduled receipts 300 Projected on hand 100 195 195 Planned receipts Planned order releases
3 130 65
Lot Size: FOQ: 300 Lead Time: 1 week 4 5 6 7 8 85 70 60 95 280 300
280
210
150
55
300
b. Lot-for-lot Item: MQ—09 Description: Rear wheel assembly Week 1 2 Gross requirements 205 Scheduled receipts 300 Projected on hand 100 195 195 Planned receipts Planned order releases
3 130 65
Lot Size: Lead Time: 4 5 6 85 70 0 20
20
0 70
0 70 60
L4L 1 week 7 60 0 60 95
8 95 0 95
c. Period order quantity, P = 4 Item: MQ—09 Description: Rear wheel assembly Week 1 2 Gross requirements 205 Scheduled receipts 300 Projected on hand 100 195 195 Planned receipts Planned order releases
3 130 65 150
Lot Size: POQ, P = 4 Lead Time: 1 week 4 5 6 7 8 85 70 60 95 130 150
130
60
0 95
0 95
Resource Planning
z
CHAPTER 15
18. Motor subassembly, Fig. 15.36 a. Fixed order quantity = 60 Item: GF—4 Description: Motor assembly Week 1 2 Gross requirements 50 Scheduled receipts 60 Projected on hand 40 40 50 Planned receipts Planned order releases
3
4 35
5
50
15
15
60
Lot Size: FOQ: 60 Lead Time: 3 weeks 6 7 8 9 10 11 55 30 10 20 60
20
50 60
50
40
12 25
40
15
Lot Size: L4L Lead Time: 3 weeks 6 7 8 9 10 11 55 30 10
12 25
0 40
0 25
60
b. Lot-for-lot Item: GF—4 Description: Motor assembly Week 1 2 Gross requirements 50 Scheduled receipts 60 Projected on hand 40 40 50 Planned receipts Planned order releases
3
4 35
5
50
15
15
40
30
0
0 30
10
0
0 10
0
25
c. Period order quantity P = 60/15 = 4. Item: GF—4 Description: Motor assembly Week 1 2 Gross requirements 50 Scheduled receipts 60 Projected on hand 40 40 50 Planned receipts Planned order releases
3
4 35
5
50
15
15
70
Lot Size: POQ, P = 4 Lead Time: 3 weeks 6 7 8 9 10 11 12 55 30 10 25 30 70
30 35
0
0
25 35
25
0
z
441
442
z
PART 3
z
Managing Value Chains
19. BOM for product A shown in Fig. 15.37 FIGURE 15.37
A
B(2)
D(1)
C(1)
D(2)
C(1)
D(2)
Item: B Description: Week Gross requirements Scheduled receipts Projected on hand Planned receipts Planned order releases Item: C Description: Week Gross requirements Scheduled receipts Projected on hand Planned receipts Planned order releases
0
1
2
0
0
3
4
0
0
Lot Size: L4L Lead Time: 3 weeks 5 6 7 1000 0
8
0 1000
1000
1
0
0
Item: D Description: Week 1 Gross requirements Scheduled receipts 2000 Projected on hand 200 2200 Planned receipts Planned order releases
2
0
3 1000
4
0 1000
0
1000
Lot Size: Lead Time: 5 6 500 0
L4L 1 week 7
8
0 500
500
2 2000
3
4
200
200
200
Lot Size: Lead Time: 5 6 1000 500 1200 2000
FOQ: 2000 1 week 7 8
700
2000
The only action required is to delay the scheduled receipt of item D from week 1 to week 2.
