KOC.SA.026 - Excavation Safety Procedure.pdf

March 21, 2018 | Author: George Lamie | Category: Excavation (Archaeology), Deep Foundation, Science, Engineering, Nature
Share Embed Donate


Short Description

Download KOC.SA.026 - Excavation Safety Procedure.pdf...

Description

KOC.SA.026 - Excavation Safety Procedure Page 1 of 14

Excavation Safety Procedure Document Number: KOC.SA.026 Document Author:

TL Safety

Approved by:

KOC HSEMS Procedures Sub-Committee

Authorized by:

KOC HSSE Implementation Committee

Original Issue Date: Revision / Review Date:

1.0

Document Coordinator:

26th August 2008

Document Control Tier:

18th February 2014

Next Review Date:

TL Standards

Tier 3 17th February 2017

Purpose / Scope The purpose of this procedure is to establish the precautions and conditions considered necessary for safety of the personnel involved in excavation work as well as integrity of above / underground services &/or facilities where such excavation work shall be carried out. The procedure is also aimed to define the roles & responsibilities of personnel associated with requesting, approving and carrying out excavation in areas under KOC jurisdiction. The procedure is applicable to all activities & facilities where excavation is carried out for maintenance, construction or inspection need. It is to note that requirement of work permit for excavation work shall be dealt in compliance with “Permit to Work Procedure”.

2.0

Definitions Backfilling: It is an activity to fill-in (with soil) a trench that is no longer needed and returning the area around its original condition. Benching: It is also one of the measures to prevent cave – ins by cutting trench sidewalls to form one or more steps. Cave - ins: It is collapse of the trench side walls due to weight of the adjacent soil. A cave – in can drop several cubic meters of soils on trench worker. Excavation: Excavation is a man made cut, cavity, trench or depression in an earth surface or sub-surface, formed by earth removal. Excavation Notification: Excavation Notification is a document to notify concerned authorities, who have responsibility and jurisdiction for safety & integrity of aboveground and / or underground services existing at the proposed site of excavation. Good Soil: Cohesive soil with an unconfined compressive strength of 1.5 tons per square foot (144 kPa) or greater. Manual Excavation: The excavation without using any powered equipment or excavating machinery such as backhoe, loader, Jack Hammer etc. Mechanical Excavation: The excavation work using powered equipment or excavating machinery such backhoe, loader, Jack Hammer etc. Medium Soil: Cohesive soil with an unconfined compressive strength greater than 0.5 tons per square foot (48 kPa) but less than 1.5 tons per square foot (144 kPa). Revision Date: 18th February 2014

Control Tier: 3 Uncontrolled Copy If Printed

KOC.SA.026 - Excavation Safety Procedure Page 2 of 14

Metal Detector: It is a device to screen the excavation area to mitigate the risk of damaging unknown pipelines, cables and utilities. Poor Soil: Cohesive soil with an unconfined compressive strength of 0.5 tons per square foot (48 kPa) or less. Shoring: Shoring involves the use of engineering structures (such as cross braces, vertical & / or horizontal rail, polling boards etc.) to support a trench side walls. Sloping: Sloping is angling the sides of an excavation to prevent cave – ins.

3.0

General Requirements 

4.0

KOC HSEMS Element HSE 5-2

Key Responsibilities 4.1

Permit Issuer 

Ensure safety & integrity of the worksite prior to issuance of appropriate permits (Cold Work Permit for Manual Excavation and Hot Work Permit for Mechanical Excavation) and related Job Safety analyses (JSAs) for safe work execution.



Ensure that the Excavation Notification had been filled up and signed by all concerned Teams representatives by verifying the drawings.



Ensures that all mobile equipment used at worksites possess valid clearance certificates as per HSEMS Procedure KOC.SA.013 for “Mobile Equipment”.



Check the site for restoring to original conditions before closing the work permit and excavation notification.



Inform Fire Team if the excavated area may cause obstructions to the main access to the facility and major operational areas such as Storage Tanks without alternate routes.

