Table of Contents 1.0
Goal of the Course:
6
1.1 Features
6
1.2 TOPICS
6
1.2.1 1.2.2 1.2.3
ITIL IT Service Management Processes ITIL Service Support Processes: ITIL Service Delivery Processes:
2.0
Introduction
3.0
IT Service Management
6 6 7
8 11
3.1 IT Service Management – Background
11
3.2 Services and Quality
13
3.2.1 3.2.2
4.0
Quality Assurance Human Resource Management
14 23
Introduction to ITIL
28
4.1 Background
28
4.2 Advantages to the Customer/End User:
29
4.3 Advantages to the IT Organization:
29
4.4 Potential disadvantages:
30
4.5 Organizations
31
5.0
Service Desk
43
5.1 Introduction
43
5.2 Objective
43
5.3 Process Description
44
5.4 Activities
44
6.0
Activities
44
6.1 Roles
45
6.2 Relationships
46
6.3 Benefits
47
6.4 Summary
48
6.5 Common Problems
49
6.6 Metrics
50
6.7 Service Desk Structure - Best Practice
50
6.7.1
Virtual Service Desk
53
6.8 Essential Terms
C3: Protected
54
Page 1 of 203
Controlled copy
7.0
ITIL Foundation Level - Certification Guide
Incident Management
56
7.1 Introduction
56
7.2 Objective
56
7.3 Process Description
57
7.4 Activities
57
7.4.1 7.4.2 7.4.3 7.4.4 7.4.5 7.4.6
Incident detection and recording Classification and initial support Investigation and diagnosis Resolution and recovery Incident closure Incident ownership, monitoring, tracking and communication
58 58 59 59 59 60
7.5 Roles
60
7.6 Relationships
60
7.6.1 7.6.2 7.6.3 7.6.4
Configuration management: Problem Management Change Management Service Delivery Processes
60 61 61 61
7.7 Benefits
62
7.8 Common Problems
62
7.9 Metrics
63
7.10 Best practice
63
7.10.1 7.10.2 7.10.3
Incident Management tools: Different types of escalation Interesting Websites
63 64 64
7.11 Essential Terms
8.0
65
Problem Management
67
8.1 Introduction
67
8.2 Objective
68
8.3 Process Description
68
8.4 Activities
71
8.5 Roles
75
8.6 Benefits
77
8.7 Common Problems
78
8.8 Metrics
78
8.9 Best practices
79
8.10 Essential Terms
80
9.0
Change Management
81
9.1 Introduction
81
9.2 Objective
82
C3: Protected
Page 2 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
9.3 Process Description
82
9.4 Activities
84
9.4.1 9.4.2 9.4.3 9.4.4 9.4.5 9.4.6
Recording Accepting (Rejecting) Classifying Planning Coordination Evaluating
84 84 84 84 84 85
9.5 Roles 9.5.1 9.5.2 9.5.3
85 Change Manager Change Advisory Board (CAB) Change Advisory Board/Emergency Committee (CAB/EC)
85 86 86
9.6 Relationships
86
9.7 Benefits
88
9.8 Common Problems
88
9.9 Metrics
89
9.10 Best practices
89
9.10.1
Interesting websites
89
9.11 Essential Terms
90
10.0 Configuration Management
91
10.1 Introduction
91
10.2 Objective
91
10.3 Process Description
92
10.4 Activities
93
10.4.1 10.4.2 10.4.3 10.4.4
Planning: Identification: Status accounting Verification and audit
94 95 95 96
10.5 Roles
96
10.6 Relationships
97
10.7 Benefits
97
10.8 Common Problems
98
10.9 Metrics
99
10.9.1 10.10
Key performance indicators
10.10.1 10.10.2 10.11
99
Best practices
100
The CMDB Interesting Websites
100 101
Essential Terms
101
11.0 Release Management
104
11.1 Introduction
104
11.2 Objective
104
C3: Protected
Page 3 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
11.3 Process Description
105
11.4 Activities
106
11.5 Roles
110
11.6 Relationships
110
11.7 Benefits
112
11.8 Common Problems
113
11.9 Metrics
113
11.10
114
Best practices
11.10.1 11.11
Interesting web sites
115
Essential Terms
115
12.0 Service Level Management
118
12.1 Introduction
118
13.0 Financial Management
135
14.0 Availability Manageme nt
151
14.1 Introduction
151
14.2 Objective
152
14.3 Process Description
153
14.4 Activities
155
14.5 Roles
158
14.6 Relationships
158
14.7 Benefits
160
14.8 Common Problems
161
14.9 Metrics
162
14.10
Best practices
162
14.11
Essentials (terminology)
163
15.0 Capacity Management
165
15.1 Introduction
165
15.2 Objective
165
15.3 Process Description
166
15.4 Activities
168
15.5 Roles
169
15.6 Relationships
170
15.7 Common Problems
172
15.8 Essentials (terminology)
176
C3: Protected
Page 4 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
16.0 IT Service Continuity Management
177
16.1 Introduction
177
16.2 Objective
178
16.3 Process Description
179
16.4 Activities
181
16.5 Roles
185
16.6 Relationships
185
16.7 Benefits
187
16.8 Common Problems
188
16.9 Metrics
189
16.10
Best practices
190
16.11
Essentials (terminology)
191
17.0 Security Management
193
17.1 Introduction
193
17.2 Objective
195
17.3 Process Description
196
17.4 Activities
197
17.5 Roles
198
17.6 Relationships
198
17.7 Benefits
199
17.8 Common Problems
200
17.9 Metrics
201
17.10
Best practices
201
17.11
Essentials (terminology)
200
C3: Protected
Page 5 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
1.0 Goal of the Course: The Art of Service’s ITIL IT Service Management Essentials Online is a Web-based training course for IT Service Management good practice. The course provides participants with a customer-focused, process-oriented approach to IT Service Management and prepares students to take the the EXIN exan 'Foundation Certificate in IT Service Management'. The course delivers: ? An introduction to IT Service Management and ITIL ? Understanding of the Structure of the ITIL 'library' ? ITIL’s key concepts and objectives
1.1 Features The IT Service Management Essentials Online course is an online presentation with added features including: •
Chat room
•
Bulletin Board
•
Progress reports
•
Short tests
•
40 question mock exam
•
Glossary, FAQs, Bookmarks, Searching, Notes and more
1.2 TOPICS 1.2.1 •
ITIL IT Service Management Processes
Service Desk: Understanding its role and function in the IT infrastructure and its relationship with
1.2.2
ITIL Service Support Processes:
•
Incident Management: Definition of an incident, description of Incident Control (including recording, classification, co-ordination, matching and resolution)
•
Problem Management: Definition of a problem and known error, proactive problem management (identification of problems and prevention of further incidents)
C3: Protected
Page 6 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
•
Configuration Management: Defining a configuration item and the configuration management database; impact of Configuration Management on other IT processes.
•
Change Management: Definition of a change and request for change (RFC); description of change control and change procedures; role of the change advisory board (CAB) and CAB/EC (for handling urgent changes).
•
Release Management: Scope and concepts; definition of definitive software library(DSL) and definitive hardware store (DHS); description of planning, testing and implementing.
1.2.3
ITIL Service Delivery Processes:
•
Service Level Management: Definition of a service catalogue; identifying, negotiating, monitoring and reviewing service level agreements (SLAs).
•
Financial Management for IT Services: Reviews of budgeting, charging and IT accounting; analysis of running costs and charging policies.
•
Availability Management: Review of reliability, availability, resilience, maintainability and serviceability, calculating availability, review of planning, monitoring and reporting.
•
Capacity Management: Review of application sizing, workload, performance, demand and resource management and their inputs to modelling, definition of the capacity management database and contents of the capacity plan.
•
IT Service Continuity Management: Re-view of business continuity, risk analysis and risk management, defining assets, threats, vulnerabilities and countermeasures (protection and recovery), development, testing and maintenance of the IT Service Continuity Plan, IT recovery options and management roles.
•
..underpinned by Security Management
C3: Protected
Page 7 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
2.0 Introduction In recent decades IT developments have changed the way that most businesses operate. The changes are most evident in the various business processes of any organization. Examples of business processes are "the sales process" (eg. Marketing generates leads and sends through to Sales, Sales develops relationships and prepares proposals, Administration prints and sends the material to the client and ensures that there is an action against the sales person to follow up the proposal, etc. etc.). All of these business processes rely a great deal on computer based tools and the underlying technology. Since the introduction of the PC, LAN, client/server technology and the Internet, organizations can bring their products and services to markets faster than ever before. These developments are responsible for the transition from the industrial to the information age. In the information age, everything has become faster and more dynamic. Traditional hierarchical organizations often find it difficult to respond to rapidly changing markets, and therefore there is now a trend towards less hierarchical and more flexible organizations. The emphasis is now on horizontal processes, and decision-making authority is increasingly granted to personnel at a lower level. IT Service Management operating & tactical processes were developed against this background - where the process is paramount and the focus moves away from the "silo" departmental or functional structure.
In the 1980s, the quality of the IT services provided to the British government lead the CCTA (Central Computer and Telecommunications Agency as it was referred to - now the Office of Government Commerce, OGC) was instructed to develop an approach for efficient and financially effective use of IT resources by ministries and other British public sector organizations. The aim was to develop a framework/methodology/approach that was vendor/supplier independent. This resulted in the Information Technology Infrastructure Library™ (ITIL). ITIL v1 grew from a collection of best practices observed in the IT service industry.
C3: Protected
Page 8 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
The ITIL framework provides a detailed description of a number of important IT practices, with comprehensive checklists, tasks, procedures and responsibilities which can be tailored to any IT organization. Where possible, these practices have been defined as processes covering the major activities of IT service organizations. The broad subject area covered by the ITIL publications makes it useful to refer to them regularly and to use them to set new improvement objectives for the IT organization. The organization can grow and mature with them. A number of other IT Service Management frameworks have been developed on the basis of ITIL, generally by commercial organizations. This is one of the reasons why ITIL has become the de facto standard for describing a number of fundamental processes in IT Service Management. Special note: The most widely known "other frameworks" that have been based on ITIL is the Microsoft Operations Framework. Microsoft do not try and conceal their proprietary framework has it's basis in ITIL. They in fact praise ITIL as an excellent starting point for organizations with Microsoft Environments. What Microsoft have done however, is extend ITIL and create a series of other processes and specific concepts. ITIL is often referred to as Best Practice, although the relatively new term of "good practice" is starting to be widely used. Note: The term "best practice" will often spark heated debate among some IT professionals. If you are not certain then the term "good practice" may be a safer option to use. The ITIL material claims that it is Best Practice. The broader adoption of ITIL has been hampered by the lack of a basic, but effective introductory textbook. This course is the electronic version of this missing text. The course is beneficial for anyone involved in IT Service Management.
This edition of this Course is based upon The Art of Service's Course material, developed as an introduction to IT Service Management. That work was based on management summaries and descriptions in official ITIL publications. Given the desire for a broad consensus in the ITIL field, new developments, additional material and contributions from ITIL professionals are welcome. They will be discussed by the editors and where appropriate incorporated into new editions. Given the rapid changes in this field, the ITIL books do not always describe the latest developments. This is because ITIL is primarily a collection of best practices taken from a variety of people in a
C3: Protected
Page 9 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
wide cross section of industry. When writing this Course we aimed to incorporate current developments in the field, without substantially diverting from the ITIL publications. Therefore the course can be used both to prepare for the official ITIL Service Management Foundation exam and as a general introduction to the broader area of IT Service Management. This course does not address the planning and implementation of ITIL processes. In chapter 2 ‘IT Service Management’ it does however address, in a more general way, relevant matters in IT Service Management, in terms of quality, processes and policies.
C3: Protected
Page 10 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
3.0 IT Service Management 3.1 IT Service Management – Background In this section we will look at services, quality, organization, policy and process management. All these topics provide the background for the development of a systematic approach to IT Service Management. The IT Service Management processes described in this course (also referred to as IT Management) are best understood against the background of the concepts about organizations, quality and services which influenced the development of the discipline. Familiarity with these terms also helps to understand the links between the various elements of the IT Infrastructure Library (ITIL). ITIL is by far the best known description of IT Service Management and is therefore used as the foundation for this Course. The Objective Tree The objective tree is used to help all members of the organization understand the benefits of ITSM. Starting at the top of the tree, the most important consideration for any business is that the Organization’s Objectives are met (eg. Increased market share, lower costs and higher customer satisfaction). Failure to meet the overall objectives means that the organization ceases to function (no matter how well the IT department is run). In order for the organization’s objectives to be met, there must be a series of business departments working together in Business Processes. An example of a business process is the "enrollment process" in a University. The "enrollment process" involves Admissions (to capture basic student details), Security (to issue id-card), Library (to provide required book lists), etc. Each of these business processes needs a variety of services (IT Service Provision in our Objective Tree) in order to work. In our University example the Admissions department has a Student system, Security has it's Security system and the Library has a Library system (hopefully all share a common repository of student information, but they all exist for a different reason). The next branch of the Objective Tree is Service Management. It is at this layer that IT professionals must consider how they need to manage all the infrastructure (including hardware, software, tools, etc.) in order to make the required Services available, to the Business Processes so that the Organization Objectives can be met. Getting this right earns everyone a medal!
C3: Protected
Page 11 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
This chapter introduces the following subjects: •
The section on the provision of services and quality addresses the relationship between the quality experienced by the customer's organizational end users, and quality management by the provider of the IT services.
•
The section on organization and policies addresses concepts such as vision, objectives, and policies and discusses issues such as planning, corporate culture and Human Resource Management. This section also discusses the coordination between the business processes of a company and the IT activities.
•
The section on process management looks at the control of IT service processes
C3: Protected
Page 12 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
3.2 Services and Quality Organizations are often highly dependent on their IT services and expect the IT services not only to support the organization, but also to present new options to achieve the objectives of the organization. Furthermore, the high expectations of customers on IT Services tend to change significantly over time (usually in a downgrading of expectations). Providers of IT services can no longer afford to focus on technology. They now have to consider the quality of the services they provide and focus on the relationship with their customers. The provision of IT services refers to the full management of the IT infrastructure. Hardware, software, tools and relationships. Before buying a product in a shop, we normally assess the quality such as the appearance, usefulness for the task and robustness. In a shop, the customer has few opportunities to influence the product quality. This is because the product is produced in a factory. By effectively controlling the production plant, the manufacturer will try to deliver a fairly constant quality. In this example, manufacture, sales and consumption of the product are quite separate. However, services are provided through interaction with the customer. Services cannot be assessed in advance, but only when they are provided. The quality of a service depends to some extent on the way in which the service provider and the customer interact. In contrast to the manufacturing process, customer and provider can still makes changes when the services are being delivered. How the customer perceives the service and what the provider thinks they supply, both depend largely on their personal experiences and expectations. The process of providing a service is a combination of production and use, in which the provider and customer participate simultaneously. The perception of the customer is essential in the provision of services. Customers will generally use the following questions to assess the quality of the service: • Does the service align with my expectations? • Can I expect a similar service the next time? • Is the service provided at a reasonable cost? Whether or not the service fulfils the expectations depends primarily on how effectively the deliverables were agreed on in the first place, even more so than on how well the supplier provides the service. A continuing dialogue with the customer is essential to refine the services and to ensure that both the customer and the supplier know what is expected of the service. In a restaurant, the waiter will first explain the menu, and ask if everything is all right when serving a new course. The waiter actively coordinates supply and demand throughout the meal. This experience with customers is then used to improve future customer contact.
C3: Protected
Page 13 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
The quality of a service refers to the extent to which the service fulfils the requirements and expectations of the customer. To be able to provide quality, the supplier should continuously assess how the service is perceived and what the customer expects in the future. Another customer may well consider what one customer considers normal as a special requirement. Eventually a customer will get used to something considered special at the start. The results of the assessment can be used to determine if the service should be modified, if the customer should be provided with more information, or if the price should be changed. Quality is the totality of characteristics of a product or service that bear on its ability to satisfy stated and implied needs (ISO-8402). Reasonable costs may be considered as a derived requirement. Once it has been agreed on what is to be expected of the service, the next step is to agree on what it may cost. At this stage the service provider has to be aware of the costs they incur, and the current market rates for comparable services. A customer will be dissatisfied about a service provider who occasionally exceeds the expectations but disappoints at other times. Providing a constant quality is one of the most important, but also one of the most difficult aspects of the service industry. For example, a restaurant will have to purchase fresh ingredients, the chefs will have to work together to provide consistent results, and hopefully there are no major differences in style among the waiting staff. A restaurant will only be awarded three Michelin Stars when it manages to provide the same high quality over an extended period. This does not often happen: there are changes among the waiting staff, a successful approach may not last, and chefs leave to open their own restaurants. Providing a constant high quality also means that the component activities have to be coordinated: the more efficiently the kitchen operates, the more quickly the guests can be served. Therefore, when providing a service, the overall quality is the result of the quality of a number of component processes that together form the overall service. These component processes formed a chain; a series of linked activities. Effective coordination of the component processes requires not only high quality at each stage, but also consistent quality.
3.2.1
Quality Assurance
Supplying products or services requires activities. The quality of the product or service depends largely on the way in which these activities are organized. Deming’s quality life cycle provides a simple and effective model to address quality. The model assumes that to provide appropriate quality, the following steps must be undertaken repeatedly:
C3: Protected
Page 14 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
• Plan: Who should do what, when, how, using what? • Do: Implementation of the planned activities. • Check: Determine if the activities provided the expected result. • Act: Adjust the plans based on information gathered while checking. To be able to make use of this life-cycle approach, the activities of supplying products and services must be divided into processes, each with their own plans and opportunities for conducting checks. It must be clear who is responsible in the organization and what authority they have to change plans and procedures, not for only for each of the activities, but also for each of the processes. Quality management is the responsibility of everyone working in the organization providing the service. Every employee has to be aware of how their contribution to the organization affects the quality of the work provided by their colleagues, and eventually the services provided by the organization as a whole. Quality management also means continuously looking for opportunities to improve the organization and implementing quality improvement activities. Quality assurance is a policy matter within the organization. It is the whole of the measures and procedures, which the organization uses to ensure that the services provided, continue to fulfill the expectations of the customer and the relevant agreements. Quality assurance ensures that improvements resulting from quality management are maintained. A quality system is the organizational structure related to responsibilities, procedures and resources for implementing quality management. The ISO 9000 series of standards is often used to develop, define, assess and improve quality systems.
C3: Protected
Page 15 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
Dr. Edward Deming was an American statistician brought to Japan by general Douglas MacArthur after the Second World War to help rebuild the destroyed economy. He had developed theories about the best possible use of expertise and creativity in organizations in the United States in the 1930s, but because of the Depression his ideas were not accepted in the US. However, his optimization methods were successfully adopted in Japan. Some of Deming’s typical statements: •
‘The customer is the most important part of the production line.’
•
‘It is not enough to have satisfied customers, the profit comes from returning customers and those who praise your product or service to friends and acquaintances.’
•
‘The key to quality is to reduce variance.’
•
‘Break down barriers between departments.’
•
‘Managers should learn to take responsibility and provide leadership’
•
‘Improve constantly.’
•
‘Institute a vigorous program of education and self-improvement.’
•
‘Institute training on the job.’
•
‘The transformation is everybody's job.’
ISO-9000
C3: Protected
Page 16 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
Some organizations require their suppliers to hold an ISO 9001 or ISO 9002 certificate. Such a certificate proves that the supplier has an adequate quality system whose effectiveness is regularly assessed by an independent auditor. ISO is the International Standards Organization. A quality system that complies with the ISO standard testifies that the supplier has taken measures to be able to provide the quality required by their customers; •
the management regularly assesses the operation of the quality system, and uses the results of internal audits to implement improvement measures where necessary;
•
the suppliers’ procedures are documented and communicated to those affected by them;
•
customer complaints are recorded, dealt with in a reasonable time, and used to improve the service where possible;
•
the supplier controls the production processes and can improve them.
An ISO certificate does not provide an absolute guarantee about the quality of the service provided, however, it does indicate that the supplier takes quality assurance seriously and is prepared to discuss it. The new ISO 9000 series of standards, ISO-9000-2000, puts even greater emphasis than the previous standard on the ability of an organization to learn from experience and to implement continuous quality improvement.
C3: Protected
Page 17 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
Organizational Maturity Experience with improving the quality of IT services has shown that it is rarely sufficient to simply define current practices. The causes of a mismatch between the service provided and the customer’s requirements are often related to the way in which the IT organization is managed. A permanent quality improvement focus demands a certain degree of maturity of the organization. The European Foundation for Quality Management (EFQM) model can be useful in determining the maturity of an organization. It identifies the major areas to be considered when managing an organization. Deming’s Quality Life-Cycle is incorporated in the EFQM model. Based on the outcomes from "result areas" actions are taken (strategy, policies). These actions serve to underpin the planning (e.g. the structure of the processes), that should lead to the desired results. The EFQM identifies nine areas. In 1988 fourteen large European companies, with the support of the European Commission, set up the European Foundation for Quality Management. The objective of the EFQM is to promote Total Quality Management, aimed at excelling in customer satisfaction, employee satisfaction and appreciation by society, and performance results. The EFQM ‘Model of Business Excellence’, generally known simply as the EFQM model, is widely accepted as the major strategic framework for managing an organization aimed at the balanced, continuing improvement of all aspects relevant to the business. Over 600 European businesses and research organizations have now joined the EFQM. For further information: http://www.efqm.org.
C3: Protected
Page 18 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
CMM In the IT industry, the process maturity improvement process is best known in the context of the Capability Maturity Model (CMM). The Software Engineering Institute (SEI) of Carnegie Mellon University developed this process improvement method. CMM is concerned with improving the maturity of a software creation processes. CMM includes the following levels:
•
Initial - the processes occur ad hoc.
•
Repeatable - the processes have been designed such that the service quality should be repeatable.
•
Defined - the processes have been documented, standardized and integrated.
•
Managed - the organization measures the results and consciously uses them to improve the quality of its services.
•
Optimizing - the organization consciously optimizes the design of its processes to improve the quality of its services, or to develop new technology or services.
Maturity models based on the CMM levels of maturity have also been developed for IT Service Management. When assessing the maturity of an organization, we cannot restrict ourselves to the service provider. The level of maturity of the customer is also important. If there are large differences in maturity between the supplier and the customer, then these will have to be considered to prevent a mismatch in the approach, methods and mutual expectations. Specifically, this affects the communication between the customer and the supplier. It is advisable to bring both organizations to the same level of development, and to operate at that level, or to adjust the communication in line with the lower level.
C3: Protected
Page 19 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
Organization and Policies We know that service quality is closely associated with the quality of an organization and its policies. This section will discuss several important aspects of the organization and policies that are relevant to process management.
Vision, objectives and policies An organization is a form of cooperation between people. Any organization, from a darts club to a multinational company, depends on a concept of why it is worth cooperating in the organization. The shared vision might be that you can make money selling or you can improve the environment. However, to be attractive to all stakeholders (e.g. customers, investors, personnel) as an organization it has to be communicated to clients why they should do business with you. For example because you are the best, cheapest or most fun. You will want to build up a suitable image. Think of the things that stick in your mind – “Just Do It” (Nike). To communicate the vision, the organization creates a Mission Statement. The mission statement is a short, clear description of the objectives of the organization and the values it believes in. The objectives of the organization describe in greater detail what it wants to accomplish. Good objectives have five essential elements: they have to be Specific, Measurable, Appropriate, Realistic and Time-bound (SMART). The policy of the organization is the combination of all decisions and measures taken to define and realize the objectives. In its policies, the organization will priorities objectives and decide how the objectives will be reached. Of course, priorities may change over time, depending on the circumstances. The clearer the organization’s policies are to all stakeholders, the less needs to be defined about how personnel are supposed to do their work. Instead of detailed procedures, personnel can independently use the policies as their guideline. Clearly formulated policies contribute to a flexible organization, as all levels in the organization can respond more quickly to changing circumstances. Implementing policies in the form of specific activities requires planning. Plans are usually divided into stages to provide milestones where progress can be monitored. For example, the policies can be used to draw up an annual plan, which is then used to develop the budgets. An organizational annual plan can be further developed into greater detail as departmental plans, quarterly plans or project plans. Each of these plans contains a number of elements: an activity schedule, the required resources, and agreements about the quality and quantity of the products or services to
C3: Protected
Page 20 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
be delivered. Realization of the planned activities requires action. Actions are allocated to personnel as tasks, or outsourced to external organizations. When translating the mission of the organization into objectives, policies, planning and tasks, there is the risk that after some time, the mission, objectives or policies are forgotten. It is therefore important that at every stage we measure if the organization is still moving in the right direction, and remedial action is taken where necessary. We have to measure if the organization or processes fulfill the objectives, and there are various methods available for this. One of the most common methods in business is the Balanced Score Card, or BSC. In this method, the objectives of the organization or process are used to define Critical Success Factors (CSF). CSFs are defined for a number of areas of interest or perspectives: customers/market, business processes, personnel/innovation and finance. The parameters used to measure if the CSFs meet the standards are known as Key Performance Indicators (KPI). Where necessary, these can be subdivided into Performance Indicators (PI). Key performance indicators, or KPIs, are parameters for measuring progress relative to key objectives or Critical Success Factors (CSF) in the organization. The outcome of the measurements and changing circumstances can lead to modification of the processes, tasks, plans, and policies, and even to a change in the objectives, mission and vision of the organization. The more mature an organization is, the better it deals with such changes. If the IT department supports the interests of the business, the objectives of the IT department will be derived from the business objectives. The IT department, for example, might have the following objective: ‘To contribute to the competitive strength of the business’. The specific objectives of the IT department will then be developed on the basis of this general objective. Depending on the nature of the business, objectives will be defined for the IT department with respect to safety, accessibility, response speed, technical sophistication and so on. Planning Horizon When considering the policies and planning of an IT department, we should be aware of the links between planning for the business as a whole and the application systems and the technical infrastructure used by the business. When planning the network and applications of a business, the IT department will have to stay ahead of the overall planning to ensure that the business has an IT infrastructure in which it can develop and grow into. The figure below gives an example of the links between the various plans.
