JOB SAFETY ANALYSIS (JSA) FORM

Company name

PROJECT NO. : ......................................................................................... Job Location/Site:

JSA NO:

Task/Activity: Cable laying/Pulling/shifting of cable drums

PCR PCR NO NO: :

Work Area/equipment No:

Other:

Date:

Gas Leak / Fire /Any Emergency: In case of emergency, all works must be stopped, equipment must be switched off Emergency situation /Evacuation SL. NO

ACTIVITY STEPS

and left in safe condition. All personnel shall reach the nearest muster point considering the wind direction (upward or cross-ward) WHO IS AT RISK

HAZARDS INVOLVED

1

Work Permit

 Unauthorized commencement of works  May result in exposing people and/or potential to harm or danger.

2

Gas test

 May found toxic gas or H2S gas leak  People or extreme oxygen limit in air Environment

3

Loading and Offloading of cable drums

 Improper handling of material.  Improper use of Lifting Equipments.

4

Hiab pickup General Operation

 Hitting to the existing facilities or  People persons  Facility  Equipment failure  Equipment  Fall of load

Job no 7/JSA-14-REV-0

   

People Equipment Facility Environment

 People  Equipment  Facility

CONTROL MEASURES

 Authorized work permit holders shall ensure obtaining and maintaining valid work permits.  The supervisor responsible for this activity has to check the PPE of his staff to ensure that all required items are available and properly used.  Inform all people regarding permit conditions before work starts.  Supervisors must conduct daily toolbox talk about nature of work and associated potential hazards and their essential precautionary measures.  Carryout gas test by QP Authorized gas tester time to time.  All groups working in different area inside station shall have H2S personal gas monitor(certified)  Equipment Check List (Verified).  Area cordon off.  Load the material as per the designed loading capacity of the vehicle.  Weight of load clearly marked / Known.  No Manual Handling will be allowed for heavy load.  Operator should be positioned on the opposite side of the truck to that which the load will be lifted or lowered.  Operator should have a clear view of the area where the load will be lifted from or lowered onto. Ensure:  That loads will not become snagged which may cause equipment failure. This may require an observer or guide ropes to be attached.

Cable laying/Pulling Page 1 of 4

PANORAMA SL.NO

5

JOB SAFETY ANALYSIS (JSA) FORM PROJECT NO. : GC10105700- EPIC FOR MECHANICAL PCRs WITHIN DUKHAN

ACTIVITY STEPS

Stabilizing Truck

the

hiab

HAZARDS INVOLVED

 Fall of load  Clops of hiab

WHO IS AT RISK

 People  Facility  Equipment

CONTROL MEASURES



Stabilisers MUST be lowered and on firm footing. NOTE: The truck wheel should not be lifted off the ground as they supply the main stability. Ensure: Parking brake is applied.  That the truck wheels are chocked if the ground slopes.  It is recommended that the ground should not slope more than 5 degrees



6

CABLE LAYING AND  Fall of objects / Tools. PULLING.

 People  Facility  Equipment

   

Provide guardrail & toe board to prevent falling of tools /objects Don’t keep the unnecessary materials/tools on the scaffold platform Hand tools to be tied with permanent structure or person If required barricade the area during the work.

7

 Accidental Fall of Person

 People

 Don’t try to cross guardrail and use always ladder only.  Use of Safety Harness/full body harness to prevent accidental fall

8

 Unstable Scaffold

 The scaffold must be inspected, certified & tagged by the competent person confirming its suitability

9

 BODY INJURIES

   