4.2

Permit Applicant / Initiator of Excavation Notification 

Initiate Excavation Notification informing concerned authorities, who have responsibility and jurisdiction for safety & integrity of aboveground and / or underground services existing at the proposed site of excavation.



Enclose drawings & sketches (with the Excavation Notification) marking the proposed site of excavation.



Identify the above / underground services (such as pipelines, cables, sewage, flume, tunnel etc.) before excavating the area without damage to those services.



Obtain necessary Explosive Ordinance Disposal (EOD) clearance certificates as per HSEMS Procedure KOC.SA.025 for “Handling of Explosive Materials, Substance and EOD”.



Ensure risk assessment and mitigation of potential hazards associated with proposed excavation work as part of Job Safety Analysis (JSA) prior to applying the appropriate work permit (Cold Work Permit for Manual Excavation and Hot

Revision Date: 18th February 2014

Control Tier: 3 Uncontrolled Copy If Printed

KOC.SA.026 - Excavation Safety Procedure Page 3 of 14

Work Permit for Mechanical Excavation) for carrying out excavation work. Please refer to sub-sections 5.1 & 5.2 of this procedure for additional information. 

Ensures that all necessary materials used for cave-in protection & isolation (like hard barricades, warning signs & flash lights) of the excavated trench/area are available at worksite before commencement of the excavation.



Ensure that earthworks are not commenced until the Permit Issuer approves the methods of excavation, the means of support to sides of excavation, the safety and support of neighboring private and public property, the system of dewatering, the demolition of existing surface and underground structures and obstacles, moving of any existing services, pipes, culverts and the like on the side or affecting the works.



Ensure that the excavation is compacted and backfilled after the work is over.

4.3

Worksite Supervisor 

Must not excavate without a valid excavation notification & authorized work permit.



Ensure safety & suitability of the equipment & materials to be used for excavation.



Conduct Tool Box Talk briefing the workers on potential hazards and precautionary measures to be taken during excavation activities.



Verify the existence of above / underground services before excavating the area.



Barricade the site of excavation along with the reflective warning notices, signs and flashing lights to alert the people approaching worksite.



Ensure that job information are posted on each excavated area for traceability purpose: Contract Number, Contract Title, Superintendent of the Contract, Controlling Team, number of work permit and excavation notification, contact numbers in case of emergency, etc.



Check the excavation safeguards (such as shoring, sloping & supporting system) daily before starting the job & after every rain storm or other hazardous occurrence.



Fill the excavation checklist (Refer to Appendix 1) ensuring safety & integrity of the worksite.



Take all necessary steps to protect any existing services, drains, water and gas mains, power and telephone cables and the like endangered by excavations and/or slips and falls, and shall affect all necessary repairs. If any such utilities are encountered, the pipes, cables, etc., shall be protected as directed by the Permit Applicant or Asset Owner for Above / Underground Services.



Separate the excavated soil into those suitable for fill and those unsuitable for backfill.



Remove the materials unsuitable for backfill shall, as soon as practicable, preferably immediately after excavation and other from the site and legally disposed off as per HSEMS Procedure KOC.EV.008 for “Waste Management”.

Revision Date: 18th February 2014

Control Tier: 3 Uncontrolled Copy If Printed

KOC.SA.026 - Excavation Safety Procedure Page 4 of 14

4.4

Asset Owners for Above / Underground Services 

The respective asset owner for aboveground / underground services will indicate (in the Excavation Notification); the required precautionary measures to be taken preventing any damage to those services at the proposed site of excavation.



Mark in the drawings / sketches attached to the Excavation Notification the locations and depths of the services.

4.5

Asset / Directorate HSE Teams 

Conduct periodical inspection of excavation site to assure the procedural compliance.



Advise the Permit Applicant, Permit Issuer and Worksite Supervisor for corrective measures in case discrepancy is noticed at the site of excavation.

4.6

5.0

Fire Team 

Assess the risk and mitigation needed in case of bund wall cutting or excavation works that might affect the integrity of the bunded area and its ability to act as a secondary containment during storage tank leaks.