C3: Protected
Page 21 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
Technical infrastructure has the longest planning horizon and in its support role it has fewer clear links with the substantive business activities. It takes time to develop a technical infrastructure and the fact that information systems and the business depend on the technical infrastructure, limits the speed at which changes can be implemented. Furthermore, developing a technical infrastructure demands significant investment and the period over which it can be depreciated has to be considered. The planning horizon is shorter for applications as they are designed for specific business purposes. Application life cycle planning is primarily based on the business functions to be provided by the system, after which the underlying technology is considered. Business plans, based on the organization’s strategy, normally cover one calendar or financial year. Budgets, planning and progress reports all fall within this period. In some markets, the planning cycle time has become even shorter as the cycle time for product development has also decreased. Planning should address four elements: • Time - this is the easiest factor to determine. It is defined by a starting date and ending date, and is often divided into stages. • Quantity - the objectives have to be made measurable to monitor progress. Terms such as ‘improved’ and ‘quicker’ are insufficient for planning purposes. • Quality - the quality of the deliverables (results) should be appropriate for the objective. • Costs and revenues - the deliverables must be in proportion to the expected costs, efforts and revenues. Differences between the planning horizons occur not only between areas, but also between the various levels of activities and processes (strategic, tactic and operational). Culture Organizations that want to change (for example to improve the quality of their services) will eventually be confronted with the current organizational culture. The organizational culture, or
C3: Protected
Page 22 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
corporate culture, refers to the way in which people deal with each other in the organization; the way in which decisions are made and implemented; and the attitude of employees to their work, customers, suppliers, superiors and colleagues. Culture, which depends on the standards and values of the people in the organization, cannot be changed, but it can be influenced. Influencing the culture of an organization requires leadership in the form of a clear and consistent policies and a supportive personnel policy. The corporate culture can have a major influence on the provision of IT services. This is due to the fact that businesses value innovation in different ways. In a stable organization, where the culture places little value on innovation, it will be difficult to adjust the IT services in line with changes in the organization. If the IT department is unstable, then a culture that values change can pose a serious threat to the quality of its services. In that case, a free for all can develop where many uncontrolled changes lead to a large number of faults.
3.2.2
Human Resource Management
Personnel policy plays an important and strategic role in fulfilling the long-term objectives of an organization (see also the EFQM model). It can also be used as an instrument to change the corporate culture. The objective of modern personnel management is to optimize the performance of all personnel in the organization. A variety of instruments such as recruitment and selection, training and career development, motivation and reward are used. Human Resource Management (HRM) is the major form of modern personnel management. Human Resource Management is based on two premises: • Personnel management should contribute to the objectives of the organization. If organizations have to respond better and more quickly in an environment which changes ever more quickly, then this will affect the deployment, quality and number of personnel. • Giving employees in the organization the opportunity to develop and use their skills will benefit the organization. There are three approaches to HRM: • The hard approach sees human resources as means of production, which have to be organized as effectively and efficiently as possible. As the corporate strategy is determined by economic, technical and market factors, the same applies to personnel policy. This approach places different values on employees. Some core employees are strategically more important than peripheral employees who are easily replaceable. For example, a company might choose to permanently employ only core personnel, and for the rest use a pool of flexible personnel. • The soft approach emphasizes that making the best possible use of human potential and opportunities will benefit the business. Modern employees are highly educated, ambitious and prepared to invest a lot in their work. For this reason, their potential must be identified early and developed continuously (career development, training policy). When selecting its strategy and policy, the business must base its choices on the talent and potential of its employees. • The integrated approach looks at the shared interests of personnel and management in an organization. To reach the objectives of the organization there will have to be good inflow, movement and outflow of personnel. Changes in the market and the organization (e.g. developments in technology) lead to constant changes in the need for skills. All aspects of personnel policy have to be carefully coordinated. The movement of employees in
C3: Protected
Page 23 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
the organization, determining and developing skills (competence) and promoting mobility in the internal labour market is becoming increasingly important in organizations. The quality of service provided by an organization benefits if the best use is made of the potential of its employees. This facilitates continuous improvement. Instruments for quality management in personnel policy include: • Policy Deployment - communicating to each employee how and to what extent their task contributes to realizing the objectives of the organization. An important condition for the success of policy deployment is that it also extends to all layers of management. • Empowerment - giving employees the opportunity to organize and implement their task in consultation with the organization. The degree of empowerment determines the extent to which employees can be held responsible for the quality of the work they provide. • Accountability - which may be the result of policy deployment and empowerment. If an employee has had an explanation of what is expected of them, and if they have had the opportunity to arrange and implement the task as they wanted, then they can be held accountable for it. This could be used as a basis for assessing and rewarding employees. The reward may be material (salary) or immaterial, for example appreciation, new opportunities for development and career opportunities. • Competence Management - this is both a method to use the competency available in an organization as effectively as possible, and as a way to systematically develop the competence the organization needs. This approach charts the competence required by the processes and projects as well as the competence of the employees. When organizing employees, the focus is not only on obtaining a good match between the required and available competence, but also on the opportunities to develop competence, transfer expertise, and learn skills. Mentors or coaches may support employees. Setting up skills groups can also support the exchange of experience and encourage the development of new competence. IT Customer Relationship Management The quality of IT services largely depends on good relationships with the customers of the IT organization. These relationships provide the basis for making and updating agreements. IT Customer Relationship Management addresses maintaining a relationship with customers and coordinating with customer organizations, at the strategic, tactic and operational levels. In IT Customer Relationship Management, the major challenge is to ensure that there are good and effective relationships between the IT organization and the customer organization at all levels. However, the extent of IT Customer Relationship Management will be different at each level. One of the elements in customer relationships is the Service Desk, and the control of the Service Levels can be based on Service Level Management. In these areas, IT Customer Relationship Management will primarily play a supportive role, for example, by organizing surveys among customers and users, providing information, and so forth. The user is the person behind the PC, the employee who uses IT services for their routine activities. The customer is the person who is authorized to conclude an agreement with the IT organization about the provision of IT services (for example a Service Level Agreement, SLA) and who is responsible for ensuring that the IT services are paid for.
C3: Protected
Page 24 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
IT Customer Relationship Management plays an important role in developing the Strategic Alignment between the IT organization and the organization purchasing the IT services. In practice, this is primarily a matter of staying in touch with the customer organization, and exploring the options for linking the strategic objectives of both organizations. This can provide the basis for a long-term relationship, in which the IT organization focuses on the customer and proposes IT solutions that the help the customer reach their business objectives. Given the dynamic nature of both the customer organization and the IT organization, the rate of change in both organizations should also be coordinated. The agreements with the customer about the services to be provided are then developed into service level proposals through Service Level Management. For example, if the customer wants to introduce an intranet, then the availability, user support, implementation of change requests and cost all have to be agreed. These agreements are laid down in a Service Level Agreement (SLA). If the customer organization wants changes (expansion or modification) to the IT services that fall within the agreements laid down in the SLA, then a Request for Change will be submitted. Change Management then processes the request. Changes outside the current agreements are introduced into the Service Level Management process. In most cases, users can contact a Service Desk for operational requests and questions, and to report problems. Coordination at a strategic level has a planning horizon of several years. Service Level Management concerns agreements at the tactical level, with a planning horizon of approximately one year. Change Management, Service Desk and Incident Management all concern the operational level, with a planning horizon of months or even weeks.
Processes When arranging activities into processes, we do not use the existing allocation of tasks, or any existing departmental (functional) divisions. This is a conscious choice. By opting for a process structure, we can often show that the certain activities in the organization are uncoordinated, duplicated, neglected, or unnecessary. A process is a logically related series of activities for the benefit of a defined objective. Instead, we look at the objective of each process and its relationships with other processes. A process is a series of activities carried out to convert an input into an output. We can label the input and output of each of the processes with quality characteristics and standards (that is,
C3: Protected
Page 25 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
what is expected to go into and what is expected to come out of the particular process). These characteristics and standards provide information about the results expected of the process. We end up with linked chains of processes, which show what goes into the organization and what the result is. As well as this we can describe monitoring points in the chains to assess the quality of the products and services provided by the organization. The standards for the output of each process have to be defined so that the complete chain of processes meets the corporate objective/s, if each process complies with its process standard. If the result of a process meets the defined standard, then the process can be said to be effective. If the activities in the process are also carried out with the minimum required effort and cost, then the process can be called efficient. The aim of process management is to use planning and control to ensure that all processes are effective and efficient. We can study each process separately to optimize its performance. The process owner is responsible for the process results. The process manager is responsible for the realization and structure of the process, and reports to the process owner. The process operatives are responsible for defined activities, and report to the process manager. The logical combination of activities results in clear points where the quality of processes can be monitored. In a restaurant for example, we can separate responsibility for purchasing and cooking; chefs may not have the authority to purchase anything as experience may show that they tend to spend too much on fresh ingredients that do not add value. The management of the organization can exercise control on the basis of the quality of the process as demonstrated by data from the results of each process. In most cases, the relevant performance indicators and standards will already be agreed. The day-to-day control of the process can then be left to the process manager. The process owner will assess the results based on a report of performance indicators and whether they meet the agreed standard. Without clear indicators, it would be difficult for a process owner to determine whether the process is under control, and if planned improvements are being implemented. Processes are often described using procedures and work instructions. A procedure is a description of logically related activities, and who they are carried out by. A procedure may include stages from different processes. A procedure defines who does what, and varies depending on the organization. A set of work instructions defines how one or more activities in a procedure should be carried out.
C3: Protected
Page 26 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
Processes and departments Most businesses are organized in a hierarchy. They have departments, which are responsible for a group of employees. There are various ways of structuring departments, for example by customer, product, region or discipline. IT services generally depend on several departments, customers or disciplines. In a hierarchical organization if there is an IT service to provide users with access to an accounting program on a central computer it will generally involve several departments. In this example, the computer centre has to make the program and database accessible, the data and telecommunications department has to make the computer centre accessible, and the PC support department has to provide users with an interface to access the application. Processes that span several departments can monitor the quality of a service by monitoring certain aspects of quality, such as availability, capacity, cost and stability. A service organization will then try to match these quality aspects with the customer’s demands. The structure of such processes can ensure that good data is available about the provision of services, so that the planning and control can be improved.
IT Service Management IT Service Management is primarily known as the process and service-focused approach of what was initially known as IT Management. In this chapter we have explained that processes should always have a defined objective. The objective of IT Service Management processes is to contribute to the quality of the IT services. Quality management and process control form part of the organization and its policies. In a process-focused approach we also have to consider the situation within an organization (policies, culture, size, etc.). ITIL, the best known approach to IT Service Management, does not dictate how an organization should be structured. ITIL cleverly describes the relationships between the activities in processes, which are relevant to any organization. ITIL also provides a framework that allows experiences to be shared in different organizations, as it is a common language.
C3: Protected
Page 27 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
4.0 Introduction to ITIL
This chapter describes the structure and objectives of the IT Infrastructure Library (ITIL) and the organizations that contribute to maintaining ITIL as the best practice standard for IT Service Management.
4.1
Background
ITIL was developed due to the fact that a growing number of organizations are becoming increasingly dependent on IT to help fulfill their corporate objectives. This increasing dependence has resulted in a growing need for IT services of a quality corresponding to the objectives of the organization, and which meet the requirements and expectations of the customer. Over the years, the emphasis has shifted from the development of IT applications to the management of IT services. An IT application (sometimes referred to as an information system) only contributes to realizing corporate objectives if the system is available to users and, in the event of fault or necessary modifications; it is supported by maintenance and operations. In the overall life cycle of IT products, the operations phase expenditure amounts to about 70 to 80% of the overall time and cost, the rest is spent on product development (or procurement). Effective and efficient IT Service Management are essential to the success of IT applications. This applies to any type of organization, large or small, public or private, with centralized or decentralized IT services, with internal or outsourced IT services. In all cases, the service has to be reliable, consistent, of a high quality, and at an acceptable cost. IT Service Management addresses the provision and support of IT services tailored to the needs of the organization. ITIL was developed to disseminate IT Service Management best practices systematically and cohesively. The approach is based on service quality and developing effective and efficient processes. ITIL offers a common framework for all the activities of the IT department, as part of the provision of services, based on the IT infrastructure. These activities are divided into processes, which provide an effective framework for further enhancement of IT Service Management. Each of these processes covers one or more tasks of the IT department, such as service development,
C3: Protected
Page 28 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
infrastructure management, and supplying and supporting the services. This process approach makes it possible to describe the IT Service Management best practices independently from the actual organizational structure of the department. Many of these best practices are clearly identifiable and are indeed used, to some extent, in most IT organizations. ITIL presents these best practices coherently. The ITIL books describe how these processes (which have sometimes already been identified) can be optimized, and how the coordination between them can be improved. The books also explain how the processes can be formalized within an organization. They provide a frame of reference within the organization for the relevant terminology, and help to define the objectives and to determine the required effort. By using a process approach, ITIL primarily describes what must be included in IT Service Management to provide IT services of the required quality. The structure and allocation of tasks and responsibilities between functions and departments depends on the type of organization, and these structures often change. The description of the process structure can help maintain the quality of IT services during and after reorganizations. The list below identifies some advantages and disadvantages of ITIL. It does not claim to be a definitive list. Any attempt to supplement it often leads to an interesting discussion about the advantages of disadvantages of ITIL and about the way in which organizations actually use ITIL.
4.2
Advantages to the Customer/End User:
• The provision of IT services becomes more customer-focused and agreements about service quality improve the relationship. • The services are better described, and in greater detail. • The quality and cost of the services are managed better. • Communication with the IT organization is improved by agreeing on the points of contact.
4.3
Advantages to the IT Organization:
• The IT organization develops a clearer structure, becomes more efficient, and more focused on the corporate objectives. • The management is more in control and changes become easier to manage. • An effective process structure provides a framework for the effective outsourcing of elements of
C3: Protected
Page 29 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
the IT services. • Following the ITIL best practices encourages a cultural change towards providing service, and supports the introduction of a quality management system based on the ISO-9000 series. • ITIL provides a uniform frame of reference for internal communication, standardization and identification of procedures.
4.4
Potential disadvantages:
• The introduction can take a long time and significant effort, and requires a change of culture in the organization. An over ambitious introduction can lead to frustration because objectives are never met. • If process structures become an objective in themselves, the service quality may be adversely affected. In that case, procedures become bureaucratic (obstacles that are avoided where possible). • There is no improvement due a lack of understanding about what processes should provide, what the performance indicators are, and how processes can be controlled. • Improvement in the provision of services and cost reductions are not visible. • A successful implementation requires the involvement and commitment of personnel at all levels in the organization. Leaving the development of the process structures to a specialist department may isolate that department in the organization and it may set a direction that is not accepted by other departments. • If there is insufficient investment in support tools, the processes will not be done justice and the service will not be improved. Additional resources and personnel may be needed if the organization is already overloaded by routine IT Service Management activities.
C3: Protected
Page 30 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
ITIL was obviously developed to capitalize on the advantages. It is appropriate to recognize and acknowledged that there can be problems with an adoption of ITIL practices. However, the ITIL Framework itself provides a lot of suggestions on recognizing and therefore preventing such problems, or how to solve them should they occur.
4.5
Organizations
OGC (CCTA) ITIL was originally a CCTA product. CCTA was the Central Computer and Telecommunications Agency of the British government. On the 1st April 2001, the CCTA was amalgamated with the OGC (Office of Government Commerce), which is now the new "owner" of ITIL. The objective of the OGC is to help its customers in the British public sector update their procurement activities and improve their services by making the best possible use of IT and other instruments. ‘OGC aims to modernize procurement in government, and deliver substantial value for money improvements.’ The OGC promotes the use of ‘best practices’ in many areas (e.g. project management, procurement and IT Service Management). The OGC publishes several series (libraries) of books written by British and international experts from a range of companies and organizations. The OGC IT Infrastructure Library consists of a number of clear and thorough ‘Codes of Practice’ to promote and provide efficient and effective IT services.
ITSMF The Information Technology Service Management Forum (ITSMF), originally known as the Information Technology Infrastructure Management Forum (ITIMF), was set up in the UK in 1991. The Dutch ITSMF (ITSMF Netherlands) was the next chapter, set up in November 1993. In 2001 it had over 500 members organizations, both suppliers and user groups. There are now ITSMF chapters in countries such as South Africa, Belgium, Germany, Austria, Switzerland, the United States, and Australia, who participate in the ITSMF International group.
The itSMF promotes the exchange of information and experiences that enable IT organizations to improve the services they provide. It organizes symposiums, congresses, special subject evenings, and other events about current IT Service Management subjects.
Working parties also contribute to the development of the subject. The association publishes a newsletter and operates a web site with information about its activities (http://www.itsmf.com).
EXIN and ISEB The Dutch foundation EXameninstituut voor INformatica (EXIN) and the UK Information Systems Examination Board (ISEB) jointly developed a professional certification system for ITIL. This was done in close cooperation with the OGC and ITSMF. EXIN and ISEB are nonprofit organizations which cooperate to offer a full range of ITIL qualifications at three levels: • Foundation Certificate in IT Service Management
C3: Protected
Page 31 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
• Practitioner Certificate in IT Service Management • Manager Certificate in IT Service Management The certification system is based on the requirements for effectively fulfilling the relevant role within an IT organization. To date, certificates have been awarded to over 30,000 IT professionals in over 30 countries. The Foundation Certificate is intended for all personnel who have to be aware of the major tasks in the IT organization, and the connections between them. After obtaining the Foundation Certificate, the Practitioner and Manager exams can be taken. Practitioners are trained to undertake specific ITIL processes or tasks in such processes, such as Incident Management, Change Management and/or Service Level Management. Managers are trained to be able to control these processes, to advise about the structure and optimization of the processes, and to implement them. By now, ITIL represents much more than a series of useful books on IT Service Management. The framework of best practice in IT Service Management is promoted and further developed by consultants, trainers and tool suppliers. Since the 1990s, ITIL has stood not just for the framework, but also the approach and philosophy shared by those using ITIL best practices in their work. A range of organizations are now cooperating internationally to promote ITIL as the de facto standard in IT Service Management. The ITIL community also allows for organizations involved to provide feedback so that the reality of current best practice is quickly reflected and incorporated into the ITIL theory. Furthermore, extensions and alternatives have been developed, some of which may be considered as IT Service Management methods in their own right. These alternatives often address the needs of certain groups or organizations whose specific problems are not adequately covered by ITIL. The unique aspect of ITIL is that it offers a generic framework based on the practical experience of a global infrastructure of professional users.
ITIL (IT Infrastructure Library) ITIL is a series of books. As the name suggests it is a Library (IT Infrastructure Library). This section will describe the various components of the library. Each of the ITIL books addresses part of the overall ITIL framework. For the ITIL purist we acknowledge that ITIL is a library of many books. This course is centred on the Service Delivery and Service Support books. We use ITIL as the description of these two books throughout the course. ITIL defines the objectives and activities, and input and output of each of the processes found in an IT organization. However, ITIL does not give a specific description of how these activities should be implemented, as this will be different in every organization. The emphasis is on an approach that has been proven in practice, but (depending on the circumstances) may be implemented in a number of ways. ITIL is not a method, instead it offers a framework for planning the most common
C3: Protected
Page 32 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
processes, roles and activities, indicating the links between them and what lines of communication are necessary. ITIL is based on the need to supply high-quality services, with an emphasis on customer service and relationships. The IT organization has to fulfill "customer" requirements, which means maintaining good relationships with them and associated partners such as suppliers. Part of the ITIL philosophy is based on quality systems, such the ISO-9000 series, and Total Quality frameworks, such as that of the EFQM. ITIL supports such quality systems with a clear description of the processes and best practices in IT Service Management. This can significantly reduce the time required to obtain ISO certification. Originally, ITIL consisted of a large number of sets of books, each of which described a specific area of the maintenance and operation of IT infrastructure. Ten books describing Service Support and Service Delivery were considered as the core of ITIL. There were approximately 40 other books on complementary subjects related to IT Service Management, from cabling to managing customer relationships. However, the original series of books in the Infrastructure Library mostly approached IT Service Management from the IT perspective. The Business Perspective Set was introduced to bridge the divide between the business and the IT organization. Even so, certain aspects of ITIL still had a slightly dated approach. The "core" ITIL books have now been revised and published as two books, one on Service Support, and one on Service Delivery. This has eliminated significant overlap and occasional inconsistencies in the earlier series and has improved cohesion. They also support the vision of IT Service Management more thoroughly. The ITIL puzzle shows the main elements addressed by the ITIL books. Each of these elements interfaces with the others, and overlaps them to some extent. The elements are: •
The Business Perspective
•
Service Delivery
•
Service Support
•
ICT Infrastructure Management
•
Applications Management
•
Planning to Implement Service Management
In this chapter, we will introduce the ITIL series of publications using the main elements of the ITIL puzzle. By the end of 2002 the original set of books, each on a specific aspect of IT Service Management, should have been replaced by six new ITIL books, as have the books on Service Support and Service Delivery. However, many of the best practices to be described in the new books are also included in the current ITIL series. For more information www.itil.co.uk Business Perspective The ITIL books in the Business Perspective Set describe many issues related to understanding and appreciating IT services as an integrated aspect of managing a business. The Business Perspective Set, and the Business Perspective book, which will eventually replace
C3: Protected
Page 33 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
the set, addresses: • Business Continuity Management • Partnerships and outsourcing • Surviving changes • Adapting the business to radical changes Other ITIL books address some of these topics, in addition to those in the Business Perspective Set. Managing Facilities Management "Managing Facilities Management" addresses the management of contracts between the IT organization and Facilities Management companies. The Facilities Management suppliers may be responsible for the operation of all or part of the IT infrastructure. However, the IT organization bears the ultimate responsibility for the services provided to the customer. This book describes what measures the IT organization can take to accept responsibility for agreements about Service Levels and how to monitor the services provided by the facilities suppliers. Managing Supplier Relationships To some extent, "Managing Supplier Relationships" is similar to Customer Relationship Management, but now covering the relationship between the IT organization and its suppliers. A good relationship with suppliers is not just a matter of contractual agreements and contacts. The primary concerns are business like forms of cooperation that contribute to the current and future provision of IT services and fulfilling the objectives of the IT organization. Relationships with suppliers can be characterised by the nature and content of the contacts. These may be to discuss the long-term prospects of existing relationships, to promote communication, or to investigate the range offered by various suppliers. The major tasks of the Managing Supplier Relationships process include selecting suppliers, assessing the performance of suppliers, and determining the way in which the IT organization handles supplier contracts.