Resource Planning
z
CHAPTER 15
20. MRP for Fig. 15.38 A
B
C(2)
D(1)
D(1)
F(2)
E(1)
F(2)
E(1)
F(1)
Item C FOQ = 220 3 weeks 280 (week 1) 25
Lot-size rule Lead time Scheduled receipts On-hand inventory
Item: D Description: Week Gross requirements Scheduled receipts Projected on hand Planned receipts Planned order releases
F(1)
F(1)
Data Category
Item: C Description: Week Gross requirements Scheduled receipts Projected on hand Planned receipts Planned order releases
E(2)
25
D L4L 2 weeks None 0
E FOQ = 300 3 weeks 300 (week 3) 150
1
2
3 170
4
280 305
305
135
135
F POQ (P = 2) 2 weeks None 600
Lot Size: Lead Time: 5 6 200 135
155 220
FOQ = 220 3 weeks 7 8
155
155
L4L 2 weeks 7
8
0
0
220
0
Item: E Description: Week Gross requirements Scheduled receipts Projected on hand 150 Planned receipts Planned order releases
1
2
3 85
0
0
0 85 180
85
1 85
2
65
65 300
3 180 300 185
4
0
Lot Size: Lead Time: 5 6 180 100 0 180
0 100
100
4 100 85
Lot Size: Lead Time: 5 6 360 25 300
25
FOQ = 300 3 weeks 7 8
25
25
z
443
444
z
PART 3
z
Managing Value Chains
Item: F Description: Week Gross requirements Scheduled receipts Projected on hand 600 Planned receipts Planned order releases
1 170
2 300
3 360
4 200
430
130
200 430
0
Lot Size: Lead Time: 5 6
0
POQ = 2 2 weeks 7
8
0
0
0
430
Two action notices are identified: order 85 units of D and 430 units of F. 21. MRP for Fig. 15.39 A
B(2)
E(2)
Item: B Description: Week Gross requirements Scheduled receipts Projected on hand Planned receipts Planned order releases Item: C Description: Week Gross requirements Scheduled receipts Projected on hand Planned receipts Planned order releases
F(1)
1
50
50
50
2 100 50 0
3
0
C(1)
D(2)
F(2)
E(1)
4
0
0 130
0
130
160 Lot Size: Lead Time: 5 6 85 20
1 20
2 70
3 20
4 20
30
40 80
20
0
80
Lot Size: Lead Time: 5 6 130
125
40 125
20
L4L 2 weeks 7
0
8 160 0 160
POQ = 3 1 week 7 20 0 100
8 100 0 100
Resource Planning
Item: D Description: Week Gross requirements Scheduled receipts Projected on hand 120 Planned receipts Planned order releases Item: E Description: Week Gross requirements Scheduled receipts Projected on hand Planned receipts Planned order releases Item: Description:
70
1
2 100
3
4
120
20
20
20
Lot Size: Lead Time: 5 6 130 140 250
250 Lot Size: Lead Time: 5 6 570
1
2
3 510
4
70
70
160 600
160
600
160
140
230 250
FOQ = 600 2 weeks 7 8
190 600
190
190
600
F
Lot Size: Lead Time:
Week Gross requirements Scheduled receipts Projected on hand 250 Planned receipts Planned order releases
CHAPTER 15
FOQ = 250 2 weeks 7 8 160
140
250
z
1 160
2
3 130
4 250
90
90
0 40 250
0 250
40
5
0 160
L4L 1 week
6 160
7 200
8
0 160 200
0 200
0
Action notices signal the need to place orders for 80 Cs and 600 Es. 22. MRP for products A, B, and C in Fig. 15.40 A D(2)
B E(1) F(2)
D(1)
C E(2) F(2)
D(2)
E(2) F(2)
z
445
446
z
PART 3
z
Managing Value Chains
Item: D Description: Week Gross requirements Scheduled receipts Projected on hand 150 Planned receipts Planned order releases Item: E Description: Week Gross requirements Scheduled receipts Projected on hand Planned receipts Planned order releases Item: Description:
0
1
2
150
150
3 160 150 140
150
150
1
2
0
120 120
4 120 20
3 80
4 120
40
0 80 250
80
F
Week Gross requirements Scheduled receipts Projected on hand 100 Planned receipts Planned order releases
1
2
3 160
4 500
100
100
530 590 110
30
590
Lot Size: Lead Time: 5 6 125 110 45 150
85 150
Lot Size: Lead Time: 5 6 250 55 0 250 55
85
L4L 1 week 7
0 55
Lot Size: Lead Time: Safety Stock: 5 6 110 30 110
FOQ = 150 3 weeks 7 8
0
30
23. MRP for Fig. 15.41
D(2)
E(1)
E(2)
B
C(2)
D(1)
E(1)
E(2)
D(1)
E(1)
8
0
POQ, P = 2 2 weeks 30 units 7 8
Action notice: Order 590 of F
A
85
30
30
Resource Planning
Product A B
1
2 125
6 150 70
80
Data Category Lot-size rule Lead time Scheduled receipts On-hand inventory Item: C Description: Week Gross requirements Scheduled receipts Projected on hand Planned receipts Planned order releases
Date 4 5 95
3
1
85
Item: D Description: Week Gross requirements Scheduled receipts Projected on hand 625 Planned receipts Planned order releases Item: E Description: Week Gross requirements Scheduled receipts Projected on hand 350 Planned receipts Planned order releases
85
2 250 200 35
155
3
4 190
35
0 155
300
2 250
3 380
4 190
470
220
450 610
260
610
8 130
E FOQ = 800 1 week 800 (week l) 350
Lot Size: Lead Time: 5 6 300 0
CHAPTER 15
0 300
L4L 3 weeks 7
0
8 260 0 260
260
1 155
1 610 800 540
7
Item D POQ (P = 3) 2 weeks None 625
C L4L 3 weeks 200 (week 2) 85
z
Lot Size: Lead Time: 5 6 260 370 0
260 630
POQ(P = 3) 2 weeks 7 8 260 260
630
2 250
3 160
4 820
290
130
110 800
800
Lot Size: Lead Time: 5 6 440 110
470 800
800
Action notice: New orders should be opened for 155 Cs and 610 Ds.