Endorse the Excavation Notification ensuring required control measures against the bund wall cutting or excavation work affecting the integrity of the bunded area for the storage tank.

Safety in Excavation 5.1

Hazards of Excavation

The following hazards may be encountered while excavating or working inside a trench: 

Cave – ins or collapse of soil / earthwork



Buried alive under earthwork / collapsed soil



Underground obstruction or damage to buried pipelines & services



Accidental fall of personnel or equipment inside a trench



Struck / hit by excavating machinery



Dropped / falling objects



Flammable & / or toxic gas release



Exposed to airborne contaminants



Fire & explosion



Electrical shock due to contact with energized electrical / telecom cable.



Drowning due to water seepage into trench



Soil vibration due to machinery / heavy vehicles operations in the vicinity.



Possible presence of explosive devices



Lack of Oxygen or asphyxiation

Revision Date: 18th February 2014

Control Tier: 3 Uncontrolled Copy If Printed

KOC.SA.026 - Excavation Safety Procedure Page 5 of 14



Damage to shallow underground services due to weight of heavy equipment such as mechanical excavator.



Encountering wet soil (mixed with water) or reaching water table.



Encountering contaminated soil

The above – mentioned list is not exhaustive and it is recommended to carry out a site specific risk evaluation to identify additional hazards as well as to incorporate mitigation accordingly. 5.2

Control of Excavation Hazard

Excavation accident can only be prevented by identifying & controlling their inherent hazards by: 

Evaluating the hazards at site before and after excavation



Site Specific Risk Assessment & Job Safety Analysis



Approval and authorization through Excavation Notification & Work Permit

Based on the site specific risk evaluation; an excavation plan shall be developed and attached to the excavation notification form. The following aspects shall be addressed in the plan: 

Size and purpose of excavation



Proposed excavation method (i.e. manual or mechanical)



Nature of soil being excavated.



Nature of soil surrounding the excavation



Stability of adjacent structure



Static and dynamic loads near the excavation



Position of any underground services (such as pipelines, cables, utilities)



Sources of soil vibration



Traffic condition on the adjacent road



Nearest road for quick access / egress from the site



Weather & soil moisture condition



Existence of Plant and equipment beside the excavation.



Slope of the ground around excavation site.



Overhead electrical cables over or around the site.



Presence of manifold / flowlines



Presence of Process pits, sewage pits, burn pits, flares, etc.



Public safety



The length of time the excavation is to remain open



Control measures Revision Date: 18th February 2014

Control Tier: 3 Uncontrolled Copy If Printed

KOC.SA.026 - Excavation Safety Procedure Page 6 of 14

5.3

Excavation Notification & Work Permit

Excavation Notification & appropriate work permit(s) are essentially required for all excavation work regardless of its depth. The following considerations shall be taken into account in this regard: a) Prior to raising an Excavation Notification, the proposed site of excavation must be thoroughly inspected to assess any underground / aboveground obstructions such as pipelines, cables, manholes, fire hydrants etc. b) The excavation notification must accompany a clear drawing of the proposed excavation site to help specifying precautions prior to its endorsement. c) The excavation notification shall be endorsed by concerned authorities, who have responsibility and jurisdiction for safety & integrity of above / underground services existing at the proposed site of excavation. d) In case of cutting the bund wall or excavation works that might affect the integrity of the bunded area and its ability to act as a secondary containment during storage tank leaks, the Excavation Notification shall be endorsed by Fire Team. e) In addition to excavation notification, a hot work permit shall be required for any excavation work involving mechanical excavator; whereas cold work permit is needed for manual excavation. f)

The excavation notification as well as work permit must be cross referenced with the other live permits & excavation activities in the vicinity of proposed excavation site.

g) Job information shall be posted on each excavated area for traceability purpose: Contract Number, Contract Title, Superintendent of the Contract, Controlling Team, number of work permit and excavation notification, contact numbers in case of emergency, etc. h) For safe excavation jobs, the flowchart in Appendix 2 shall be followed. 5.4