C3: Protected
Page 34 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
Service Delivery As indicated above, Service Support and Service Delivery are considered to be at the heart of the ITIL framework for IT Service Management. The ITIL book on Service Delivery describes the services the customer needs, and what is needed to provide these services. The following subjects are addressed: • Service Level Management • Financial Management for IT Services • Capacity Management • Availability Management • IT Service Continuity Management • Security Management (with reference to the ITIL book on Security Management) There is continual reference to how these areas also integrate the essential element of Client Relationship Management. The complex interrelationship between the processes described in the books on Service Support and Service Delivery is almost impossible to show in a diagram. We will briefly describe each of these areas now: IT Customer Relationship Management Most organizations appreciate the need to apply cohesion and structure to relationships within the customer organization at several levels. The IT Customer Relationship Management activities involve several processes. The Service Desk is the first point of contact for most "users". However, the "customer", who has commissioned and paid for the service, will initially contact IT Customer Relationship Management. IT Customer Relationship Management provides a bridge between the IT organization, which has traditionally taken a technical approach, and the customers who want to fulfill their business objectives. Service Level Management The objective of Service Level Management is to make clear agreements with the customer about the IT services required, and to implement these agreements. Consequently, Service Level Management needs information about the customer needs, facilities provided by the IT organization, and the financial resources available. Service Level Management addresses the service provided to the customer (Customer Focus). By analysing the information needs of the customer (Information Pull) rather than what is technically feasible (Technology Push), the IT organization can improve customer satisfaction. The chapter on Service Level Management in the Delivery book describes: How, by clearly defining, a Service Level Agreement can optimise the IT services at a cost that can be justified to the customer. How the service can be monitored and discussed.
C3: Protected
Page 35 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
Underpinning Contracts support the service with sub-suppliers/sub-contractors. Financial Management for IT Services Financial Management addresses the prudent provision of IT services. For example, Financial Management provides information about the costs incurred while providing IT services. This enables a proper consideration of costs and benefits (price and performance) when deciding on changes to the IT infrastructure or IT services. The identification, allocation, forecasting and monitoring of the costs, as discussed in the chapter on Financial Management in the Service Delivery book, are all covered by the term ‘costing’. These activities support cost awareness (what cost is incurred where?) and can also be used in drawing up budgets. With respect to the revenue stream of the IT organization, this ITIL book describes various charging methods. Capacity Management Capacity Management is the process of optimizing the deployment of IT resources, to support the agreements made with the customer. Capacity Management addresses resource management, performance management, demand management, modeling, capacity planning, load management and application sizing. Capacity Management promotes planning to ensure that the agreed Service Levels can also be fulfilled; now and in the future. Availability Management Availability Management is the process of ensuring the appropriate deployment of resources to support the availability of IT services agreed with the customer. Availability Management addresses issues such as optimizing maintenance, and design measures to minimise the number of incidents. IT Service Continuity Management This process addresses the preparation and planning of disaster recovery measures for IT services. Other common names are Contingency Planning and Disaster Recovery Planning. The starting emphasis for IT Service Continuity Management is the requirement to safeguard the continuity of the customer organization in the event of a disaster (this means that the IT organization must be aware of the "Business Continuity Plan"). IT Service Continuity Management is the process of planning and coordinating the technical, financial and management resources needed to ensure continuity of service after a "disaster", as agreed with the customer. Security Management The objective of Security Management is to protect the IT infrastructure against unauthorized use (such as unauthorized access to data). This is based on security requirements laid down in Service Level Agreements, contractual requirements, legislation, and policy. When updating the Service Delivery part of ITIL it was decided that the recently published book on Security Management did not have to be replaced. The ITIL book on Service Delivery does not address security management directly but refers to the Security Management book.
C3: Protected
Page 36 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
Service Support The ITIL book on Service Support describes how a customer can get access to the appropriate services to support their business. This book covers the following subjects: • Service Desk • Incident Management • Problem Management • Configuration Management • Change Management • Release Management Service Desk The Service Desk is the initial point of contact with the IT organization for users. Previously, the ITIL books referred to it as the Help Desk. The major task of the Help Desk was recording, resolving and monitoring problems. A Service Desk can have a broader role (for example receiving Requests for Change) and it can carry out activities belonging to several processes. The new book on Service Support now distinguishes between the Service Desk (i.e. as a function or organizational unit), and processes such as Incident Management, Configuration Management and Change Management.
Incident Management The distinction between "incidents" and "problems" is possibly one of the best-known discussion points in the ITIL field. There are clear differences and by understanding both processes the reasons become very clear. Although the difference may be confusing there is a major advantage in that a distinction is made between the rapid return of the service (the goal of incident management) and identifying and remedying the cause of an incident (the goal of problem management)
C3: Protected
Page 37 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
Incident Management aims to resolve the incident and restore service quickly. Incidents are recorded, and the quality of the incident records determines the effectiveness of a number of other processes. Problem Management If a problem is suspected within the IT infrastructure, Problem Management aims to identify the underlying cause. A problem may be when there are multiple occurring and seemingly related incidents. The intention of problem management is to eliminate these re-occurring incidents. Once the cause of a series of re-occurring incidents has been identified (Known Errors), a business decision is taken whether to make permanent improvements to the infrastructure to prevent new incidents. Submitting a Request for Change makes this improvement. By creating the Incident Management process in the Service Support book, Problem Management is neatly split off and is not a part of solving incidents. Note that your end users may still refer to what they experience as a "problem". It may not be appropriate to educate your users that what they are experiencing is in fact an "incident". This is a classic example of when the framework needs to be interpreted sensibly. Configuration Management Configuration Management addresses the control of a changing IT infrastructure (standardization and status monitoring), identifying configuration items (inventory, mutual links, verification and registration), collecting and managing documentation about the IT infrastructure and providing information about the IT infrastructure to all other processes. Change Management Change Management addresses the controlled implementation of changes to the IT infrastructure. The objective of the process is to determine the required changes, and how they can be implemented with a minimum adverse impact on the IT services, by effective consultation and coordination throughout the organization. Changes are made in consultation with the status monitoring activities of Configuration Management, the customer organization, Problem Management and several other processes. Changes are implemented by following a path of definition, planning, building and testing, accepting, implementing and evaluating. Release Management The actual implementation of changes is often carried out through Release Management activities. Both hardware and software (central processing, data communications and clients) changes are often planned on the basis of releases. The main objective of Release Management is to control the distribution of hardware and software, including integration, testing and storage. Release Management ensures that only tested and correct versions of authorized software and hardware are provided. Release Management is closely related to Configuration Management and Change Management activities. IT Infrastructure Management Eventually, technical operational management processes will be addressed in a new ITIL book on IT Infrastructure Management. This book will cover: • Network Service Management
C3: Protected
Page 38 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
• Operations Management • Management of Local Processors • Computer Installation and Acceptance • Systems Management IT Infrastructure Management also includes Environmental Management.
Network Services Management The Network Services Management process addresses planning and controlling communications networks. These include telephone systems, LAN and WAN networks. The ITIL module for Network Services Management also addresses the long-term communications needs of the organization. In essence, it describes how the ITIL best practices can be applied in a network environment. Operations Management Computer Operations Management (Computer Operations) addresses the management of computer hardware and systems software, including mainframes and midrange systems, but also file servers, to ensure that the agreed Service Levels are provided. The ITIL book of the same title concentrates on production tasks in an environment of large computer systems. Management of Local Processors The Management of Local Processors process addresses management operations at decentralized sites. The objective is to support the provision of IT services at the user site. This specifically includes making agreements about the activities of various processes (especially the processes to support IT services) when IT services are provided at multiple locations. A good definition of responsibilities is important to optimize the service. Computer Installation and Acceptance Computer Installation and Acceptance primarily concerns guidelines for planning the acceptance, installation and eventual removal of large computer hardware in the IT infrastructure. These guidelines are a development/extension of the activities in the Change Management and Release Management processes. Systems Management To date, the ITIL Books have not covered Systems Management. In future a new book on IT Infrastructure Management will cover it. Environmental Management Environmental Management concerns managing the environment of the IT infrastructure (power supply, cooling, etc.). One of the tasks of this process is to set up and maintain climate controlled computer and network rooms.
C3: Protected
Page 39 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
Applications Management The ITIL book on Applications Management will address the relationship between management and the software lifecycle. This includes issues such as Software Lifecycle Support and testing IT services. A major issue in Applications Management is effectively responding to changes in the business. Clearly defining the requirements and implementing a solution that meets the needs of the customer organization is paramount. Software Lifecycle Support Software Lifecycle Support aims to define the approach for supporting the entire software lifecycle, in consultation with those responsible for software development. The way in which software is designed, built, tested, introduced, operated, maintained, and eventually decommissioned, is extremely important in IT services. In every stage of the software lifecycle, there have to be agreements between those developing and those operating the IT infrastructure. The selection of Software Lifecycle models can have a significant impact on the IT services. Testing an IT Service for Operational Use The objective of testing an IT Service for Operational Use is to ensure that the proper operation of new or modified IT services is tested before they enter operations. A system test, installation test and acceptance test are undertaken to determine if the developed application works, is correctly installed, interfaces with the rest of the IT infrastructure, and offers the "users" the functions agreed with the "customer".
Management and Organization The ITIL series also includes some books on subjects at the strategic level, the Managers Set. Developing policies and long-term planning of IT services are specifically addressed in the books on Quality Management, IT Service Organization and Planning and Control for IT Services. Quality Management for IT Services Quality Management for IT Services addresses setting up and maintaining a coherent quality system, based on the IT Service Management processes described in other ITIL books. This book describes the introduction of a quality management system (based on the ISO-9000 series of standards) in an IT organization, and the evaluation of an existing quality management system. The relationship between the ISO standards and ITIL modules is also identified. Quality Management activities include defining and implementing the quality policy and managing the quality system, including audits. IT Services Organization IT Services Organization addresses the structure of the IT organization. This ITIL book describes how the organization can be analyzed and assessed, particularly in terms of tasks, authority and responsibility. A framework is provided for dealing with organizational changes, based on the process descriptions in the other ITIL books. Major activities in this process include determining and defining the organizational structure and role and function descriptions. Planning and Control for IT Services Planning and Control for IT Services aims to provide a coherent system of planning, reporting and
C3: Protected
Page 40 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
control for the IT organization, to ensure that the organization fulfils the objectives and requirements based on the business strategy and the strategy of the IT organization. This includes coordinating the planning and reporting of the various IT Service Management processes (for example in the form of annual plans and quarterly reports).
Planning and Implementation There is now much experience throughout the world with planning and implementing programmes to optimize IT Service Management. A recent ITIL book is devoted to this subject. In essence, the concept of planning and implementing changes in IT Service Management processes is shown in the process improvement model. In practice, the situation illustrated by this model is often obscured by the way in which important decisions are taken in organizations, which may be affected by historical and political issues. It is therefore necessary for management to commit to the improvement programme (Management Commitment), and for them to understand the organizational culture. You should also be aware that there will generally already be processes that meet the needs of the organization, albeit only partly. Lack of commitment will create resistance from the very people needed to align these processes with the business needs. And alignment is at the very heart of benefits gained in a process driven approach for IT Service Management. Analyzing the needs of the organization and implementing the required solution could require the creation of a temporary organization. This could be considered as a one project, or as a series of projects in an improvement programme. One advantage is that it will provide the organization with clear decision points where it can decide to terminate, continue, or modify the project. In this context, the ITIL books recommend the adoption of PRINCE2 (Projects IN Controlled Environments) as a Project Management methodology. Each project is based on an analysis of the current situation, the desired situation, and the path in between. In most cases, the alternatives will be compared on the basis of: • Advantages to the organization • Risks, obstacles and potential problems • Transition costs and long-term costs • Costs of continuing the current approach Identifying the potential alternatives may well be a project in itself. You should be aware that ITIL is no magic formula. Do not expect miracles. You should be particularly wary of so-called ITIL implementation projects that have a hidden agenda, such as a reorganization or merger. ITIL describes the best practice for improving IT Service Management; it is not an organizational handbook. ITIL primarily provides a frame of reference for process structures in the IT organization and, to a much lesser extent, a guideline for the structure of that organization. If a project aims to improve the IT organization along these lines, then it is wise to seek out experts in this field (a good starting point is outside consultants who are certified IT
C3: Protected
Page 41 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
Service Managers (according to the certification requirements laid down by Exin or the ISEB). A baseline measurement or health check can provide a good start for process improvements. Such an assessment of the IT Service Management processes can help identify the strengths and weaknesses of the organization, and define clear objectives for an improvement project. After some time the measurement can be repeated to show the progress of the project or programme.
C3: Protected
Page 42 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
5.0 Service Desk 5.1
Introduction
Here is a familiar situation..... You have just started a complicated job, which requires all your concentration. The phone rings....Someone is facing computer difficulty!!! The printer is not working. You solve the issue and just when you are back into the job … Someone walks into your office asking when his or her expected upgrade will be done. 1 hour later you still haven’t started your job….. Wouldn’t it be great if you could complete this job without interruption? It is the role of the Service Desk to act as the single contact point between the customer and the IT Service Provider. They will handle all incoming calls and only direct them through to the second or third level support when necessary. For the customer the advantage is that they don’t have to ring around, before finding the right person to solve their problem and for IT personnel it means that they only have to deal with issues that are related to their skills or area of responsibility. 5.2
Objective
The Service Desk offers "first line" support to users. Users need help if they are not sure how to behave in a specific situation when using IT services or when they need assistance to solve a particular issue involving IT. As well, the Service Desk is the central point of contact where incidents or inaccuracies in IT systems can be reported. The Service Desk is the face of the IT department to the clients. Furthermore, the Service Desk is an important source of management information. Objectives of the Service Desk: ?
To provide a single point of contact for Customers
? To facilitate the restoration of normal operation service with minimal business impact on the Customer within agreed service levels and business priorities
C3: Protected
Page 43 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
5.3
Process Description
The Service Desk is not regarded as a process within ITIL but as a function. As IT has become a greater part of business over the years the role of the Service Desk has become crucial. Businesses relies on there IT service to stay on top of the market and be competitive. The service provided by the Service Desk tends to be broader then just the IT part of business hence the change in name from Helpdesk (which was more IT related) into Service Desk. It plays a vital role in IT Service management as from a customer point of view the service desk is the IT Service Provider and therefore plays a critical part in how the customers perceives the IT organization as a whole. Among the activities performed by the Service Desk are Incident recording and Incident Control. This used to be part of the Helpdesk Process but is now included in the process called Incident Management (covered in a later module).
5.4
Activities
The Service Desk has a number of primary responsibilities. These are:
6.0
•
To provide a single point of contact for the customers;
•
To facilitate the restoration of normal operational service (with minimal business impact on the Customer) to the agreed service levels and according to the business priorities.
Activities
1. Keep users informed by.... 2. Providing information, in the form of: ?
The status of their incident
?
Planned changes in IT Service
?
Likely disruptions in the IT Service
?
Any changes or additions in the services that are provided or the service levels.
The obvious benefits in proactively providing service information is that: If the customers know before hand that a specific service (e.g. email) will be unavailable during the lunch hours you (a) reduce the amount of calls being received but also (b) reduce the impact of the disruption. The end result will be fewer angry or annoyed customers. 3. Provide management information By logging all calls the Service desk can provide information to Management about, the amount off calls per category, the amount of calls as a result of a change etc. But also in case of a disruption in the IT Service they are likely to be the first to know. This makes the Service Desk an excellent
C3: Protected
Page 44 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
First Point of contact for users, customers and management alike. The objective is to produce reports from which management can make decisions and measure performance based on agreed service levels and deliverables. 4. Conduct customer satisfaction analysis and surveys 5. Recording and controlling of incidents Incident control The Service Desk is responsible for recording all incidents and then controlling them. The Service desk can use different ways in recording the incidents: •
Phone
•
E-mail
•
Internet
•
Fax
•
Personal visit
By making use of different ways of recording incidents and even automating the solution then the workload of the service desk will be reduced and by association so will the costs. Think about how much time it costs to reset a password for a user and how often that is required. If by sending an email a set of actions would be started including: creating the incident, resetting the password, informing the customer and closing the incident a great deal of time could be saved.
6.1
Roles
The new Service Desk tends to be more then the just the place to lodge calls related to IT. It has a role to provide and improve the service to the business in general. The changing role is that the Service Desk is a more customer focused, whereas the traditional Help Desk tended to be more technical in nature. As there are different types of Service Desk models the skills required by the Service Desk staff also must be carefully analyzed. Interpersonal skills are one of the more important ones. Technical skills become more important when the Service Desk becomes more skilled and aims to solve most of the incidents without rerouting them to higher levels of support.
C3: Protected
Page 45 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
6.2
Relationships
Being the single point of contact for IT Service, the Service Desk has a link with all processes within ITIL. With some processes the link is a clearer than others.
The Service Desk is, in fact, an operational aspect of the important process of Incident Management, e.g. incident control. The Service Desk registers and "controls" Incidents. Incidents can be related to Configuration Items. If this link is supported by software, a powerful aid in mapping/identifying weak links in the IT infrastructure evolves. This allows the Service Desk staff to quickly solve incidents by searching on a Configuration Item, category and/or error code and applying a previously used solution. Note: A Configuration Item (or C.I.) is discussed in the Configuration Management process section. A C.I. is an item that we want to store information about. In some cases the Service desk does some minor changes and so has a link with Change Management and Release Management. The link between the Service Desk and Service Level Management can be illustrated as a result of the Service Desk monitoring Incident levels and reporting whether the IT service is restored within the limits defined in Service Level Agreements (SLA's). Service Desk will report to Service Level Management if IT Service is not restored within time frames and escalation procedures are properly defined and adhered to.
C3: Protected
Page 46 of 203
Controlled copy
6.3
ITIL Foundation Level - Certification Guide
Benefits
The benefits from a properly implemented Service Desk flow across Users, Customers, IT Staff and the business as a whole. Note: The difference between a Customer and a User should be explained. A Customer is the person who may often be the representative of the business for the service provided and/or the person who funds the service. The user is the ultimate end user of the service provided. Benefits for the Customer •
Easily defined metrics for measuring performance
Benefits for Users •
Single point for all queries
•
Better informed
•
Quicker turn around of request, queries and incidents
Benefits for IT staff •
Being able to focus more on the job
C3: Protected
Page 47 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
•
Greater efficiency
•
Better use of the skills the staff has resulting in motivated personnel
•
Improved team work
Benefits for the business •
Source of useful management information
•
Internal cost savings and productivity efficiencies
•
Meet customers business support requirements with responsiveness at all times when and wherever it is needed
•
Better use of available resources
6.4
Summary
An effective Service Desk will deliver overall cost reduction and increases in staff morale, service reliability and identification of business opportunities. All this leads to increases in Customer satisfaction ratings, with the associated improvement in perception this brings.
C3: Protected
Page 48 of 203
Controlled copy
6.5
ITIL Foundation Level - Certification Guide
Common Problems
There is no doubt in denying that along with any move towards improvement there will be problems and barriers to success. Recognizing this in advance goes a long way to solving the problem when (not "if") it comes up. •
Users do not call the Service Desk, but try to go around it to the person they know, the one who helped them so well the last time.
The Service Desk needs to be easily accessible, easy to remember phone number, out of office process established, after hours process established, low waiting times and different ways of communicating/interfacing. Processes for dealing with different levels of staff within the organization (eg. creating a group of "Critical Users") will also ensure that Service Desk staff realistically deal with those in highly critical roles as a top priority. All Customers must be redirected to the Service Desk if they try to contact someone directly. This can be done politely and does not have to be used as a threat (eg. "if you don't contact the Service Desk, we won't help you" versus "if you can contact the Service Desk it will mean that we properly track and fix your problem"). Users who wish to circumvent the proper procedure will be annoyed and cause disruption. However, this short term problem should be ridden out, rather than "giving in". In time, all users will become accustomed to change and eventually start to accept and see the benefits (refer to SD Benefits). •
Not aware what the needs of the business and/or users are.
If the Service provided by the Service Desk (IT Service Provider) is not the one needed by the business or the user then it matters little that the service is perfect. If a business is only operating between 9 am and 4 pm, having a Service Desk that’s is open 24 hours a day, is not very useful and might result in under staffing of the Service Desk during the business hours.
•
Not all parties involved are informed about the Service provided and the Service Levels agreed upon, resulting in unrealistic expectations.
This is a simple case of communication and making sure that that all procedures, Service levels etc are well documented and available to all parties involved. Also periodically revisiting and reeducating involved staff, BEFORE issues arise. This is not to say that staff will use this information against users who require service, it simply means that users approach the Service Desk with realistic expectations. Naturally, everyone's problem is critical when it happens - when a user is irate or stressed it is not appropriate to point out that the agreed service levels allow for a 48 hour response. This highlights the people skills that Service Desk staff need to have. A well-marketed Service Desk is only half the job. Involve key customers in the process of implementing the Service Desk and reap the rewards from having their support in times of crisis.
C3: Protected
Page 49 of 203
Controlled copy
6.6
ITIL Foundation Level - Certification Guide
Metrics
Metrics are essential in monitoring any IT Service provided. The Service Desk as a service for users is no different in this regard. Day to day reports can provide information on Calls and Incidents. For instance; •
How many and what kinds of incidents (classifications) the Service Desk solves at first point of call.
•
How long calls last, how many there are and how long the waiting time is before a call is answered. This information can be extracted from appropriate tools or from PABX records.
If standards are set before the Service Desk starts operating one can monitor the progress of the Service Desk. The crucial factor is in defining what it is that should be measured. It is realistic to start with a very simple set of metrics and possibly this is a better approach as it means that there is no time lost in creating a long series of reports that add no value to a customer. The easiest way to begin to define what metrics are required is to look to the Service Level Agreements (SLA's) that should define the response times, etc. for the Service Desk from the Customer perspective. However, even if all Service Levels are met the most important measurement for any Service organization is the perception of the Customers of the service provided. Therefore Customer satisfaction should be measured regularly.
6.7
Service Desk Structure - Best Practice
Structure of a Service Desk A Service desk can be structured in one of three ways: •
The Local Service Desk
•
Centralized Service Desk
•
Virtual Service Desk
The "hybrid" model is also a genuine Service Desk structure that uses a combination of two or more Service Desk structures.
Local Service Desk Very "visible" to the organization. The Service Desk is most probably in the same building or locality as the users of the IT Services. The advantage of this concept is the fact that Service Desk staff are very well versed with the local situation and local conditions. However, be aware of the fact that, if the organization is spread out over various locations with their own local service desks (ie multiple "local"), a high standard of process adherence should be apparent. All Service Desk staff should follow the same processes and procedures to prevent differences between the different Service Desk operations.
C3: Protected
Page 50 of 203
Controlled copy
C3: Protected
ITIL Foundation Level - Certification Guide
Page 51 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
Centralized Service Desk A centralized Service Desk is a physical point in one location. All users from the different sites contact this one Service Desk. This model leads to a reduction in operational costs, easier management of the IT Service and better use of Resources.
C3: Protected
Page 52 of 203
Controlled copy
6.7.1
ITIL Foundation Level - Certification Guide
Virtual Service Desk
Due to advanced network and telecom technologies it is now possible to have a Service Desk that has no physical location as far as the user is concerned. It might be staffed in different locations at different times during a day resulting in a 24 hour Service Desk. The issue to consider is the need for a physical engineer at the various locations to solve local incidents. Also time differences have to be taken in consideration when setting up Service Level Agreements.
C3: Protected
Page 53 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
Virtual Service Desk Hybrid models combine two or more of these particular structures into a customized solution for a particular organization. This is a genuine structure as the ITIL Framework provides guidelines only for structure and is not a prescriptive solution book.
Interesting websites: ?
http://openview.hp.com/products/servicedesk/
?
http://www.interpromusa.com/hdicerti.htm
?
http://www.interpromusa.com/The Integrated Service Desk.pdf
?
http://www.itilworld.com/n-america/service-support_helpdesk.htm
http://www.itil-service-support-management.com/Pages/Service support/Service Desk/Service_Desk_scope.htm ?
?
http://www.itil.co.uk/online_ordering/serv_supp_graphs/serv_desk.htm
6.8
Essential Terms
Escalation:
C3: Protected
Page 54 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
When the time limit for resolving an incident has passed, the incident escalates into a problem (depending on the priority and impact of the incident) and a different level of support (Problem Management) comes into force and this: •
Edits the problem if necessary
•
Determines the impact on the service delivery and with that, the priority. The Service Desk continually informs clients about the progress of their calls.
Routing: An incident is deposited at the second line support because no specialist knowledge for the solution is available at the Service Desk Incident: An incident is every operational event that is not part of the standard operation of an IT service. An incident influences the service delivery, although it can be small and in some cases even transparent (not noticeable) for the user. Problem: A problem is the as yet unknown cause of the occurrence of one or more incidents. Known error: This is the situation where a successful diagnosis of a problem has shown what the cause is and which CI is at fault. A possible solution may also be found as to how the problem can be avoided. Expert or Super user: Some organizations may use “expert” users to solve some first line support queries, depending on the structure of the organization. This can solve some short term people resource issues. Call Each time the user contacts the service desk.
