KAPCO Internship Report

July 8, 2017 | Author: MIan Muzamil | Category: Transformer, Gas Turbine, Inductor, Electric Generator, Electromagnetic Induction
Share Embed Donate


Short Description

KAPCO field study of six weeks....

Description

Chapter 01 Introduction Kot Addu Power Plant (the "Power Plant") was built by the Pakistan Water and Power Development Authority ("WAPDA") in five phases between 1985 and 1996 at its present location in Kot Addu, District Muzaffargarh, and Punjab. In April 1996, Kot Addu Power Company Limited ("KAPCO") was incorporated as a public limited company under the Companies Ordinance, 1984 with the objective of acquiring the Power Plant from WAPDA. The principal activities of KAPCO include the ownership, operation and maintenance of the Power Plant. Kot Addu Power Company Limited ("KAPCO") was incorporated in 1996 with the purpose to contribute economic power to the national grid. KAPCO has shown exceptional results in the area of plant maintenance, availability, quality standards and financial performance. In April 2005

KAPCO

was

formally

listed

on

all

the

three

Stock

Exchanges.

KAPCO is committed to contributing to Pakistan's economy by powering the lives of its people by continuously improving its performance through efficient systems, capable workforce and good governance. Kot Addu site is situated in District Muzaffargah, 100 KM north east of Multan on the left bank of river INDUS at a distance of 16 Km from TAUNSA BARRAGE. The area is surrounded by agricultural land stretched on the north and west side of Kot Addu. There are some adjacent areas covered with wind blown sand dunes which were formed with the passage of time. These sand dunes too are being gradually converted into agricultural land. Apart from above, there were very little educational facilities available in the area prior to setting up of this Power Station which has now almost been doubled and some of the School has been upgraded. The essential amenities are also now made available to the residents.

1.2 BRIEF HISTORY OF POWER HOUSE COMPLEX The complex comprises three blocks, 1, 2, and 3. Each block is independent in it and can be considered a separate power station. There are 2 combined cycle modules in each block no. 1 and 2 whereas block 3 has only one module. This is the physical distribution. For the 1

commercial purpose the complex is divided into three blocks called Energy block 1, 2, and 3. The power purchase agreement provides different energy charges for the electricity generated and dispatched from each block. The energy block 1 (plant block 3) is the latest and was in commissioning stage when NP took over management in June 1996 whereas other blocks were completed and commissioned between 1986-1995. The plant block 3, being latest, is the most efficient plant and provides the cheapest electricity to customer. Its total capacity is 397 MW. In order of priority, whenever there is generation demand from the customer, this block is run first. When the demand exceeds then only other plants are run. The complex history over past 4 years shows that plant block 3 runs round the clock throughout the year at maximum capacity. In case this plant can not run at full capacity due to any fault or break down of machines, the customer need is made up from other available plants that are relatively expensive but the customer pays lowest energy charges (of block 3) for the deficit generation. This results in significant loss. Therefore this block is the most valuable asset of the company. 1.2.1 HEAT RECOVERY STEAM GENERATING SYSTEM The gas turbines, despite of their low installation cost, easy and speedy erection and high loading rate could not win the deserving popularity over the steam turbines due to the poor efficiency of the former. In the conventional gas turbine unit, substantial amount of heat energy was lost through the turbine exhaust gases which leave the turbine at about 580 Deg. Centigrade. To make use of this wasteful energy, an innovative concept of combined cycle plant, now has been introduced by the gas turbine manufacturers. Under this design, the exhaust of the gas turbine is made to pass through a conduction type boiler (commonly called as HEAT RECOVERY STEAM GENERATOR). High-pressure steam so generated is then used to run the steam turbine, which thus produces power without any fuel. This raises the plant efficiency to nearly 49 % against the 28 % of the conventional gas turbine. 1.2.2 AGREEMENTS BETWEEN WAPDA & KAPCO WAPDA entered into an agreement with KAPCO for the purchase of the power for next 25 years from this plant. The tariff covered two kinds of payments viz. capacity and energy payment. The capacity payment is made on the available capacity of the plant and is mainly used by the company to meet the fixed expenses and 756 million dollar debt liability that it