Control Measures for Excavation

The following precautionary measures must be taken to ensure safety of the personnel as well as integrity of the worksite: a) No excavation work in KOC area shall be taken without ensuring Explosive Ordinance Disposal (EOD) clearance for that location. b) No mechanical excavation shall take place closer than 5 meters to any hydrocarbon carrying pipeline. Such restriction will apply even for levelling (with the use of mechanical excavator) at a worksite near hydrocarbon carrying pipelines. c) Similarly no mechanical excavation shall take place closer than 3 meter to a nonhydrocarbon carrying pipeline, cables and services. However for any mechanical excavation closer than 3 meter to pipelines, cables or services, it is recommended to apply Management of Change, thorough risk assessment and control measures. d) In order to reduce the risk of striking the pipe or underground services, the excavation will start at the side of the pipeline or midway between parallel lines. Manual slit trench shall be done along the length of identified underground services at appropriate intervals in the area marked for excavation in order to expose and positively locate such known or suspected underground services before commencing the use of

Revision Date: 18th February 2014

Control Tier: 3 Uncontrolled Copy If Printed

KOC.SA.026 - Excavation Safety Procedure Page 7 of 14

mechanical excavator at the work site. The appropriate interval for pilot slit trench shall be indicated in the Job Safety Analysis (JSA) sheet. e) Manual Slit trench in X-cut, shall be performed to ensure that underground services are identified, if any, prior to excavations for temporary & permanent Evaporation Pit / Pond or any other deep foundation activities. f)

Ground conditions shall also be assessed to confirm additional protection for shallow buried services prior to deploying any mechanical excavator at site.

g) Excavations adjacent to buildings or other obstructions may require temporary support, and accordingly the relevant safety instruction must be stated in the Excavation Notification before taking up excavation activity. h) Use of trench-box, while working inside trenches at close vicinity of roads / Heavy vehicle movement. i)

For any excavation deeper than 1m, suitable ladder must be positioned projecting a minimum of 1 metre above the edge of the excavations. Ladders shall be provided every 7.5 meters (25 feet) of lateral travel in the trench. Ladders shall be securely supported at the bottom as well as at the top. Where provision of ladders is not feasible, access & egress shall be provided by means of a ramp, steps, stairways or any suitable safe means of access.

j)

Any walkway across trench shall have scaffold type platform with handrails to protect personnel from falling into it.

k) All trenches shall have barrier (such as fixed guardrails) and reflective warning notices clearly displayed. Flashing lights are mandatory during poor visibility. l)

Excavated material shall be placed at a distance not less than 1m from the edge of the excavation for depth up to 1.2 meter. Accordingly placement of excavated material shall be increased proportion to the depth of excavation.

m) Adequate measures shall be taken to remove the piled up soil at the edge of excavation on a regular basis. n) Heavy equipment, material or excavating machinery shall be kept clear from the excavation area by at least 3 metres away. o) The access to plant, equipment and emergency services must not be obstructed by the trenches. p) The trenches shall not be left uncovered in the plant area and must be backfilled immediately on completion of work. q) For the non-plant area, the trenches may be left covered and barricaded up to the expiry of the work permit. In such cases, the same must be specified on the work permit and the Permit Issuer must be informed for his approval. Necessary control measures shall be indicated in the Job safety Analysis and implemented carefully by the Permit Applicant and the Worksite Supervisor. r) No mechanical excavation is allowed inside the existing KOC facilities (Gathering Center, Booster Station, water injection and handling facilities, etc.) s) Personnel carrying out excavation work must use Personal Protective Equipment (PPE) in line with the requirements of HSEMS Procedure KOC.SA.010 for “Personal Protective Equipment” and as indicated in the Job Safety Analysis (JSA) sheet.