C3: Protected
Page 55 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
7.0 Incident Management
7.1
Introduction
The Incident Management process contains activities that are aimed at restoring an IT service following a disruption. The Service Desk is usually the owner for this process however all support groups across an IT organization will play their part. Disruption of an IT service, questions about the functionality of an application or requests for advice are all regarded as Incidents that are dealt with by this process. Requests for Change are handled in a similar way as Incidents so they can also fall under Incident Management. A business may decide however to describe the handling of RFC’s in a special procedure in order to keep the Incidents and RFC’s separated. Note: An RFC is a Request for Change and will be dealt with in the Change Management process area. An RFC is the "trigger" that begins the Change Management process. 7.2
Objective
The objective of Incident Management is to restore normal operations as quickly as possible with the least possible impact on either the business or the user, and at a cost-effective price. The definition of how quickly is quickly should not subject to interpretation. The timeframes for Incident resolution should be defined in the Service Level Agreements (SLAs) that exist between the IT Department and the customer. The speed of resolution will affect the cost. It is this cost-to-speed ratio that is often forgotten when a user faces problems. Issues that are low priority during negotiations are "somehow" escalated to the status of requiring high levels of attention when the issue occurs. Often support staff will simply respond to user pressure in such situations and immediately the expectation is adjusted and anything less than immediate response to this otherwise low priority
C3: Protected
Page 56 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
issue is considered as poor service (the IT Support dilemma!) 7.3
Process Description
As with every process there is an Input and an Output. The main input to this process are incidents. As shown in below Incidents can come from many sources like users, management Information or infrastructure monitoring tools. The Input for Incident Management mostly comes from users, but can have other sources as well like management Information or Detection Systems. The outputs of the process are RFC’s, resolved and closed Incidents, management information and communication to the customer. This concept is illustrated in the following diagram. The centre diamond shows the activities of Incident Management.
7.4
Activities
The activities included in Incident Management are: •
Incident detection and recording
•
Classification and initial support
C3: Protected
Page 57 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
•
Investigation and diagnosis
•
Resolution and recovery
•
Incident closure Incident ownership, monitoring, tracking and communication 7.4.1
Incident detection and recording
Throughout an Incident lifecycle specialist IT groups will handle the incident at different stages. To do this efficiently and effectively a formal approach is required, which will facilitate the timely restoration of service following an incident. As shown incidents come from many sources. The Service Desk (more commonly known as a Help Desk) is the primary point for recording incidents, although other IT staff can play this role as well. The Service Desk is the single point of contact between service providers and users, or their representatives, on a day-to-day basis and typically the owner of the Incident Management process. Incident tracking is highly recommended. Information about incidents should be held in the same Service Management tool as problem, known error and change records. Records should be crosslinked to eliminate the need for re-keying data. This improves information interfaces and makes data interrogation and reporting far easier. Incident priorities and escalation procedures need to be agreed as part of the Service Level Management process and documented in SLAs.
7.4.2
Classification and initial support
Incidents should be classified according to three criteria (Priority, Impact & Urgency). Priority One of the important aspects of managing an Incident is to define its priority. How important is it and what is the impact on the business? The responsibility for this definition lies with the Service Level Management process. The priority with which Incidents need to be resolved, and therefore the amount of effort put into the resolution of and recovery from Incidents, will depend upon: o
The impact on the business
o
The urgency to the business
o
The size, scope and complexity of the Incident
o
The resources availability for coping in the meantime and for correcting the fault.
Impact 'Impact' is a measure of the business criticality of an Incident or Problem. Often this equates to the extent to which an Incident can lead to degradation of agreed service levels. Impact is often measured by the number of people or systems affected. Criteria for assigning impact should be set up in consultation with the business managers and formalized in SLAs. When determining impact, information in the Configuration Management Database (CMDB) should be assessed to detect how many users will suffer as a result of the technical failure of, for example, a hardware component. The Service Desk should have access to tools that enable it rapidly to:
C3: Protected
Page 58 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
o
Assess the impact on users of significant equipment failures
o
Identify users affected by equipment failure
o
Establish contact to make them aware of the issue
o
Give a prognosis
o
Alert second-line (specialist) support groups, if appropriate
Urgency 'Urgency' is about the necessary speed in solving an Incident of a certain impact. A high-impact Incident does not, by default, have to be solved immediately. For example a User having operational difficulties with his workstation (impact 'high') can have the fault registered with urgency 'low' if he is leaving the office for a fortnight's holiday directly after reporting the Incident. Urgency is seen as to what degree the service is affected (stopped, partially affected, functionally changed). If a user calls with an Incident and they can’t work (service stopped) then it is of greater urgency than a user calling to request a functionality change.
7.4.3
Investigation and diagnosis
Once logged the activity of investigation and diagnosis will take place. If the Service Desk can’t solve an Incident it will be assigned to other support levels. They will then investigate the Incident using the available skills sets and tools such as a knowledge base of Known errors etc, and diagnose the problem. It is important that all parties that work on the Incident keep record of their actions by updating the Incident record.
7.4.4
Resolution and recovery
Once a "work-around" or a solution to the incident is found it will be implemented. If a change is needed an RFC will be submitted to Change Management.
7.4.5
Incident closure
For the Incident Management process to be effective it is necessary that the Incidents closure be done properly. This step includes: o
Updating Incident details
o
Communication with the user about solution
To ensure the solution provided meets the user needs they are the only person that can give the authority to close an Incident. The Incident record in the Service Desk tool should be ‘closed’ so that accurate reporting can be carried out. An Incident will be closed as soon as the agreed service is restored. In some cases the Incident record is closed but a Problem record is still open (Refer to Problem Management for more information about a Problem record).
C3: Protected
Page 59 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
7.4.6 Incident ownership, monitoring, tracking and communication Whilst an Incident may be passed across different IT groups during investigation and diagnosis the Service Desk remain the owner of the Incident (in terms of tracking through to closure). They will monitor the progress of the Incident in light of service levels and maintain/manage communication with the user. If the Incident is not progressing appropriately then the Service Desk may trigger either a functional or hierarchical escalation. These different types of escalation are covered in the Best Practices section. 7.5
Roles
The role of Incident Manager in most organizations is assigned to the Service Desk Manager. The Incident Manager role includes responsibility for: •
Monitoring the effectiveness and efficiency of the process
•
Controlling the work of the support groups
•
Making recommendations for improvement
•
Developing and maintaining the Incident Management system
•
Reporting to management and other process areas
Support roles: First line support will be done by the Service Desk and includes the recording, classifying, matching, routing, resolving and closing incidents. Second and third level support is responsible for in investigation, diagnosis, and recovery from incidents. 7.6
Relationships
Incident Management has a close relationship with other ITIL processes. Some of these interprocess relationships are described here. 7.6.1
Configuration management:
Every Incident is connected to a Configuration Item (C.I.) stored in the CMDB. An incident will typically involve more than one C.I. The CMDB provides information about CI’s and the parent/child relationships between them. This helps to determine the cause, solution and routing of an incident by tracing a fault back through the C.I. relationships. For example, if a user cannot access the Internet, by looking back through the parent/child relationships of that users PC could find that a Hub that the user connects to (parent of the child PC) is a potential C.I. that should be investigated.
C3: Protected
Page 60 of 203
Controlled copy
7.6.2
ITIL Foundation Level - Certification Guide
Problem Management
Incidents with unknown causes are routed to Problem Management where they are processed. Known Errors, Work-arounds, Quick Fixes is given to Incident Management by Problem Management.
7.6.3
Change Management
This process can be the cause of Incidents if a Change is not implemented correctly. Therefore it is very important that Incident Management knows all planned changes so they can relate Incidents to a change and notify the Change Management process so that roll-back plans can be implemented if necessary. On the other hand some Incidents will be solved by a Change, as will be the case when faulty equipment is replaced.
7.6.4
Service Delivery Processes
Incident Management provides and gets information from all the Service Delivery processes. Service Level Management, for example, is responsible for establishing service levels that relate to work done within the Incident Management process. The Service Desk will then report against these service levels.
C3: Protected
Page 61 of 203
Controlled copy
7.7
ITIL Foundation Level - Certification Guide
Benefits
A well implemented Incident Management process will have easily visible benefits. Unlike some other ITIL processes where benefits may be hard for end users to identify, the benefits of good incident management will be felt by them directly. For customers •
Quick restoration of Service following an Incident
•
Incidents are not lost or forgotten
•
Up to date status of their Incident provided
For IT Organization •
Remove the problem of duplication of effort (once an Incident is solved the resolution will be easily found and can be applied to future incidents if the re-occur or the resolution can be a starting point for a different but related incident).
•
Clear view of the status and priorities of the Incidents
•
Possibility to measure performance against SLA’s.
•
Higher user and customer satisfaction
For the business •
Prioritization - the high impact, high urgency, incidents are the ones that jump to the front of the queue. Resulting in the least possible impact on the business activities.
•
Quicker resolution of Incidents leading (productivity gains).
•
Management information is provided.
Defining benefits is relatively easy. Realising benefits is difficult as during times of incident a lot of end users will not want to be convinced that their incident is not a high impact/high priority task and that there are other incidents demanding attention ahead of them. This is where the communication skill of IT Staff must be at it's highest (and most tactful). Carefully selecting the words used to convey this message can be learnt. For instance acknowledging the frustration they are facing and providing a very brief overview of the things ahead of them in the queue. This way the person can (hopefully) understand that there are more pressing issues ahead of theirs. Not dismissing their call as "unimportant" or "I'm busy with other people" or "You'll have to wait". 7.8
Common Problems
We know there are many benefits of a good incident management process. Likewise, there can be some real "show stoppers". The following major obstacles if not dealt with will mean the process will be inefficient and ultimately unsuccessful. Critical Success factors for successful Incident Management:
C3: Protected
Page 62 of 203
Controlled copy •
ITIL Foundation Level - Certification Guide
A CMDB needs to be set up before Incident Management is implemented. This makes the determination of impact and urgency a lot faster. The CMDB will ideally be an electronic system, but it can be a manual system.
Note: The CMDB is the Configuration Management Data Base. The CMDB is covered in the Configuration Management process chapter. The CMDB holds information about C.I.'s (Configuration Items). •
A knowledge database. This database will hold Known errors, work arounds and resolutions. This will help Incidents to be resolved much faster and with less effort.
•
An Incident Management tool to record and monitor Incidents easily. (Preferably this tool is part of a complete Service Management tool that integrates the tools from all processes).
The challenge in the implementation of these tools and databases is not to let the work of setting up the system stand in the way of making progress. Any ITIL process can be started in a very simple form. The biggest challenge facing IT professionals is that it takes "discipline" to use the tools and procedures. The sooner the discipline of logging information, searching for solutions rather than re-working solutions can begin, the better. If people start to use the tools and start to see benefits in doing so, then so the proper "habits" are formed. It is then a relatively easy task to modify behaviours to use a different tool or introduce new features/functionality as tool development or tool selection progresses.
Metrics
7.9
Many metrics can be obtained from this process, some of the more notable and useful are: • • • • •
Number of Incidents per time period Number of Incidents per category Number of Incidents per priority level Incident resolution performance against service levels Number of closed Incidents per time period
7.10
Best practice
7.10.1
Incident Management tools:
There are many Service Management tools on the market that now align and provide functionality to support ITIL processes. These tools have many features, which assist in automating the process such as: • • • • •
Quick Call Logging (one click to log a call) Auto population of data Automated alerts from infrastructure devices and applications that automatically generate an Incident record Advanced knowledge bases Customizable reporting 7.10.2
C3: Protected
Page 63 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
Different types of escalation In a functional escalation environment, the physical escalation of an incident usually takes place because of either a lack of expertise at a specific level or due to service levels being breached. Hierarchical escalation occurs usually more proactively (e.g. when the service desk identifies early that there is the likelihood of a breach and escalates manually rather than waiting for the time lapse). Incident life Cycle The following diagram shows the activities throughout the Incident Management process and the status that each activity can be set at. Throughout the activities the continual issue surrounding ownership, monitoring and tracking must also be considered.
7.10.3
Interesting Websites
•
http://www.helpdeskinst.com/publications/practices.asp
•
http://www.itil-service-support-management.com/Pages/Service support/Incident management/Incident_mgmt.htm
•
http://www1.worldcom.com/au/resources/whitepapers/pdf/WorldCom_White_Paper_On_eC RM.pdf
C3: Protected
Page 64 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
•
http://www.itil.co.uk/online_ordering/serv_supp_graphs/incident_mngt.htm
•
http://tools2manage-it.com/serv_mgt.php
7.11
Essential Terms
Incident "Any event that deviates from the (expected) standard operation of a system." An incident is often simply a user requesting help for something that is not working. For example “I can’t see my network drive”, “I can’t access the Internet”, “I can’t send email”. It is any situation where something does not work and the specific details are not known.
C3: Protected
Page 65 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
Work around It is possible for Problem Management to identify “work-around” in the investigation of problems. These should be made known to Incident Management so that they can be passed to the user until the permanent fix is implemented.
C3: Protected
Page 66 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
8.0 8.1
Problem Management
Introduction
Problems have a tendancy to always happen !!. No matter how well things are running. Even with the most reliable IT, the service delivery will be troubled by disruptions that cannot always be avoided. We have learnt that an incident is a deviation from standard operation. This means that users can face many incidents and a lot of the time they will face the same incident many times. A user calls with an "incident" - the Service Desk captures the call and gives great Incident Management support : "re-boot your PC and see if that fixes it". It does. The user is happy. The next day the same user calls with the same incident, with the same great incident support. "Reboot your PC". On the third day the user does not call again, they just re-boot their PC and start to live with the issue. Then they start to tell other users - just re-boot your PC that'll fix it. All of a sudden we have a plague of PC re-booting users !!! So how do we avoid the plague? By introducing Problem Management. The first incident that was fixed by re-booting the PC should have been passed to Problem Management. An example where Problem Management can make a difference: In an organization a user calls the Service Desk with the complaint that his document is not printing. The Service Desk investigates the incident and sees that the print queue has the status ‘On Hold’. The Service Desk releases the queue, the document is printed and the Incident closed. A few minutes later another users calls the Service Desk … Their document is not printing .. As this is a different person answering the phone he investigates the Incident and sees that the queue is on Hold, releases the queue and the incident is closed.. In the mean time users print their documents over and over again as they think they’ve done something wrong. The next day users still call with the same problem, the document still not printing … The Service Desk releases the queue when applicable, the document is printed and Incident is closed. If Problem Management were in place a problem would have been identified and recorded. The "Known Error" related to this problem would be found in the configuration of the Printer. The solution, to reconfigure the printer so the queue is automatically released, would be found and implemented. The stream of Incidents regarding this printer would cease. The releasing of the queue by the Service Desk would be used as a workaround to restore the IT service in the event of the printer facing a similar issue in the future.
C3: Protected
Page 67 of 203
Controlled copy
8.2
ITIL Foundation Level - Certification Guide
Objective
The objective of Problem Management is to minimize the total impact of problems on the organization. Problem Management plays an important role in the detection and repair of problems to prevent their reoccurrence. The following slide says this in a different way but also introduces the crucial element of proactive problem management.
8.3
Process Description
The Problem Management process is focused on finding weaknesses in the IT infrastructure and through the use of Change Management removing them so that future disruptions do not occur. The process focuses on finding patterns between incidents, problems and known errors. These three areas are key things to understand in this "root cause analysis". The basic principle is starting with many possibilities and narrowing down to a final root cause. Note: "Root Cause analysis" is often used interchangeably with Problem Management. The ITIL Framework doesn't prescribe what a process area should be called and Root Cause Analysis is fine. However, Root Cause Analysis is typically a reactionary exercise. ITIL's Problem Management caters for reactive work, but more importantly recognizes the value of proactive problem management. We use Root cause analysis interchangeably with Problem Management.
C3: Protected
Page 68 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
Incidents: An incident is defined as a deviation from the standard expected operation of a service. It is a general description of something that has gone wrong. It is not known what the exact cause is at this stage. For example users will call a Help Desk and say, “I can’t print”, “I can’t access the Internet”, “I can’t see my network drive”. They expected to be able to do these things yet could not, so these are "incidents". Problem: A problem is the “unknown underlying cause of one or more incidents”. This is the second stage of "root cause analysis"/problem management. From the general incidents, more investigation will uncover an underlying cause of these incidents. A “network problem” is a good example of a problem definition in this case. Users don't call saying I have a "network problem", they call and say "I can't save to my H: drive" or "I can't print or surf the web". IT staff then piece all these incidents together and identify that we are facing a "network problem". Root cause analysis has taken us closer to finding the root cause but not completely. A problem is then a more specific definition. Known Error: A Known Error is the final step in the root cause analysis process. A Known Error can be defined as, “when the root cause of the problem is known”. In our network problem example it is where the faulty equipment or system has been identified. This is the end of the root cause analysis process. Following the above example the Known error would be “Router x is faulty”. From the above we see the initial general issues being faced through to the final definition of the root cause. The following diagram illustrates this flow.
C3: Protected
Page 69 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
The process of Problem Management requires the following inputs: •
Incident records and details about Incidents
•
Known Errors
•
Information about C.I.’s from the CMDB
•
Information from other processes (eg. Service Level Management provides information about required timeframes, Change Management provides information about recent changes that may be part of identifying the known error).
The outputs of the process are: •
RFC’s (Request for Change) to start the change process to solve the Known Errors.
•
Management Information
•
Work arounds
•
Known Errors
•
Update Problem records and solved problems records if the known error is solved.
The following picture summarizes this. The center diamond highlights the Problem Management activities which we will look at in the next module.
C3: Protected
Page 70 of 203
Controlled copy
8.4
ITIL Foundation Level - Certification Guide
Activities
The ITIL Problem Management has four primary activities as follows: •
Problem Control
•
Error Control
•
Proactive Problem management
•
Completion of Major Problem Reviews
C3: Protected
Page 71 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
Problem Control The Main activities within Problem Control are: •
•
Identification and recording of Problems o
Some problems can be identified by processes outside Problem Management (eg. Capacity Management).
o
It is also wise to note that the time, effort and cost that goes into fixing problems must be weighed up against the benefits of doing so. If costs outweigh benefits a simple Problem record can be created that links all affected C.I.'s, RFC's and Incidents.
Classification of Problems o
•
This activity centres on understanding what the impact on agreed service levels is of the problem. Classification of problems is similar to Incident classification (impact, urgency, priority).
Investigation and diagnosis of Problems o
C3: Protected
This is the step where we get to understand what it is that is causing the problem. This step is vastly different from Incident Management investigation where the focus is "rapid restoration" of service.
Page 72 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
Error Control Error Control is the process in which the Known Errors are researched and corrected. The request for change comes from this sub-activity and is submitted to Change Management and then following approval the change is actioned.
C3: Protected
Page 73 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
Proactive Problem Management The best problems are the ones that never happen. ! Proactive Problem Management focuses the analysis of data gathered from other processes and the goal is to define “Problems”. These problems are then passed off to Problem and Error Control procedures, as if they had happened. The activity includes: •
Trend analysis •
•
Using data to highlight potentially weak components.
Targeting preventative action •
Trend analysis can lead to identifying general problem areas.
The aim of proactive Problem Management is to redirect efforts away from always being reactive, to proactively preventing incidents occurring in the first place.
C3: Protected
Page 74 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
Completion of Major Problem reviews At the end of a major problem cycle, there should be a review to learn:
8.5
1.
What things were done right?
2.
What things should we have done differently?
3.
What lessons do we take away from solving this problem?
Roles
Problem Manager Role The role of Problem Manager is responsible for: •
Developing and maintaining Problem Control and Error Control
•
Assessing the efficiency and effectiveness of Problem Control and Error Control
•
Providing management information
•
Managing Problem Management personnel
•
Obtaining the resources for the required activities
•
Developing and improving Problem Control and Error Control systems
•
Analyzing and evaluating the effectiveness of Proactive Problem Management
Problem Support role The Problem Support team is responsible for: •
Identification of Problems
•
Investigation of Problems leading to the Known Errors
•
Monitoring the Process of eliminating Known Errors
•
Raise RFC’s when necessary
•
Identify trends
•
Communicate Work arounds and quick fixes to Incident Management
Relationships The Problem Management process has a close connection with the following ITIL processes" Incident Management: A very close and obvious link as we have learnt. Problem management aims to solve the root cause for the Incidents that are recorded by Incident Management. It is important that Incident
C3: Protected
Page 75 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
Control provides accurate information so that Problem Control can solve the Known Errors easier. Problem management will supply Incident Management with workarounds and quick fixes where possible. Change Management: If Problem Management finds the solution to a Known Error they have to submit a RFC for the Change. Change Management is responsible for the implementation of the Change. When it is implemented they, together with Problem Management, review the Problem to verify that it is solved by the Change. This is called a Post Implementation Review after which Problem Management can close the problem record. Configuration Management: The information that is provided by Configuration Management is important in diagnosing problems. It includes information about C.I.’s and relationships with other C.I.’s. Other processes: Service Level management, Configuration Management and Availability management all provide Problem Management with information, which help to define and determine the impact of problems. In return Problem Management provide these and the other process with relevant information, for example, to SLM if a problem causes a IT Service to operate outside the Agreed Service levels or to Capacity Management if a certain hard disk is the cause of a Problem.
C3: Protected
Page 76 of 203
Controlled copy
8.6
ITIL Foundation Level - Certification Guide
Benefits
Problem Management improves the IT service quality by resolving the root cause of incident(s). This leads to lower amounts of Incidents - benefiting users, customers, the organization and the IT department: Advantages are: •
Better quality of IT Service Management
•
Reliable IT Service results in a better reputation of the IT service
•
Ability to learn from the past
•
IT staff will be more productive
•
Higher resolution rate for Incidents at the Service Desk first time around
•
Less Incidents
C3: Protected
Page 77 of 203
Controlled copy
8.7
ITIL Foundation Level - Certification Guide
Common Problems
Common problems for Problem Management include: 1. 2. 3. 4.
Incident Management and Problem Management don’t have well defined interfaces with each other. Known Errors are not communicated to Service Desk/Incident Management No Commitment from Management Unrealistic expectations of the Problem Management process.
The following slide raise these and other points of attention that have to be considered.
8.8
Metrics
Successful Problem Management can be measured by: •
Reduction in Incidents because the underlying causes are removed
•
The time that is needed to resolve Problems
C3: Protected
Page 78 of 203
Controlled copy •
ITIL Foundation Level - Certification Guide
The other costs that are incurred associated with the resolution
Within Problem management there is lot that can be measured. It depends on the scope of Problem management as to what is relevant. Some examples are: •
Time spent per organizational unit fixing problems
•
Number of RFC's raised
•
Ratio of proactive to reactive problem management
8.9
Best practices
Considerations for Problem Management, a high-pressure area for IT. The variety, complexity, volume and difficulty of problems facing Support teams today compared to the "early days" (those of a decade ago) seem child's play. Why? Increases in user demand have led to vast numbers of PCs; distributed Client/Server networks; multi-site, multi-platform systems; cheap but complex software packages; all in addition to the traditional mainframe systems, and all needing the same high levels of technical support, and all to be delivered with a sensitive 'customer care' attitude. This increasing workload is threatening the whole stability of IT. If we don't find a lateral solution for managing it, demand will simply continue to grow at its present rate. The result? Support functions will soon dwarf the rest of IT in terms of number of personnel, running costs, and quality of expertise. And ignoring the problem, in the vain hope that it will go away, is even worse. Demand must be managed down, resources re-allocated, recurring problems eliminated, and difficulties anticipated and addressed before they become problems. Aggressive, effective and
C3: Protected
Page 79 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
financially viable Problem Management is an integral step in achieving this. Otherwise IT will simply grind to a halt, grid locked and unable to function. Note: the following web links provide some additional research material. The Kepner-Tregoe link is an interesting one. KT Analysis is a long serving tool that can be very useful in carrying out the Problem Management process activities. Interesting Websites •
http://www.itilworld.com/n-america/service-support_probmanage.htm
•
http://www.kepner-tregoe.com
•
http://www.itil-service-support-management.com/Pages/Service support/Problem management/Problem_mgmt.htm
•
http://www.itil.co.uk/online_ordering/serv_supp_graphs/problem_mngt.htm
8.10
Essential Terms
Work Around: A "quick-fix" solution to an incident, which will produce an acceptable outcome for a limited period. Proactive Problem Management: Activities aimed at removal of errors while the errors are in a state of inactivity. Key success factors in Problem Management: •
Automated registration of incidents with correct classification.
•
Setting attainable objectives of the Process. Depending on the size of the operation, not even treating this as a full time role.
•
Good inter-process co-operation (especially Incident and Change).