FOQ = 800 1 week 7 8 260 470
210
z
447
448
z
PART 3
z
Managing Value Chains
24. MRP for Fig. 15.42 A
D(2)
C(3)
E(1)
B(2)
D(1)
F(2)
E(1)
Data Category Lot-size rule Lead time Safety stock Scheduled receipts
B L4L 3 weeks 0 150 (week 2) 125
Beginning (on-hand) inventory Item: B Description: Week Gross requirements Scheduled receipts Projected on hand 125 Planned receipts Planned order releases Item: C Description: Week Gross requirements Scheduled receipts Projected on hand Planned receipts Planned order releases
1
125
2 240 150 35
205
240
1
0
C FOQ = 700 3 weeks 0 450 (week 2) 0
0 700
2 360 450 90
F(2)
Item D FOQ = 700 4 weeks 0 700 (week 1) 235
3
4 240
35
0 205
3
4 360
90
430 700
E L4L 2 weeks 50 None 750
Lot Size: Lead Time: 5 6 240 0 240 240
0
Lot Size: Lead Time: 5 6 360 70 700
F L4L 1 week 0 1400 (week 1) 0
70
L4L 3 weeks 7
0
8 240 0 240
FOQ = 700 3 weeks 7 8 360 70
410 700
Resource Planning
Item: D Description: Week Gross requirements Scheduled receipts Projected on hand 235 Planned receipts Planned order releases Item: Description:
2 480
3
4 240
250
250
10
700
1 700
2
3
4 700
50
50
50
50 700
230
FOQ = 700 4 weeks 7 8 240 230
690 700
Lot Size: Lead Time: Safety Stock: 5 6
50
50
L4L 2 weeks 50 units 7
8
50
50
700
F
Week Gross requirements Scheduled receipts Projected on hand Planned receipts Planned order releases
230 700
CHAPTER 15
700
E
Week Gross requirements Scheduled receipts Projected on hand 750 Planned receipts Planned order releases Item: Description:
1 205 700 730
Lot Size: Lead Time: 5 6 480
z
1 1400 1400 0 0
2
0
3
4 1400 0
Lot Size: Lead Time: Safety Stock: 5 6
0 1400
0
0
1400
Action notices are to issue orders for 700 Ds, 700 Cs, and 205 Bs. 25. MRP for Fig. 15.21 A LT = 1 B(3) LT = 2
C(1) LT = 3
D(1) E(2) F(1) D(1) LT = 3 LT = 6 LT = 1 LT = 3 G(1) LT = 3
L4L 1 week 0 units 7
0
8
0
z
449
450
z
PART 3
z
Managing Value Chains
Data Category Lot-size rule Lead time Safety stock Scheduled receipts On-hand inventory
B L4L 2 weeks 30 150 (wk 2) 30
C L4L 3 weeks 10 50 (wk 2) 20
Item: A Lot Size: 50 Final Asm. Lead Time: 1 wk Quantity On Hand: 5 MPS Start Item: Description:
3
4
1
30
30
2 150 150 30
20
20
2 50 50 20
3
4
30
30
3
4
20
20
40
60
1
2
3 40
60
60
20
180
7
Lot Size: Lead Time: Safety Stock: 5 6 7 150 30
150
1
F L4L 1 week 0 40 (wk 3) 0
50
D
Week Gross requirements Scheduled receipts Projected on hand Planned receipts Planned order releases
Week 5 6
50
C
Week Gross requirements Scheduled receipts Projected on hand Planned receipts Planned order releases Item: Description:
2
B
Week Gross requirements Scheduled receipts Projected on hand Planned receipts Planned order releases Item: Description:
1
Item D E POQ (P = 2) L4L 3 weeks 6 weeks 0 0 None 400 (wk 6) 60 400
350
30 150 150
50
10 40 50
0
8
9
50
50
L4L 2 weeks 30 units 8 9 150 150
30
30 150
30 150
L4L 3 weeks 10 units 8 9 50 50
10
10 50
10 50
Lot Size: POQ = 2 Lead Time: 3 weeks Safety Stock: 0 units 4 5 6 7 8 9 150 50 200 150 50 180
0
150 350
10
10
30
150
Lot Size: Lead Time: Safety Stock: 5 6 7 50 02
G FOQ = 100 3 weeks 0 None
0
0
10
10
10
0
0
Resource Planning
Item: Description:
E
Week Gross requirements Scheduled receipts Projected on hand Planned receipts Planned order releases Item: Description:
400 400
2
3
400
400
z
451
10
0
100
1
0
2
0
0
3 40 40 0
Lot Size: Lead Time: Safety Stock: 5 6 7 50 50
