Nominate on Subcontractors NDT% Form amount and type of NDT required. i.e PT/MT or UT/RT - Construction code acceptance criteria shall be SPEC 000-S-0011 on all NATA NDT testing reports
Verify & accept by signing section 4.6 of this ITP Verify & accept by signing section 4.6 of this ITP
Responsibility ST EX SC
Storeman Inspection/Expeditor Sub-Contractor
Inspection & Test Plan
Contract No. XXXXXXX ITP Number XXXX XXXXX
Authorised: XXXXX XXXXX Date: XXX XXX XXX
Piping Fabrication No.
Operation Document Number
Standard, Spec or Drawing
Verifying Document/ Report
Response .
Workshop Fabricator
Fabricato r
Client
Inspection
Remarks
3.14
Record welding traceability information
AS4041
Not Report
WF/QC
R
M
M
3.15
Final dimensional check
AS4041
AFC Dwg
WF/Ex
V/D/M
M
M
AS4041
This ITP
WF/QC
V
M
M
H
R
W
Punch list
M
M
M
Engineering Drawing marked in red pen NDT Reports
R
R
H
R
R
Ex/PE Ex/PE
M H
M H/W
M M
PE/Ex
H/R
H/R
R
Ex Ex
M H/R
M M
M M/R
4.0
Inspection and Testing
4.1
All Welds 100% Visual
4.2
NDE as per AS4041 • 5% RT and MPI for Class 2A Piping • Exempt for Class 3 Piping
Project Quality Plan
4.3
Pipework marking and identification correct
4.4
Mark up drawings as built as necessary
4.5
Veryify NDT% has been completed
5.0 5.1 5.2
6.0
(May be used as a sign off column by xxxxxxxxxxx or the Client to indicate that the activity has been satisfactorily completed)
Verify & Accept by signing section 4.1 of this ITP
NATA Report Engineering Drawings
AS 4041
Final Inspection Inspect delivery dockets to ensure that they record every item Final inspection and release
Project Quality Plan
AS4041
Project Management Plan
AS4041 AFC Drwgs P. O./ Scope
This ITP
Verify & Accept by signing section 5.2 of this ITP
Delivery
6.1
Ensure that all inspections and tests are completed, all reports and documentation are available and all results comply with requirements
6.2 6.3
Check tagging/marking is in place, correct and secure Check Delivery Docket completed and forwarded to projects office
Every item shall be marked and listed on the Delivery Docket
Responsibility ST EX SC
Storeman Inspection/Expeditor Sub-Contractor
Inspection & Test Plan
Contract No. XXXXXXX ITP Number XXXX XXXXX
Authorised: XXXXX XXXXX Date: XXX XXX XXX
Piping Fabrication No.
Operation Document Number
6.4
6.5
6.6
7.0 7.1
Ensure that all items are loaded with sufficient dunnaging to allow safe transport and unloading and prevent damage to material and surface coatings Weights and dimensions of the load shall comply with statutory requirements. Compliance is the responsibility of the approved transport contractor Deliver product and documentation to nominated location
Standard, Spec or Drawing
Verifying Document/ Report
Inspection
Remarks
Response .
Workshop Fabricator
Fabricato r
Client
Ex
M
M
M
Ex
M
M
M
Contract/ Purchase Order
D/Dkt
Ex/PE
R
R
R
AS4041 SEP.70
MDR Records
PE/QC
R
R
R/H
(May be used as a sign off column by xxxxxxxxxxx or the Client to indicate that the activity has been satisfactorily completed)