2

inherited from WAPDA. The energy payment is done on the actual dispatch from the plant. It covers the fuel cost and there is hardly and saving from this part. The agreement allows 36 complex days for the scheduled outages and 500 complex hours for the unscheduled / forced outages. In case the accumulated outage period over the year exceeds the agreed allowance, the company is liable to pay the liquidated damages at a rate of 1.6 times of what it gets as capacity payment. The first year of the business went very well. WAPDA was prompt in making payments, but it did not lost very long. WAPDA as well as Govt. of Pakistan were in financial crises because of corruption and in efficiencies. Ultimately WAPDA engaged KAPCO and National Power in a complicated legal battle over the tariff issue by filing petitions in the high court. The court finally passed an interim order in October 1998 that restricts KAPCO to receive Rs. 1.98 per KWh of electricity. The objective behind this legal wrangling was to pressurize KAPCO / National Power to agree and out of court settlement for deduction of tariff. With the incoming of present Govt. the matters have been solved to fair extent. 1.2.3 VISION STATEMENT To be a leading power generation company, driven to exceed shareholders’ expectations and meet customer’s requirements. 1.2.4 MISSION STATEMENT •

To be a responsible corporate citizen



To maximize shareholders' return



To provide reliable and economic power for our customer



To excel in all aspects relating to safety, quality and environment

1.3 Blocks There are three blocks in the power plant. Block-1 GT 1,2,3,4 and ST 9, 10 GT 1, 2 Manufacturer

Siemens, Germany

Base load rating of GT at 15 °C

125 MW (HSD)

Base load rating of GT at 50 °C

96 MW (HSD)

3

GT 3, 4 Manufacturer

GIE, Italy

Base load rating of GT at 15 °C

96 MW (HSD)

Base load rating of GT at 50 °C

73 MW (HSD)

ST 9, 10 Manufacturer

ABB, Germany

Rated power Steam turbine

112 MW with 2 HRSG’s

Block-2 GT 5,6,7,8 and ST 11, 12

GT 5,6,7,8 Manufacturer

Alstom, France

Base load rating of GT at 15 °C

106 MW (HSD)

Base load rating of GT at 50 °C

81 MW (HSD)

ST 11, 12 Manufacturer

RATEAU, France

Rated power Steam turbine

103.4 MW with 2 HRSG’s

Block-3 GT 13, 14 and ST 15

GT 13, 14 Manufacturer

Siemens, Germany

Base load rating of GT at 15 °C

139 MW (HSD)

Base load rating of GT at 50 °C

108.6 MW (HSD)

ST 11, 12 Manufacturer

Siemens, Germany

Rated power Steam turbine

148.6 MW with 2 HRSG’s 4

Chapter 02 Safety The basic need of the safety is to prevent human being from any type of injury. 2.1 General Safety: Security is first stage of safety. When we working in the plant area we should use PPE’s (Personal Protection Equipment’s) They are mention as below: 

Helmet



Overall



Safety shoes



Goggles



Ear plug/ muff



Gloves

Helmet: It prevent us from the head injury.

Overall: It’s a special type of dress and this dress is fit to body. Loose dress may be cause of any accident.

5

Safety Shoes: They are prevent us from slipping and if something fell down they can bear 25kg weight by its toe and prevent us by feet injury.

Goggle: It is used to save our eyes from dust.

Ear Plugs: An earplug is a device that is meant to be inserted in the ear canal to protect the user's ears from loud noises produced by the heavy machines, dust or excessive wind.

Gloves: Gloves protect and comfort hands against cold or heat, damage by friction, abrasion or chemicals, and disease; or in turn to provide a guard for what a bare hand should not touch. They prevent us from hand injury.