4
0 50
G
Week Gross requirements Scheduled receipts Projected on hand Planned receipts Planned order releases
CHAPTER 15
Lot Size: L4L Lead Time: 6 weeks Safety Stock: 0 units 4 5 6 7 8 9 300 300 300 400 100 100 200 0 0 0 100
F
Week Gross requirements Scheduled receipts Projected on hand Planned receipts Planned order releases Item: Description:
1
z
1
0
2
0
0 50
0
Lot Size: Lead Time: Safety Stock: 4 5 6 7 50 50
3
0
0 50 50
L4L 1 week 0 units 8 9
0
50 100
0
0
0
10
0
FOQ = 100 3 weeks 0 units 8 9
0
0
0
0
10
0
100
CASE: FLASHY FLASHERS, INC. * A. Synopsis Flashy Flashers, Inc. is a company that produces a line of automotive electrical components and serves about 75 auto parts suppliers and car dealers regionally. Recently the company installed an MRP system. After one year’s use, the MRP system was not living up to expectations. Jack Jacobs, the production and inventory control manager, has been assigned the duty of finding out why the system is not performing well. B. Purpose This case provides the data to develop the MRP records for two products of Flashy Flashers, Inc. In addition to reinforcing the skills of developing dependent demand *
This case was prepared by Dr. Soumen Ghosh, Georgia Institute of Technology, as a basis for classroom discussion.
452
z
PART 3
z
Managing Value Chains
production plans, the case affords the opportunity to discuss the causes of some of the implementation problems experienced by the company. The instructor may want to assign the Master Production Scheduling supplement prior to discussing this case because the linkage between the MPS (available to promise quantities) and MRP can be fruitfully discussed. The case also emphasizes the role and value of action notices in the operation of an MRP system. C. Analysis A summary of the planned order release schedule is contained in Exhibit TN.1. The MRP records for both of the end items and each of the component items are contained in Exhibit TN.2. Examination of the MRP records indicates that some of them show shortages (negative projected on-hand balances). Some of these shortages are due to bad timing of outstanding scheduled releases. Often, expediting the scheduled receipt will rectify the record imbalance. Whether or not the scheduled receipt can indeed be expedited is debatable, given the case description. In addition, three of the shortages must be rectified by releasing a planned order with less than the normal lead time. In one instance, a scheduled receipt can be delayed because it is scheduled for arrival too early. These are symptoms of an MRP system that is not working well. D. Recommendations Recommendations to management include the following: 1. Stabilize the master production schedule so that new orders are not inserted into the schedule with less than normal lead times. 2. Synchronize the operations in the shop with the material planners so that priorities are valid. This will require updating priorities (scheduled dates of need for a component) as they change. 