Inception Report

December 27, 2017 | Author: animesh91 | Category: Transport, Road Transport, Science, Geology, Nature
Share Embed Donate


Short Description

ROB Inception report...

Description

Ministry of Road Transport & Highways Government of India

CONSULTANCY SERVICES FOR PREPARATION OF DETAILED PROJECT REPORT FOR CONSTRUCTION OF PROPOSED ROB & ITS APPROACH ON NH-60 NEAR KM 193.800 (LC GATE NO. 39/A/3E) IN STATE OF WEST BENGAL

INCEPTION REPORT FEBRUARY - 2015

Chaitanya Projects Consultancy Pvt. Ltd 2nd Floor, Plot No. 21-22, R.K.Tower, Sector-4, Vaishali, Ghaziabad – 201010 Ph: - 0120-4120472, Fax: - 0120-4110472 Email:[email protected]

Ministry of Road Transport & Highways, Regional Office, Kolkata Project: DPR for proposed ROB on NH-60 near Km 193.8 (LC Gate no. 39/A/3E) Document: 2015/P-109/IR/TOC Table of Contents

Sheet: i of 36 Date: February 2015 Revision: R0

Table of Contents Table of Contents.............................................................................................................................................. i 0.0 EXECUTIVE SUMMARY ............................................................................................................................... 3 0.1 0.2 0.3 0.4 0.5 0.6

Introduction ................................................................................................3 Project Background .......................................................................................3 Project Appreciation ..................................................................................... 3 Methodology .......................................................................................... 3 Mobilisation and work programme .................................................................. 3 Quality Assurance Plan .................................................................................. 4

1.0 INTRODUCTION ......................................................................................................................................... 5 1.1 1.2 1.3 1.4 1.5 1.6

General ......................................................................................................5 Commissioning of Consultant ..........................................................................5 Objectives of Consultancy ..............................................................................5 Scope of Services ..........................................................................................6 Deliverables ................................................................................................7 Current Submission: Inception Report ...............................................................7

2.0 PROJECT BACKGROUND ............................................................................................................................ 8 2.1 2.2

State Profile ................................................................................................8 Roads ......................................................................................................9

3.0 PROJECT APPRECIATION .......................................................................................................................... 10 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10

General Setting of the Project ....................................................................... 10 Location ................................................................................................... 10 Climate .................................................................................................... 11 Land use ................................................................................................... 11 Terrain Classification ................................................................................... 11 Geography ................................................................................................ 11 Existing Road features ................................................................................. 12 Existing Railway Crossing.............................................................................. 12 Existing Rail features ................................................................................... 12 Clearances required .................................................................................... 12

4.0 DETAILED METHODOLOGY ...................................................................................................................... 13 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 4.9 4.10

General .................................................................................................... 13 Collection and Review of available Data .......................................................... 13 Reconnaissance Survey ................................................................................ 13 Socio-economic Profile ................................................................................ 13 Site visit.................................................................................................... 14 Exploration and Testing for Construction Materials............................................ 14 Geo-Technical Investigations......................................................................... 15 Design of Bridges and Structures ................................................................... 16 Technical Specifications ............................................................................... 16 Rate Analysis and Cost Estimates ................................................................... 17

Ministry of Road Transport & Highways, Regional Office, Kolkata Project: DPR for proposed ROB on NH-60 near Km 193.8 (LC Gate no. 39/A/3E) Document: 2015/P-109/IR/TOC Table of Contents

Sheet: ii of 36 Date: February 2015 Revision: R0

4.12 Bid Documents........................................................................................... 18 5.0 MOBILIZATION AND WORK PROGRAMME .............................................................................................. 19 5.1 5.2 5.3 5.4

General ........................................................................................ 19 Project Team Organization ........................................................................... 19 Work Programme ....................................................................................... 20 Mobilization and Submission schedules........................................................... 20

6.0 QUALITY ASSURANCE PLAN ..................................................................................................................... 22 6.1 6.2 6.3 6.4 6.5 6.6 6.7 6.8 6.9

General ........................................................................................ 22 Quality Goals and Objectives......................................................................... 22 Concepts of Quality Assurance ...................................................................... 22 Purpose of the QAP..................................................................................... 22 Elements of Quality Assurance Systems........................................................... 22 Approach & Methodology ............................................................................ 23 Team of Experts ........................................................................................ 28 Quality Assurance Cell ................................................................................. 28 Quality Assurance Methodology .................................................................... 28

7.0 ALIGNMENT OPTIONS .............................................................................................................................. 31 7.1 7.2 7.3 7.4

Fixing Alignment option ............................................................................... 31 Site Photographs ........................................................................................ 31 Matrix Comparison ..................................................................................... 34 Cross-section near ROB location .................................................................... 35

LIST OF ANNEXURES a)

Annexure-1:

Work Programme………………………………………………………………….21

Ministry of Road Transport & Highways, Regional Office, Kolkata Project: DPR for proposed ROB on NH-60 near Km 193.8 (LC Gate no. 39/A/3E) Document: 2015/P-109/IR/Chap.-0.0 Executive Summary

Sheet: 3 of 36 Date: February 2015 Revision: R0

0.0 EXECUTIVE SUMMARY 0.1

Introduction

0.1.2 The proposed ROB is to be constructed near Km 193.8 of NH-60 in the state of West Bengal. After construction of the ROB, the need of the level crossing at the location would be eliminated, thus ensuring a smooth traffic movement on the highway. The nearest railway station from the level crossing location is Bishnupur. The concerned railway authority for level crossing is Eastern Railway (Howrah Division). The proposed ROB would be a part of NH-60. HN-60 starts from NH-5 at Balasore district of Odisha and ends at NH-34 in Morgram district of West Bengal; crossing cities of Jaleswar, Dantan, Belda, Narayanpur, Kharagpur, Medinipur, Salboni, Durllabhganj, Bishnupur, Bankura, Gangajalghati, Mejia and Raniganj, Pandaveshwar, Dubrajpur, Suri, Deucha, Mollarpur, Rampurhat, Nalhati. The Consultancy services for Project Preparation have been entrusted to M/s. Chaitanya Projects Consultancy Pvt. Ltd. 0.2

Project Background

0.2.1 The Department of Road Transport & Highways, Government of India intends to undertake construction of ROB in lieu of the existing level crossing (LC Gate No.: 39/A/3E). 0.3

Project Appreciation

0.3.1 Near the project location, there is a manned level crossing. The nearby land use comprise of habitation and agriculture as seen from preliminary reconnaissance. 0.3.2 The Detailed project appreciation report is given in chapter-3.0 0.4

Methodology

0.4.1 Based on an in-depth study of the scope of services contained in the Terms of Reference (TOR) for the project, a detailed reconnaissance made along the project road and previous experience with similar projects successfully completed in India, the Consultant has evolved a methodology wherein the entire work, has been divided into different activities as described in Chapter-4.0. 0.4.2 Engineering Design is itself a dynamic evolution of concepts based on a detailed study of different inter-related aspects. The approach formulated by the Consultant gives flexibility to the methodology and any modification of any item(s) in the scope of services can be easily and efficiently adjusted to suit the requirements. 0.5