6

2.1.1 Special PPE’s:There are some special PPE’s used in KAPCO which are mention below: 

Harness



Face shield

Simply, we can say that safety is the basic need of any place where hazards are occurred, In KAPCO there are many hazards some are mention below: 

High temperature



Noise



High voltage



Chemicals



Rotating machines

2.2 Emergency Situation:2222 is the emergency number in the KAPCO. If you found any type of emergency in KAPCO you can call at 2222 as soon as possible for the help. There are many spots are provided from where you can call at this number 2222. 2.2.1 Alarm: Here in KAPCO there is an alarm system for emergency situations. This alarm system checked every Monday at 11:00am. 

Accident alarm will ring with continuous sound for 1.5min.



Evacuation alarm will ring with wobbling sounds for 3min.



Clearance alarm will ring with continuous sound for 0.5min.

2.2.2 Muster Point: There are two muster point. When an evacuation alarm rings then all workers will reach at the possible muster point with no time. 2.3 Fall Protections: Any edge whose height more than 6 feet we should Use protection if we cannot use protection we can fell down. If you see an open grill anywhere in plant area you can inform at 2222 as emergency situation. You should not cross that area which is covered by red tape. 7

Chapter 03 Combines cycle power plant A combined cycle is characteristic of a power producing engine or plant that employs more than one thermodynamic cycle. Heat engines are only able to use a portion of the energy their fuel generates (usually less than 50%). The remaining heat (e.g. hot exhaust fumes) from combustion is generally wasted. Combining two or more “cycles”. 

Brayton cycle



Rankine cycle

In a combined cycle power plant (CCPP), or combined cycle gas turbine (CCGT) plant, a gas turbine generator generates electricity and the waste heat is used to make steam to generate additional electricity via a steam turbine; this last step enhances the efficiency of electricity generation. In a thermal power plant, high-temperature heat as input to the power plant, usually from burning of fuel, is converted to electricity as one of the outputs and low-temperature heat as another output. As a rule, in order to achieve high efficiency, the temperature difference between the input and output heat levels should be as high as possible. This is achieved by combining the Rankine (steam turbine cycle) and Brayton(gas turbine cycle) . bulky components. High temperatures require expensive alloys made from nickel or cobalt, rather than inexpensive steel. These alloys limit practical steam temperatures to 655°C (while the In a thermal power station water is the working medium. High pressure steam requires strong,lower temperature of a steam plant is fixed by the boiling point of water. With these limits, a steam plant has a fixed upper efficiency of 35 to 42%. Difference between open cycle and combined cycle: An open circuit gas turbine cycle has a compressor, a combustor and a turbine. In this type of cycle, the input temperature to the turbine (the firing temperature), is relatively high (900 to 1,400 0c). The output temperature of the flue gas is also high (450 to 650 0c). This is therefore high enough to provide heat for a second cycle which uses steam as a working fluid; (a Rankine cycle) In a combined cycle power plant, the heat of the gas turbine's exhaust is used to generate steam by passing it through a heat recovery steam generator (HR5G) with a live steam 8

temperature between 420 and 580 0c. The condenser of the Rankine cycle is usually cooled by water from a lake, river, sea or cooling towers. This temperature can be as low as 15 °C. Combined cycle plants are usually powered by natural gas; although fuel oil, synthesis gas, Furnace Oil, High speed diesel or other fuels can be used. The supplementary fuel may be natural gas, fuel oil.

Combined cycle components: 

Gas turbine



Heat recovery steam generator (HRSGs)

3.1 Gas turbine: The major component of the combine cycle power plant is the gas turbine. In installation where the gas turbine exhausts directly to the atmosphere, it is said to be operating in “open cycle” mode. When a gas turbine exhausts into a heat recovery steam generator (HRSG) the resultant steam is used to operate a steam turbine generator, the plant is referred to as a combined cycle power plant. A common arrangement of a gas turbine driving an electric generator is shown in figure. The basic gas turbine consists of a compressor, a combustion chamber and a turbine. The air is drawn into the compressor, which raise the pressure. The temperature also increases with compression and may be as high as 350°C at the compressor discharge.