C3: Protected
Page 80 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
9.0 Change Management 9.1
Introduction
As organizations become more dependent on IT services and technology changes rapidly succeed one another, the need for proper management and control of change grows with it. Many problems in the quality of IT Service Support emerge from changes in existing IT systems. The ITIL Change Management process is designed to act as a planning and control process. Proper planning and control ensures the implementation of change can take place without interrupting the operational IT service delivery. It is Monday July 1st. End of financial year. For many organizations it is the time of the year to close out and get final figures for the previous 12 months. Lots of reports being run, lots of heavier than normal requests on systems, lots of printing, etc. Imagine then a Service Desk where the phones start ringing at the start of the day. “My report is not showing any figures.” “I can’t find any details of last year.” “All figures for last year are lost.” Mild panic quickly escalates to all out concern as no-one really knows what has happened. They all individually try and solve the incident of each user by investigating the software etc. Nothing seems to be wrong, with the system functionality, it's just that the reports are all blank ! By now the IT Director is looking for some answers from his staff. He has to report to the business manager on what has happened and why should he keep his job ! Then one of the Service Desk staff strolls in. He's had a late start as he worked back last night. He notices the panic and asks what is wrong. When he hears the story he turns red and tells them about the change they made the night before. You can hear a pin drop ! He thinks he may have caused the problem. They look into it and it seems it is the problem so the staffer is asked to roll-back the change. Only trouble is no-one seems to have kept a copy of the configuration prior to the change. So, the only way to solve this issue is to correct the problem in the change. At the end of the day the problem is fixed and the figures for last year are back. Things start to go back to normal at the Service Desk … But the IT Director stills feels the wrath of the business people, along with the known business cost of the lost hours of productivity and still considers finding another role ! This is a situation that you want to avoid and with a good Change Management process it is possible! In our example, with ITIL Change Management in place: •
The Service Desk would have known about a change being done the night before so they could have made the connection between problem and change a lot earlier.
•
The change wouldn’t be scheduled prior to such an important day in this organization because of the risks involved.
•
The Change would have been tested properly so the whole issue might have been avoided.
C3: Protected
Page 81 of 203
Controlled copy • 9.2
ITIL Foundation Level - Certification Guide
A proper roll-back would be in place resulting in a quicker solution of the problem.
Objective
For an effective and efficient IT service delivery it is necessary to have the capability to implement many changes correctly. Changes in reality often lead to (implementation) problems. The created problems are subsequently resolved by the implementation of a change, which in turn leads to more problems. Breaking this negative spiral is an important task for Change Management. ITIL's goal statement for Change Management is... "Assuring that standardized methods and procedures are in use for the efficient and timely implementation of all changes, in order to minimize the impact of change related problems on the quality of the IT service delivery". The goal also build an internal understanding of the "how and why" for the process (how = standardized methods and procedures, why = to minimize impact). Remember.... "Not every Change is an improvement but every improvement requires a change"
9.3
Process Description
The common trigger for Change Management is a Request for Change (RFC). RFC's come from within the IT organization as well as from the Customers. Another trigger for change can be the Forward Schedule of Changes (FSC). This schedule is drawn up in advance in agreement with the customer. The FSC documents known change events or agreed windows of change, that can be used for unforeseen (non-urgent) changes. Other inputs for the process is CMDB information about the affected Configuration Items (C.I.’s) and the relationships that exist between the affected CI's. This vital information contributes to the assessment that the Change Management process has to make about the impact (potential or otherwise) or a proposed change. The output of the process includes reports regarding the changes, triggers for Configuration Management to change the CMDB, triggers for Release Management to release, develop or implement new software or hardware and Change Advisory Board (CAB) agenda and planned actions. Note: The CMDB (Configuration Management Data Base) is discussed in the Configuration Management chapter. Change records can be held in the CMDB, which allows them to be "linked" to affected CI's or Configuration Items.
C3: Protected
Page 82 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
The Scope of Change Management is determined along with defining the scope of Configuration Management. If the Configuration Management process is to track details of hard disks and floppy drives, then replacing a hard disk counts as a change (albeit a "minor change"). Determining the scope is a dynamic activity, as the scope can change and therefore the need for information needed from the CMDB can change as well. Reviewing the scope on a regular basis is important. It is not necessary that not all changes are controlled by the Change Management process. For example minor changes, such as resetting a password etc can be done by the Service Desk (following set procedures) but doesn’t need to be controlled by Change Management. To do so, would lead to increased workload, frustration and "by-passing" the process.
C3: Protected
Page 83 of 203
Controlled copy
9.4
ITIL Foundation Level - Certification Guide
Activities
The Change Management process includes the following activities: •
Recording
•
Accepting
•
Classifying
•
Planning
•
Co-ordination of activities
•
Implementing
•
Evaluating
9.4.1
Recording
Although this activity is not carried out by Change Management itself, it is the responsibility of Change Management to make sure all Changes are recorded correctly.
9.4.2
Accepting (Rejecting)
At this stage RFC’s will be reviewed and accepted or rejected. Any rejection should always be communicated and explained. A reason for the rejection of an RFC might be that it is incomplete or illogical. Accepted RFC's then be classified.
9.4.3
Classifying
In this stage the RFC will be categorized and a prioritized. The category depends on the impact the change has and the resources needed to do the change. The priority is derived form the urgency and the impact of the change, along with knowledge that the Change Management process may have from other process areas, that the change requestor is not aware of.
9.4.4
Planning
The change will be planned and put on the Forward Schedule of Change (FSC), if appropriate. The Change Advisory Board (CAB) meets to review the FSC. The FSC will consist of: ? ? ?
Planning in time, people, and budget Indication of consequences for other changes Advice on whether the change should be a go or no-go
9.4.5
Coordination
If approved the change must be built, tested and implemented. Change Management doesn't do
C3: Protected
Page 84 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
this work, but it co-ordinates the activities to ensure progress is made. Change Management will also verify that a back out plan has also been developed and submitted for approval.
9.4.6
Evaluating
Each change (except minor standard changes) should be evaluated to see if the changes had the desired effect. The effort put into a post change evaluation will be dependant on the size of the change and the impact it had on the organization (good or bad, what lessons can be learnt).
9.5
Roles
9.5.1
Change Manager
The Change Manger is responsible for:
C3: Protected
Page 85 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
•
Processing of the RFC’s, including filtering, accepting and classifying them.
•
Planning, coordinating (with all parties) and the implementation of the Changes.
•
Closure of RFC's
•
Authorization, after advice from the CAB or the CAB/EC
•
Where appropriate, to obtain authority for Changes to proceed (the level of authority required will depend on the impact that the change is expected to have, it's cost and it's urgency).
•
To issue the FSC's (Forward Schedule of Changes) via the Service Desk 9.5.2
Change Advisory Board (CAB)
This board should to be made up of representatives from all areas within IT and representatives from business units. The CAB can have an element of flexibility so if there are no changes on the Agenda that effect a specific business perhaps they don’t have to be present at the CAB Meeting. The CAB assess and plans the major changes.
Change Advisory Board/Emergency Committee (CAB/EC)
9.5.3
A sub-set of the CAB that can meet at short notice to consider Emergency changes. 9.6
Relationships
The Change Management process depends on the accuracy of the configuration data to ensure the full impact of making changes is known. There is a very close relationship between Configuration Management, Release Management and Change Management. The following diagram illustrates some of the major process relationships.
C3: Protected
Page 86 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
Advising the Service Desk of changes is crucial. Changes are nearly always first "discovered" in the Incident Management process, via the Service Desk. Also the Problem Management process can submit RFC’s to solve Known Errors and sometimes this can cause a snow-ball effect, if the Configuration Management process is unable to explain what the affected components will be as a result of the change (including hardware, software, SLA's). Note: SLA's (Service Level Agreements) are discussed in the Service Level Management process. It is possible to store information about an SLA in the Configuration Management Database (CMDB). By doing this relationships can be created between hardware or software components and the SLA. So when a change is proposed to a component the linked SLA can be investigated to determine if the change will breach the SLA. The others processes are also linked to Change Management in the sense that they either request changes (Availability Management) or they will be consulted to determine the impact of changes (IT Service Continuity Management, Service Level Management and Capacity Management).
C3: Protected
Page 87 of 203
Controlled copy
9.7
ITIL Foundation Level - Certification Guide
Benefits
Change Management is one of the ITIL processes that can often be not really liked. IT Staff have a tendancy to think that "it's only a small change, no-one will be affected". It is in these situations that most damage is often done. Discipline is required to adhere to the process. As an IT support person if you are told to implement the change without following the process, ask for the directive in writing, that way there can be no mis-understanding when problems come up. Remember that low impact, low risk changes can be covered by creating a change request that is open-ended and approved. For example, hard disk archiving. Provided the change is documented, the affected parties listed and the RFC is closed, reviewed and re-opened on a periodic basis then there is no need to create a seperate RFC every time the change is required. The concrete advantages of Change Management are: •
Less impact of changes on the quality of the IT service delivery and the Service Level Agreements (SLA's).
•
Through structured planning, the cost of a change can be estimated more accurately
•
Fewer changes need to be reversed, but if the need arises it is a simpler process
•
Collection of management information is possible on changes.
•
Increase in productivity of the user because of a reduction of service interruptions.
•
Increase in productivity of IT staff (less time lost of fixing changes).
9.8
Common Problems
Along with the benefits of the any process, we have to acknowledge the inherent problems as well. Change Management is a highly visible process, both within the IT Department and the business users and business customers. Note: The distinction between Customer and User is straightforward. The customer is the one paying for the service. The User is the ultimate end-user of the service. Tool Selection You need an appropriate tool to support the Change Management process. Ideally, a single tool will be able to accommodate the activities of a number of ITIL processes. With Change Management, it would be almost essential that the same tool be used as the Configuration Management Data Base. Defining the Scope If the changes that are controlled by Change Management are too wide (eg it includes password rests) the workload will become to high and people will try to bypass the process. Commitment IT staff might be reluctant to follow procedures because Change Management will be involved in so
C3: Protected
Page 88 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
many aspects. It is important to make the IT Staff aware of the positive effect the Change Management process will have on the IT Service as a whole. It is also necessary to ensure that the team designing the process do not over engineer a solution. Start simple and build up complexity if it's (a) necessary and (b) value-adding.
Metrics
9.9
The beauty of all ITIL processes is that they can be measured. Measurement allows baseline setting and targets to be set for improvement. Change Management is no different in this regard and the following indicators are common for measuring this process. •
Number of Incidents recorded as a result of a change
•
Time taken to implement a change successfully
•
Number of Changes that required a roll-back
•
Number of Urgent/Emergency changes
•
Number of RFC's submitted for consideration
•
RFC rejection count
•
Change back-log
•
Changes by business unit/areas/department
9.10
Best practices
The following list of sites provide some excellent background reading on Change Management.
9.10.1
Interesting websites
•
http://www.itil-service-supportmanagement.com/Pages/Service%20support/Change%20management/Change_mgmt.htm
•
http://www.itilworld.com/n-america/service-support_changeman.htm
•
http://www.infra.com.au/TuDelft.htm
•
http://www.itil.co.uk/online_ordering/serv_supp_graphs/sschange.htm
•
http://www.microsoft.com/technet/treeview/default.asp?url=/technet/itsolutions/ecommerce/ maintain/operate/rmdotcom.asp
•
http://www.atlsysguild.com/
•
http://www.guild.demon.co.uk/SpecTemplate8.pdf
C3: Protected
Page 89 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
•
http://www.guild.demon.co.uk/SpecTemplate8.rtf..zip
•
http://www.atlsysguild.com/GuildSite/Robs/Template.html
9.11
Essential Terms
Change Change to a system or service. CAB Representative group of stakeholders, who assess the change requests. The Change Advisory Board advises the change manager on whether the change should be accepted or rejected. Request for Change (RFC) All requests for modification of the managed infrastructure that are not Service Requests. Service Request Fully defined and approved changes, which are individually recorded, but not individually assessed by Change Management. These changes are made routinely. Forward Schedule of Change (FSC) A change schedule, which contains all the planned changes for a certain period of time.
C3: Protected
Page 90 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
10.0 Configuration Management 10.1
Introduction
Through the storage and management of data regarding the IT infrastructure the Configuration Management process gives the IT organization greater control over all the IT assets. The more dependent on their IT systems organizations become, the more important Configuration Management becomes. It is, therefore, necessary to keep a register of all Configuration Items (C.I.'s) (IT Assets) within the IT infrastructure. Configuration Management aims to provide a "logical model" of the IT infrastructure by identifying, controlling, maintaining and verifying the versions of all C.I.'s.
10.2
Objective
The main objectives of the Configuration Management process are to: •
Provide IT Management with greater control over the C.I.s (IT Assets) of the organization.
•
Provide accurate information to other ITIL processes.
C3: Protected
Page 91 of 203
Controlled copy •
ITIL Foundation Level - Certification Guide
Create and maintain a reliable Configuration Management Database (CMDB).
Note: The keyword in the following slide that defines the difference between asset management and configuration management is "relationships". Traditional asset management provides a list of items (typically hardware and software). Configuration Management defines relationships between all C.I.'s. Note: In the earlier Change Management process chapter we discussed the importance of getting accurate information from the Configuration Management process.
10.3
Process Description
The Configuration Management Process could almost be considered as a pivotal process for all other (especially the Service Support) processes. Configuration Management is considered central and supportive to the other ITIL processes by providing information about the IT Infrastructure. Reminder Note: •
Service Support processes =
Incident, Problem, Change, Configuration, Release
•
Service Delivery processes =
Service Level Management, Availability, Capacity, Financial, Continuity
o
Service Desk is a function and Security Management has an active part in all processes.
A major input into the Process is from Change Management either requesting information about items that will be affected or advising the status of changed items.
C3: Protected
Page 92 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
The process starts with the design, populating and implementing of the CMDB (Configuration Management Data Base) It is the responsibility of Configuration Management to maintain the CMDB. Populating the CMDB can be a costly and lengthy exercise depending on the scope of IT infrastructure that is to be managed and the depth of detail about each item required (automated tools can play a large part here). The Outputs of the Process are reports to IT management and also the constant availability of Information that can be supplied from the CMDB to other processes.
10.4
Activities
The activities of the Configuration Management process are: •
Planning
•
Identification
•
Control
•
Status accounting
•
Verification and Audit
C3: Protected
Page 93 of 203
Controlled copy
10.4.1
ITIL Foundation Level - Certification Guide
Planning:
This includes setting up the process "boundaries" like the goal, scope, objectives, policies, procedures and interaction expected with other processes. It is the task of the Configuration Manager to determine what can be achieved, at what cost balanced against the business requirements. This combination affects the level of detail and how many C.I.'s will be specified. Scope: The scope of the process must be decided. This essentially answers the question: What will and will not be included within the process? For example some IT organizations will manage the PABX and phone systems, in this case these infrastructure items would be within the scope of the process. CI Level: The CI Level refers to the amount of detail that will be captured for each CI. For example is a PC considered enough detail or is it necessary to capture the hard disk, network card and memory details. The decision about the level of detail required should depend upon how the information will be used. A lot of detail requires extra work to keep updated, while too little detail defeats the purpose of the process and does not contribute towards good decision making.
C3: Protected
Page 94 of 203
Controlled copy
10.4.2
ITIL Foundation Level - Certification Guide
Identification:
The identification activity involves the gathering of all C.I. information within the scope of the process. C.I. information is gathered either manually and/or by the use of automated tools. At the time of gathering this data each CI should be labeled for reference and control purposes. Note: The labeling of IT Infrastructure can be incorporated into the Security Management process. Labeling techniques include visible labels, that include common contact numbers (eg. Service Desk), reference numbers and even hidden labeling (security paint that shows up under "black lights" and microchip identifiers that are not visible to the human eye). The information gathered will be governed by the scope, C.I. level and attributes decided upon. Note: The attributes of a C.I. are the "things" about that C.I. that we want to record (eg. the attributes of a Personal Computer can be hard disk size, processor type, processor speed, Operating system version). Values are the quantifiable measurement of attributes (eg. the value of a hard disk size can be 3Gig or 8Gig, the value of a processor speed can be 1 GigaHertz or 10 GigaHertz) Before gathering any information control procedures and the Change Management process should be in place so that after information is gathered and populated into the CMDB changes to the infrastructure don’t make it redundant. Note: The gathering of data can take several weeks or months. Control Before the CMDB is populated control procedures should be in place. It is vital that changes to the CMDB and the CI’s within are only made with the proper authorization. Procedures need to be set up so that all changes are always documented, for example with authorized RFC’s. We can start to see the very strong relationship that Change and Configuration Management share.
10.4.3
Status accounting
Status accounting is the activity that records the current and historical states of a C.I. so every change to a C.I. is traceable. Status levels can be defined as part of the planning process (eg. On order, In use, Out of order, Under repair, Retired).
C3: Protected
Page 95 of 203
Controlled copy
10.4.4
ITIL Foundation Level - Certification Guide
Verification and audit
By conducting regular audits an organization can verify that all C.I.’s are recorded correctly. The first audit should be held right after the CMDB has been implemented to be make sure it is a correct representation of the actually IT infrastructure. Other times for audits can be after disasters, major changes and following a pre-defined timetable. The degree of audit will again need to take into consideration the value that will be derived from the audit and the size (and therefore cost) of doing the audit. Partial audits, spot audit checks are all feasible strategies to "get a feeling" about the level of C.I. accuracy. 10.5
Roles
The Configuration Manager will assist in determining the scope and level of detail required in the process, implement procedures for interaction with other processes and take responsibility for the planning and population of the CMDB. The Configuration Librarian is the person who controls access to master copies of software and documentation. Like any librarian the focus is on physical items. These items will be held in the "definitive software library" (DSL). Note: In small organizations the role of the Configuration Manager and the Change manager can be combined.
C3: Protected
Page 96 of 203
Controlled copy
10.6
ITIL Foundation Level - Certification Guide
Relationships
As indicated, the IT infrastructure forms the foundation of the IT organization. All processes within ITIL therefore have links with Configuration Management or retrieve information from the Configuration Management Database. Change Management and Release Management however, have the closest relationship to Configuration Management and could even be considered as an integral part of it. The flow chart shows the relationships between the 3 processes and how the flows between the processes occur at every stage.
10.7
Benefits
Some of the benefits that come from implementing Configuration Management include: •
ability to provide Information to the other processes about C.I.’s and the relationships that exist between them.
•
contribution to IT Service Continuity planning
•
control of the IT Infrastructure. Knowing where a C.I. is and who’s responsible for it.
•
efficient and effective Problem management
•
efficient and effective processing of Changes
C3: Protected
Page 97 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
•
as an insurance that legal obligations are being met
•
optimal support on security issues
The following slide restates some of these benefits and introduces some new ones.
10.8
Common Problems
Problems that can prevent an effective implementation of Configuration Management are: •
Level of detail for the CI’s is not right. If the level is too deep too much information is recorded which will take to much time, money and effort to maintain. However, if the level of detail is not detailed enough parts of a C.I. can be changed without anyone knowing. This can result in increased incidents and problems due to the difficulty in tracing the faulty component.
•
Urgent Changes. Emergency changes often happen outside normal hours of operation. There may be no authorized person to record the changes in the CMDB. This can be combated through a solid procedure of post-change updating. Otherwise the overall reliability of the CMDB is compromised.
•
Commitment: There needs to be a firm commitment from Management to implement this process, as it can be a high activity process. Discipline is required from IT Staff to ensure that changes to the infrastructure follow the appropriate steps to keep the CMDB accurate.
C3: Protected
Page 98 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
•
Interaction with other processes. As Configuration Management relies on Change and Release Management to a large degree it is wise to implement these processes at the same time. Failing to do so might result in a non-reliable CMDB and an ineffective process.
•
Control. There needs to be a process in place that secures the validity of the CMDB. For example users who can purchase software themselves via the Internet may create incidents that are difficult to solve due to unknown configuration changes (the typical "I didn't change anything !!")
10.9
Metrics
10.9.1
Key performance indicators
The measurement of the Configuration Management process has many potential KPI's that can be analysed. To measure the effectiveness of Configuration management, realistic targets should be set. The targets can be changed over time to ensure improvement of the process. •
Result of audits. Number of unauthorized C.I.’s, C.I.’s not in use
•
Number of changes that due to wrong Configuration information cause incidents or problems
•
RFC’s that were not completed successfully because of poor impact assessment, incorrect data in the CMDB, or poor version control
C3: Protected
Page 99 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
•
The time a change takes from start to finish
•
Software licenses that have been wasted or not put into use
Other Indicators could include: •
The amount of calls per month that are solved whilst the User is on the phone using information from the CMDB.
•
Reduction in Incidents and problems over time and the change in impact they have on the business
•
Improvement in the time needed to resolve Incident and Problems that can’t be fixed immediately
•
The number of changes to the CMDB per month because of identified errors in the CMDB.
•
Time needed to record a C.I.
10.10
Best practices
10.10.1 The CMDB Most organizations already use some sort of CMDB, in a spreadsheet or paper based. In most cases the CMDB is based on database technologies, which makes gathering information more user friendly. Information that can be gathered from a CMDB include: •
Information about C.I.'s
•
List of C.I.s affected by a scheduled a Change
•
All Requests for Change relating to one C.I.
•
The history of a particular C.I.
•
List of change and problem records associated with a C.I.
•
List of C.I.'s affected by a Problem.
C3: Protected
Page 100 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
A CMDB also contains information on relationships between Incidents, Problems, Known Errors, Changes, Releases and C.I.'s. The CMDB can aid as a support tool in the creation and on-going maintenance of legal contracts. Note: Examples of "relationships" that can be defined are: •
•
Relies on.... o
SLA "Provision of Banking Services" relies on Server 2
o
SLA "Provision of Banking Services" relies on Printer 9
Is part of.... o
•
•
Affects.... o
SLA "Provision of Banking Services" affects Customer 11
o
SLA "Provision of Banking Services" affects Customer 12
Is linked to... o
•
Hard disk 12 is part of Server 2
Banking system is linked to Admin system
Had ...... o
Printer 9 had RFC 0013 applied
o
Printer 9 had RFC 0035 applied
An additional bonus is the use of the CMDB to cover the legal aspects associated with the maintenance of licenses and contracts. The Definitive Software Library (DSL) is a storage place where all software versions are kept secure. New releases will be built on copies of the software from the DSL, not from the software that is being used in the production environment. The DSL is plays an important part in the Release management process and is discussed in more detail in that chapter.
10.10.2 Interesting Websites •
http://www.itilworld.com/n-america/service-support_configman.htm
•
http://www.itil-service-support-management.com/Pages/Service support/Configuration management/Configuration_mgmt.htm
•
http://www.itil.co.uk/online_ordering/serv_supp_graphs/ssconfiguration.htm
10.11
Essential Terms
IT infrastructure: All parts of importance to the provision of IT services. These include: hardware, software, network and components, documentation, manuals, procedures, air-conditioning, cooling, organization etc
C3: Protected
Page 101 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
etc. Staff, however, is not a C.I. (according to ITIL, many organizations choose to include staff into their CMDB as soon as the organization is mature enough to handle this). Configuration item (CI): The IT infrastructure is built from components. Every component of the infrastructure, under the management of the IT organization, is called configuration item (C.I.). A C.I. may have any form of complexity or size and may vary from a complete mainframe to, for instance, a PC as well as a monitor, keyboard or a floppy disk drive.
C3: Protected
Page 102 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
Attribute: An attribute is a characteristic that is recorded about a C.I. Examples of this are: identification number, colour, type, size, manager, user, price, depreciation, supplier, serial number, version, status, etc. Values: A value is the quantifiable part of an attribute. (examples of values are "red", "10", "E9", "critical") Links/Relations: All relationships are normally recorded in a hierarchical structure (such as a parent-child relation). Other relationships are "is linked to" or "is used by". These relationships should be made between C.I.s in the CMDB. Configuration Control: Ensures C.I.’s are only changed with the appropriate documentation and that C.I.’s are tracked from procurement to disposal. Asset Management: The difference between Asset Management and Configuration Management is that Asset Management has a list of assets and Configuration Management has a database with relationships between C.I.s. Configuration baseline A Configuration baseline is the configuration of a product or system established at a specific point in time, which captures both the structure and details of a configuration. It serves as reference for further activities.
C3: Protected
Page 103 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
11.0 Release Management 11.1 Introduction With the increasing complexity of systems and a greater need for IT organizations to provide a stable environment, the release of new software and hardware into the business must be closely controlled. Quite often however a poor release strategy leads to the very thing that others in the IT organization are working hard to avoid; downtime and loss of infrastructure stability. The "Catch 22" however is that there in an ever increasing pressure to “have the release sooner”, as it will deliver immediate “benefits” to the organization. External forces often drive the demand to get the latest hardware of software into production as businesses strive to be first to market or to help them gain a competitive edge. This process within ITIL aims to provide a structured approach to the management of releases into the infrastructure from release planning through to actual installation. The relationships with Change Management and Configuration Management are key for this process as all three are very closely related. Release Management provides the physical management of software and hardware. Information about the software and hardware components of the IT and their relationships with one another are stored in the Configuration Management Database (CMDB). Release Management manages the planned and applied changes to software and hardware in the IT infrastructure. To support Change Management and Configuration Management, Release Management utilizes the Definitive Software Library (DSL) and the Definitive Hardware Storage (DHS). These secured libraries provide the physical storage location of all software Configuration Items (CI's) (DSL) and spare parts for hardware (DHS). Software comes in various forms such as source codes, loads, libraries and executables. The different versions of the same software held in the DSL have been through authorization and quality controls and are used for the construction and implementation of releases. Spare hardware held will be dependant on a risk assessment (looking at the assets of the organization and then the threats and vulnerabilities), as well as third party involvement regarding support contracts (Underpinning Contracts). Changes to the production hardware environment must flow through to the DHS, so that any held spares can be compatible with latest production hardware.
