JSA -Piling Work

July 5, 2019 | Author: muh_yusufs | Category: Safety, Labour, Nature
Share Embed Donate


Short Description

asas...

Description

FALIH SDN BHD

JOB SAFETY ANALYSIS

JSA/PILING DOC. NO.

1 OF 5 PAGE NO.

Project

Ladang 3, Kuala Terengganu Terengganu

Ref. No

HI / PILING

Title

Hazard Identification

Date Start

Nov 19, 2011

Scope / Location

Piling for Substructure Substruct ure

March 19, 2012

Personal Protective Equipment Safety Equipment

Safety helmet / safety boot /goggles

Completion Date Prepared Prepar ed By

Machinery / Tool / Equipment

Fire extinguisher / signage / safety signage 1. Hydraulic Injection Piling machine-3 nos.

Remark Manpower

2. Mobile crane -25 ton

 No 1

2

3

4

5

6

WORK ACTIVITY ACTIVITY 1. Mobilization of 3 numbers of hydraulic piling machine, tool equipments, counter weight and  parts to site. site. 2. Mobilization of various sizes of spun piles to site. Installation, Installat ion, testing & commissioning of piling machinery & equipments. Survey work for piling point & Install survey peg / Marking on ground

Lift-up of spun piles of various size & weight and piling works

Welding of extension piles.

Piling machine / generator generat or set leaks oil onto ground

Mohd Yahizan

HAZARD IDENTIFIED IDENTIFIED 1. Hit by machine & parts during unloading activity. 2. Hit by spun piles during lifting down from trailers

1. Struck by moving parts during installation of machine

1. Surveyor/chainman Surveyor/chainman knock down by piling machine

Supervisor Supervisor –2 Surveyor – 1 Chainman – 1 Cut-off pile head – 2 Piling Operator-3 Piling Worker - 10

SAFETY CONTROL CONTROL 1. Ensure safe download  procedure. 2. Ensure mobile crane & wire rope in good working condition . 1. Installation manual

1. Beware movement of  piling machinery. machinery.

REF 1. SOP 2.Crane checklist. 3.Delivery Schedule Machinery Manual

Piling Plan. .

2. Trip & fall into exposed  pile hole.

2. Cover-up exposed pile holes

1. Wire rope snapped during lifting of spun pile into piling machine.

1. Regular checking of wire rope sling before lifting of spun piles.

1. Spark & toxic gas from welding works Ground contamination with oil.

2. Replace damaged wire rope. 1. Wear eye protection. 2. Wear gas mask. 1. Regular maintenance of machinery & gen set. 2. Provide drip tray.

1.PM Crane 2. PMA 3.SOK

Welder Certification EQA 1974

FALIH SDN BHD

JOB SAFETY ANALYSIS

JSA/PILING DOC. NO.

Project

Ladang 3, Kuala Terengganu

Ref No

Title

Risk Assessment of Worker

Date

ESTIMATED MANPOWER Total workforce per day

ASSESSMENT POINT  No of Worker 0–4 5–8 9 – 12 13 -16 17 - 20

App. 17 workers

RAW / PILING November 19, 2011

Working Hours

No of Point 1 2 3 4 5

2 OF 5 PAGE NO.

8 hours per day

Exposure/Day 0 –2 3–4 5-6 7-8 9 - 10

No of Point 1 2 3 4 5

 No of Worker Exposed 4

Point A

Exposure hour/day

Point B

Point C (A + B)

1

4

2

3

2. Struck by moving parts during installation, testing & commissioning of piling machines.

4

1

4

2

3

3. Knock down by piling machine during survey & pegging work.

2

1

4

2

3

4. Lift-up of spun piles from ground into piling machines & piling works

4

1

8

4

5

5. Spark & toxic gas from welding of extension  piles.

2

1

3

2

3

6. Trip & fall into exposed pile hole in ground.

10

3

8

4

7

7. Operate piling machinery without Sijil Operator Krin from JKKP.

3

1

8

4

5

8. Excessive black smoke from exhaust.

2

1

1

1

2

9. Oil leakage from hydraulic & machinery.

2

1

1

1

2

10. Excessive noise exposure.

4

1

4

1

2

TYPE OF HAZARD / RISK / DANGER 1. Hit by falling machine, equipments, spun  piles during unloading from low loader, trailers

FALIH SDN BHD

JOB SAFETY ANALYSIS

JSA/PILING DOC. NO.

3 OF 5 PAGE NO.

Project

Ladang 3, Kuala Terengganu

Ref No

QRT / PILING

Title

Qualitative Risk Table

Date

November 19, 2011

Accident Likelihood

Point

Injury Consequences

Point

Risk

Point

Highly Unlikely Unlikely Likely Very Likely

0 1 2 3

Nil Minor Injury Major Injury Fatal

0 1 2 3

Nil Low Medium High

0 1 2 3

Type of Hazard /Risk / Danger

Accident Likelihood

Point D

Injury Consequences

Point E

Risk

Point F

Point G (D + E + F)

1. Hit by falling piles / machines.

Likely

2

Major Injury

2

High

3

7

2. Struck by moving parts of machine during install.

Likely

2

Minor Injury

1

Low

1

4

3. Knock down during survey /pegging

Likely

2

Minor Injury

1

Low

1

4

4. Lift-up piles into machine & piling works

Likely

2

Fatal

3

High

3

8

5. Spark & toxic gas from welding

Likely

2

Minor Injury

1

Medium

2

5

6. Trip & fall into pile hole in ground.

Very Likely

3

Minor Injury

1

High

3

7

7. Unlicensed operator

Likely

2

Nil

0

Nil

0

2

8. Excessive black smoke

Likely

2

Nil

0

Nil

0

2

9. Oil leakage from machines

Likely

2

Nil

0

Nil

0

2

10. Noise pollution

Likely

2

Nil

0

Nil

0

2

FALIH SDN BHD

JOB SAFETY ANALYSIS

JSA / PILING DOC. NO.