Main components of gas turbine: 

Intake air filters



Compressor



Combustion chamber



Turbine



Exhaust diffuser

9

3.2 HEAT RECOVERY STEAM GENERATOR(HRSG) The HRSG is basically a heat exchanger composed of a series of economiser,evaporator and super heater sections.These sections are positioned from gas inlet to gas outlet to maximize heat recovery from the gas turbine exhaust gases. The heat recovered in the HRSG is used to supply steam to the steam turbine at the proper temperature and pressure. In open cycle mode of operation,the temperature of exhaust gases of unit 1 and 2 leaving KAPCO is 500° C to 550° C. High temperature gas represents a source of heat energy,some of which can be recovered if the means to do are available. By recovering some of this waste heat,the output and the efficiency of a power plant is increased. The function of heat recoThe function of heat recovery steam generator (HRSG) is to recover the waste heat available in these exhaust gases and transfer that waste heat to water and steam.The heat is used to generate steam at high pressure and high temperature.The steam is then used to generate additional power in a steam turbine driven generator.The HRSG provides the critical link between the gas turbine and the rankine cycle in a combined cycle plant. The HRSG is a key component in combined cycle efficiency. HP section The HP section consists of Economizer, Evaporator, and Circulation system for economizer and evaporator and Super heater. LP section The LP section consists of Evaporator and Circulation system for evaporator. The re-circulating pumps cause the mechanically induced circulation in the boiler. 3.3 Generator: Synchronous generator or alternator is used to convert mechanical energy into electrical energy. Its working principle is as follows: Working principle: According to Faraday’s law of electromagnetic induction: “If there is a relative motion between conductor and magnetic field, then an EMF will be induced into the conductor”. To create this relative movement, it doesn’t matter whether the magnet is rotating and the conductor is stationary or weather the conductor is moving and magnet is stationary. 10

The magnitude of the induced EMF is directly proportional to the No of conductors (N) and the rate of change of magnetic flux crossing the conductors.

E = N (dΦ/dt)

Difference between AC generator and DC generator: There is one important difference between an AC and DC generator. In DC Generator the armature rotates but the field system remains stationary but in AC generator the case is reverse because here armature remains stationary but field winding rotates. 3.3.1 Data Sheet: Type of generator

3 – phase

Type of winding

YY

Designed for frequency

50 Hz

Rating

135000 KVA

Designed for power factor (cos φ)

0.85

Sequence of phases

UVW

Type of excitation

External

Excitation voltage

333 V

Excitation current

641 A

Type of cooling

Air cooling

Max air cooling temp.

40°C

Stator weight

165 tons

Rotor weight

39 tons

3.3.2 Details of construction: The two pole generator uses directly air cooling for the rotor winding and indirect air cooling for the stator winding. All types of losses (iron, friction, windage, stray and etc) are also dissipated through air. Generally a generator consists of following parts: 

Stator



Rotor



Excitation system 11



Carbon brushes and Slip rings



Retaining rings



Bearing



Rotor grounding system



Cooling system

3.3.3 Stator: It is a stationary part of the generator. The stator has two main components: 

Stator frame



Magnetic core



Stator winding



Stator End shields

Stator frame: The frame is for to support the laminated core and winding and also for to increase the mechanical strength of the machine. It is the heaviest part of the generator. Air ducts are provided for the rigidity of stator frame. End shields are also bolted to this frame. For the foundation purposes feet are provided. Magnetic core: The stator core is stacked from insulated electrical sheet-steel laminations with a low loss index and suspended in the stator frame from insulated guide bars. The entire magnetic core is buildup of thin laminations in order to minimize the hysteretic and eddy current losses of rotating magnetic field which interact with core. Each lamination core is made up from a number of individual segments. The segments are punched in one operation from .35 thick electrical sheet steel lamination having high silicon content. The core is stacked with lamination segments in individual layers while being supported on the pressure plate. The segments are staggered from layer to layer so that a core of high mechanical strength and uniform permeability to magnetic flux is obtained. The No of slots are created in the core to accommodate the stator winding. The complete stack is kept under pressure and located in the frame by means of clamping bolts and pressure plates.