11.2 Objective Release Management is the process that "protects" the live or production environment. Protection comes in the form of formal procedures and extensive testing regarding proposed changes to software or hardware within the production environment. Note: The use of the term "Production Environment" conjures up images of a factory or manufacturing facility. However, it is a generic term applied to all areas of infrastructure in use that contribute towards the realization of organizational objectives.
C3: Protected
Page 104 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
Note: It is the use of this term Production Environment that probably provides an answer to a question that gets raised a lot regarding the ITIL framework. Can the (ITIL) framework be used in other business areas, other than IT ? The answer is most definitely yes. The framework is not a prescriptive set of processes that lack flexibility. They are a set of generic guidelines that, with the right perspective, can be applied just as easily to manufacturing & engineering disciplines. Objectives of Release Management process include: •
To manage, distribute and implement approved hardware and software items.
•
Provision for physical and secure storage of approved hardware and software items in the Definitive Hardware Store (DHS) and Definitive Software Library (DSL)
•
Ensuring that only authorized and quality controlled software & hardware versions are used in the test and production environments.
Note: Even the test environment can be subject to the Release Management process. Many businesses have a very high reliance on their test centres and cannot afford uncontrolled actions, simply because the environment is not the front line of the business.
11.3
Process Description
The main components controlled under a good Release Management process include:
C3: Protected
Page 105 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
•
In-house developed applications,
•
Purchased software and custom built software,
•
Utility applications,
•
Software provided by suppliers for use on specialist systems,
•
Hardware and hardware rollouts
•
Instructions and user manuals
Release Management manages all software and hardware from purchase or development until testing and the eventual migration into production. The process starts with the planning of a new release, be it for hardware or software and ends with a well documented, securely stored, implemented new release with the lowest possible impact on the organizations day-to-day activities. The following diagram illustrates some of the basic before and after situations surrounding the Release Management process.
11.4 Activities The following diagram shows the activities of Release Management and their relationships with the Configuration Management Database (CMDB):
C3: Protected
Page 106 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
In a list format the activities described in the picture include: •
Planning and describing the Release Policy of a Release
•
The design, building and configuration of Releases
•
Testing and signing off of new releases
•
Planning the rollout of releases
•
Communication, preparation and training
•
Release , distribution and the installation
Planning and describing the Release Policy The Release Policy will document how the organization will approach the release of new hardware and software in to the infrastructure. Specified in this policy will be items such as: •
The frequency of releases that is acceptable to the business
•
A policy on how to issue emergency releases
•
A policy on testing and subsequent release into production
C3: Protected
Page 107 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
•
The scope of the Release Management process ie. What level of control and what parts of the infrastructure will be under the control of the process
•
Naming conventions for releases?
Preparation for any release requires a structured planning approach to increase the chance of success. The use of a formal project management methodology like PRINCE2 will assist in this to define items such as: •
Contents of the Release
•
A release schedule
•
Resource requirements
•
Roles and responsibilities
•
Project Approach
•
Definition of the release components
•
Back up plan
•
Quality plan
•
Acceptance plan
Note: PRINCE2 is an acronym for Projects IN Controlled Environments. Like ITIL PRINCE2 is a methodology or framework, not a tool for Project Management. PRINCE2 is published by the same body that publishes ITIL (the Office of Government Commerce (OGC) in the UK). And like ITIL it is a widely accepted framework for best practice. You can find extra information on PRINCE2 at: http://www.ogc.gov.uk/prince/ The Design, Building and Configuration of Releases This activity within Release Management can be considered as the technical stage of the process. All the actions associated with designing, configuration and building are completed by relevant staff, in a "controlled" manner. Note: The term "controlled" is not intended to create an image of bureaucracy. Controlled environments are reproducible and that is the critical issue here. At the end of this stage a Back-Out Plan should also have been created. Back-Out plans can be aimed at restoring all services to their state before any change OR to restore as close to the prechange state as is feasible given the nature of the change. The suitability and content of the Back-Out plan will be assessed during the Change Management process. The output of this activity should be a release complete with instructions on its installation, a test plan and a backout plan. Testing and Signing-Off of New Releases
C3: Protected
Page 108 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
Lack of adequate testing is the most common cause of failure of all (changes) releases. Testing should not only be done on the release expected end result but also on the implementation activities and the back out procedure. Representatives of the Business should test for expected functionality. This is referred to as "User Acceptance Testing" (UAT). IT staff perform technical tests including the test of the installation (ideally the test staff will not be the build staff). Each of these stages should be signed off separately. Release acceptance should be performed in a controlled test environment that can be reset to known configurations of both software and hardware. These configurations should be described in the Release definitions and stored in the CMDB, along with any other related CI’s. Planning the Rollout of Releases The overall release plan that was originally created must now be enhanced with detailed information on the rollout of the release. This will include: •
Task list and resources needed for the task
•
A list of all the CI’s to be installed and decommissioned
•
In case of multiple sites: action plans for the separate sites taking local differences into consideration.
•
Communications to all involved (users, IT staff)
•
Plans for the release rollout purchases (if any)
•
Acquiring hardware and software. The rollout plan should include the procedures to be followed for their secure storage prior to rollout and the mechanisms to trace their deployment during the implementation.
•
Scheduling meetings for managing staff and groups involved in the Release.
Communication, Preparation and Training It is important to communicate with all parties involved in order to increase the acceptance and success of the release. This might involve several meetings/training sessions with user groups, IT staff and Managers. The timing of any training and/or communication must be planned in accordance with the expected actual release date. The Service Desk is a key area that must be informed about the release, any known issues (or workarounds) that have been established during testing and generally how the new release should be supported. The release plan should be made public in case of a large release so users know what to expect and when. Release, Distribution and the Installation Release Management will be responsible for the process of purchase, storage, transport, delivery,
C3: Protected
Page 109 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
and hand-over of hardware and/or software. Distribution and installation are seen as different activities. Often a release will be distributed and (in the case of software) not "go live" until a log-on script is changed and the release activated. Following the distribution of the release installation will take place making it available to the user community. Release Management must work closely with the other processes (mainly Change Management and Configuration Management) to maximize the success of the release. The CMDB should be updated with the new Release details and all old C.I.s should be decommissioned and appropriately marked in the CMDB (retired, decommissioned, etc.) 11.5
Roles
The main role within the Release Management process is that of the Release Manager. This person is responsible for defining and maintaining the definition of the release policy and controlling the activities within the process. The Release Manager will have a good technical background and a good knowledge regarding latest utilities and support tools. The combination of roles is permissible for certain ITIL processes. In smaller IT organizations the combination of the Release Manager, Change Management and Configuration Management processes is realistic. Release Management staff will need to receive technical training for development, software maintenance and hardware build skills. Project Management is another essential characteristic that is evident in a Release Management environment. 11.6
Relationships
Release Management is very closely linked with Change Management and Configuration Management. Change Management controls all the changes and determines when a new release will be implemented and what changes will be in any release. In most major organizations a representative for the Release Management process will have a representative in the Change Advisory Board (CAB). Note: The CAB is the authorizing body for changes to proceed. Can you remember the term given to the group of people who approve Emergency Changes? Configuration Management needs to be informed by Release Management about every change to a Configuration Item (C.I.) so they can update the CMDB. They also need to make sure that new versions of software and hardware are being stored in the DSL or DHS. Release Management will use Configuration Management to get information about C.I.'s that may be affected by a new release and importantly their relationship with other C.I.s.
C3: Protected
Page 110 of 203
Controlled copy
C3: Protected
ITIL Foundation Level - Certification Guide
Page 111 of 203
Controlled copy
11.7
ITIL Foundation Level - Certification Guide
Benefits
Implementation of the ITIL Release Management process provides the following advantages: •
Software is being released for testing and production in a controlled manner, reducing the chance of errors.
•
The software (source, loads and executables) of the organization is held in a secure location (the Definitive Software Library (DSL)).
•
Ability to implement many concurrent changes in the software being used in the production environment without adversely affecting the quality of the IT environment.
•
Software in remote locations can be managed effectively and economically from a central point.
•
The possibility of the use of illegal copies is dramatically reduced.
•
The impact of new hardware is tested prior to installation in the infrastructure.
•
With end users more informed of new releases and involved in testing the new releases the risk of resistance will be reduced significantly.
C3: Protected
Page 112 of 203
Controlled copy
11.8
ITIL Foundation Level - Certification Guide
Common Problems
In order for Release Management to be successful the following issues need to be taken in consideration as they may cause problems: •
Lack of Commitment: End Users might be reluctant at first to be told by this process how to act in case of a new release. The advantage of this process needs to be communicated before the process is implemented.
•
Urgent fixes. Procedures need to be in place to make sure that they are dealt with correctly and don’t compromise the accuracy of the CMDB, DSL or DHS.
•
Testing. A proper tests environment needs to be available in order to assess the impact and reduce the risk of a new release.
•
Bypassing of the process my cause illegal software or viruses to enter the IT Infrastructure. Regular audits can help to minimize this potential issue.
11.9
Metrics
In order to assess the effectiveness of the Release Management process a number of key performance indicators (KPI’s) should be monitored. Examples of possible indicators are:
C3: Protected
Page 113 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
•
Releases built and implemented on schedule, and within budgeted resources
•
Number of Releases that result in a back out due to unacceptable errors
•
Number of Incidents caused by the release
•
Outcome of audits of the DSL and the DHS. Security - all software can be accounted for etc.
•
Proper use of the DSL for software development
•
Compliance with all legal restrictions relating to purchased software
•
Accurate and timely recording of all build, distribution and implementation activities within the CMDB
11.10
Best practices
Different Types of Releases ITIL defines three different release types as described. Delta release Includes only those CI’s within the release unit that have actually changed or are new since the last full or package release. For example: In a word processing package the help file has a bug and requires an update. Only the help file module is updated whilst the rest of the program remains the same. The same analogy could be used with the word processing package as a part of the whole office automation suite.
Full release In a full release all components of the release are updated. For example: An update is made to the whole office automation suite including the word processing package, spreadsheet database etc. Package release The Package release includes all previous delta and full releases. These releases are generally implemented less frequently and therefore allow for longer periods of stability for the live environment. An example of a Package Release might be an SOE (Standard Operating Environment) for a desktop PC that includes the hardware, office automation and business applications. Types of relevant environments •
Development. Only here can new software be developed. Newer versions will be based on a copy of the software in the DSL. Each new version will cause an increased version number.
•
Testing. Should be a replication of the live environment in order to reduce risks of the implementation. Developers do not work in this area.
C3: Protected
Page 114 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
•
Production. Where the software/hardware is in production. Developers do not work in this area.
•
Archiving. Old release versions that are no longer in use
11.10.1 Interesting web sites •
http://www.itil-service-support-management.com/Pages/Service support/Release management/Release_mgmt.htm
•
http://www.itil.co.uk/online_ordering/serv_supp_graphs/release_mngt.htm
•
http://www.microsoft.com/technet/treeview/default.asp?url=/technet/itsolutions/ecommerce/ maintain/operate/rmdotcom.asp
11.11
Essential Terms
Definitive Software Library: A library, which stores in their definitive, accepted form, all the versions of software configuration items that have been accepted from the developer or supplier. This logical library can be physically present in several locations. Definitive Hardware Store:
C3: Protected
Page 115 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
A physical secure storage of definitive hardware spares. These are spare components and assemblies that are maintained at the same level as the comparative systems within the live environment.
C3: Protected
Page 116 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
Release: A software CI introduced into the test environment and subsequently into the production environment. In most cases documentation and accompanying hardware also are part of the release. Release Unit: A Release Unit includes the CI’s that can be released together. Type of Releases: Full Release: all components of a release unit are built, tested, distributed and implemented together. Delta Release: or partial release, only those CI's in the Release Unit that have actually changed since the last delta or full release. Package Release: combination of full releases and delta releases (helps to reduce the risk of incompatible releases, by changing many systems concurrently).
C3: Protected
Page 117 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
12.0 Service Level Management 12.1 Introduction
Imagine the following situation: The Managing Director (MD) announces to the Chief Information Officer (CIO) that the company is thinking about outsourcing the IT Organization. Over the last two years there have been numerous and major complaints about the current IT services by the business. The customers say it doesn’t do what it should, it is not working properly etc. The CIO is puzzled to say the least. He had no idea that they were doing so badly. They actually thought they were doing well. The services were up and running for most of the time. They resolve incidents quickly and didn’t get many complaints from the users that they were aware of. His staff have been putting in an enormous amount of effort to upgrade the server that the payroll system has been running on. How could we have done any better? See the problem?
C3: Protected
Page 118 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
1.
The IT Organization thinks it is delivering services of a high standard but they have no figures to back that up. The loosely defined "up and running most of the time" didn't take into account the outages during critical times.
2.
The effort on upgrading the server is commendable, but of no benefit as the business recently decided to outsource the company payroll activities.
3.
There probably is no official procedure in place to ask for the Customers opinion or a how to make a complaint so how could they have know about the perception of the customer regarding there services?
Implementing the Service Level Management process will solve the main problems in this situation. The most widely known element of Service Level Management are Service Level Agreements (SLA's). SLA's allow the IT organization and the customer to come to agreement about which services are been provided, the availability required of them and their costs. These levels would be measurable so both sides can verify if the levels are being met. Service Level Management is the process that forms the link between the IT organization and the customers. Implementing Service Level Management can only be completely successful when the other ITIL processes are implemented as well. The main aim of SLM is to ensure the quality of the IT services provided, at a cost acceptable to the business. Note: There are some who feel that Service Level Management is the single most important process within ITIL. This is a difficult argument to defend. By its very nature of processes within ITIL are of equal standing. It is true that SLM has more of a 'customer focus' than most other processes, but without those other processes, there is nothing to see the customer about!
C3: Protected
Page 119 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
Objective
The Service Level Management process manages the quality of IT service delivery according to a written agreement between the users and IT department called the Service Level Agreements (SLAs). The goal for SLM is to maintain and improve on service quality through a constant cycle of agreeing, monitoring, reporting and improving the current levels of service. It is strategically focused on the business and maintaining the alignment between the business and IT.
C3: Protected
Page 120 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
Process Description
In order to understand the Service Level Management process it is necessary to understand some basic concepts that are used, we will be explaining them here so the process is easier to understand. Service Level Requirements (SLR) This is a document that contains customer requirements regarding which IT services they want and the availability/performance they need for those services. This is the starting point of setting up the Service Level Agreements. Service Specifications The IT organization draws up the Service Specifications based on the SLR. This is the translation of the customer requirements into "how" the IT organization is going to provide these services. What are the technical needs? It also will show relationships between the SLAs, the third parties and IT the organization itself. Service Level Agreement (SLA) The SLA is a document that defines agreed service levels between the customer and provider, i.e. between IT and the business. SLAs should be written in language that the business understands (clear, concise and free of jargon). SLAs should not include detailed procedure diagrams for other processes or content such as technical information that the business will not understand.
C3: Protected
Page 121 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
Underpinning Contracts (UPCs or UCs) With the an external supplier or third party is involved in the delivery of IT Services then a contract has to be drawn up to ensure that they provide their service within a certain agreed time, cost, level, etc. The IT organization passes through the business requirements to external suppliers. This document will be reflective of the service levels defined in SLAs. For example, if the SLA states a fix of a printer in 5 days then the UC with the third party should support this i.e. Fix printer and return to organization in 3 days. Operational Level Agreement (OLA) or Service Provisioning Agreement (SPA) Some IT services depend on other service being provided from within the IT organization. For example a service to provide a program that runs via the network depends on the availability of the network. Agreements about the availability of the network will be drawn up in an Operational Level Agreement or SPA. As with the UPC these internal "contracts" will support the SLAs in the same manner except the focus is towards the internal IT organization. Service Quality Plan (SQP) This plan will contain information about performance indicators for the IT organization to measure the Services. It will contain performance indicators for each of the processes that are implemented in the organization. It is important to also include the performance indicators in the UCs and OLAs as they contribute to the IT service as a whole. Service Catalogue This is a document that contains all the Services that are provided, a description of the service, service levels, cost of the service, the customer and the person/department responsible for the maintenance of the service. The content of a Service Catalogue will vary depending on the requirements of the IT organization. Service Specification sheets often form part of the Service Catalog. Note: Be sure to understand the principal difference between an Underpinning Contract and an Operational Level Agreement.
C3: Protected
Page 122 of 203
Controlled copy
C3: Protected
ITIL Foundation Level - Certification Guide
Page 123 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
Activities
The main activities of Service Level Management consist of: •
Composing a Service Catalogue
•
Negotiating with clients over the possibilities and price of automation and drafting
•
Securing and maintaining the Service Level Agreement (SLA).
This is done trough a continuous cycle of the following actions: •
Identifying
•
Defining
•
Negotiating
•
Monitoring
•
Reporting
•
Reviewing
Identifying
C3: Protected
Page 124 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
Within this activity the IT organization will need to define the services it provides within a Service Catalogue. The Service Catalogue is like a menu of services that will clarify for IT what is on offer and the components of these services. In this stage the relationship between the IT organization and the customer is built or maintained. The aim is to find out the customer requirements with regard to IT services. As part of this activity the SLR document is written documenting the customer requirements. This document should be signed off by both parties to ensure that a clear understanding is achieved by IT and the business regarding requirements. Defining The results of this activity the first time around will be the delivering of the SLR, the service specs and the SQP. On an ongoing basis this activity will include taking the SLRs as well as the content of the Service Catalogue and defining a draft SLA that aligns both into acceptable service levels. During the creation of this document consideration of the UCs and OLAs is critical as these documents support the SLA. Later on the needs of the customer and the specs need to be verified on a regular basis as they might change. The needs of the customer might change due to a change in the business procedures and the specs made need changing as a result of the changed Requirements or the introduction of advanced technology. Negotiating Once the draft SLA is formulated negotiation is carried out to gain agreement, acceptance and a signature for the following documents. •
Service Level Agreement
•
Underpinning Contracts
•
Operational Level Agreements
It is critical that the above documents are negotiated and signed off.
C3: Protected
Page 125 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
Monitoring If service levels cannot be measured and monitored their value is substantially reduced. Why set service levels if you do not know if they are being met? In order to be able to measure the service levels they need to be clear and have to be objective. It is not enough to define how much time a service can be unavailable, one also needs to define when a service is said to be available again. Is it when the IT organization restored the service or when the users are aware of it? In order to monitor the performance, availability and support service levels other processes such as Capacity, Availability and Incident Management should be in place. These processes will manage and report on service levels reporting back to the Service Level Management process. Reporting The reports should show the figures about the service levels that are required and the actually measured service levels. Subjects that can be included are: •
Time needed to resolve Incidents
•
Down time of the network and any other occasion where the service levels have not been met.
•
Time needed for a change.
•
All major disruptions to the IT service in detail.
•
Use of the capacity (minimum and maximum)
•
Amount of interactions with various services
Reviewing Reviewing the Service with the Customers on a regular basis will help discover opportunities to improve the IT service that is provided. With the help of a Service Improvement Plan (SIP) this can be achieved. Once the Service Level Agreements are documented is it not end of the process it is the start! It is also important to regularly review how the process itself operates and update where necessary.
C3: Protected
Page 126 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
Roles Service Level Manager Role The Service Level Manager is responsible for the implementing of the process and maintaining or improving the Service Levels by initiating improvement actions. The role requires a position that allows the person to negotiate the service levels with the customers on behalf of the IT organization. The Service Level Manger oversees the steps that result in the following official documents: •
Service Level Requirements
•
Service Specs
•
Service Level Agreement
•
Underpinning contract
•
Operational Level Agreements
•
Service Quality plan
•
Service Improvement plan
C3: Protected
Page 127 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
Relationships
Service Level Management is at once the basis and, the result of, the implementation of Service Management processes. Service Level Management is related to every other module within Service Management. You can’t implement Service Level Management to a full maturity without the other nine processes and the Service Desk function, due to the holistic approach required for Service Management. The Service Support processes - Incident and Problem and the Service Desk - aim to restore the services as soon as possible when there is a breach within the Service Levels. They provide SLM with valuable information as the customer’s perception of the Service Levels. The Service Delivery processes are more focussed on keeping the services running within the parameters defined in the SLAs. They get information from SLM about the required levels and give information about the actual levels and advice about the impact of new or changed services. Note: Remember the Service Support Processes are: o
Incident Management
o
Problem Management
o
Change Management
o
Release Management
C3: Protected
Page 128 of 203
Controlled copy
o
ITIL Foundation Level - Certification Guide
Configuration Management
Benefits
Introducing Service Level Management will have the following benefits for the Business and the IT organization: •
The IT service will be of a higher quality and will cause less interruption. Hence the productivity of the IT customers will improve as well.
•
The resources of IT staff will be used more efficiently.
•
The IT organization will provide services that meet the expectations of the customers.
•
The service provided can be measured.
•
The perception of the IT organization will improve.
•
Cost reduction.
•
The services provided by the third parties is more manageable with the underpinning contracts in place and therefore any possibility of negative influence on the IT service provided is reduced.
•
Monitoring the service make it possible to identify week spots that can be improved.
C3: Protected
Page 129 of 203
Controlled copy
C3: Protected
ITIL Foundation Level - Certification Guide
Page 130 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
Common Problems
The following issues need to be addressed in order to ensure a successful Service Level Management process: •
The service levels set out in the SLAs must be achievable for the IT Organization in the first place.
•
UCs and or OLAs much be set up properly otherwise external suppliers or internal parties may inadvertently create a breach of the agreed Service Levels.
•
The services need to be measurable and objective for IT Customers and the IT organization.
•
There needs to be a commitment to negotiate the Service Levels required and in the drawing up Service Level Agreements. This must be backed with a commitment to conduct regular reviews and not simply let the agreements get outdated.
Note: A useful acronym when thinking about Service Level Agreements (or any contract) is SMART •
Simple
•
Measurable
C3: Protected
Page 131 of 203
Controlled copy •
Achievable
•
Realistic
•
Time driven
C3: Protected
ITIL Foundation Level - Certification Guide
Page 132 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
Metrics
The following question will help determine if the Service Level Management process is effective and efficient: •
Are all services covered by SLAs?
•
Do the services within the SLAs have the necessary UCs and or OLAs?
•
Is there an improvement in the Service Levels?
•
Are the actual Service Levels measured?
•
Is the perception of the IT organization improving?
Best practices Interesting websites: Assessment http://www.itil.co.uk/online_ordering/serv_del_graphs/servlevel_mngt.htm
White papers
C3: Protected
Page 133 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
http://www.interpromusa.com/SLA Challenges for ASPs.pdf
Books http://www3.gartner.com/1_researchanalysis/focus/entmgmt013002.html
More theory http://www.microsoft.com/technet/treeview/default.asp?url=/TechNet/prodtechnol/windo ws2000serv/maintain/opsguide/cfgmgtog.asp
Essentials (terminology) Service Level Management: The process of negotiating, defining, drafting, securing and revising a demanded and cost justified level of service delivery to the user. Service Level Requirements Business demands and requirements for service levels. Examples are: downtime, availability % and opening hours of the helpdesk. Together with the service catalogue they can be input for the SLA negotiations. Service Catalogue Overview of all current services as delivered by IT. May have a price list attached. SIP = Service Improvement Program / Plan Actions, phases and due dates for the improvement of the services SQP = Service Quality Program / Plan A document that contains all the information for the managers, including the Performance Indicators for the other ITIL processes.
C3: Protected
Page 134 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
13.0 Financial Management Introduction
Over recent years modern businesses have become more and more dependent on IT to operate their business processes efficiently. As a consequence the number of end users drastically increased and so did the total amount of money spent on IT (the IT budgets). All too often customers of IT organizations and senior managers often perceive that there is too much money spent on IT. This has, therefore, led to a demand for increasingly higher quality and cost-effectiveness of the provided services. The IT organization on the other hand is often under the impression that they are doing ‘a good job’, but find it very difficult to clearly explain in business language what the real costs and benefits are of the provided IT Services. Organizations (the Customers and senior managers) are reluctant to spend money on improving IT services if they don’t have a clear picture of the costs involved and the benefits it has for the business. Financial Management for IT Services can make the costs clear, set up a charging method and give customers an idea about the quality / price relation. In other words, Financial Management for IT Services promotes the running of IT Services as a business operation. The slide below shows some common thoughts and remarks often heard in organizations through out the world.