Mobilisation and work programme

0.5.1 The Letter of acceptance (LOA) for the assignment was issued by Superintending Engineer (B)-S&R on 09.09.2014 and the agreement has been signed on 28.11.2014. The Consultant has mobilized the Team on 5th December, 2014 to carry out the Reconnaissance Survey of the project site. During the reconnaissance survey, the

Ministry of Road Transport & Highways, Regional Office, Kolkata Project: DPR for proposed ROB on NH-60 near Km 193.8 (LC Gate no. 39/A/3E) Document: 2015/P-109/IR/Chap.-0.0 Executive Summary

Sheet: 4 of 36 Date: February 2015 Revision: R0

Consultant has collected available relevant data from WBPWD for the project road. The Consultant has also studied the available maps & other secondary data of project area. 0.5.2 Work program is given as Annexure-1 after Chapter-5. 0.6

Quality Assurance Plan

0.6.1 Quality Assurance (QA) refers to the operational activities put in place to control the quality of the service. These include such activities as providing clear decisions and directions, constant supervision by experienced individuals, immediate review of completed activities for accuracy and completeness, and accurate documentation of all decisions, assumptions, and recommendations. 0.6.2 Quality control procedures, if followed, should ensure that the work is done correctly the first time. Essentially, QA is what is done to confirm that a QC program is effective and provides feedback upon which further development of the QC program can be made.

Ministry of Road Transport & Highways, Regional Office, Kolkata Project: DPR for proposed ROB on NH-60 near Km 193.8 (LC Gate no. 39/A/3E) Document: 2015/P-109/IR/Chap.-1.0 Introduction

Sheet: 5 of 36 Date: February 2015 Revision: R0

1.0 INTRODU CTION 1.1 General 1.1.1 Ministry of Road Transport & Highways desires to convert all Level Crossings on National Highways to ROBs/RUBs in a phased manner in time bound period. Under this scheme, MORT&H desires to convert the level crossing (LC Gate No.: 39/A/3E) at Km 193.8 of NH60 to ROB to ensure free and safer movement of traffic on the highway, with enhanced safety features. 1.1.2 The level crossing is manned having a TVU of 36000 as on May, 2010. The Consultancy services for Project Preparation have been entrusted to M/s. Chaitanya Projects Consultancy Pvt. Ltd. 1.2 Commissioning of Consultant 1.2.1 The Letter of acceptance (LOA) for the assignment was issued by Superintending Engineer (B)-S&R on 09.09.2014 and the agreement has been signed on 28.11.2014. The Consultant has mobilized the Team on 5th December, 2014 to carry out the Reconnaissance Survey of the project site. During the reconnaissance survey, the Consultant has collected available relevant data from WBPWD for the project road. The Consultant has also studied the available maps & other secondary data of project area. 1.2.2 After initial understanding of the project, the Consultants have prepared the Inception Report, which includes initial project appraisal, alignment options and the work plan for carrying out all activities for project preparation, approach and methodology. 1.3 Objectives of Consultancy 1.3.1 The main objective of consultancy service is to establish technical, environmental, social, economic, and financial viability of the project and prepare Detailed Project Report for proposed ROB in lieu of existing level crossing. The location of the proposed ROB has to be decided based upon various aspects like land availability, cross slope of the country and railway line features. 1.3.2 The viability of the project shall be established taking into account the requirements with regard to rehabilitation, upgrading and improvement based on ROB design, pavement design, quantities of various items of works and cost estimates and economic analysis. 1.3.3 The Detailed Project Report would inter-alia include detailed design of ROB structure and cross drainage structures, design of approach/solid embankment, quantities of various items, detailed working drawings, detailed cost estimates, environmental and social feasibility, social and environmental action plans as appropriate and documents required for tendering the project on commercial basis for international / local competitive bidding.

Ministry of Road Transport & Highways, Regional Office, Kolkata Project: DPR for proposed ROB on NH-60 near Km 193.8 (LC Gate no. 39/A/3E) Document: 2015/P-109/IR/Chap.-1.0 Introduction

1.4

Sheet: 6 of 36 Date: February 2015 Revision: R0

Scope of Services Scope of consultancy services includes following major tasks i.

Prioritization based on traffic and it’s financial viability;

ii.

Review of all available reports and published information about the project ROB and the project influence area;

iii.

Detailed reconnaissance;

iv.

Identification of possible improvements in the existing alignment with evaluation of different alternatives and proposal of best suited alignment/geometric for proposed ROB;

v.

Inventory and condition surveys of existing approach Road;

vi.

Inventory and detailed condition surveys for cross drainage structures in approaches alignment of proposed Major Bridge and drainage provisions;

vii.

Topographic surveys using Total Stations as per guide lines of latest IRC SP-19. Fixing of TBM (connected to GTS Bench Mark) and all reference Point on Ground during survey and should be clearly shown on detailed survey drawings.

viii. Geotechnical Investigation work for proposed Major Bridge as per guide lines of latest IRC SP-19 and IRC 78. ix.

Preparation of Alignment Option Study Report & General Arrangement Drawing for approval of concerned authorities.

x.

Finalization of GAD of proposed ROB and submission to Employer for Approval of GAD by Railway Authorities. The Consultant will have to interact with Railway Authorities on technical issue during approval of GAD by Railway Authority. However, during the process of approval of GAD, the required P&E charges shall be paid by the employer

xi.

Preparation of GAD for construction of proposed ROB and its approaches (in accordance with approved GAD by Railway Authorities), plan and profile of approach road as per guidelines of relevant IRC Codes, IS Codes and IRS Codes.

xii.

On case to case basis the consultant is supposed to provide required schedules as per EPC/BOT document.

xiii. Preparation of Tentative Cost Estimate strictly as per Ministry’s Data Book. xiv. Obtaining approval from MORT&H. xv.

At the time of bidding the Consultant will be required to provide updation of cost estimate and tender document. The time of bidding may be even after the completion of the Consultancy contract.

Ministry of Road Transport & Highways, Regional Office, Kolkata Project: DPR for proposed ROB on NH-60 near Km 193.8 (LC Gate no. 39/A/3E) Document: 2015/P-109/IR/Chap.-1.0 Introduction

1.5

Deliverables Stage 1: Inception report with alignment options Stage 2:

Prioritization of Level Crossings

Stage 3(a):

Survey, Investigation and Preparation of GAD

Stage 3(b):

Draft Detailed Project Report

Stage 4:

Complete Detailed Project Report

 1.6

Sheet: 7 of 36 Date: February 2015 Revision: R0

As per minutes of meeting held on 21/11/2014 in chamber of SE(B)-S&R, Jeevan Tara Building, New Delhi.