4 OF 5 PAGE NO.

Project

Ladang 3, Kuala Terengganu

Ref No

HR / PILING

Title

Hazard Ranking

Date

November 19, 2011

Type of Hazard / Risk /Danger

Point H (C + G )

Hazard Ranking

1. Hit by falling machine, equipments, spun piles during unloading from low loader, trailers.

10

3

2. Struck by moving parts during installation, testing & commissioning of piling machinery.

7

5

3. Knock by piling machine during survey / pegging work.

7

7

4. Lift-up of spun piles of various size & weight into piling machine and piling works.

13

2

5. Spark & toxic gas from welding of extension piles.

8

4

6. Trip & fall into exposed pile hole in the ground.

14

1

7. Operate piling machinery without SOK license.

7

6

8. Excessive black smoke from exhaust.

4

8

9. Oil leakage from machines.

4

9

14

10

10. Noise pollution from piling activities.

FALIH SDN BHD

JOB SAFETY ANALYSIS

JSA / PILING DOC. NO.

5 OF 5 PAGE NO.

Project

Ladang 2, Kuala Terengganu

Ref No

RSM / PILING

Title

Recommended Safety Measures

Date

November 19, 2011

 No

Work Activity

Recommended Safety Measures

Remark

1

Unloading of spun pile, piling machine parts & equipments.

1. Unload material / parts / spun piles in safe manner. 2. Inform workers during Safety Briefing of unloading activities. 3. Secure unloading area from trespassers.

Delivery Schedule Safety Briefing Falling object hazard

2

Install piling machinery parts and equipments.

1. Ensure safe installation procedures for machinery  parts. 2. Work in pairs.

Machinery Manual Tool Box Meeting

3

Survey work & pegging

1. Beware of movement of piling machine. 2. Ensure personal safety around machine

Piling Schedule

4

Lifting of spun pile into piling machine

1. Ensure piling machine, lifting gear, wire rope sling in good condition. 2. Check for fatigue, damaged, bird cage & broken wires.

Piling machine checklist

5

Welding of extension piles

1. Welders to wear gas mask. 2. Provide fire extinguisher at welding area. 3. Ensure welders possess welding certificate.

Welding safety

6

Trip & fall into pile hole

1. To cover-up exposed pile hole.

7

Operating piling machine

1. Operators to possess Sijil Operator Krin fro JKKP 2. To operate in safe manner.

SOK Piling Plan

8

Excessive black smoke

1. To ensure periodic maintenance of piling machine. 2. To ensure compliance to environmental regulations.

Maintenance Sch EQA 1984

9

Oil leakage from machines.

1. To maintain machinery in good condition. 2. Provide drip tray for leaking oil.

EQA 1984

10

Noise pollution from piling works.

1. Wear ear protection at high noise level areas. 2. Ensure noise level kept to minimum.

Ear protection

CONTROL COPY NO

FALIH SDN BHD JOB SAFETY ANALYSIS FOR PILING WORKS. for

CADANGAN MEMBINA & MENYIAPKAN 1 BLOK RUMAH MAMPU MILIK YANG MENGANDUNGI 24 LAPIS KEDIAMAN (407 UNIT), 7 LAPIS TEMPAT LETAK KERETA BERTINGKAT DAN KERJA-KERJA INFRASTRUKTUR YANG BERKAITAN DI ATAS LOT KERAJAAN, LADANG TOK PELAM MUKIM BANDAR, DAERAH KUALA TERENGGANU, KUALA TERENGGANU, TERENGGANU DARUL IMAN.

DOCUMENT NO: JSA / PILING JKKP SITE REGISTRATION NO: TG/

JSA / PILING

NOVEMBER 19, 2011

Doc. No.

Date

MOHD YAHIZAN Safety & Health Officer

Work Activity No.1: Unloading of spun piles/ material / machinery parts / equipments from trailers / Hazard: Falling object from lifting activities. Safety Control Measures: 1. Beware of lifting activities. 2. Secure lifting area against trespassers.

Work Activity No.2: Installation of machinery / equipments. Hazard: Struck by moving parts. Safety Control Measures: Beware of moving parts of machinery.

Work Activity No.3: Survey work / pegging / marking point for piling. Hazard: Knock down by piling machine. Safety Control Measures: Beware of machinery/ Wear luminous safety vest.

Work Activity No.4: Lifting of spun pile into piling machine. Hazard: Spun fall down due to breakage of wire rope sling.. Safety Control Measures: Beware of lifting & piling by piling machinery

Work Activity No.5: Welding of extension pile. Hazard: Spark & toxic gas from welding activities.. Safety Control Measures: Wear gas mask / Use blower to blow away gases..

Work Activity N0. 6: Exposed pile h ole in ground. Hazard: Trip & fall due to uncovered hole. Safety Control Measures: Cover-up pile hole with plywood.

View more...

Comments

Copyright ©2017 KUPDF Inc.
SUPPORT KUPDF