Revision Date: 18th February 2014

Control Tier: 3 Uncontrolled Copy If Printed

KOC.SA.026 - Excavation Safety Procedure Page 8 of 14

t)

Employees exposed to public vehicular traffic shall be provided with, and shall wear; warning vests or other suitable garments marked with or made of reflectorized or high-visibility material. As per KOC.SA.036 for “Safe Work Practice While Working on Road”.

u) Equipment which are run on internal combustion engines shall not be kept inside the excavated area to prevent accumulation of toxic smokes such as Carbon Monoxide (CO) and Carbon Dioxide (CO2). 5.5

Inspection of Trenches

To identify and control hazards all parts of a trench and its safeguards must be inspected by the Worksite Supervisor everyday in consideration to following issues: a) All materials to be used in shoring & support must be inspected for its suitability b) The timbering and shoring must be checked for any strain or slackness before commencement of daily work. Moreover timbering and shoring must also be checked carefully after heavy rains and or exposure to high temperature. c) All excavations must be carefully inspected following after any event that may have affected their strength or stability such as heavy rains for collapse of trenches or fall of equipment or materials inside. d) If an unsafe condition is found or suspected, work in trenches must stop until the necessary precautions have been taken to control the hazards. e) Necessary records of inspection of trenches should be maintained. 5.6

Excavation Process 5.6.1

Excavation in Good Soil

a) For excavations in good soil, shoring is not usually required, provided the excavations depth does not exceed more than one metre b) If the surface area permits, greater depth can be made by sloping the side down to an angle of 45°. c)If surface area is limited and needed excavation depth is more than one metre, then polling boards must be placed approximately two metres apart with horizontal brace (support), whereas horizontal brace should not be more than one metre apart. d)

Where a long trench is being made, the mechanical digging must be limited to approximately two metres ahead of shoring to give a protected position.

Revision Date: 18th February 2014

Control Tier: 3 Uncontrolled Copy If Printed

KOC.SA.026 - Excavation Safety Procedure Page 9 of 14

5.6.2

Excavation in Medium Soil

a) If the depth of the excavation exceeds one metre, shoring must be used. Sheeting shall project at least 450mm (18") above ground level to prevent falling objects. The polling boards should be placed not more than 750mm (30") apart facing the wall, whereas horizontal brace should not be more than one metre apart. b) Extra polling boards should be inserted across if the condition of the ground deteriorates. 5.6.3

Excavation in Loose Sand or Poor Soil Condition

If excavations are to be made in loose sand or poor soil condition, then close sheeting or continued series of polling boards shall be used. The polling board & walling shall have a minimum cross-section as mentioned hereunder:

5.6.4



Polling board = 200mm x 50mm, (8" x 2")



Walling = 150mm x 50mm (6" x 2")

Using Excavation Machinery

The use of excavating machinery (such as backhoe, jack hammer, loader etc.) near above / underground services will require a Hot Work Permit in addition to Excavation Notification. The following precautions are to be taken while using mechanical means of excavation: a) Extreme care shall be taken to prevent any damage to above / underground services or power lines while using mechanical excavators. b) A mechanical excavator shall not be used until all underground obstructions have been uncovered through manual excavation. Once underground services are exposed the area should be further excavated manually as per clause 5.4 b & c on either side of the exposed services before using mechanical excavator. c) Mechanical excavation shall not be carried out while personnel are inside the trench/excavation.

Revision Date: 18th February 2014

Control Tier: 3 Uncontrolled Copy If Printed

KOC.SA.026 - Excavation Safety Procedure Page 10 of 14

d) The machinery operator shall take extra care and follow banksman instruction while reversing or turning the excavator to prevent any accidental strike to the workers or equipment at location. e) The bucket must always be lowered to the ground if the loader or backhoe is not in operation. f)

The machinery operator shall take necessary care to prevent exhaust gases entering the nearby trench or pit, in case personnel are working inside it.

g) Workers should not be permitted to work under raised loads and must be protected from loads or objects falling from equipment involved during excavation. 5.6.5