3. Train all employees who provide information to the MRP system in addition to those who must update the system. Only selected employees received training in the past. Everyone should be aware of the need for accurate and timely data. Also train those who will be primary users of the MRP information. E. Teaching Suggestions Initially the instructor should get agreement on the planned order release form (Exhibit TN.1). Be sure to rationalize any differences in the student forms because they will spur the discussion of the mechanics of producing MRP reports. The results lay the foundation for the conclusion that something definitely is wrong. After the mechanics are understood, the instructor should raise the question, “What are the causes of these problems?” The students will provide a host of possibilities, including: Ambitious salespeople accepting orders on short notice Poor estimates for lead times Bad priority planning system Lack of capacity Bad input data
Resource Planning
z
CHAPTER 15
z
453
Ineffective follow-up with suppliers Blaming everyone else
The issue of whether the problem is one of capacity or priority scheduling is one that merits some discussion. Although specific data are not available to provide a definitive answer, the symptoms could be entirely the result of poor priorities—working on components that are not needed at the cost of those that are needed. EXHIBIT TN.1
Completed Planned Order Release Form Week
Item Description and Part Number 1)* RELEASE ACTION NOTICE Side Lens (SL111P) Side Lens Rubber Gasket (SL113P) Side Frame Subassembly (SL112A) 2)* RELEASE ACTION NOTICE (with 2 wk. lt) 3)* EXPEDITE NOTICE FOR SR (70) BY 1 WK. Side Frame (SL121F) Side Bulb Subassembly (SL122A) 4)* RELEASE ACTION NOTICE Flasher Bulb Subassembly (SL123A) 5)* RELEASE ACTION NOTICE Side Cable Grommet and Receptacle (SL131F) 6)* EXPEDITE NOTICE FOR SR (180) BY 1 WK. Flasher Cable Grommet and Receptacle (SL133F) Side Bulb (SL132P) 7)* RELEASE ACTION NOTICE Flasher Bulb (SL134P) 8)* DELAY NOTICE FOR SR(50) BY 2 WKS. Head Frame Subassembly (HL211A) Head Lens (HL212P) 9)* RELEASE ACTION NOTICE (with 3 wk. lt) 10)* EXPEDITE NOTICE FOR SR (110) BY 2 WKS. Head Lamp Module (HL222P) Head Frame (HL223F) Back Rubber Gasket (C3 I 0P) Screws (C206P)
11
12
13
14
15
100
100
350 100 60
110
100 110 60
110
110
100
60 350
90
80 180 2500
75 180
75
75
16
454
z
PART 3
z
Managing Value Chains
EXHIBIT TN.2
Completed MRP Worksheets
Item: SL111P Description: Side Lens Date Gross requirements Scheduled receipts Projected on hand: 15 Planned receipts Planned order releases
11
12
13 140
14
15 80
16 145
15
15
225 350
225
145
0
Lot Size: Lead Time: Safety Stock:
350 units 2 weeks 0 units
Lot Size: Lead Time: Safety Stock:
L4L 3 weeks 0 units
Lot Size: Lead Time: Safety Stock:
100 units 1 week 20 units
Lot Size: Lead Time: Safety Stock:
L4L 3 weeks 0 units
350
RELEASE ACTION NOTICE Item: SL112A Description: Side Frame Subassembly Date Gross requirements Scheduled receipts Projected on hand: 20 Planned receipts Planned order releases
11
12
20
20
13 100 100 20
60
110
14
15 80
16 110
20
0 60
0 110
Item: SL113P Description: Side Lens Rubber Gasket Date Gross requirements Scheduled receipts Projected on hand: 20 Planned receipts Planned order releases
11
12
13 100
14
15 80
16 110
20
20
20 100
20
40 100 100
30 100
100
100
Item: SL121F Description: Side Frame Date Gross requirements Scheduled receipts Projected on hand: 0 Planned receipts Planned order releases
11
0 100
12 60
13 110 70 –60 –100
14
15
16
0 100
0
0
Resource Planning
EXHIBIT TN.2 (Cont.)
