Microwave Radio System System Optix RTN 600 Installation Acceptance Protocol
Customer:
PT Hutchison CP Telecomunications
Country / Region:
ID Station A:
ID Station B:
Inspected Date:
Inspected Date:
Provided by:
Name: Sign :
Date :
Approved by:
Name: Sign :
Date :
INDONESIA /
1. INDOOR MECHANICAL MECHANICAL ASSEMBLY Station A
Station B
Major
Yes No NA
Yes No NA 1. Does the installation material match the expected quantities on the packing lists? 2. Are all racks or sub-rack equipped in accordance with MW Link Budget?
M
2. IF OR IDU-ODU CABLES Station A Yes No NA
Station B
Major
Yes No NA 1. Are the cables installed on the cable tray/ladder and entries? 2. Are the cables correctly laid out and correctly grouped? 3. Are all cables and wires correctly terminated on the ODU? 4. Are the cable routing & bending radius according to specifications? 5. Are all connectors properly fixed and protected against linking water according to the installation specifications? 6. Are the cables labelled on both ends & at all entry/exit points?
M M
3. ELECTRICAL SUPPLY Station A Yes No NA
Station B
Major
Yes No NA 1. Is the power cables from the IDUs to the Power distribution box (PDB) properly connected? 2. Are all supply conductors correct as to polarity and earthing? 3. Is the power cable labelled on both ends & at all entry/exit points?
M M
4. ANTENNA AND ODU ASSEMBLY Station A Yes No NA
Station B
Major
Yes No NA 1. Are antenna properly accessories assembled? 2. Is the antenna mounted in the right position? 3. Is the antenna wind braced properly installed? 4. Is the horizontal and vertical polarization correct? 5. Is the ODU properly connected to the antenna? 6. Is the ODU 1+1 Kit properly connected to the antenna? 7. Is the flexible wave-guide properly laid and fastened? 8. Is the flexible wave-guide correct for the antenna diameter used?
M M M M M M
5. GROUNDING SYSTEM Station A Yes No NA
Station B
Major
Yes No NA 1. Is the IDU-ODU cable (cable entrance side) properly connected to the ground bar? 2. Is the ODU properly connected to the grounding? 3. Is the Rack properly connected to the grounding system? 4. Is the IDU properly connected to the rack ground collector?
6. E1-CABLES Station A Yes No NA
Station B
Major
Yes No NA 1. Are all cables and wires correctly terminated on racks and terminal blocks (DDF)? 2. Are all the cables properly installed and fastened?
M M
3. Are all the cables labelled properly? 4. Is 2M connection match to 2M (mux) planning?
M
7. ALARM, AUX, SERVICE AND EOW CABLES Station A Yes No NA
Station B
Major
Yes No NA 1. Is the alarm cable properly connected to the transmission rack and according to the project specifications 2. Is the AUX Service cable properly connected according to the project specifications? 3. Is the V-bus cables properly connected to the other systems according to the project specifications? 4. Is the D.ext cables properly connected to the other systems according to the project specifications? 5. Is the ETH cables properly connected to the other systems according to the project specifications? 6. Are all the cables labeled properly?
8. LINE-UP Station A Yes No NA
Station B Yes No NA 1. Are all cables and wires correctly tested?
9.SITE PHOTO CHECKLIST
Station A B MW antenna, IF spare loop and ODU labelling photos MW antenna direction and label MW antenna and ODU grounding IF cable grounding kit Front view of IDU and grounding IDU labelling E1 cable installation on DDF Power cable connection and label on MCB
Photo Attachment 1. MW antenna, IF spare loop and ODU labelling photos on Site A and B
Major
2. MW antenna direction and label on Site A and B
3.
MW antenna and ODU grounding on Site A and B
4. IF cable grounding kit on Site A and B
5.
Front view of IDU and grounding on Site A and B
6. IDU Labelling on Site A and B
7. E1 cable installation on DDF on Site A and B
8.
Power cable connection and label on MCB on Site A and B
Thank you for interesting in our services. We are a non-profit group that run this website to share documents. We need your help to maintenance this website.