Prevention of Accidental Fall inside a Trench

Adequate fencing, barriers and reflective warning notices are to be provided around any excavated area to alert and prevent accidental fall into it. Posting flaggers and / or watchman will be required if the trench is in a heavy traffic area. It is also recommended to illuminate the excavated area in the night and provide flashing hazard light. Any person entering the barricaded area must follow safety procedures to eliminate fall from height hazard in line with requirements of HSEMS Procedure KOC.SA.031 for “Working at Height”. Where equipment, workers or public are required or permitted to cross over a trench; then it is essential to provide a close – planked bridge or walkway with standard guard rail. 5.6.6

Trench as Confined Space

An excavation that exceed 1.2 meter shall be treated as Confined Space and shall be checked for toxic gas, flammable gas as well as lack of oxygen. In such situation the requirement as applicable to Confined Space Entry Permit will be adhered.

5.6.7

Backfilling & Reinstatement

If a trench is no longer needed then it has to be backfilled returning the area around it to its original condition. The following precautionary measures to be considered while backfilling a trench: a) Backfilling and removal of trench support shall be taken from the bottom of the trench layer by layer.

Revision Date: 18th February 2014

Control Tier: 3 Uncontrolled Copy If Printed

KOC.SA.026 - Excavation Safety Procedure Page 11 of 14

b) The trench will be backfilled up to the level that allows removal of lower brace. After removing lower brace, the trench will be backfilled further to remove next level of braces. This process will be repeated until the trench is completely backfilled. c) In case of soil being unstable; the removal of brace / trench support shall be made with ropes from outside the trench without worker entry it. d) Removal of trench support shall be done slowly preventing collapse of side wall. e) Any surplus excavated materials shall be removed from the site making it tidy and compact. f)

No contaminated soil shall be used for backfilling, whereas contaminated soil shall be disposed complying with HSEMS Procedure KOC.EV.008 for "Waste Management".

g) On completion of backfilling; the area including walkways, access roads, drainage etc. shall be reinstated to a condition equivalent to that before the commencement of excavation work. h) Excavations shall be backfilled in 150mm layers in such a manner as not to disturb the structure, and be solidly rammed down and tamped with proper tools made for this purpose.

6.0

Key Documents / Tools / References  HSEMS Procedure KOC.EV.008 for “Waste Management”  HSEMS Procedure KOC.SA.001 for “Control & Use of Stepladders”  HSEMS Procedure KOC.SA.004 for “Permit to Work”  HSEMS Procedure KOC.SA.007 for “Entry into Confined Space”  HSEMS Procedure KOC.SA.010 for “Personal Protective Equipment”  HSEMS Procedure KOC.SA.013 for “Mobile Equipment”  HSEMS Procedure KOC.SA.024 for “Job Safety Analysis”  HSEMS Procedure KOC.SA.25 for “Handling of Explosive Materials, Substance and EOD”  HSEMS Procedure KOC.SA.031 for “Working at Height”  HSEMS Procedure KOC.SA.036 for “Safe Work Practice While Working on Road”  Standard Guideline KOC.S.001 for “Safe Roads, Road Closure and Installation of Display Boards/ Signs on KOC Roads”  Appendix 1 - Excavation Checklist  Appendix 2 - Excavation Flowchart

7.0

Abbreviations 

CO – Carbon Monoxide



CO2 – Carbon Dioxide Revision Date: 18th February 2014

Control Tier: 3 Uncontrolled Copy If Printed

KOC.SA.026 - Excavation Safety Procedure Page 12 of 14

8.0



EOD – Explosive Ordinance Disposal



HSE – Health Safety & Environment



HSEMS – Health Safety & Environment Management System



JSA – Job Safety Analysis



KOC – Kuwait Oil Company



kPa – Kilo Pascal



PPE- Personal Protective Equipment

HSE Records (Retention Time) 

Excavation Checklist Records (1 Year)



Trench Inspection Records (1 Year)



Excavation Notification (Refer Permit to Work Procedure KOC.SA.004)