Current Submission: Inception Report This inception reports consists of following chapters:-

0.0

Executive Summary

1.0

Introduction

2.0

Project Background

3.0

Project Appreciation

4.0

Detailed Methodology

5.0

Mobilization and Work Program

6.0

Quality Assurance Plan (QAP)

7.0

Alignment Options

Ministry of Road Transport & Highways, Regional Office, Kolkata Project: DPR for proposed ROB on NH-60 near Km 193.8 (LC Gate no. 39/A/3E) Document: 2015/P-109/IR/Chap.-2.0 Project Background

Sheet: 8 of 36 Date: February 2015 Revision: R0

2.0 PROJECT BACKGROUND 2.1

State Profile

2.1.1 The name West Bengal stands as a misnomer for the first timers as the state is actually located in the east of India. Having 9.1crores inhabitants, it is the fourth-most populous state in the country bordered by countries of Bangladesh, Nepal and Bhutan and the Indian states of Odisha, Jharkhand, Bihar, Sikkim and Assam. A major agricultural producer, West Bengal is the sixth largest contributor to India’s net domestic product. 2.1.2 West Bengal also boasts of rich flora and fauna having 15 wildlife sanctuaries and 5 national parks. Sundarban National Park a mangrove forest area in the Ganges delta which has been declared a biosphere reserve is one of the largest reserves for Royal Bengal Tiger. It also houses wide variety of bird, reptile and invertebrate species. 2.1.3 The proposed ROB lies in the Bishnupur town of Bankura district. It is also referred to as Mallabhum after the Malla rulers of this place who ruled during 17th and 18th century. Bishnupur is famous for its terracotta temples built by the Malla rulers. These temples are the best specimen of the classical style of Bengal architecture. Royal patronage in the region also gave rise to Bishnupur Gharana (school) of Hindustani Classical music in the late 18th century and the Bishnupur School of painting. The Bishnupur Gharana is rooted to Dhrupad style of music. Bishnupur is mostly plain land lying 59m above MSL. 2.1.4 There are many temples in this region which stand testimony to the exquisite craftsmanship of the artisans of the region. The temples were crafted from the local laterite and brick and covered with terracotta tiles depicting scenes from the epic Mahabharatha. Apart from the temples, terracotta pottery, artefacts and even jewellery made in this very traditional material is famous. The most famous of the terracotta products are the handmade beautiful jars, disks, horses, elephants, Ganesha and Nataraj. The potters here derive their inspiration from the glorious history of kings, soldiers and wars. Bishnupur is also known for its silk, particularly the Baluchari sarees. Bellmetalware, conch-shell and terracotta jewelry is also available here.

Ministry of Road Transport & Highways, Regional Office, Kolkata Project: DPR for proposed ROB on NH-60 near Km 193.8 (LC Gate no. 39/A/3E) Document: 2015/P-109/IR/Chap.-2.0 Project Background

2.2

Sheet: 9 of 36 Date: February 2015 Revision: R0

Roads

2.2.1 Roads are the lifeline of the people for transportation of goods and passengers and provide linkage in the inaccessible terrains. NH-60 connects to Bankura district towards north-west of Bishnupur and Garhbeta town towards south of Bishnupur.

Ministry of Road Transport & Highways, Regional Office, Kolkata Project: DPR for proposed ROB on NH-60 near Km 193.8 (LC Gate no. 39/A/3E) Document: 2015/P-109/IR/Chap.-3.0 Project Appreciation

Sheet: 10 of 36 Date: February 2015 Revision: R0

3.0 PROJECT APPRECIATION 3.1

General Setting of the Project

3.1.1 The proposed ROB would be located near the existing level crossing at chainage Km 193.8 of NH-60 depending upon feasibility of alignment options as mentioned further in this report. The existing level crossing is manned gate (LC Gate no. 39/A/3E) having TVU of 36000 as on May, 2010. 3.2

Location

3.2.1 The Location map of site is shown below:

PROJECT LOCATION

Level Crossing

Fig 3.1: Location Map of the Project Area

Ministry of Road Transport & Highways, Regional Office, Kolkata Project: DPR for proposed ROB on NH-60 near Km 193.8 (LC Gate no. 39/A/3E) Document: 2015/P-109/IR/Chap.-3.0 Project Appreciation

3.3

Sheet: 11 of 36 Date: February 2015 Revision: R0

Climate

3.3.1 The climate, especially in the upland tracts to the west, is much drier than in eastern or southern Bengal. From the beginning of March to early June, when the monsoon sets in, hot westerly winds prevail, the thermometer in the shade rising to around 45 °C. The westerly winds die down around sunset and allow cool winds to blow from the south. Nor'westers are frequent during this period and help to mitigate the excessive heat. 3.3.2 The monsoon months, June to September, are comparatively pleasant, as the weather is not as sultry as in other parts of Bengal. The total average rainfall is 1400mm, the bulk of the rain coming in the months of June to September. 3.3.3 Winters are pleasant with temperatures dropping down to below 27 °C in December. 3.4

Land use

3.4.1 Most of the land near the vicinity of project location is agricultural land or forest land. 3.5

Terrain Classification

3.5.1 The nature of terrain near the project location is plain in nature. 3.6

Geography

3.6.1 Bankura district has been described as the connecting link between the plains of Bengal on the east and Chhota Nagpur plateau on the west. The areas to the east and north-east are low lying alluvial plains, similar to predominating rice lands of Bengal. To the west the surface gradually rises, giving way to undulating country, interspersed with rocky hillocks. Much of the country is covered with jungles. 3.6.2 The area consists of two different tracts. The western portion marks the gradual descent from the table land of Chhota Nagpur to the delta of lower Bengal, consisting largely of spurs projecting from the western tableland and of low swelling ridges. However, there is no marked ridge of hills. In the central portion of the district there are rolling downs eventually merging with the alluvial plains. 3.6.3 The western part of the district has poor, ferruginous soil and hard beds of laterite with scrub jungles and sal woods. Long broken ridges with irregular patches of more recent alluvium have marks of seasonal cultivation. During the long dry season large extents of red soil with hardly any trees lend the country a scorched and dreary appearance. In the eastern part the eye constantly rests on wide expanses of rice fields, green in the rains but parched and dry in summer. 3.6.4 The rivers of the area flow from the north-east to the south-west in courses roughly parallel to one another. They are mostly hill streams, originating in the hills in the west. The rivers come down in floods after heavy rains and subside as rapidly as they rise. In summer, their sand beds are almost always dry. 3.6.5 The greater portion of the district consists of a rolling country covered by laterite and alluvium. While metamorphic or gneissose rocks are found to the extreme west, to the east there is a wide plain of recent alluvium. Strong massive runs of hornblendic varieties

Ministry of Road Transport & Highways, Regional Office, Kolkata Project: DPR for proposed ROB on NH-60 near Km 193.8 (LC Gate no. 39/A/3E) Document: 2015/P-109/IR/Chap.-3.0 Project Appreciation

Sheet: 12 of 36 Date: February 2015 Revision: R0

stretch across the region in tolerably continuous lines, the general strike being nearly east and west. 3.6.6 The most characteristic geological feature of the district is the area of laterite and associated rocks of sand and gravel. At some places one finds hard beds of laterite. At other places it is decomposed and reorganized. Locally, the ferruginous rock is called kankar. The calcareous concretions, commonly used as the sources of lime, are known as ghutin. 3.7

Existing Road features The terrain at the project location is plain in nature. NH-60 at the project location consists of two lane carriageway having flexible pavement.

3.8

Existing Railway Crossing The level crossing at the project location is manned LC having a TVU of 36000 as on May, 2010. Approximately, 2 trains cross the said LC on a daily basis as per the data collected from railway cabin log book.

3.9

Existing Rail features Rail line lies approximately at level with the existing natural ground level. The cabin of level crossing lies on left side of the road. There is one rail line at the LC connecting Bishnupur station on one side to Birshamunda Halt on other side. Bishnupur railway station is located near to the level crossing.