11
10
12 60 50 0
13 110
14
15
16
0 110
0
0
0
Lot Size: Lead Time: Safety Stock:
L4L 1 week 0 units
Lot Size: Lead Time: Safety Stock:
L4L 1 week 0 units
Lot Size: Lead Time: Safety Stock:
POQ (P = 2) 2 weeks 0 units
110
Item: SL123A Description: Flasher Bulb Subassembly Date Gross requirements Scheduled receipts Projected on hand: 0 Planned receipts Planned order releases
CHAPTER 15
Completed MRP Worksheets
Item: SL122A Description: Side Bulb Subassembly Date Gross requirements Scheduled receipts Projected on hand: 10 Planned receipts Planned order releases
z
11
12 60
13 110
14
15
16
0
0 60 110
0 110
0
0
0
60
RELEASE ACTION NOTICE Item: SL131F Description: Side Cable Grommet & Receptacle Date Gross requirements Scheduled receipts Projected on hand: 0 Planned receipts Planned order releases
11
12 110
13
14
15
16
0
–110
0 110
0
0
0
110
RELEASE ACTION NOTICE (WITH 1-WK LT) Item: SL132P Description: Side Bulb Date Gross requirements Scheduled receipts Projected on hand: 35 Planned receipts Planned order releases
Lot Size: Lead Time: Safety Stock: 11
35
12 110 100 25
13
14
15
16
25
25
25
25
100 units 1 week 25 units
z
455
456
z
PART 3
z
Managing Value Chains
EXHIBIT TN.2 (Cont.)
Completed MRP Worksheets
Item: SL133F Description: Flasher Cable Grommet & Receptacle Date Gross requirements Scheduled receipts Projected on hand: 0 Planned receipts Planned order releases
11 60 –60
12 110 180 10
Lot Size: Lead Time: Safety Stock:
13
14
15
16
10
10
10
10
POQ (P = 2) 2 weeks 0 units
EXPEDITE NOTICE FOR SR(180) BY 1 WK Item: SL134P Description: Flasher Bulb Date Gross requirements Scheduled receipts Projected on hand: 20 Planned receipts Planned order releases
11 60 100 60
12 110
13
14
15
16
50 100
50
50
50
50
Lot Size: Lead Time: Safety Stock:
100 units 1 week 25 units
Lot Size: Lead Time: Safety Stock:
L4L 2 weeks 0 units
Lot Size: Lead Time: Safety Stock:
350 units 2 weeks 15 units
100
RELEASE ACTION NOTICE Item: HL211A Description: Head Frame Subassembly Date Gross requirements Scheduled receipts Projected on hand: 10 Planned receipts Planned order releases
11
12
13
14 120
15 90
16 75
10
50 60
60
0 60 75
0 90
0 75
60
90
DELAY SR(50) BY 2 WKS Item: HL212P Description: Head Lens Date Gross requirements Scheduled receipts Projected on hand: 15 Planned receipts Planned order releases
11
12
13
14 120
15 90
16 75
15
15
15
245 350
155
80
350
Resource Planning
EXHIBIT TN.2 (Cont.)
CHAPTER 15
Completed MRP Worksheets
Item: HL222P Description: Head Lamp Module Date Gross requirements Scheduled receipts Projected on hand: 50 Planned receipts Planned order releases
z
11
50
12 60
Lot Size: Lead Time: Safety Stock: 13 90
14 75 110 –10 –100 –65
15
16
10 75
10
POQ (P = 4) 4 weeks 10 units
75
RELEASE ACTION NOTICE (WITH 3-WK LT) EXPEDITE NOTICE FOR SR(110) BY 2 WKS Item: HL223F Description: Head Frame Date Gross requirements Scheduled receipts Projected on hand: 70 Planned receipts Planned order releases
11
12 60
13 90
14 75
15
16
70
10
0 80 75
0 75
0
0
80
Item: C310P Description: Back Rubber Gasket Date Gross requirements Scheduled receipts Projected on hand: 30 Planned receipts Planned order releases
11
30
12 120 180 90 180
13 200
14 75
15
16
70 180 180
175 180
175
175
Item: C206P Description: Screws Date Gross requirements Scheduled receipts Projected on hand: 150 Planned receipts Planned order releases
11
12 120
13 380
150
30
2150 1520 1000 480 2500
2500
14 630
15 520
16 520
Lot Size: Lead Time: Safety Stock:
L4L 1 week 0 units
Lot Size: Lead Time: Safety Stock:
180 units 1 week 20 units
Lot Size: Lead Time: Safety Stock:
2500 units 1 week 30 units
z
457
View more...
Comments