12

If there is any damage to the core occur during operation, then Alcid test is performed to check the insulation between layers. Stator winding: It is noble part of the generator. It is composed of conductors wedged into the magnetic core. Each stator slot accommodates two bars. There are two distinct parts of stator winding: The straight part is within magnetic core. The end winding which are outside the core and which serve to connect bars of different slots together to complete the winding. This winding is fractional pitch two layer type consisting of individual bars. In order to minimize the stray losses, the bars are composed of insulated strands which are transposed by 360°. According to the Moralistic system, high voltage insulation is provided by which several halfoverlapped layers of mica are applied to the bars. The mica tapped is sandwiched between two fabric layers with epoxy as an adhesive. The No of layers depends upon the machine voltage. This high voltage insulation obtained is characterized by excellent electrical, mechanical and thermal properties in addition to being fully waterproof and oil resinant. To minimize the Corona discharge between the insulation and the slot wall, a final coat of semiconducting varnish is applied to the surface of all bars within the slot range. Stator End shields The stator end shields are attached to the end of the stator frame. It contains the generator bearings and also the generator coolers. The generator coolers are accommodated in the vertical wells of stator end shields. The bearing oil is supplied to the bearing saddle via a piece permanently installed in the end shield and is then passed on to the lubricating gap via ducts in the lower bearing sleeve. The oil drained from the bearing is collected in the bearing compartment, then it is discharged from the lower half of the end shield and then is returned to the turbine oil tank. Electrical connection of bars and Phase connectors Electrical connection between the top and bottom bars is made by brazing. One top bar strand being brazed to one strand of associated bottom bar, so that the beginning of each strand is connected without having any electrical contact with the remaining strands. 13

This connection offers the advantage that circulating current losses in the stator bars are kept small. The phase connectors consist of flat copper sections, the cross section of which results in a low specific current loading. The ends of each phase are attached to the circular phase connector, which leads from winding ends to the top of the frame. The phase connectors are mounted on the winding support, using clamping pieces and glass fabric tape. 3.3.4 Rotor: It is the rotating part of the generator. It is driven by the turbine and it creates rotating magnetic field. There are two types of rotor: 

Cylindrical type



Salient-pole type

The cylindrical type rotor is used in turbo alternators and a having a uniform air gap. Normally it is used in all types of thermal power stations where the rotating speed of rotor is high like 3000 rpm in PAKISTAN. For 3000 rpm, it has two poles. The field winding is accumulated in slots on the solid rotor. Salient pole rotors are used for low speed operation like about 167 rpm for 50 Hz. For this arrangement, we use 36 poles of the rotor. Rotor has the following main components: Rotor shaft: The rotor shaft is made of single gorging whose ingot is made in an electric furnace and then vacuum cast. The rotor consists of an electrically active portion and the two shaft ends. A forged coupling is used to couple the rotor to the turbine. The longitudinal slots hold the field winding. Slot pitch is selected so that two solid poles are displaced by 180° electrical. In these slots field coils are milled into shaft body and is arranged so as to generate magneto motive force wave approaching a sine wave. Rotor teeth are provided with axial and radial ducts enabling the cooling air to be discharged into the air gap for intensive cooling of the end winding.

14

Rotor winding:

Rotor winding has also two distinct parts: The shaft contained in shaft body. The part outside the shaft body.

The rotor winding consists of several coils which are inserted into the slots and series connected such that two coil groups form one pole. Each coil consists of several series connected turns, each of which consists of two half turns which are connected by brazing in the end section. The insulated turns are insulated from each other by strips of laminated glass fabric. The edges of slots is made up of high conductivity material and they are there to act as damper winding. At the ends the clots are short circuited by retaining rings.