3.10

Clearances required

3.10.1 From the initial reconnaissance it is observed that the proposed ROB may pass through adjoining forest area. The consultant would carry out consultation with various departments that would be involved in the project. 3.10.2 From the above it is inferred that the clearances from the following departments may be required for the project, however, the required clearances shall be confirmed after all the data are collected and the alignment is fixed. a)

Department of State Electricity Board

b)

Indian Railways

c)

West Bengal PWD

Ministry of Road Transport & Highways, Regional Office, Kolkata Project: DPR for proposed ROB on NH-60 near Km 193.8 (LC Gate no. 39/A/3E) Document: 2015/P-109/IR/Chap.-4.0 Detailed Methodology

4.0 4.1

Sheet: 13 of 36 Date: February 2015 Revision: R0

DETAILED METHOD OLOGY

General

4.1.1 For successful and efficient rendering of services, the Consultant proposes to take a sound engineering approach based on a clear understanding of the Terms of Reference and the relevant planning and systems approach. 4.2

Collection and Review of available Data

4.2.1 The secondary data requirements are broadly classified under the following major groups:

4.3



General Data



Socio-economic profile (State and project Influence Area)



Relevant Study Reports



Development Schemes in the Project Influence Area



Relevant Documents on design, construction and maintenance of bridges



Transport Characteristics and Vehicle Operating Costs



Accident records



Geological and soil maps; and

Reconnaissance Survey

4.3.1 The Consultant has carried out a preliminary field reconnaissance of the Project ROB. The aim of this preliminary reconnaissance was to familiarize the Team members with the project site. Potential locations for feasible bridge options were also identified. 4.3.2 The Consultant has reviewed all the collected data from secondary sources and the data collected during preliminary reconnaissance survey. 4.4

Socio-economic Profile

4.4.1 Review of Development Plan- The construction of the proposed ROB would greatly reduce the existing traffic problems near level crossing due to gate closures and also provide enhanced safety. The development plans, future and on-going, for the state in general and for the project influence area in particular, would be collected and studied so as to make an assessment of the impact of implementation of the project on demand for traffic and on the growth of economy. 4.4.2 Preparation of Socio-Economic Profile - The data on demography, economy, development plans, transportation system, road development plan, vehicle fleet, expenditure on the construction and maintenance of roads, road taxes, transport industry and accidents would be ascertained.

Ministry of Road Transport & Highways, Regional Office, Kolkata Project: DPR for proposed ROB on NH-60 near Km 193.8 (LC Gate no. 39/A/3E) Document: 2015/P-109/IR/Chap.-4.0 Detailed Methodology

Sheet: 14 of 36 Date: February 2015 Revision: R0

4.5 Site visit 4.5.1 To obtain the features of the existing LC like habitation and its nature, land use of the area, TVU, location of LC cabin etc. site visit would be done. 4.6

Exploration and Testing for Construction Materials

4.6.1 Exploration and testing for construction materials will cover:     

borrow areas for normal fill and embankment; natural gravel (for sub-base); hard stone (for crushed aggregate base, asphalt surfacing courses and concrete); sand (for concrete) and, Water for construction.

4.6.2 Potential sources for the construction material will be identified for the whole stretch. The testing for borrow areas for ascertaining their suitability as Subgrade and fill materials will include:    

identification tests (grain size and Atterberg’s Limits); organic matter content (if deemed necessary); moisture-density characteristics); and, CBR and swell.

4.6.3 Gravel: - Gravel quarries will be investigated and tested in the laboratory to establish their soundness and engineering characteristics. Each quarry located will be explored in order to identify suitable sources of sub-base material. The testing on gravel samples will include:  identification (grain size and Atterberg’s Limits);  sand equivalent (if deemed necessary);  natural moisture content;  density - moisture content relationships (modified proctor); and, 4-day soaked CBR. 4.6.4 Hard stones: - The investigations for hard stones will comprise qualitative and quantitative assessment of potential quarries and to determine their suitability for use in:  graded crushed stone base and sub-base;  chippings for surface dressing layers;  asphalt base and wearing courses; and,  concrete works. 4.6.5 The potential sources of hard stones identified on the basis of desk study of geological maps and information collected from the reconnaissance of the area will be thoroughly investigated during this task. The sources of hard stone in the area will be identified and sampled, as far as possible, within the economic hauling distance. 4.6.6 Stone samples: - The testing of hard stone samples for ascertaining their suitability in road construction and concrete works will include:

Ministry of Road Transport & Highways, Regional Office, Kolkata Project: DPR for proposed ROB on NH-60 near Km 193.8 (LC Gate no. 39/A/3E) Document: 2015/P-109/IR/Chap.-4.0 Detailed Methodology

       

Sheet: 15 of 36 Date: February 2015 Revision: R0

specific gravity; water absorption; flakiness index (for crushed aggregates from existing crushing plants); Los Angeles Abrasion Value (LA V); aggregate impact value (AIV)); bitumen affinity and stripping value; chemical tests (total soluble salts, chloride content, sulphate content, alkali-silica reaction); and, sodium sulphate soundness;

4.6.7 Sand: - Potential sources of sand will be identified. The testing for sand samples in the laboratory will include:   

grain size analysis; sand equivalent; and, chemical tests (sulphate and chloride).

4.6.8 Each potential borrow area and source will be assigned a unique code number for easy reference. For potential hard stone quarries, the Consultant will also suggest quarrying method based on engineering geology. 4.7

Geo-Technical Investigations

4.7.1 The consultant shall submit the detailed proposal for geotechnical investigation after the approval of Alignment and GAD submitted during the Feasibility Study. After approval of the same, the consultant shall start the geotechnical investigation for the ROB. Detailed Geotechnical and sub-surface investigations conforming to the established standards and as deemed necessary, will be carried out at proposed ROB location and high embankments locations (where required). The sub-soil exploration investigations will also be used for span arrangement for bridges. The data of particular importance for the design of structures include:    

soil profile; foundation stratum; Strength characteristics; safe bearing capacity;



Rock stratum.

4.7.2 The strength of soil layers will be evaluated in the field using SPT tests. The laboratory testing of soil samples will include:    

soil characterization (grain size distribution and Atterberg Limits); moisture content, natural density and chemical tests; shear strength parameters; and, Consolidation parameters.

Ministry of Road Transport & Highways, Regional Office, Kolkata Project: DPR for proposed ROB on NH-60 near Km 193.8 (LC Gate no. 39/A/3E) Document: 2015/P-109/IR/Chap.-4.0 Detailed Methodology

Sheet: 16 of 36 Date: February 2015 Revision: R0

4.7.3 The geological investigations will be preceded by a detailed study of engineering geology and also seismological information for the area. The project area fall under seismic zoneV. The parameters for design will be selected after careful consideration of the engineering strength values and geological information. The investigations for high embankment (where required) will be carried out as per IRC special specifications No.75. For major bridges, the boreholes will be investigated under each foundation.