Review/Revision Log: Review / Revision Date

Revision Details

1st May 2008

Drafted the procedure

21st May 2008

Draft circulated among HSEMS Implementation Committee for review

15th June 2008

Reviewed & approved. by HSEMS Implementation Committee

25th August 2008

Document approved by Technical & Administrative Approvers

31st May 2011

Clause1.0 Services added, Clause 4.4 3rd bullet rephrased, clause 4.6 retitled and 2nd bullet rephrased, Clause 5.1 - 3 bullets points added, Clause 5.4 bullet c),d) &J) rephrased and new bullets (n), (o) & (p) added, Clause 5.6 sub clauses renumbered, Clause 5.6.4 Bullet b) & c) rephrased, Clause 5.6.5 Referred working at height procedure , Clause 6.0 new document added, Clause 7.0 & 8.0 added to aligning with Document Control Procedure & Added Not Applicable column on the Checklist

18th February 2014

Changed Procedure Title. Added sub-surface excavation to the scope. Added definitions for good, medium and poor soil as per OSHA. Updated requirements for Fire Team notifications. Allowed the nonclosure of excavated areas in non-plant areas up to the expiry of the work permit.

Revision Date: 18th February 2014

Control Tier: 3 Uncontrolled Copy If Printed

KOC.SA.026 - Excavation Safety Procedure Page 13 of 14

Appendix 1 Excavation Checklist Location:………………………………………………………………………………………………………Permit No. ………….……………………. S. No 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

Description of Checks & Measures

Yes

No

Not Applicable

Remarks

Required & to be reviewed

The proposed area of excavation is EOD cleared and certificate obtained Asset owner contacted & permission / clearance obtained before excavation. The proposed location checked with appropriate detectors for any underground services Slit trenching to locate any underground services Only manual excavation will be carried out Excavation to be carried out by mechanical means only Excavation to be carried out both utilizing manual & mechanical means. Protection provided to control source of ignition for equipment to be used in hazardous area. Earthmoving & other mechanical equipment are fixed with approved spark arrestor Electrical wiring, termination joints & battery terminals of excavating machinery are safe.

Excavation area to be isolated partially / completely from other adjacent facilities. Temporary supports are required for existing underground services to protect from exposure due to excavation. Area of excavation requires continuous Gas (flammable & toxic) monitoring. Fire protection (portable or fixed) system required. Staff protected from cave-ins & loose rock / soil that could roll into the excavation. Excavation area is provided with safe access Area of excavation properly barricaded and danger signs (e.g. warning tape, reflective cone, safe cross over with handrail, flashing light etc.) are provided. Area of excavation / trenches is to be protected against possible ingress of rainwater / spilled liquid from adjacent facilities. Excavation will not lead to water / liquid ingress through the trench into adjacent building. The site of disposal for excess excavated material is determined Banksman / Signalman for excavating machinery operator is required. Continuous onsite supervision required during excavation work. Safe detour / by-pass along with warning signs are provided as per requirement. Excavated area backfilled, compacted and made as original.

Name of Worksite Supervisor: ……………………………………………….Designation: …………………………………..Id. No. …….……… Controlling Team: ………………………………………………… …………..Signature: ……………………………………..Date …………….. Control Tier: 3

Revision Date: 18th February 2014 Uncontrolled Copy If Printed

KOC.SA.026 - Excavation Safety Procedure Page 14 of 14

Appendix 2 - Excavation Flowchart Need for Excavation Work (The Initiator to raise the Excavation Notification)

Endorsement of Excavation Notification (By all concerned Teams / Groups)

Is endorsement complete?

No

Take remaining Endorsement

Yes Apply for Appropriate Work Permit (By Permit Applicant)

No

Are potential hazards identified & mitigated? (In association with Permit Applicant & Issuer)

Address the hazard

Yes Worksite Supervisor completes Excavation Checklist

Work Permit authorized by Issuer

Excavation work carried out safely.

Work is complete & trenches no more needed

Backfill the trenches safely & return the area to original condition

Site condition verified & Permit Closed

Revision Date: 18th February 2014

Control Tier: 3 Uncontrolled Copy If Printed

View more...

Comments

Copyright ©2017 KUPDF Inc.
SUPPORT KUPDF