3.3.5 Excitation system: The excitation system is to supply the direct current to rotor which allows the generator to maintain a controlled voltage between it’s terminals when connected to the network. The excitation system is driven by a voltage regulator. The excitation power for the generator is supplied by an exciter with rotating diodes that are fitted at the end of main generator shaft. The excitation voltage is developed by rotating diode bridge that supplies the rotor winding. These rectifying diodes are given supply by an excitation transformer of which the primary winding is supplied by the main generator. Then the secondary winding is rectified by a three phase thyrister bridge. The excitation equipment, Slip ring, and carbon brushes are used to supply the excitation current to the rotor. If there comes a need to change the brushes of the machine during operation at full load or any load, brush gear assembly is used to do this job. During start up and in case of stator voltage drop, the excitation power is supplied by 220 V DC source. De- excitation of the generator is performed by the opening of the excitation contactor and a non linear resistor ensures the discharging of the exciter. Excitation connection: 15

The current supplied by excitation unit to the rotor winding is sent through D bars (central shaft connection), radial connecting rod, and outer axial connection that feed directly into the winding. It is made up of two D shaped solid bars, separated by a layer of insulation and housed in shaft bore. Carbon brushes and two slip rings arranged at the end of the shaft. The electrical connection between slip rings and rotor winding is established by means of radial bolts and insulated conductors arranged in hollow bore of rotor at the exciter end. 3.3.6 Carbon brushes and slip rings: Field connection provides electrical connection between rotor winding and slip ring. Steel slip rings are fitted to the shaft extension at the non-drive end and insulated from the end. The slip ring contains a uniform current distribution.

Carbon brushes are used to make live connection between the excitation system and rotor winding, because our rotor is moving continuously and this is the only option to make such a connection. The slip rings have axial and radial holes for ventilation of slip ring. This forced ventilation system ensure the removal of carbon dust sue to brush wear.

3.3.7 Retaining ring: The end winding which are extend beyond the shaft body are held against centrifugal forces by retaining ring of nonmagnetic steel cylinders. One end of each ring is shrunk on the rotor body, while other end of the ring over hangs the end winding without contacting the shaft. The shrunk on the end ring at the free end of the retaining ring serves to reinforce the retaining ring and also secures the winding in the axial direction. A snap ring is provided for additional protection against axial displacement of the retaining ring. To reduce the straw losses the ring is made up of non-magnetic material. Comprehensive tests such as ultra-sonic examination and liquid penetration examination ensure the specified mechanical properties.

16

3.3.7 Bearings: Bearing are used to lift the shaft, to make the vibration of rotor as small as possible and to make the friction during the movement of the shaft. As shaft is connected with bearing, this shaft is lifted by oil flowing in the bearing. Ta main purpose of using oil in these bearings is cooling of bearings which are heated because of running of the shaft. Friction is also reduced when we use oil in the bearing. To eliminate the shaft currents, all bearings are insulated from the stator and base plate respectively. The temperature of the bearing is monitored by thermocouples mounted in the lower bearing part so that the measuring points are located directly below the Babbitt.

3.3.8 Rotor grounding: Grounding system is necessary thing to make the generator grounded because when we are working at the generator then flux or static charge which was stored in the rotor winding during operation is needed to be grounded. That flux can be harmful if not grounded Grounding brushes are fitted to the stator end shield.

3.3.9 Generator cooling system The heat losses arising in the generator interior are dissipated to the secondary coolant (cooling water) through air. Direct cooling of rotor removes hot spots and differential temperature between the adjacent components. Indirect cooling is used for stator winding. Air and hydrogen are two cooling media for the generator cooling. The field and armature copper losses are evacuated by air/ hydrogen gas flowing inside the generator. The axial fans circulate the air. In KAPCO all generators are air cooled. Advantages of Air cooling 1.

lower cost price

2.

Easy maintenance

3.

Short inspection

17

3.3.10 Advantages of hydrogen cooling system 1. 2.

Windage losses of the rotor turning are only 1% of those in air. The higher thermal conductivity of Hydrogen allows generator to develop 25% more

output than those of air. 3. 4.

Hydrogen increases the life of generator because of the absence of Oxygen. The η of generator can be taken as 98% with air cooling and 99% with hydrogen

cooling.

3.3.11 Drawbacks of Hydrogen cooling 1.

Generator body must be gas tight.

2.

Special type of oil seal is used on the bearing to stop the leakage of Hydrogen.

3.

Precaution should be taken to prevent any air leakage into the machine.

4.