10

CABLE DRUM FALLING

People Facility Equipment People

 People  Equipment

 Personnel shall wear Personal Protective Equipment such as Hardhat, Eye Protection, Hand Gloves and Safety Shoes during CABLE LAYING, PULLING and or TERMINATION.  Supervisor or Foreman shall give TOOLBOX talk to his workers prior to start of work.  Cable Drum’s Steel Roller shall be provided with END STOPPER to prevent cable drum from falling.  Do not use Steel Roller made of RSC or Pipe tubing.  Assessment of the weight of cable to be pulled and numbers of workers required shall be defined.  Workers shall keep distances to the cable drum being pulled.  Pulling cable crew should not pull the cable fast. Teamwork must be followed.  SIGNAL PERSONS shall be provided during cable Laying / Pulling and shall be equipped with RED and GREEN signal flags.  Cable Drums should be properly located on CABLE JACK designed for the purpose and of suitable capacity and base.  Cable Jack shall be repaired if welded joints are already deteriorated. Page 2 of 4

PJ247/JSA-14-REV-0

Cable laying/Pulling

PANORAMA SL.NO

ACTIVITY STEPS

JOB SAFETY ANALYSIS (JSA) FORM PROJECT NO. : GC10105700- EPIC FOR MECHANICAL PCRs WITHIN DUKHAN HAZARDS INVOLVED

FALL FROM HEIGHTS

11

BACK INJURIES FOR MANUAL HANDLING

12

WHO IS AT RISK

CONTROL MEASURES

 People  Equipment 

 Full Body Harness shall be used when working at heights and shall be TIED OFF on strong materials.

 People

 Workers shall be taught in cable laying and pulling techniques including the requirement for ensuring good manual handling techniques.

 LIFELINES shall be provided as necessary as practicable when working at elevated areas.

 Workers shall not run when pulling cables TRAPPING INJURIES

13

 People  Equipment

 CABLE JACK shall be of sufficient capacity and placed on an even and hard surface.  WARNING SIGNS shall be positioned adjacent to cable laying  Area for loading and unloading shall be barricaded properly.  Damaged Cable Drums shall be repaired before they are loaded or unloaded for the jobsite.

14

HEALTH HAZARDS / HEAT STRESS

 People

15

TRIPPING HAZARDS / DAMAGE TO MATERIALS

 People  Facility  Equipment

 Provide COLD DRINKING WATER at the jobsite during hot weather condition.  Drink plenty of COLD DRINKING WATER especially during hot weather condition.  QP work and rest procedure shall be followed.  Immediately GET OUT from the cable pulling / laying area when symptoms of heat stress attacked and inform your Supervisor or Safety Officer immediately.  SHADED AREA shall be provided for rest period. Resting adjacent to or under plant or equipment is prohibited.  Workers shall NOT RUN on installed or laid cables during cable pulling.  Cables shall be KEPT AWAY from foot and equipment traffic. Stored materials shall be barricaded and provided with signs.  Avoid storing materials on walkways or ingress or egress.

Page 3 of 4 PJ247/JSA-14-REV-0

Cable laying/Pulling

PANORAMA SL.NO

16

ACTIVITY STEPS

TERMINATION

17 18

JOB SAFETY ANALYSIS (JSA) FORM PROJECT NO. : GC10105700- EPIC FOR MECHANICAL PCRs WITHIN DUKHAN

Housekeeping Clean up worksite

HAZARDS INVOLVED

WHO IS AT RISK

CONTROL MEASURES

HAND INJURIES

 People

 Trained and competent electricians using suitable tools shall carry out Cable Termination. Modified Power and Hand tools are not acceptable.  Avoid slashing cables while sliding it on your hand  Apply the LOCKOUT / TAGOUT procedures as necessary as practicable.

TRIPPING HAZARDS

 People

 Do not store scrap cables on walkways.

Slips trips and falls due to poor housekeeping

   

 Remove tools equipment and rubbish from worksite and maintain a clean work environment.  Arrange housekeeping on daily and every shift bases  Supervisor shall conduct tool box meeting in this regards

People Environment Facility Equipment

Project Engineer

HSE Manager

PREPARED BY:

REVIEWED BY:

Project Manager APPROVED BY:

Page 4 of 4 PJ247/JSA-14-REV-0