4.8

Design of Bridges and Structures

4.8.1 The scope of services covered in TOR indicates that General Arrangement Drawings have to be prepared and the same will be done in accordance to design standards, the relevant IRC and Bureau of Indian Standards Codes: The following types of loading would generally be considered while evolving GAD      

dead load; superimposed dead loads; live loads (two lanes of class –A or one lane of class 70 R for each carriageway); seismic load; temperature loads; and wind load

4.8.2 The bridges will be designed for the live loading which gives the worst effect at the point under consideration. Appropriate relationships for earth pressure effects will be taken into consideration. The coefficients for active and passive earth pressure will be calculated based on properties of soil used for backfilling behind abutments and wing walls. The type of foundations, either open or caissons will be decided taking into consideration, the properties of soil and the type of foundations for the nearby structures. 4.9

Technical Specifications

4.10.1 The Technical Specifications in accordance with which the entire work described in Bid Document shall be constructed and completed by the Contractor shall comprise of the following: PART-I: General Technical Specifications The General Technical Specifications shall be the "SPECIFICATIONS FOR ROAD AND BRIDGE WORKS (LATEST REVISION)” issued by the Ministry of Road Transport and Highways, and published by the Indian Roads Congress with all up-to-date amendments issued by Ministry of Road Transport and Highways (MORT&H). In the absence of any definite provisions on any particular issue in the aforesaid Specifications, reference may be made to the latest codes and specifications of IRC, IS, BS and AASHTO in that order. Where even these are silent, the construction and completion of the works shall conform to sound engineering practice as approved by the Engineer

Ministry of Road Transport & Highways, Regional Office, Kolkata Project: DPR for proposed ROB on NH-60 near Km 193.8 (LC Gate no. 39/A/3E) Document: 2015/P-109/IR/Chap.-4.0 Detailed Methodology

Sheet: 17 of 36 Date: February 2015 Revision: R0

and in case of any dispute arising out of the interpretation of the above, the decision of the Engineer shall be final and binding on the Contractor. 4.10

Rate Analysis and Cost Estimates

4.11.1 The unit rates for different items of works will be analyzed based on the Standard Data Book by MoRTH and survey conducted by the Consultant and the relevant data collected from the Client and the concerned departments in the construction and maintenance of roads in the area. While working out the unit rates, the inputs of man (labour), material and machine will be computed and considered. The basic rates worked out for the study will be compared with those obtained in other similar projects and recently completed/ awarded/ on-going construction and maintenance works in the area. 4.11.2 Quantities Based on the designs and drawings, a bill of quantities will be prepared by the Consultant as under:  preliminary and general items;  site clearance and earthworks;  road furniture;  ancillary works; and,  Miscellaneous items of works. 4.11.3 Construction Costs The costs for construction of the proposed bridge will be worked out on the basis of design proposals. The item-wise construction costs will be computed using the bill of quantities derived from the designs, drawings and specifications and the unit rates worked out. The construction costs will also include the costs of ancillary works and diversion works necessary for traffic movement during the construction of works. 4.11.4 Maintenance Cost Based on the study on the prevailing standards in the country and also standards adopted elsewhere, the maintenance treatment type and the intervention criteria most appropriate for the Project Road will be recommended by the Consultant. Consultants’s experience in this regard gained through detailed engineering and maintenance management studies carried out in India will be immensely helpful in selecting the most appropriate and cost-effective maintenance treatment and policy. The maintenance treatment and intervention criteria will be finalised in consultation with the Client. The costs will be worked out on the basis of unit rates and the quantities of maintenance treatments (routine recurrent and periodic surface renewals) anticipated during the design life.

Ministry of Road Transport & Highways, Regional Office, Kolkata Project: DPR for proposed ROB on NH-60 near Km 193.8 (LC Gate no. 39/A/3E) Document: 2015/P-109/IR/Chap.-4.0 Detailed Methodology

4.12

Sheet: 18 of 36 Date: February 2015 Revision: R0

Bid Documents

4.12.1 The draft international competitive bidding (ICB) documents will be prepared by the consultant, based on the sample bidding documents as agreed by the MoRT&H. The tender documents will be prepared as stipulated in the TOR. The first stage will cover the commercial documentation including:  

Instruction to bidders; General conditions of contract;

  

Special conditions of contract; Outline of BOQ ;and Schedule for additional information like formats for bank guarantee, contract agreement etc.:

Ministry of Road Transport & Highways, Regional Office, Kolkata Project: DPR for proposed ROB on NH-60 near Km 193.8 (LC Gate no. 39/A/3E) Document: 2015/P-109/IR/Chap.-5.0 Mobilization and Work Programme

Sheet: 19 of 36 Date: February 2015 Revision: R0

5.0 MOBILIZATION AND WOR K PROGRAMME 5.1

General

5.1.1 The Letter of acceptance (LOA) for the assignment was issued by Superintending Engineer (B)-S&R on 09.09.2014 and the agreement has been signed on 28.11.2014. The Consultant has mobilized the Team on 5th December, 2014 to carry out the Reconnaissance Survey of the project site. During the reconnaissance survey, the Consultant has collected available relevant data from WBPWD for the project. The Consultant has also studied the available maps & other secondary data of project area. 5.2

Project Team Organization

5.2.1 The Consultant has drawn professionals from a pool of several eminent engineers with extensive experience and proven track record in the field of planning, programming, field studies and investigations, detailed design and preparation of tender documents for major highway projects. While selecting the personnel, due considerations have been given not only to the tasks to be carried out during the proposed assignment of experts but also the desirability of the expert being fully familiar with the similar ground situations in the project area.

THE TEAM COMPOSITION

Sr. Highway Engineer cum Team Leader Mr. S.K.Sinha

Bridge Engineer

Mr. Omkar Verma

Material cum Geotech/Foundation Engineer Mr. Amod Thakur

Sr. Survey Expert

Traffic Engineer

Md. Aboo Asif

Mr. Jitendra Jain

Financial Analyst Mr. Rahul Arora

Ministry of Road Transport & Highways, Regional Office, Kolkata Project: DPR for proposed ROB on NH-60 near Km 193.8 (LC Gate no. 39/A/3E) Document: 2015/P-109/IR/Chap.-5.0 Mobilization and Work Programme

Sheet: 20 of 36 Date: February 2015 Revision: R0

5.2.2 Support Staff: SI. No.

5.3

Name

Position

Task Assignment

1.

Neeraj Kr. Sinha

Asst. Highway Engineer

Responsible for all field design and documentation activities and timely completion of study

2.

Mohd. Salik

Asst. Bridge Engineer

Responsible for all field investigation related to design of bridgesand other structures

3.

Abhishek Gupta

Asst. Traffic Engineer

Responsible for traffic survey and data analysis

4.

Animesh Dutta

Asst. Material Engineer

5.

Shadab Ahmed

Asst. Survey Engineer

6.

Prakash Shukla

Draughtsman-I

Responsible for drawings in AutoCAD

7.

Parminder Kaur

Draughtsman-II

Responsible for drawings in AutoCAD

8.

Khushi

Draughtsman-III

Responsible for drawings in AutoCAD

Responsible for material investigation Responsible for topographical survey

Work Programme As Enclosed in Annexure- 1 (At the end of this chapter)

5.4

Mobilization and Submission schedules

5.4.1 The following activities have been planned for preparation of Draft Project Report (DPR). The schedule is also attached herewith SI. No.