A mixture of air and hydrogen inside the machine casing is risky and may cause in

explosion

3.3.12 Stator cooling: The magnetic core is cooled by the air flowing through the radial vent ducts under the action of the fans. The vent ducts are formed by splitting up the core, along it’s whole length into packets separated from each other by radial spacer ribs. Core cooling is thus of radial type. The current flowing through the stator winding creates heat losses which are escaped to the core due to close contact between the winding and core. This is called indirect cooling. The end winding area is cooled circulation of air.

3.3.13 Rotor cooling: The main rotor heat losses occur in the field winding. It is dissipated by direct contact with air flowing through the coil. The slot portion of the winding is cooled circulating air. All rotor winding is subdivided into four cooling zones. One cooling zone includes the slots from center to the end of the rotor body, while another cover s half of the end winding.

18

This generator is now connected to the unit transformer converting the out put voltage into 132 kv(block 1) or 220 kv (block 2 & 3) which then goes to the switch yard for the transmission purposes. The cooling air for the slot portion is admitted into the slot bottom ducts below the rotor winding. The hot air is then discharged into the air gap between the rotor body and stator sore though radial opening in the conductors and in the rotor slot wedges. The cooling air is drawn from below the rotor end winding. It rises radially along the individual coils and is then discharged into the air gap via axial and radial slots in the end portion of the rotor teeth.

3.3.13 End winding cooling The end winding cooling circuit is independent of the slot portion cooling circuit. Part of the cold air passing under the end winding flows through the space between coil. Cold air enters through longitudinal ducts and warm air flows to the air gap through radial ducts.

3.3.14 Air cooling circuit Cooling air is circulated in the generator by two axial-flow fans on the rotor shaft. Cold air is drawn by fans from cooler and then divided into three parts. Flow path 1: Is directed into the rotor end winding and cools the rotor winding. Along this path heat of the rotor winding is directly transferred to the cooling air. Flow path 2: Is directed over the stator end winding to the cold air ducts and in the stator frame space between the generator housing and the stator core. Flow path 3: Is directed into the air gap via the rotor retaining rings. This path mainly cools the rotor retaining rings, the end of the rotor body and end portion of the stator frame. Then this flow of air is mixed up in air gap from where it goes for the cooling of the other remaining portion of the stator core and the stator winding. The hot air is returned to the cooler via hot air ducts recooling and draw again by the fans. Air cooler:

19

Air cooler is shell and tube type heat exchanger which cools the air in the generator. Four identical coolers are provided. The stator end shields contain the vertically mounted coolers. The cooler section is solidly bolted to the upper half of the stator end shield. All four coolers are parallel connected on their water side. The required cooling water flow depends on the generator output and is adjusted by control valves on the hot water side.

3.3.15 Abnormalities in generators:

Abnormal conditions that may occur with rotating elements include the following: 

Faults in windings



Overheating of winding



Over speed



Over load



Loss of excitation



Motoring of generator



Unbalance current operation



Out of step

Several of these conditions do not require that the unit is tripped automatically; they can be corrected while the machine remains in service. These conditions are signaled by alarms. Other conditions, however, such as faults, require prompt removal of the machine from service

20

Chapter 04 Transformers A transformer is a static machine used for transforming power from one circuit to another without changing frequency. This is very basic definition of transformer. 4.1 Working Principle of transformer

The working principle of transformer is very simple. It depends upon Faraday’s laws of Electromagnetic Induction. Actually mutual induction between two or more winding is responsible for transformation action in an electrical transformer.

4.2 Faraday’s laws of Electromagnetic Induction According to these Faraday’s laws,

"Rate of change of flux linkage with respect to time is directly proportional to the induced EMF in a conductor or coil". e= M dI / dt where e = Induced voltage M = mutual inductance dI = rete of change in the current dt = rate of change in time

If the circuit of the second coil is closed, current flows in it and so in this way electric energy is transferred from one coil to the coil. The first coil in which electric supply is connected is called the primary coil and other coil to which the power is supplied is called the secondary coil. In a brief transformer is a device that 4.3 Transfers electric power form one circuit to the other: 

It does so without change in frequency.



It accomplishes it by the electromagnetic induction.