C3: Protected
Page 135 of 203
Controlled copy
C3: Protected
ITIL Foundation Level - Certification Guide
Page 136 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
Objective
The objective of the Financial Management for IT Services process for an in-house IT organization should be: •
‘to provide cost-effective stewardship of the IT assets and resources used in providing IT Services.’
In a commercial environment, there may be additional statements that reflects the profit-making and marketing aims of the organization, but for any IT Services organization the objectives should include: •
‘to be able to account fully for the spend on IT Services and to attribute these costs to the services delivered to the organization’s Customers.’
•
‘to assist management decisions on IT investments by providing detailed business cases for Changes to IT Services.’
The main focus of this process, therefore, is on understanding the costs involved in delivering IT Services (by attributing the costs to each specific IT Service and Customer). This awareness of costs improves the quality of all decisions made in regards to IT expenditure. Charging (notional or by sending real bills) the costs to the Customers is optional.
Process Description
C3: Protected
Page 137 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
Financial Management for IT Services consists of the following three sub-processes: Budgeting (mandatory) Budgeting is the process of predicting and controlling the spending of money within the organization and consists of a periodic negotiation cycle to set budgets (usually annual) and the day-to-day monitoring of current budgets. Budgeting ensures that the correct finance is available for the provision of IT Services and that during the budget period they are not over-spent. All organizations have a periodic (e.g. annual) round of negotiations between the business departments and the IT organization covering expenditure plans and agreed investment programs which ultimately sets the budgets for IT. IT Accounting (mandatory) IT Accounting is the set of processes that enable the IT organization to account fully for the way its money is spent (particularly the ability to identify costs by Customer, by service and by activity). It is in this regard more important to understand the costs than to know up to the dollar cent how much something costs. Charging (optional) Charging is the set of processes required to bill Customers for the services supplied to them. This requires sound IT Accounting and needs to be done in a simple, fair and accurate way. Within organizations there are two distinct cycles associated with Budgeting, IT Accounting and Charging: •
A planning cycle (annual) where cost projections and workload forecasting form a basis for cost calculations and price setting.
•
An operational cycle (monthly or quarterly) where costs are monitored and checked against budgets, bills are issued and revenue collected.
All these processes are discussed in more detail in the following chapter.
C3: Protected
Page 138 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
Activities Each of the three sub-processes of Financial Management for IT Services consist of a set of activities, which will be discussed in this chapter. Budgeting •
•
Determine the budget method: o
Incremental budgeting Last year’s figures are used as the foundations for this year’s budget
o
Zero-based budgeting A fresh start: Called the Zero base. The purpose and need of every expense needs to be determined, together with the actual amount.
Determine the budget period
In most cases this will be the period of a financial (fiscal) year which can we subdivided in smaller periods. •
Set up the budget
Determine all the categories available and estimate the costs for the next budget period. Take in consideration that demand might increase over time. Some costs might need to be estimated. IT Accounting
C3: Protected
Page 139 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
IT Accounting aims to provide the information about what the money was spent on. All Configuration Items necessary to deliver an IT Service to the Customer bear a certain cost. These costs together add up to the total costs necessary for IT Service delivery. In order to understand costs we need to discuss costs in a general way. Direct or Indirect costs. Direct costs are costs that can be assigned to specific services. For example the cost of a printer that is used by one department only can be seen direct costs. Indirect costs are costs that can’t be related to a certain service. For example the electricity of the IT department they are also called shared costs. Capital versus Operational costs Capital costs are costs involved with the purchasing of items that will be used over a few years and need to be depreciated. (The depreciation amount is part of the total costs). Operational costs are those resulting from the day-to-day running of the IT Services organization (e.g. staff costs, electricity, hardware maintenance) and relate to repeating payments whose effects can be measured within a short timeframe (usually less than 12 months). Fixed or variable costs Fixed costs are costs that stay the same regardless. The rent of a building is an example of fixed costs. Variable costs change with the use of the service. If you take a telephone service as an example the line rental costs are fixed, as they will be the same each month regardless how many
C3: Protected
Page 140 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
calls you make. The costs for the calls are variable costs as they depend on the amount of calls are made. Cost types Cost types need to be determined (they are also used in the budgeting activity). The main cost types are Hardware, Software, People, Accommodation, Transfer and External Service costs. Depreciation methods Capital costs are depreciated over the useful live of the fixed asset (e.g. desktops in three years, the mainframe in ten years). There are three methods of depreciation: •
Straight-line method. An equal amount is written off the value of the asset each year.
•
Reducing balance method. A percentage of the capital cost is written off the net book value each year.
•
Depreciation by usage The Depreciation is written-off to the extent of usage during a period.
In most cases there already will be an accounting model in place for the rest of the business. It is important to define a Cost Model that complies with the overall business accounting model.
Charging
C3: Protected
Page 141 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
In a Profit Centre the objective is to recover, through Charging, an amount greater than the costs incurred. For an in-house IT organization the aim could be to recover the costs back in a fair and simple way. But it could also be just to influence the behaviour of the Customers and end users. That is, via Charging the IT organization can influence the demand and actual usage of IT Services, and the way the service are provided. Before Charging can take place a few decisions need to be made regarding the Charging policy, Cost Units and Pricing. A Charging policy needs to be chosen: •
Communication of information Only the actual costs will be calculated, reported and charged to the customer (plus specific amounts, if this is agreed with the customer).
•
Pricing flexibility Establish and charge the prices each year. This method gives the option to influence excessive use.
•
Notional charging All costs are invoiced, but the customer doesn’t have to pay the physical dollars. This method is used to gain experience and eliminate mistakes.
In order to be able to charge the costs to the IT customers Cost Units or chargeable items need to be set up. These have to be clear, so they can be checked and are understood by the Customer. Examples would the PC they use, the amount of print jobs they request. Pricing moves the budget responsibility from the IT department to the user organization. A good pricing system gives the client the sense that they get value for their money. A pricing method (or a combination) need to be chosen: •
Cost price
•
Cost price plus (to cover expenses made for R&D and overhead)
•
Market prices, the price that is charged for the service on an outside market
•
Going rate. Rate that is also used in similar organization or other departments within the business.
•
Fixed price. The price is negotiated with the customer beforehand
C3: Protected
Page 142 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
Roles The IT Finance Manager can be a person from the IT organization or the Finance department. An alternative would be that the tasks, associated with this role, are shared between both. The main responsibilities are: •
To oversee the implementation of the Financial Management for IT Services process and their sub processes (Budgeting, IT Accounting and Charging).
•
Assist in setting up the budgets and the accounting plans.
•
To work, at an appropriate level, with representatives of the organization management and the Finance Department, to develop the policies of Budgeting, IT Accounting and Charging.
If the IT Finance Manger is from the IT organization maintaining a close relationship with the Finance Department becomes one of the responsibilities.
C3: Protected
Page 143 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
Relationships Financial Management for IT Services provides (depending on which pricing system has been chosen within the organization), important information to Service Level Management about the introduced costing, pricing and charging strategies. As well as this the Financial Management process analyses which level of service delivery is technically cost realistic for the business. Financial Management for IT services can, together with Capacity Management and Availability Management, develop pricing strategies. These strategies can realize an optimal spread of the workload within an organization, which will result in optimal use of resources. It can also use asset and cost information from Configuration Management to analyze different scenarios of equipment (different costs for different configurations).
Benefits The benefits of implementing the Financial Management for IT Services process include: •
Increased confidence in setting and managing budgets.
•
A more efficient use of IT resources throughout the organization.
•
Higher satisfaction of Customers as they know what they are paying for.
•
Investment decisions can be made on accurate information.
•
Increased professionalism of staff within the IT organization.
C3: Protected
Page 144 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
Divided per sub process the benefits will be: For budgeting: •
Ability to estimate the total costs needed to run the IT organization.
•
Reducing the risk of spending more money then is available.
•
The ability to verify if the actual costs compare to the estimate costs.
•
The guarantee that the money resources are available to run the IT organization within the agreed Service Levels.
For IT Accounting: •
Availability of management information on the costs of providing IT Services.
•
IT and Business managers make better decisions, which ensures that the IT Services organization runs in a cost-effective manner.
•
Ability to accurately account for all the expenses made by the IT organization.
•
Demonstrate under- or over-consumption of services in financial terms.
•
Maximizing the value for money of the provided IT services.
•
The possibility to determine the costs of NOT making a specific investment.
•
Form the basis to implement Charging.
For Charging: •
Providing a sound business method of balancing the shape and quantity of IT Services with the needs and resources of the Customer.
•
The ability to recover IT costs in a fair manner.
•
Influence the demand for the provided IT Services; hence influence the behaviour of the Customer.
Common Problems
C3: Protected
Page 145 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
In order for the process to work effective and efficiently the following issues should be addressed as they are typical areas that can cause problems in this process area; •
Cost Models that are used for IT Accounting are too detailed, creating too much administrative overhead.
•
Not enough commitment from senior IT and Business management.
•
Financial Management for IT Services is not in alignment with the way the overall organization manages its finances.
•
Charging policies are not well communicated to customers possibly causing unwanted behaviour (eg. actions by users/customers to try to avoid incurring charges).
Note: The area of Financial Management for IT Services is often glossed over. Typically, customers agree to charges at a point in time, but when the actual charges are levied the challenges begin. To offset this, it is wise to quite often ensure that your customer has had their expectations set, so that levied charges do not come as a shock.
Metrics Key performance indicators to report on the process are: •
Accurate cost–benefit analysis of the services provided
C3: Protected
Page 146 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
•
Customers consider the charging methods reasonable
•
The IT organization meets its financial targets
•
The use of the services by the customer changes
•
Timely reporting to Service Level Management
Other issues that can be reported on are: •
Creditor / Debtor management
•
Other specialized accounting measurements (eg. liquidity of assets)
Note: Accountancy is a respected profession around the world. It is very unlikely that this process can be properly implemented without some specific expertise in accounting. Best practices
Interesting websites: Assessment http://www.itil.co.uk/online_ordering/serv_del_graphs/financial_mngt.htm White paper
C3: Protected
Page 147 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
http://www.interpromusa.com/IT Cost Charging Challenges. PDF
C3: Protected
Page 148 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
More theory http://www.microsoft.com/technet/treeview/default.asp?url=/TechNet/prodtechnol/windows2000serv /maintain/opsguide/cfgmgtog.asp
Essentials (terminology) Financial Management for IT services: The implementation of Financial Management for IT services is the foundation for an independent IT organization, which is not only aware of costs, but is also oriented on future investments. Budgeting: The process of predicting and controlling the spending of money within the organization and consists of a periodic negotiation cycle to set budgets and the day-to-day monitoring of the current budgets. IT Accounting: The set of processes that enables the IT organization to account fully for the way its money is spent. Cost Model: A framework in which all known costs can be recorded and allocated to specific Customers, activities, or other category. Most Cost Models are based on calculating the cost for each Customer, but other models can be developed to show the cost for each service or the cost for each location. The calculation of Costs-by-Customers is the usual start-point if a Charging system is to be introduced. Depreciation: The measure of the wearing out, consumption or other reduction in the useful economic life of a fixed asset, whether from use, passage of time, or obsolescence through technological or market changes. Charging: The set of processes required to bill customers for the service supplied to them. This requires sound IT accounting. Pricing: Pricing is just one element of the marketing quartet – ‘product, pricing, promotion, place’. Deciding upon the appropriate charge/price is, therefore, not merely a question of cost recovery but also of its impact upon the demand for the product. Billing: Passing on charging information to managers to make them aware of the cost of the resources used by their business. This can be done with a real transfer of money (Full Charging) or without (No Charging or Notional Charging).
C3: Protected
Page 149 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
TCO Total Cost of Ownership, a method of calculating the cost of a product or service as promoted by Gartner. ROI Return on investment (= average increase in profit / investment) ROCE Return on capital employed (= net profit before tax and interest / total assets less current liabilities)
C3: Protected
Page 150 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
14.0 Availability Management 14.1 Introduction
Organizations are increasingly dependent on IT services, when they are unavailable, in most cases the business stops as well. There is also an increasing demand for 7 days per week 24 hrs a day availability of IT services. It is therefore vital for the IT organization to manage and control the availability of the IT Services. This is done by defining the requirements from the business regarding the availability of the IT services and then matching them with the possibilities of the IT organization.
C3: Protected
Page 151 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
14.2 Objective
The objective of Availability Management is to get a clear picture of business requirements regarding IT Services availability and then optimize infrastructure capabilities to align with these needs. Or one can put it this way: To ensure the highest availability possible of the IT services as required by the business to reach its goals.
C3: Protected
Page 152 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
14.3 Process Description
Availability Management depends on a lot of inputs to be able to function well. Among the inputs are: •
The requirements regarding the availability of the business
•
Information regarding reliability, maintainability, recoverability and serviceability of the CI’s
•
Information from the other processes, Incidents, Problems, SLAs and achieved service levels
The outputs of the process are: •
Recommendation regarding the IT infrastructure to ensure the resilience of the IT infrastructure
•
Reports about the availability of the services
•
Procedures to ensure availability and recovery are dealt with for every new or improved IT service.
•
Plans to improve the Availability of the IT services
C3: Protected
Page 153 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
Key terminology and actions that form the basis of this process are: Availability: The availability and flexibility of components of the infrastructure. This is expressed in the following formula:
A = (ST - DT)/ST x 100, whereby A - Availability, ST = agreed Service Time and DT = Down Time. Availability is defined as: “Availability of a IT Service or component to perform its required function at a stated instant or over a stated period’ (ITIL Service Delivery Book, OGC,2001) Reliability: The reliability of components of the infrastructure. In this case the Mean Time Between Failures (MTBF) can be used as a measuring tool. Reliability is defined as: “…freedom from operational failure” (ITIL Service Delivery Book, OGC, 2001) Resilience is a key aspect of reliability Resilience is defined as: “The ability of an IT component to continue to operate even though one or more of its sub components has failed” Maintainability: The capability to maintain or restore a service or component of the infrastructure at a certain level, so that the required functionality can be delivered. Some services or indeed components of the infrastructure are easier to maintain and/or restore to service in the event of a failure. For example, an application has been developed that requires daily housekeeping to ensure its operation and a highly qualified Database Administrator can only do this. This application is not easy to maintain. The maintainability of C.I.'s within the infrastructure is an important consideration as the speed of recovery and the ease of maintenance will impact the uptime and hence availability of services. Operational Level agreements (OLA's) within the Service Level Management process tie in here. Note: Remember that C.I. = Configuration Item Serviceability: Serviceability refers to the agreements that are held with third parties providing services to the IT organization. These contracts will define how these external parties will perform to ensure the availability of the services they interface with. For example, how will they ensure resilience, how will they maintain the infrastructure they are responsible for. Underpinning Contracts within Service Level Management tie in here. Security: This is divided into confidentiality, integrity and availability (CIA). It can be desirable (for security reasons, which might endanger the availability) not to make certain components of the infrastructure available, logically or physically.
C3: Protected
Page 154 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
Security is of great concern to most organizations these days and it is important to ensure that IT services are made available to the organization in a secure way. That means that services and information is available to the right people. It is also important to ensure that services are not so secure that it impedes that ability of the organization to use these services.
14.4 Activities
The activities within the process can be divided in three main activities, which will be discussed in detail in the remainder of this chapter: •
Planning
•
Improving
•
Measuring and reporting
Planning Planning involves the following activities: Determine the Availability Requirements
C3: Protected
Page 155 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
It is important not only to find out the requirements but also to find out if and how the IT organization can meet these requirements. The Service Level Management process maintains contact with the business and will be able to provi de the availability expectations to the Availability Management process. The business may have unrealistic expectations with respect to availability without understanding what this means in real terms. For example, they may want 99.9% availability yet not realize that this will cost five times more than providing 98% availability, for their organizations infrastructure. It is the responsibility of Service Level Management and the Availability Management process to manage expectations. Design When considering the design of the infrastructure the IT organization can either design for “availability” or “recovery”. Design for Availability When the business cannot afford for particular service/s to have downtime for any length of time designing the infrastructure for availability should be the approach. In this instance the IT organization will need to build resilience into the infrastructure and ensure that preventative maintenance can be performed to maintain services in operation. In many cases building “extra availability” into the infrastructure is an expensive task that must be justified by business need. Designing for Availability is considered a pro-active approach to avoiding downtime in IT services.
C3: Protected
Page 156 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
Design for Recovery When the business can tolerate some downtime of services or the cost justification cannot be made for building in additional resilience into the infrastructure then designing for recovery is the appropriate approach. In this approach the infrastructure will be designed such that in the event of a service failure recovery will be as fast as possible. Spare part for example will assist in the speedy of infrastructure components that fail. Designing for recovery can be seen as more reactive management of availability. The processes (like Incident Management) need to be in place to recover as soon as possible in case of a service interruption. Other Considerations •
Security issues
Define the security areas and the impact they might have on the availability of services. Make sure it is clear who has access to what and where. •
Maintenance management
This is a maintenance window that is agreed upon and known to the customers in which the IT organization can do the maintenance and repairs. This way the impact on the IT service of the maintenance and repairs will be reduced. Improving Developing the Availability Plan The Availability Plan will look into the future (for example 12 months) and document what measures will be put in place to ensure that the infrastructure and IT services will be available to meet business requirements. Input from monitoring and other processes, such as Service Level Management, will provide the basis for decisions on what “availability” measures will be put in place. All plans must be cost justifiable and aligned with business needs. Measuring and reporting This involves reporting about the availability of each service, the down times and recovery times. These reports will often go to the Service Level Management process to use in reporting comparisons (planned versus actual) on service levels back to the customer. It is also important to measure and report on the perception of the customers on the availability of the IT service. You can use many ways to identify (un-) availability and potential problems. The following are a few mentioned by the OGC: CFIA Component Failure Impact Assessment can be used to predict and evaluate the impact on IT Service arising from component failures within the IT infrastructure. FTA
C3: Protected
Page 157 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
Fault Tree Analysis is a technique that can be used to determine the chain of events that causes a disruption to IT services. CRAMM CCTA Risk Analysis and Management Methodology can be used to identify new risks and provide appropriate countermeasures associated with any change to the business availability requirements and revised IT infrastructure design. SOA Systems Outage Analysis is a technique designed to provide a structured approach to identifying the underlying causes of service interruption to the user.
14.5 Roles The Availability Manager The Availability Manager has a guiding role and has a general, yet sound knowledge of the IT infrastructure. They will assemble and analyze data from processes like Problem Management, Change Management, Service Desk and Capacity Management to assist in management and planning with regard to availability. Using the results of this data they steer other Service Management processes in order to guarantee the agreed availability, thus helping to prevent problems. For example they may attend Change Advisory Board meetings within Change Management. The Availability Manager communicates their findings to the Service Level Manager and, through that, makes an important contribution to the establishment of the SLAs. They implement the policies of Security Management in relation to the security of data.
14.6 Relationships The introduction of Availability Management without the other processes in place is likely to fail, as without the support of the other processes it can’t deliver the agreed availability. Incident Management and Problem Management provide a key input to ensure the appropriate corrective actions are being progressed. The measurements and reporting of IT availability ensures that the level of availability delivered, meets the Service Level Agreement (SLA). Availability Management supports the Service Level Management process in providing measurements and reporting to support service reviews.
C3: Protected
Page 158 of 203
Controlled copy
C3: Protected
ITIL Foundation Level - Certification Guide
Page 159 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
14.7 Benefits
The main benefit is: Optimal use of the capability of the IT Infrastructure and delivering the availability of the IT services that is according the agreed requirements of the customers. Other benefits include: •
Constant striving to improve the availability
•
Higher Customer Satisfaction
•
In case of a disruption corrective action will be undertaken
•
Higher availability of the IT service
C3: Protected
Page 160 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
14.8 Common Problems
As with every process there are some issues that need to be addressed as they can make or break the success of the process. For Availability management they are: •
Unclear requirements from the business regarding the availability expected of the IT service
•
No official contract is drawn up to specify the agreed availability of each service. (Risk of conflict and arguments at a later stage)
•
Commitment to the process
The business and the IT organization must share a common understanding on the definition of availability and the definition of downtime.
C3: Protected
Page 161 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
14.9 Metrics By reporting on the following items the effectiveness and efficiency of the process can be measured: •
The total downtime per service
•
Time it takes to recover from an incident
•
The availability of the services
•
The improvement of the availability of the IT services
Note: Check the AV Essentials section for defined availability terms (eg. MTBF, MTTR, etc.)
14.10 Best practices Interesting websites: Assessment http://www.itil.co.uk/online_ordering/serv_del_graphs/avail_mngt.htm
C3: Protected
Page 162 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
14.11 Essentials (terminology)
Down time: The total period during which an IT service is not operational within the agreed service times. Mean Time Between Failures (MTBF): The average period between the first moment the service is fully operational and the moment that this service is no longer operational. Mean Time To Repair (MTTR): The average period between commencement of an incident and its solution. Mean Time to Restore Services (MTRS): The average period between the commencement of an incident and the restoration of the service delivery. Fault, Failure: The moment at which a functional unit no longer provides the required function. High Availability A characteristic of the IT Service that masks the effects of IT component failure to the user. Continuous Operation A characteristic of the IT operation that masks the effects of planned downtime to the user.
C3: Protected
Page 163 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
Continuous Availability A characteristic of the IT Service that minimizes or masks the effects of all failures and planned downtime to the user.
C3: Protected
Page 164 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
15.0 Capacity Management 15.1 Introduction
The Capacity Management process is designed to ensure that the capacity of the IT infrastructure is aligned to business needs. The main purpose of Capacity Management is to understand and maintain the required level of service delivery (via the appropriate capacity) - at an acceptable cost. Through gathering business and technical capacity data this process plans for and delivers the, cost justified, capacity requirements of the business. The Capacity plan is the core document that describes how this will take place over the coming period.
15.2 Objective The main objective of Capacity Management is to understand the business’s capacity requirements and deliver against them both in the present and the future.
C3: Protected
Page 165 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
Capacity Management is also responsible for understanding potential advantages new technology could have and assessing its suitability for the organization.
15.3 Process Description The Capacity Management process breaks down into three sub-processes listed below: Business Capacity Management This sub process has the focus on the long term. It is responsible for ensuring that the future business requirements are taken into consideration then planned and implemented as necessary. Service Capacity Management Is responsible for ensuring that the performance of all current IT services falls within the parameters detailed as targets within SLA’s. Resource Capacity Management Is responsible for the management of the individual components within the infrastructure. Resource capacity management has more of a technical focus.
C3: Protected
Page 166 of 203
Controlled copy
C3: Protected
ITIL Foundation Level - Certification Guide
Page 167 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
15.4 Activities
Each of the sub process mentioned before involve, to a higher or lesser degree, the following activities: •
Iterative Activities
•
Storage of Capacity Management Data
•
Demand management
•
Application Sizing
•
Modeling
•
Capacity Plan
•
Reporting
Iterative Activities The following iterative activities take place within Capacity Management: •
Monitoring; checking if all the service levels are being met.
C3: Protected
Page 168 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
•
Analysis; the data collected by monitoring needs to be analysed and predictions been made for the future
•
Tuning; implement the outcomes and results of the 2 previous steps to ensure optimal use of the infrastructure for now and in the future.
•
Implementation; to actual implement new capacity or changed capacity with Change Management.
Storage of Capacity Management Data The Capacity Database (CDB) is the cornerstone of the process. It is used to form the basis of the reports for this process and contains technical, business and relevant information for capacity Management. As well, the information contained here provides the other processes with the data necessary for their analysis. Demand management: Demand Management is responsible for the management or workload in the infrastructure to better utilize the current capacity rather than increasing capacity. User behaviour is influenced to shift workload, for example to another time of the day to relieve capacity shortages. Application Sizing: Application Sizing related to the assessment of the capacity requirements of applications during their planning and development. The capacity requirements of a new application will be understood and the infrastructure can be tuned as necessary to meet the new requirements. Modeling: By simulation or with assistance of mathematical models modeling allows for the prediction of future capacity requirements. The results from this can be used as an input into the Capacity Plan. Capacity Plan Capacity Plan, this plan is drafted on the basis of data from the CDB (Capacity Database), financial data, business data, technical data, etc. The plan is future oriented and covers a period of at least 12 months. Reporting Reporting entails the reporting of capacity performance over any given period. Reporting for example could be (but not limited to) against the capacity metrics in SLAs.