Activity

i) Alignment options & inception report ii) Prioritization of Level crossings

Submission February, 2015 March, 2015

Survey/Investigation and preparation of GAD of proposed ROB including it's iii) approaches for approval by Railway authorities

September, 2015

GAD and final report for construction of proposed ROB & it's approaches iv) alonwith schedules as per EPC/BOT document

May, 2016

NH Planning & Design Division-I, P.W. (Roads) Directorate, Govt. of West Bengal Project: DPR for proposed ROB on NH-60 near Km 193.8 (LC Gate no. 39/A/3E) Document: 2015/P-113/IR/Chap.-5.0 Mobilization and Work Programme

Sheet: 21 of 36 Date: February 2015 Revision: R0

Annexure-1: Work Programme (Refer to Para 5.3)

Ministry of Road Transport & Highways, Regional Office, Kolkata Project: DPR for proposed ROB on NH-60 near Km 193.8 (LC Gate no. 39/A/3E) Document: 2015/P-109/IR/Chap.-6.0 Quality Assurance Plan

Sheet: 22 of 36 Date: February 2015 Revision: R0

6.0 QUALITY ASSURANCE PLAN 6.1

General The prime objective of the management of Chaitanya Projects Consultancy Pvt. Ltd (CPCPL) an ISO 9001:2008 Certified Company is to provide services in a manner, which conforms to the contractual and regulatory requirements. In order to achieve this objective, it is the policy of CPCPL to maintain and implement an efficient and effective Quality Assurance Plan (QAP) with the full commitment of management for its ongoing vitality and relevance. Determination and conformance of our firm’s work to requirements is verified on the basis of objective evidence of quality.

6.2

Quality Goals and Objectives The objective of quality assurance is the continual improvement of the total delivery process to enhance quality and client satisfaction. Essentially, quality assurance describes the process of enforcing quality control standards. When quality assurance is wellimplemented, progressive improvement in terms of both reducing errors and omissions and increasing project usability and performance should be noted. Quality assurance should function as a "voice" for the client who expects a certain level of quality to be provided.

6.3

Concepts of Quality Assurance Quality Assurance (QA) refers to the operational activities put in place to control the quality of the service. These include such activities as providing clear decisions and directions, constant supervision by experienced individuals, immediate review of completed activities for accuracy and completeness, and accurate documentation of all decisions, assumptions, and recommendations.

6.4

Purpose of the QAP Quality control procedures, if followed, should ensure that the work is done correctly the first time. Essentially, QA is what is done to confirm that a QC program is effective and provides feedback upon which further development of the QC program can be made.

6.5

Elements of Quality Assurance Systems CPCPL has documented the QAP and shall maintain the same as a means of providing a design product that conforms to specified requirements.

6.5.1 Quality Plan Procedures - All work to be performed on the project shall be as defined by the appropriate personnel of the Consultant. The key personnel of the project team shall determine the technical effort and schedule required for the completion of the project. 6.5.2 Quality Audit - CPCPL shall be responsible for in-house auditing of the implementation and conformance of the QAP. This may be done by way of periodic project audits. Spot checks, interviews with staff, or other means as determined by the key personnel of the project team.

Ministry of Road Transport & Highways, Regional Office, Kolkata Project: DPR for proposed ROB on NH-60 near Km 193.8 (LC Gate no. 39/A/3E) Document: 2015/P-109/IR/Chap.-6.0 Quality Assurance Plan

6.6

Sheet: 23 of 36 Date: February 2015 Revision: R0

Approach & Methodology

6.6.1 Project Schedule Control - With the Inception Report, CPCPL shall update the Contract Activity Schedule as required and shall develop a detailed Project Activity Schedule. The Schedule shall depict the time periods allotted to perform the individual project activities. The Project Activity Schedule shall be updated as required and shall be used as a reference throughout the duration of the project. Communications and status meetings with the sub- consultants shall also provide input to the Project Activity Schedule. Project activities shall be tracked against this schedule, which shall provide early identification of possible Schedule Exceptions. This type of early warning shall allow the consultant’s time to redistribute project resources to offset potential project delays or, where a potential delay is due to events beyond the consultant’s control, to notify the MoRT&H as soon as possible of the potential for schedule changes. 6.6.2 Project Progress Monitoring and Reporting - The Consultants shall be responsible for reporting progress in terms of milestones, deliverables, and/or other units of measurements. The Consultant shall submit the following in addition to QAP: Stage 1:

Inception report with alignment options

Stage 2:

Prioritization of Level Crossings

Stage 3(a):

Survey, Investigation and Preparation of GAD

Stage 3(b):

Draft Detailed Project Report

Stage 4:

Complete Detailed Project Report

6.6.3 Traffic Survey - The Traffic Survey shall be conducted in conformance with the requirement of the Project. 6.6.4 Topographical Survey Data - For topographical survey work total station shall be used to collect the topographical survey. Auto CAD -2010 software shall be used for registering topographic survey data and plotting of topographic maps. The details of all-important physical features along the alignment shall be collected. These include buildings & Structures, monuments, burial grounds, places of worship, railway lines, streams /rivers/canals, water mains, sewers, gas/ oil pipes, crossings, trees plantations, utility services such as electric and telephone lines (O/H &U/G), OFC in conformance with the TOR. 6.6.5 Soil Investigation - Consultant shall thoroughly investigate the soil at desired locations of the proposed ROB in order to determine the sub-strata characteristics and to define the design parameters. The subsoil investigation for bridges /structures and high embankments will be carried out. Its findings shall define the depth and bearing capacity of sub-strata for foundations. The investigation results for high embankment shall define design parameters for long term settlement of high embankment, stability of slopes for embankments and cut

Ministry of Road Transport & Highways, Regional Office, Kolkata Project: DPR for proposed ROB on NH-60 near Km 193.8 (LC Gate no. 39/A/3E) Document: 2015/P-109/IR/Chap.-6.0 Quality Assurance Plan

Sheet: 24 of 36 Date: February 2015 Revision: R0

sections and replacement of compressible layer(s), if any. Similar investigation shall be conducted for landslide prone areas, if any. 6.6.6 Studies and Reports - The Consultant shall establish the procedures for developing studies and reports in conformance with the TOR. The Consultant shall also write the reports / studies himself as required. The studies and reports required for the projects shall be as stated in the contract agreement. The objective of the reports /studies shall be established in Inception Report to complement those defined in the TOR. These shall be re-evaluated during the course of studies. Calculations and drawings required for the development of the reports /studies shall be prepared in accordance with the Quality Assurance Procedures. The purpose of Quality Assurance Review shall be to assure that the reports’ objectives have been met; the report is comprehensive and up-to-date with respect to scope, approaches, design criteria, assumptions, theories and conclusions. The Consultant shall resolve any problems by the QA Review. 6.6.7 Calculations - Calculations shall be organized in a logical manner with sufficient notes such that a person technically qualified in the subject can review and understand the calculations and verify the adequacy of the results without clarification from the originator. Results of calculations shall be clearly identified and superseded/voided calculation shall be marked as such. The originator shall check to see that results of a design are adequately reflected in the documents. The Consultant shall ensure that all the calculations and revisions are subjected to a QA review and shall include but not be limited to the following: 

Purpose of Calculation



Assumptions



Input Data with Sources



Design Methods or Theories



Design Criteria and Applicable Codes



Conclusions and



References

The calculations shall be checked by Senior Engineers to assure that all work intended to be covered by the calculation have been performed. The calculations shall also be examined for the following:  Purpose of Calculation has been clearly identified, 

Approach is satisfactory,



Most Current Design Criteria and Codes have been used,

Ministry of Road Transport & Highways, Regional Office, Kolkata Project: DPR for proposed ROB on NH-60 near Km 193.8 (LC Gate no. 39/A/3E) Document: 2015/P-109/IR/Chap.-6.0 Quality Assurance Plan

Sheet: 25 of 36 Date: February 2015 Revision: R0



Assumptions are clearly identified and are reasonable,



Design methods are consistent with accepted practice,



Mathematics are correct and accurate, and results are reasonable based on engineering judgment and comparison with previous solutions to similar problems,



Computer Programs used are applicable for the problem being solved,



Calculations are legible and suitable for the reproduction and filling,



Superseded and voided calculations are so noted, etc.