Where two circuits are electrically isolated but magnetically coupled.

21

4.4 Voltage Ratio of Transformer: This above said ratio is also known as voltage ratio of transformer if it is expressed as ratio of the primary and secondary voltages of transformer.

4.5 Turns Ratio of Transformer: As the voltages in primary and secondary of transformer is directly proportional to number of turns in the respective winding, the transformation ratio of transformer is sometime expressed in ratio of turns and referred as turns ratio of transformer. 4.6 Types of the transformer In all types of transformer, the core is constructed of transformer sheets, steel laminations to provide a continuous magnetic path with minimum air gap. Transformers are classified by several means, 

According to Construction.



According function.



According to consumer.



According to connections.

4.6.1 According to Construction: Construction ally, transformers are of two general types. 

Shell type.



Core type.

4.6.2 According to functions: 

Power transformer

4.6.2.1 Power transformer: 

Two winding transformer



Three winding transformer



Auto transformer

4.6.2.2Special transformer: 

CT (Current Transformer)



PT (Potential Transformer)

22

4.6.3 According to consumer

Transformers are also classified by means that how a consumers uses it. 

Step up transformer

Here turns of secondary are large then that of primary. i.e. output voltage is greater than input voltage but on the other hand, primary current is large than that of secondary. 

Step down transformer

Here reverse process takes place than that of the step up transformer. Generally following type of transformers are used in our power house.

23

Chapter 05 Switch Yard Inside the switch yard Mainly there are different but most important things for the protection, measurement, metering and for the other purposes. 

Circuit Breaker



Isolator



Insulator



Insulator strings



Bus Bar



Current transformer (C.T.)



Potential transformer (P.T.)



Conductor



Control Switch



Relays

There are different type of schemes are used but in our block III one and half scheme is used.

ONE AND HALF SCHEME:

The benefit of this scheme is that if for example any fault occurs on any bus bar then the supply of the feeder will not disconnect. Then the supply will go to the second bus bar without an interruption. CIRCUIT BREAKER: As we know circuit breaker is an on load device it means that it can do proper work and do ON and OFF with safety due to supply. In these circuit breaker we used SF6 for arc quenching medium and these circuit breaker are air operated. And the air pressure becomes 18 bar.

24

ISOLATERS: While isolators are off load device means that it just like work as a fuse it do work only at off supply. Because it did not keep any arc quenching medium if we use at an on load supply then it will become damage ,So every bay consists of six isolators three circuit breaker and three current transformers, which measure the current and give protection. One isolator is used for generator protection it is installed in start of the bay. CURRENT TRANSFORMER: We also use the current transformer in Series of every bay. There are five coils of CT and three basic purposes of using CT. 

Measurement of the current.



Protection of the relays and breakers etc.



Metering



For the Breaker failure protection.

POTENTIAL TRANSFORMER: We also use the potential transformer in parallel of the bus bar. It is used to measure the voltages and it has been installed with the bus bar to measure the voltage across the bus bar. We are checking for high voltage and low voltage but carefully for the low voltage because the auxiliaries which we are running from this voltage will draw very high current if the voltage is very low and this can damage our equipment. So, we keep on checking for the low voltage and the high voltage. We have to use P.T. because we can’t design such a big voltmeter. BUS BAR: Now we discussed about the bus bars we are using two bus bars in KAPCO power plant, first of all we will define bus bar “Bus bar is a conducting piece of bar which connect among the source and the distribution circuit” It work as a medium between feeder and source. The bus bar voltages remain same. So the six feeders go out from the KAPCO power plant of 220KV and the six are 132KV.

25

Relays: These are operated by taking information from C.T. and P.T. Each and every thing of the system even in the switchyard is being protected by relays because they are made very much sensitive for the faults. They sense every fault for which it has been designed and then some other important devices are operated from the signal of the relay. There are many types of the relays, 

Differential over current relay.



Over current relay.



Over and under voltage relay.



Directional over current relay.

Similarly there are many other types of the relays which we will discuss later.

26

View more...

Comments

Copyright ©2017 KUPDF Inc.
SUPPORT KUPDF