JSA 003 Rev B - Lifting and Rigging

October 7, 2017 | Author: Ashirvad Rath | Category: Crane (Machine), Safety
Share Embed Donate


Short Description

JSA...

Description

Form No. JI 2004-FORM-HSE-002

Petrofac

Job Safety Analysis Activity: Project:

Lifting and Rigging EFFLUENT WATER INJECTION NK-PH-I AND CENTRAL SEAWATER INJECTION NK-PH-II

Work Area:

Site/Facility:

JSA No: JI 2004-JSA-003 Rev B Project No: EF 1071 & 1082 KOC Permit No & Date:

In Case of Emergency, contact KOC @ 160

PPE & Tools: SEQUENCE OF JOB STEPS

Hard Hat, Safety Shoes, Safety Goggles/ Glasses, Hand Gloves, Overall, Dust mask, Cranes, Boom trucks, trailers, lifting & rigging Tools and Hand Tools, Full Body Harness RISK RATING

POTENTIAL HAZARDS

MITIGATION MEASURES • • • •

Poor Task Planning

3(D) MEDIUM

• • • •

• •

Pre - Work Non Compliance of KOC F & S Regulations and KOC HSEMS Documents

3(D) MEDIUM









Poor communication / ERP

3(D) MEDIUM

Page 1 of 3

• •

RESIDUAL RISK RATING

Ensure the equipment operator, riggers are experienced to do the task and have the necessary valid documents and licenses of the state of Kuwait Ensure the ground condition is in safe working condition and underground services if any are generated Ensure access way is free of obstructions Ensure the approach to emergency equipment is not blocked by properly planning and placing the equipments/ materials. Obtain all necessary personnel and equipments entry permissions from company Use all necessary PPE and conduct TBT. First Aid kit shall be available at all times at the work station. Ensure lifting and rigging Awareness training is given to all personnel involved in the lifting / rigging activity

2(B) LOW

Ensure all personnel have undergone Project HSE Induction and EOD training All personnel must comply with KOC HSEMS Document KOC SA 004-n Permit to Work Procedure, (KOC-SA-029) for “lifting / shifting and Material handling”. Also chapter 17 of “ Fire & safety regulation on lifting Equipment” Ensure the equipment is certified by company as per KOC SA 013- Temporary Mobile Equipment Procedure and fit for the intended purpose as required Ensure all lifting gears and shackles are inspected with necessary authorized 3rd party inspection certificates and color coded. Ensure all crane operator and riggers having 3rd party certification

2(B) LOW

Ensure that the Emergency Numbers are posted at site, and personnel are informed in the TBT once per week Ensure proper communication means available Mobile Phone – outside Live Plant areas) and in case of any emergency contact PIL Construction: 97205041,PILHSE: 97218253/97216597, PMC Lead: 66159067, PMC HSE: 60630965 and/or KOC Emergency # 160

2(B) LOW

JSA No. JI-2004-JSA-003 Rev B

Form No. JI 2004-FORM-HSE-002 • • Poor positioning of crane during lifting operation

4(D) HIGH

• •



Overloading the crane rated capacity 4(D) HIGH

Mechanical failure

3(B) LOW



Ensure preventive maintenance schedules followed as per manufacturer instructions

3(B) LOW



Do not attempt any lifting operation on an extreme weather condition i.e., heavy sandstorm, strong wind, thick fog, rain, lightning etc No lifting operation during evening / dark time as required

• • •

Irregular maintenance for the equipments

4(D) HIGH

Lifting and rigging Poor visibility

4(D) HIGH



• • Personnel injury/ damage of equipment

4(D) HIGH • • • •

Incompetent lifting /rigging / unclear instruction

4(D) HIGH

• • • • •

Not complying Methods Statement /JSA/ Site Safety Analysis for lifting

4(D) HIGH

Personnel injury due to poor housekeeping

2(C) LOW





Post Work

Page 2 of 3

3(B) LOW

Conduct regular visual inspection of all lifting gears and mechanism of crane prior to start any lifting operation by a competent rigging supervisor/ foreman Do not exceed 80% of the rated capacity of the crane for any loading/ unloading works Do not overload the lifting capacity of the crane as per manufacturer standards under any circumstances Do not override any inbuilt safety devices or take short cut during the lifting operations. All worn lifting tools/ tackles and those who don’t have 3rd party certification must be removed from site. All lifting tools and tackles must be free from grease



Lifting tackles and sling failure during the operation

Ensure ground is stable and properly compacted as required for positioning of crane. Do not position the equipment close to the trench/ excavation, overhead power line Do not position crane close to overhead power cable lines Out rigger must have an outrigger pad of adequate size and thickness



are

Do not stand below the suspended load Provide proper sign boards, barricade the lifting radius/ area where the activities are in progress and remove all possible tripping hazards in the lifting working area. Drink water frequently to avoid dehydration ( during both summer and winter) Clear instruction should be given to work crew regarding their individual roles and responsibilities Riggers must wear fluorescent vest for visibility during the full duration of lifting operation Provide adequately strong and long tag lines at both ends of the load Close supervision by a competent rigging supervisor Ensure signal man or rigger is visible with fluorescent vest to the crane operator during every phase of lifting activity Only one competent rigger to do the signaling or rigging activity. Ensure rigging crew is competent for the task and contractor’s SSA for lifting is completed Ensure to follow approved Method statement for any critical lifting as required.

Ensure the work place is maintained clear of debris, waste and other rubbish and make the place clean and tidy After job, ensure crane is secured to a safe position and all lifting tools * tackles are safely stored

JSA No. JI-2004-JSA-003 Rev B

3(B) LOW

3(B) LOW

3(B) LOW

2(B) LOW

Form No. JI 2004-FORM-HSE-002 Reviewed by (Worley Parsons)

Worksite Supervisor (Subcontractor or Petrofac)

Approved by (Petrofac HSE)

Name:

Name:

Name:

Company:

Company: Petrofac International Ltd

Company: Worley Parsons Kuwait LLC

Designation:

Designation:

Designation:

Signature:

Signature:

Date:

Date:

Signature:

Date:

Page 3 of 3

JSA No. JI-2004-JSA-003 Rev B

View more...

Comments

Copyright ©2017 KUPDF Inc.
SUPPORT KUPDF