Conception, design criteria and the assumptions and conclusions for ROB and Structure shall be reviewed jointly by the experts of the consultant. The Sr. Engineer shall control arithmetical correctness and conformity of drawings with design calculation. The reviewer shall record all comments and shall indicate which calculations were found to be satisfactory and which were found to be unsatisfactory. The reviewer shall also record his review of the calculations by initialing the “checked by” space on each sheet. The reviewed calculations with comments shall be given to the key personnel, who shall resolve any problems revealed by the reviewer. 6.6.8 Drawings - Drawings shall be prepared and reviewed specifying the characteristic elements, which, if properly constructed, shall produce a product, which is consistent with the design objective. The Consultant shall assign the responsibility for preparing drawings to the key personnel and shall ensure that they have the proper information. The key personnel of the project team shall conduct frequent review of drawings to assure that proper standards and formats are being utilized in their preparation. The Senior Experts shall be responsible for checking drawings for the following: 

Compliance with the design requirements and codes,



Dimensional accuracy and consistency with design,



Sufficient dimensions and staging for constructability,



Material specifications referenced in design incorporated into drawings,



Previous comments to check prints have been incorporated into completed drawing,



Drawings incorporate design elements of the supporting engineering disciplines, etc.

The reviewer shall give the checked prints to the key personnel, who shall resolve any problems identified in the review. The drawings shall then be revised to satisfaction of the key personnel. In addition to periodic quality assurance reviews, CPCPL shall schedule at critical times during the design and sufficiently in advance of submissions, specific quality and construct ability reviews. These reviews shall be performed based on design level

Ministry of Road Transport & Highways, Regional Office, Kolkata Project: DPR for proposed ROB on NH-60 near Km 193.8 (LC Gate no. 39/A/3E) Document: 2015/P-109/IR/Chap.-6.0 Quality Assurance Plan

Sheet: 26 of 36 Date: February 2015 Revision: R0

reached to ensure compliance with design criteria and construct ability. The key personnel of the project team shall review Quality Assurance comments. 6.6.10 Specifications - The team leader and the Key Personnel shall jointly prepare the supplementary specifications to the current edition. The Consultant shall review the specifications and ensure all elements are expanded and modified as necessary to reflect the particulars of the project. 6.6.11 CAD Control - Drawing files shall be stored on the CAD system and shall be appropriately named and layered in accordance with the CAD standard manual. The CAD data shall be backed up systematically on a separate system to safeguard against a network failure. 6.6.12 Design Changes - All design deviations and modifications from the standards shall be identified, documented and reviewed. These shall be reported to the M/oTR&H for approval prior to their implementation.

6.6.13 Document Control 6.6.13.1 Document and Data Approval and Issue - It shall be the Consultants responsibility to verify that all the reports have been reviewed prior to their submittal. 6.6.13.2 Document and Data Changes - The review and approval of changes to document and data after the first issue of the documents shall be the responsibility of the Consultant. Document changes made subsequent to a QA review shall require another QA review. 6.6.13.3 Design Product Identification and Trace ability - The project file index shall identify the location of potential design product such as design calculation, bill of quantities, specifications, reference drawings and original drawings. These books and file drawers shall be clearly labeled with the project name. For identification, all manually generated design documents shall be marked with the project number and name and filed with all the design phase related documents. Electronically generated documents such as CAD files and design program files shall be stored on the master file of the project directory. These files shall be backed up rightly. For long-term storage, all hard copies of the project documents shall be catalogued and filed in secured location, so that the same can be retrieved easily. MoRT&H supplied materials shall be itemized, the date received noted and filed with the project reference materials. 6.6.13.4 Process Control - This QA program has been developed to assure that the project assignment is carried out in planned, controlled and correct manner. Controlled conditions include the following:  CPCPL provides suitable design equipment and a suitable working environment,

Ministry of Road Transport & Highways, Regional Office, Kolkata Project: DPR for proposed ROB on NH-60 near Km 193.8 (LC Gate no. 39/A/3E) Document: 2015/P-109/IR/Chap.-6.0 Quality Assurance Plan

Sheet: 27 of 36 Date: February 2015 Revision: R0

 MoRT&H approved procedures and standards defining design to be used,  Any exceptional report and subsequently reviews are approved by MoRT&H,  CPCPL shall ensure compliance with reference to QA plans and  CPCPL shall carefully monitor and control suitable process parameters and end product characteristics. 6.6.13.5 Control of Compliance with QAP - A successful QAP requires that all project participants implement the segments of the QAP, which shall apply to their work task. The key personnel shall provide direct daily oversight to the engineers and CAD operators in their disciplines. 6.6.13.6 Control of Noncompliance - In addition to the above measures, the reviewers shall provide a written description of the areas of noncompliance. These areas shall be discussed with the key personnel team leader and the employer, MoRT&H if necessary and the method of resolution shall be doted on the written description of areas of noncompliance. 6.6.13.7 Client Changes - Upon receipt of MoRT&H review comments to a submittal, CPCPL shall document written comments and comments received at review meetings. Responses to the review comments shall be formulated and filed in the project file, “Review comments and Responses.” The Consultant shall determine the cause by review of design criteria and minutes of meetings. Where necessary, new and additional calculations shall be performed and plans shall be revised. When the corrected actions have been taken, a QA review shall be performed to ensure compliance. The review of the noncompliance shall identify the cause and, if it is found to be the result of poor procedural practice, measures to eliminate reoccurrence of the practice such as more training shall be developed. These revised QAP procedures shall then be issued to all the members of the project team. 6.6.13.8 Control of Quality Records - Sufficient documentation and records shall be accumulated to provide objective evidence that the design development and review process has been performed in accordance with good engineering practice, in conformance with contractual requirements and according to M/o RT & Hs direction. The documentation shall include but not limited to design documents such as drawings, studies, reports, design calculations, communications, instructions and directives which have a direct bearing on the project. The subcontractor appointed if any shall be required to maintain their quality records and, as requested by Consultants, copies shall be provided to CPCPL. The quality record shall be stored with the project documents for the duration identified in the Consultancy Contract Agreement.