15.5 Roles The Capacity Manager The main responsibilities of the capacity manager are: •
To develop and maintain the Capacity plan
•
Manage the process
•
Make sure the Capacity database is up to date.
To do this, the manager must be involved in evaluating all changes, to establish the effect on
C3: Protected
Page 169 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
capacity and performance. This should happen both when changes are proposed and after they are implemented. They pay particular attention to the cumulative effect of changes over a period of time. The cumulative effects of single changes can often cause degraded response times, file storage problems, and excess demand for processing capacity. Other roles within Capacity Management are the roles of the network manager, application and system manger. They are responsible for translating the business requirements in to required capacity to be able to meet these requirements and to optimize the performance.
15.6 Relationships Capacity Management is part of Service Delivery and is directly related to the business requirements. It is not simply about the performance of the system’s components, individually or collectively. Service Desk, Incident Management and Problem Management. These processes will provide Capacity Management with information about incidents and problems related to Capacity. Capacity Management will support the processes with solving the incidents and or problems and also provide them with information about the capacity performance. Change Management and Release Management Capacity Management activities will raise Request for Changes (RFC's) in order to ensure that the appropriate capacity is available. These are subject to the Change Management process, and
C3: Protected
Page 170 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
implementation may affect several Configuration Items (C.I.'s), including hardware, software and documentation, and will require effective Release Management. Availability Management The link between Capacity Management and Availability Management is strong, as the availability that is needed requires a certain amount of capacity within the configuration items. Without enough capacity, you will never have enough availability. Furthermore, the values measured by Capacity Management are of importance to Availability Management in relation to availability and reliability. Service Level Management Both Capacity Management and Availability Management need to provide the service level manager with input for effective SLA negotiations. Capacity Management informs Service Level Management about the result levels that can be provided to the client. Financial Management The drafted capacity plan delivers important input for Financial Management, which on this basis can draft a very accurate investment plan capacity Management gets information in return about the available budget. IT Service Continuity Management Capacity Management provide ITSCM with the information about the minimum required Capacity needed for recovery. It is important to consider the impact (for needed capacity) of changes to the IT services on the ITSCM procedures.
C3: Protected
Page 171 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
Benefits
Implementation of Capacity Management offers the following benefits: •
An actual overview of the current capacity in place
•
The possibility to plan capacity in advance.
•
Being able to estimate the impact of new applications or modifications
•
Cost savings
•
Better service that is in tune with the requirements of the Business.
15.7 Common Problems Common problems that can be encountered while the process is already implemented include: •
Capacity information from suppliers is not available or is too general and can be misleading for infrastructure components.
•
The expectation to what Capacity Management can do is over estimated. If an application is poorly designed, more capacity won’t fix the problem.
•
The detail of monitoring can be to deep causing the process to be too expensive.
C3: Protected
Page 172 of 203
Controlled copy •
ITIL Foundation Level - Certification Guide
Information is difficult to obtain. It is not always easy to predict what future capacity is required before you build an application.
Note: This final point is important. All too often end users and customers are interviewed at length about their expected capacity requirements, only to demand more as soon as the new application goes live. It is up to the IT professionals to have built in the ability for the application to scale to match any new requirements.
Metrics To verify if the process is operating within it goals one should check: •
If the forecast is in line with the actual demand at that time?
•
If the Capacity plan is correct?
•
Are the requirements being met?
•
Is capacity not a cause for the breach of Service Levels, Incidents or Problems?
•
Are ad hoc expenses being reduced because better planning is in place?
•
Performance against SLAs
C3: Protected
Page 173 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
Best practices
Why a Capacity Plan? With cheap hardware prices, capacity planning may seem unimportant; you can always upgrade later. A simple guess of the capacity requirements should be sufficient, right? Why give this subject any more thought?
There are two main issues that make capacity planning critical. The first is the rate of technical change. We now measure progress in "Internet years" -- equivalent to about 90 days of a calendar year. The second is with Internet/Intranet at the helm. Today’s systems are primarily being developed within a 3-tier architecture. This rapid change, coupled with the increase in complexity of 3-tier architecture, is causing system designers to pay closer attention to capacity. Five years ago, a designer could roll out a new system with a rough estimate of capacity and performance. The system could then be tuned or more capacity added before all of the users had been converted to the new system. The process was reasonable because the systems were typically not missioncritical. Today, there’s no time for this approach. Once systems are in place they become an integral part of the overall design. Downing the system for upgrades becomes increasingly expensive in both time and resources. In addition, the added complexity of the environment typically requires more care, due to the interdependency between various application components. Capacity planning is driven purely by financial considerations. Proper capacity planning can significantly reduce the overall cost of ownership of a system. Although formal capacity planning takes time, internal and external staff resources, software and hardware tools, the potential losses incurred without capacity planning are staggering. Lost productivity of end users in critical business functions, overpaying for network equipment or services and the costs of upgrading systems already in production more than justify the cost of capacity planning.
C3: Protected
Page 174 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
Interesting websites: http://www.capacityplanning.com/ Assessment http://www.itil.co.uk/online_ordering/serv_del_graphs/capacity_mngt.htm White Papers http://www.interpromusa.com/ASPs and Application Performance Mgmt.pdf http://www.iccmforum.com/iccm.asp?r=Capacity&s=CPUResource Tools http://regions.cmg.org/regions/cmgarmw/shortarm.html http://www.iccmforum.com/iccm.asp?r=Tutorial&s=Benchmarks&t=Standard http://www.iccmforum.com/iccm.asp?r=Tutorial&s=Benchmarks&t=ZiffDavis
C3: Protected
Page 175 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
15.8 Essentials (terminology) Capacity Plan, A plan that is drafted on the basis of data from the CDB, financial data, business data, technical data, etc. The plan is future oriented and looks forward for a period of at least two years. Performance Management This is the monitoring of results, signaling of trends, analysis of information and tuning (e.g. by spread of workloads). Workload Management The identification and registration of use of resources of each workload and the detection of peaks and patterns. Resource Management The optimization of the use of resources.
C3: Protected
Page 176 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
16.0 IT Service Continuity Management 16.1 Introduction
There are still quite a few managers that see IT Servi ce Continuity Management (ITSCM) as a luxury for which they do not have to allocate any resources. However, statistics show that disasters regularly occur. Causes of such disasters are events like fire, lighting, flood, burglary, vandalism, power failure or even terrorist attacks. Thinking about - and actually establishing - a Business Continuity Plan could have saved affected companies a lot of troubles or even their business itself. As businesses are becoming increasingly dependent on IT, the impact of the unavailability of IT Services has drastically increased. Every time the availability or performance of a service is reduced, the users cannot continue with their normal work. This trend towards dependency on IT will continue and will increasingly influence users, managers and decision-makers. That is why it is important, that the impact of a total or partial loss of the IT Services is estimated and Continuity Plans established to ensure that the business will always be able to continue.
C3: Protected
Page 177 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
16.2 Objective
The objective of the ITSCM process is to support the overall Business Continuity Management (BCM) process by ensuring that the required IT technical and services facilities can be recovered within required and agreed business time-scales.
C3: Protected
Page 178 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
16.3 Process Description ITSCM is concerned with managing an organization’s ability to continue to provide a pre-determined and agreed level of IT services to support the minimum business requirements, following an interruption to the business. This includes: •
Ensuring business survival by reducing the impact of a disaster or major failure.
•
Reducing the vulnerability and risk to the business by effective risk analysis and risk management.
•
Preventing the loss of Customer and User confidence.
•
Producing IT recovery plans that are integrated with and fully support the organization’s overall Business Continuity Management (BCM) Plan.
ITSCM should be closely aligned with and driven by the overall BCM process, as a sub-set of this process. BCM manages risks to ensure that the organization can continue to operate at a specified minimum level in case of a disaster. ITSCM is focused on the IT Services and ensures that the minimum of IT Services can be provided in case of disaster. One won’t work with out the other. If the BCM process has a solid plan to evacuate part of the business process and continue to work in a separate building, but there is no IT infrastructure ready, the plan is of no use. The same apply
C3: Protected
Page 179 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
if you do have plans which enable the IT organization to provided the IT Service elsewhere if the business process can’t be continued because there’s is no contingency plan in place for that.
The process can be divided in 4 stages, which will be described in the next chapter in detail: •
Initiation
•
Requirements and strategy
•
Implementation
•
Operational Management
C3: Protected
Page 180 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
16.4 Activities
Each of the stages has its own activities, which will be described in more detail throughout this chapter. Initiation •
Initiate BCM
The initiation process covers the whole of the organization. The policies around BCM and ITSCM are defined, the scope of the process and the terms of reference determined, resources allocated and a project plan established. Requirements and strategy •
Business Impact Analysis
The impact of a disaster on the business will be investigated. Questions that can be asked are: Can the business still operate in case of a disaster? For how long can it survive? Does it rely on the IT services to be able to operate? How much the organization stands to lose as a result of a disaster or other service disruption and the speed of escalation of these losses will be assess by: o
C3: Protected
Identifying the critical business processes
Page 181 of 203
Controlled copy
o
•
ITIL Foundation Level - Certification Guide
Identifying the potential damage or loss that may be caused to the organization as a result of a disruption to critical business processes.
Risk Assessment
This activity analyses the likelihood that a disaster or other serious service disruption will actually occur. This is an assessment of the level of threat and the extent to which an organization is vulnerable to that threat. Risk Assessment consists of two parts:
•
o
Risk Analysis is focused on identifying the risks by analyzing the vulnerabilities of and the threats to all critical assets.
o
Risk Management is about identifying countermeasures to keep those risks under control. These can either be actions to reduce the impact or likelihood of the risk, or the development of plans (Recovery Plans), which detail how to handle when the risk eventuates.
Business Continuity Strategy
An appropriate strategy needs to be developed with contains an optimal balance of risk reduction and recovery options. The actual balance will very much depend on the nature of the business and the dependency on IT Services (e.g. a stockbroker will focus on risk reduction, while the local bakery can probably afford the time involved in recovering a failed system).
C3: Protected
Page 182 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
In case of a Recovery Plan decisions have to made on how to recover. The options are: o
No contingency. This choice can be made if a risk analysis suggests that the failure of (a part of) the IT service delivery does not irretrievably affect business. It may be sensible however, to confirm in writing, that in case of a calamity no concrete contingency plan is available.
o
Administrative procedures. If the infrastructure is no longer available, a switch is made to administrative procedures. Disadvantage is, that when the availability of the IT infrastructure is restored a catch-up activity must be performed.
o
Fortification strategy. In this approach, one chooses a security method where, in fact, nothing can happen. The costs of such are high and if, despite this, something does go wrong, no alternatives are available.
o
Reciprocal agreements. In the case of a calamity, organizations make (parts of the) infrastructure available to each other. Disadvantage is reciprocal dependency and confidentiality of data.
o
Gradual Recovery (Cold stand-by) permanent or portable. In this strategy the organization itself has a space available with infrastructure such as electricity, telephone connections and air-conditioning, where appliances can be "brought in", after which the service level can be restored. This space could also be located or erected on site (Porto cabin).
o
Intermediate Recovery (Warm stand-by) internal/external/mobile. In this scenario a completely fitted evacuation facility is available, hired, or brought in. Examples are the Computer Evacuation Centre or the IBM truck. The last option is only feasible for mid range systems. The internal warm start means having an evacuation facility available within the organization.
o
Immediate Recovery (Hot stand-by). This is normally an extension of the Intermediate Recovery options provided by third party suppliers. This usually covers extremely critical services that can affect the survivability of the organization or, at least such an impact that would stop the organization from making money or other significant long-term effects.
Implementation •
Organization and implementation planning
Several plans need to be set up in order to be able to Implement the ITSCM process. These plans address issues like, emergency procedures, damage assessment, what to do with data, recovery plans etc.
•
Implement stand-by arrangements and risk reduction measure
The risk reduction measures need be implemented. In most cases this will be done with help of
C3: Protected
Page 183 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
the Availability process. Also stand-by procedures will have to be put in place. For example setting up an agreement with a third party to supply goods in case of a disaster without having to go through the proper channels. •
Develop ITSCM plans and procedures
The Recovery Plan (or Continuity plan) has to be set up. The plan should cover at least the following subjects:
•
o
How it is going to be updated
o
Routing list to specify which section has to go to which group?
o
Recovery initiation
o
Specialist sections to cover the actions and responsibilities of these sections individually. Sections are Administration, IT infrastructure, personnel, security, recovery sites and restoration.
Perform initial testing
Testing is a critical part of the overall ITSCM process and is the only way of ensuring that the selected strategy, stand-by arrangements, logistics, business recovery plans and procedures will work in practice. Operational Management •
Education, training and awareness
These are essential issues that need to be taken care of in order for the ITSCM process to be successful. This ensures that all staff are aware of the implications of Business Continuity and of IT Service Continuity and consider these as part of their normal working routine and budget.
•
Review and audit
It is necessary to review and audit the plans on a regular basis to make sure they are still up to date. •
Testing
By testing on a regular basis not only can the effectiveness of the plan be tested but also people will know what happens, where the plan is and what is in it. •
Change Management
Following tests and reviews and in response to day-to-day Changes, there is a need for the ITSCM plans to be updated. ITSCM must be included as part of the Change Management process to ensure that any Changes to the IT infrastructure are reflected in the contingency arrangements provided by IT or third parties. •
Assurance
C3: Protected
Page 184 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
The quality of the process is verified to assure that the business requirements can be met and that the operational management processes are working satisfactorily.
16.5 Roles A distinction can be made in roles and responsibilities in and outside crisis times. Different levels within this process can be defined, starting with the board followed by senior management, management, team leaders and their team members. It is vital to document the responsibilities of each and every role. The main responsibilities of the ITSCM manager include: •
Develop and manage the ITSCM Plan to ensure that, at all times, the recovery objectives of the business can be achieved.
•
Ensure that all IT Service areas are prepared and able to respond to an invocation of the Continuity Plans.
•
Maintain a comprehensive IT testing schedule.
•
Communicate and maintain awareness of ITSCM objectives within the business areas supported and the IT Service areas.
•
Manage the IT Service delivery during times of crisis.
16.6 Relationships ITSCM has a close relationship with all the other ITIL processes and the business in general. The relationship with some of the processes is described in more detail. Service Level Management Service Level Management provides the ITSCM process with information about the required service levels. Availability Management
Availability Management has more a supportive role and helps the ITSCM process to prevent and reduce the risk of disasters by delivering / implementing risk reduction measures.
C3: Protected
Page 185 of 203
Controlled copy
Configuration Management
ITIL Foundation Level - Certification Guide
Configuration Management provides information about Configuration Items that are needed in order to be able to restore the IT service
after a disaster. Change Management
Change Management needs to make sure that the ITSCM is aware of the impact of the Changes on the Continuity and Recovery Plans, so the plans are updated if necessary. Capacity Management Capacity Management makes sure the appropriate infrastructure can support the business requirements. Service Desk & Incident Management Service Desk in combination with Incident Management provides the ITSCM process with historical data (statistics).
C3: Protected
Page 186 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
16.7 Benefits
ITSCM supports the BCM process and delivers the required IT Infrastructure and Services to enable the business to continue to operate following a service disruption. The main benefits of implementing the ITSCM process are: •
Management of risk and the consequent reduction of the impact of failure.
•
Potentially lower insurance premiums
•
Fulfillment of mandatory or regulatory requirements
•
Improved relationships between the business and IT through IT becoming more business focused, and more aware of business impacts and priorities.
•
Increased Customer confidence, possible competitive advantage and increased organizational credibility.
In case of an actual disaster the process has the following benefits: •
Reduced business disruption, with an ability to recover services efficiently in business priority order.
•
Recovery will take place in less time
C3: Protected
Page 187 of 203
Controlled copy •
ITIL Foundation Level - Certification Guide
More stable IT infrastructure and a higher availability of the IT Services
16.8 Common Problems
A few of the problems one can encounter while implementing the ITSCM process are: •
Not enough resources to set up and run the process properly.
•
The ITSCM is not based on the BCM.
•
No enough commitment from senior IT and business management.
•
Overlooking critical components, applications, and dependencies, and misinterpreting business impacts.
•
Recovery isn’t working, due to lack of testing.
•
Lack of awareness and support of the users and the IT personnel causing the process to fail in case of a disaster.
C3: Protected
Page 188 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
16.9 Metrics During normal operation one can report on: •
The results of testing the plan
•
Costs of the process
During/after a disaster one can report on: •
Weaknesses in the plan
•
Time that it took to recover versus estimate time
C3: Protected
Page 189 of 203
Controlled copy •
ITIL Foundation Level - Certification Guide
Losses due to the disaster
16.10 Best practices Interesting websites: http://www.globalcontinuity.com/ http://www.microsoft.com/technet/itsolutions/idc/oag/oagc20.asp http://www.iccmforum.com/iccm.asp?r=Tutorial&s=Benchmarks&t=ZiffDavishttp://www.disasterrec overyworld.com/
Whitepages http://www.interpromusa.com/IT Service Continuity Mgmt.pdf
Assessment http://www.itil.co.uk/online_ordering/serv_del_graphs/itserv_cont.htm
C3: Protected
Page 190 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
16.11 Essentials (terminology) Business Continuity Management (BCM) BCM is concerned with managing risks to ensure that at all times an organization can continue operating to, at least, a pre-determined minimum level. The BCM process involves reducing the risks to an acceptable level and planning for the recovery of business processes should a risk materialize and a disruption to the business occur. IT Disaster The unavailability for a longer period of time of IT Service provision which makes in necessary to switch to an alternative system and for which the actions to be taken are not part of a daily routine. Business Recovery Plans Documents describing the roles, responsibilities and actions necessary to resume business processes following a business disruption. Disaster Recovery Planning A series of processes that focus only upon the recovery process, principally in response to physical disasters that are contained within BCM. Gradual Recovery (Cold Stand-by) This is applicable to organizations that do not need immediate restoration of business processes an can function for a period of up to 72 hours, or longer, without a re-establishment of full IT facilities. Intermediate Recovery (Warm Stand-by) Typically involves the re-establishment of the critical systems and services within a 24-72 hour period, and is used by organizations that need to recover IT facilities within a predetermined time to prevent impacts to the business process. Immediate Recovery (Hot Stand-by) Provides for the immediate restoration of services following any irrecoverable incident. Stand-by arrangements Arrangements to have available assets which have been identified, as replacements should primary assets be unavailable following a business disruption. Typically, these include accommodation, IT systems and networks, telecommunication and sometimes people. Vulnerability A weakness of the system and its assets, which could be exploited by threats.
C3: Protected
Page 191 of 203
Controlled copy
C3: Protected
ITIL Foundation Level - Certification Guide
Page 192 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
17.0 Security Management 17.1 Introduction
Everyone has heard about the impact a virus can have on a business. Names as the Kournikova virus, Nimda and the Trojan Horse does ring bells about the vulnerability of our Business and the reliability of the businesses on IT services, The following example of a different nature occurred recently in The Netherlands. A national event would take place, which would attract a lot of attention. The event was the life chat session with Prince Willem Alexander and his fiancé Maxima on the Internet. The main telecom provider in the Netherlands provided it and they bragged about how they could ensure the availability and the high performance of the event. A group of activists thought this was the time to show the country how vulnerable even the big companies are by hacking in to the systems, causing the servers to go down and so interrupting the life chat session for a period of time. In this case no harm was done but if they had bad intentions they could have easily caused a lot of damage
C3: Protected
Page 193 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
In both cases there is a risk of information being damaged or misused due to a breach in security or lack thereof. The security of Information is a key management concern in the modern, electronic business world. In order for companies to maintain their competitive edge, business decisions must be based on accurate, complete and accessible information. According to BS 7799, Security of information refers to the preservation of: Confidentiality - Ensuring that information is accessible only to those authorized to have access. ?
Integrity- Safeguarding the accuracy and completeness of information and processing methods. ?
Availability– Ensuring that authorized users have access to information and associated assets when required. ?
The degree to which these aspects are preserved must be based on the business requirements for security. This can be properly understood through accurate risk and impact analysis. Security management is concerned with addressing activities that are required to maintain risks at a manageable level.
C3: Protected
Page 194 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
17.2 Objective
The objective of Security Management is twofold: •
To ensure that it complies with the external requirements of, legislation regarding privacy, insurance policies, and the SLA’s.
•
To create a secure environment regardless of the external requirements
C3: Protected
Page 195 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
17.3 Process Description
The process of Security Management is a flexible one and needs to be reviewed continuously to ensure that it is still up to date. It therefore should, plan, do, check and act in a continuous cycle. The activities of Security Management are undertaken either by the process itself or by other processes under the control of Security Management.
C3: Protected
Page 196 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
17.4 Activities
The following activities are part of the security management process: o
Control
o
Plan
o
Implement
o
Evaluate
o
Maintenance
o
Reporting
Control In this process the basics for the Security Process are laid out. This includes among others; describing the roles and responsibilities, description of the sub processes, the Security plan and the implementation thereof and selecting the tools. Plan
C3: Protected
Page 197 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
This sub process will plan the security sections of the SLA’s with Servi ce Level Management. It also includes addressing the Security sections in the Under Pinning Contracts (UPCs) and the operational level agreements. Implement Implementation of all the security measures is the aim of this sub process. Evaluate It is necessary to evaluate the implementation of the security measures to see if they are effective. Regular audits also need to be done to ensure that the process is working efficiently en effectively. Maintenance The maintenance of the security aspects of the SLA’s and the maintenance of the security plan are the responsibilities of this sub process. Reporting Main things that will be reported are: •
Security incidents
•
Results of audits
•
Performance of security tests
•
Identification of incident trends
17.5 Roles In most cases there will be only the Security Manager however in very large organization there may be more persons involved in the process. The security manager is responsible for implementing and maintaining the process. The Security Manager has close ties with the Business Information Security officer
17.6 Relationships The Security Management process has links with all the ITIL processes. Each process carries out one or more of the activities of Security Management. Although the responsibilities for these actions are still within the separate processes Security management provides the input for the activities. Service Level Management provides information about the required service levels and receives input about the achieved levels. Configuration management: The CMDB contains the information about the C.I.’s. Every C.I. should be classified indicating the required availability, integrity and confidentiality, which will determine the level of security that is required. Incident and Problem Management: Incident Management records incidents regarding a
C3: Protected
Page 198 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
breach of security levels and the cause is investigated and resolved by Problem Management. Change Management implements the changes, which ensure security or enhance it. On the other hand they need to address the security issues for every change. In most cases the Security Manager will be part of the CAB. Availability Management is supported by Security Management in the way that the measures to increase security result in a higher availability of the IT services.
17.7 Benefits
Benefits of implementing Security management are: •
Information that is vital to the business is kept secure
•
Higher availability of the Information
•
Quality of information that goes outside the business is increased.
C3: Protected
Page 199 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
17.8 Common Problems
The following issues may cause problems: •
Commitment: extra rules and regulations are most likely to generate resistance rather than appealing to end users.
•
Attitude. Most security issues are caused by human errors. Quite often this is due to complacency.
•
Verification. It needs to be possible to check if the security measures are working if they are there for the right reasons
•
Changes. Over time the security aspect of changes might not get as much attention as is needed.
•
Awareness. As with every other process it is important to communicate with the organization to gain the cooperation of the business.
C3: Protected
Page 200 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
17.9 Metrics The metrics of this process are similar to the ones of Service Level Management but focus on the security aspect. •
Is the security aspect covered of the services in the SLA’s?
•
Do the services within the SLA’s have the necessary security aspects covered in the UPC’s and or OLA’s?
•
Is there an improvement in the Security levels?
•
Are the actual Security Levels measured?
•
Is the perception of the IT organization improving?
17.10 Best practices
http://www.securitymanagement.com/ http://www.ismanet.com/
Also....To Outsource or not to outsource? The challenge to meet security requirements, to prevent such disastrous impacts, is becoming more overbearing to organizations. Outsourcing security management could offer the solutions. The key questions faced by any organization are: ?
Should they keep the responsibilities of information security in-house?
?
Should they develop and train their own IT staff?
?
Should they develop their own security policies?
Or Should they contract such services to an outsourcing specialist who is using the latest available technology, tools and expertise to offer the most efficient service? The decision to outsource Security Management needs to be weighed carefully as this highly debatable decision has both pros and cons.
C3: Protected
Page 201 of 203
Controlled copy
ITIL Foundation Level - Certification Guide
17.11 Essentials (terminology)
Confidentiality Ensuring that information is accessible only to those authorized to have access. Integrity Safeguarding the accuracy and completeness of information and processing methods. Availability Ensuring that authorized users have access to information and associated assets when required Privacy Confidentiality and integrity of information relating to individuals Verifiability Being able to verify that the information is used correctly and that the security measures are effective.