Itp for Bus Duct

April 8, 2017 | Author: Utku Can Kılıç | Category: N/A
Share Embed Donate


Short Description

Download Itp for Bus Duct...

Description

DOCUMENT REVIEW AND COVER SHEET Construction Contractor:

Company:

Engineering Contractor:

Engineering and Technical Services:

Review:

Revision :

Document Number:

RSAE

ITP

QA

PROJECT CODE

DEPARTMENT CODE

DOCUMENT TYPE

DICIPLINE CODE

SEQUENCE NUMBER

Gasprom Neftehim Salavat Acrylic Acid / Acrylates Plant (RSAE) Project Bashkortostan, Russian Federation

PROJECT CONTRACT NO DOCUMENT TITLE

ITP for LV BUS DUCT

DOCUMENT NUMBER DOCUMENT DESCRIPTION Status

RSA - IT - QA E P Inspection and Test Plan (ITP)

Status

Code Description

Code



1



2



3



4



5

Revieved Engineer:

REV.

APPROVED WITHOUT COMMENT REVISE AND RESUBMIT. WORK MAY PROCEED SUBJECT TO INCORPORATON OF CHANGES INDICATED. REJECTED. TO BE REVISED B: RESUBMITTED. WORK MAY NOT PROCEED INFORMATION ONLY. REVIEW NOT REQUIRED. WORK MAY PROCEED CANCELLED/SUPERSEDED

NAME

SIGN

DATE

Remarks or Comments:

A1

Issued for Approval Revision :

Document Number:

RSAE

ITP

QA

PROJECT CODE

DEPARTMENT CODE

DOCUMENT TYPE

DICIPLINE CODE

SEQUENCE NUMBER

Rev.

Amendment

Prepared

Checked

Approved

Date

Company:

Construction Contractor:

Engineering Contractor:

Engineering and Technical Services:

Project Title:

Gasprom Neftehim Salavat Acrylic Acid / Acrylates Plant (RSAE) Project Bashkortostan, Russian Federation Document Title:

Inspection and Test Plan LV BUS DUCT

Revision :

Document Number:

RSAE

ITP

QA

PROJECT CODE

DEPARTMENT CODE

DOCUMENT TYPE

DICIPLINE CODE

SEQUENCE NUMBER

REVISION SHEET Revisio n A1

Description of changes

Page

First Issued For approval

Revision :

Document Number:

RSAE

ITP

QA

PROJECT CODE

DEPARTMENT CODE

DOCUMENT TYPE

DICIPLINE CODE

SEQUENCE NUMBER

Gasprom Neftehim Salavat Acrylic Acid / Acrylates Plant (RSAE) Project

Inspection and Test Plan LV BUS DUCT Issue Date:

No

Revisio n:

Doc. Number:

DESCRIPTION OF ACTIVITY

CONTROL DOCUMENT

ACCEPTANCE CRITERIA

VERIFICATION DOCUMENT

Page:

1 of 1

INVOLVEMENTS OWN RC MHI ER

1

Installation Check 1- Inspect panel assembly for 1.1

2345-

alignment, level, tightness of bolts Inspect bus duct connection (Torque check and marking) Check frame earthing Inspect termination Check bus duct supports

1.2

Check phase connection

1.3

Insulation resistance measurement

DWG: 1. LV Busduct: 3935 E323-00100 2. Transformer: 3935 E322-00600 3. LV SWGR/MCC: 3935 E32300200 Instruction manual : 1. LV Busduct: 3935 E423-00100 2. Transformer: 3935 E422-00600 3. LV SWGR/MCC: 3935 E42300200 & 201 DWG: 1. LV Busduct: 3935 E323-00100 2. Transformer: 3935 E322-00600 3. LV SWGR/MCC: 3935 E32300200 Instruction manual : 1. LV Busduct: 3935 E423-00100 2. Transformer: 3935 E422-00600 3. LV SWGR/MCC: 3935 E42300200 & 201

Correct Installation

Correct phase connection

500 VDC, 1 Min >10MOhm

RSAE-FRM-216

RSAE-FRM-216

RSAE-FRM-216

Attachment 1- RSAE-FRM-216 INSPECTION CHECK LIST LV BUS DUCT LEGEND RC: Renaissance Construction, MHI: Mitsubishi Heavy Industries, OWNER: Gasprom Neftekhim Salavat, W: Witness, R: Review, H: Mandatory Hold Point, S: Surveillance (Random Check),

W

W

S

W

W

S

W

W

S