Ministry of Road Transport & Highways, Regional Office, Kolkata Project: DPR for proposed ROB on NH-60 near Km 193.8 (LC Gate no. 39/A/3E) Document: 2015/P-109/IR/Chap.-6.0 Quality Assurance Plan

6.7

6.8

Sheet: 28 of 36 Date: February 2015 Revision: R0

Team of Experts SI. No.

Name

Position

1.

Mr. S.K.Sinha

Sr. Highway Engineer cum Team Leader

2

Mr. Jitendra Jain

3.

Mr. Amod Thakur

4.

Mohd. Aboo Asif

Traffic Engineer Material cum Geotech/Foundation Engineer Sr. Survey Expert

5.

Mr. Omkar Verma

Bridge Engineer

6.

Mr. Rahul Arora

Financial Analyst

Quality Assurance Cell

6.8.1 Quality Assurance (QA) Review Team will have a primary point of contact with the Team Leader. Review team will include representatives from all appropriate disciplines or specialty areas appropriate for the project that will be reviewed. For example, the Bridge Engineer may be asked to coordinate a review of bridges and the Traffic Engineer may be asked to coordinate a review of traffic & safety aspects of the project. There shall be a review co-ordinator who would co-ordinate the entire review process. The review coordinator will be from the Technical Services staff. Field/ Project Region staff may also be tasked to review projects occasionally. The coordinator and review team will be selected based on expertise and to reflect the dominant disciplines in the project. 6.9 Quality Assurance Methodology 6.9.1 The Team Leader is responsible to ensure that Project assignments are implemented in accordance with the Consultancy Contract Agreement, to make available any resource and coordinate as necessary for the successful completion of the project. He also monitors managerial activities; overall progress of the project, general conformance to established office procedures, and specific Employer’s requirements. 6.9.2 The Project Manager designated for the Project shall interact directly with the employer, M/oRT&H. They shall discuss the QAP with the Employer and get the same approved after incorporating their suggestions /comments. CPCPL shall ensure adherence to the approved QAP. CPCPL shall be responsible for all technical and administrative aspects of the project, for establishing and maintaining the control necessary to ensure completion of assignment on time to the satisfaction of the M/oRT&H. CPCPL shall work closely with the MoRT&H to ensure that the project goals are met. CPCPL shall also organize the specific assignments in terms of sequence of work, the type and number of people required for each phase, and the timing at which various tasks are to be started and completed. The key personnel (defined in the Consultancy Contract) are the task leaders for their respective technical and administrative aspects related to their discipline. They are responsible for the direct supervision of all technical and administrative aspects related to address the issues, compile the deliverable documents. CPCPL shall ensure

Ministry of Road Transport & Highways, Regional Office, Kolkata Project: DPR for proposed ROB on NH-60 near Km 193.8 (LC Gate no. 39/A/3E) Document: 2015/P-109/IR/Chap.-6.0 Quality Assurance Plan

Sheet: 29 of 36 Date: February 2015 Revision: R0

that, the Sub-Consultant’s work shall be submitted with ample time to incorporate it into the contractual submissions. CPCPL personnel shall ensure that they as envisaged in the contract are exercising proper checks on quality, which is over and above the contractual obligations.

Ministry of Road Transport & Highways, Regional Office, Kolkata Project: DPR for proposed ROB on NH-60 near Km 193.8 (LC Gate no. 39/A/3E) Document: 2015/P-109/IR/Chap.-7.0 Alignment Options

Sheet: 30 of 36 Date: February 2015 Revision: R0

PROJECT PROCEDURE DOCUMENT CHART 

BASIC INPUT/ DATA TRANSFER & INTER-ACTION (Survey Maps, Sub-soil Data, Site Map, Concept Designs) INITIAL

Field Engineers

FINAL

Bridge Engineer

Team Leader

Process Dwgs/Docs.

Final

REVIEW REVIEW

 INTER-DISCIPLINE INPUT DATA AND DRAWINGS & DOCUMENT

BRIDGE ENGINEER OR TEAM LEADER

Asstt. Engineers & Draughtsman REVIEW Final

Initial

TRANSFER AND INTER-ACTION:

Initial

Discipline Engineer: (BE/TE/ SSE/GME/EE/R&R/QS); OR,

Initial

 DRAWINGS & DOCUMENTS TRANSFER (DISCIPLINES – T.L. – CLIENT): FINAL

Team Leader

DESIGN ENGINEERS Final

Review

WWw

Issue Final Dwgs. & Documents

Ministry of Road Transport & Highways, Regional Office, Kolkata Project: DPR for proposed ROB on NH-60 near Km 193.8 (LC Gate no. 39/A/3E) Document: 2015/P-109/IR/Chap.-7.0 Alignment Options

Sheet: 31 of 36 Date: February 2015 Revision: R0

7.0 ALIGNMENT OPTIONS 7.1

Fixing Alignment option After reconnaissance survey at site and discussion held with local people, alignment options have been worked out for the purpose of ROB at Km 193.800. These alignment options have been shown on satellite image in Fig. 7.1.

7.2

Site Photographs

TVU of LC KM stone: NH-60

Level Crossing: View-1

LC Cabin

Level Crossing: View-2

Ministry of Road Transport & Highways, Regional Office, Kolkata Project: DPR for proposed ROB on NH-60 near Km 193.8 (LC Gate no. 39/A/3E) Document: 2015/P-109/IR/Chap.-7.0 Alignment Options

Sheet: 32 of 36 Date: February 2015 Revision: R0

Option-1

Option-2

Fig.- 7.1: Alignment options for ROB

Ministry of Road Transport & Highways, Regional Office, Kolkata Project: DPR for proposed ROB on NH-60 near Km 193.8 (LC Gate no. 39/A/3E) Document: 2015/P-109/IR/Chap.-7.0 Alignment Options

Sheet: 33 of 36 Date: February 2015 Revision: R0

Option 1

Existing Road

Railway cabin

Option 2

Fig.- 7.2: Details near Level Crossing

Ministry of Road Transport & Highways, Regional Office, Kolkata Project: DPR for proposed ROB on NH-60 near Km 193.8 (LC Gate no. 39/A/3E) Document: 2015/P-109/IR/Chap.-7.0 Alignment Options

7.3

Matrix Comparison Parameter

Length of ROB

Option-1

Option-2

Length of RE wall

80m

85m

Length of structure

525m

540m

Length of railway span

32m

40m

NIL

1

2

2

Length of Approach

No. of demolitions No. of horizontal curves Geometrics

Recommendation



Sheet: 34 of 36 Date: February 2015 Revision: R0



Radii of horizontal curves

1 curve having radius of 200m  1 curve having radius of 250m This option is recommended as it avoids the demolition of a major building

 

1 curve having radius of 200m 1 curve having radius of 200m NA

The approach for the ROB would consist of reinforced earth wall up to a height of 6m from natural ground level. After that, approach would consist of structural elements.

Ministry of Road Transport & Highways, Regional Office, Kolkata Project: DPR for proposed ROB on NH-60 near Km 193.8 (LC Gate no. 39/A/3E) Document: 2015/P-109/IR/Chap.-7.0 Alignment Options

7.4

Cross-section near ROB location Typical cross-section for proposed ROB and its service road is as shown below:

Sheet: 35 of 36 Date: February 2015 Revision: R0

View more...

Comments

Copyright ©2017 KUPDF Inc.
SUPPORT KUPDF