Idamalayar Hydro Electric Project
Short Description
Download Idamalayar Hydro Electric Project...
Description
Draft tube with Circular Inlet & Rectangular Outlet. Increase in
net head by establishing a negative head at theturbine outlet Converts a large proportion of ke rejected at the outlet into pressure energy Without a draft tube, the pressure at the outlet of the turbine will be equal to the atm pressure. Draft tube increases efficiency
Excitor
DC System
at Idamalayar Power Station A 220V dc system for the Units & 110kV Feeders A 110V dc system for the 66kV IMKM feeder A 48V dc system for the PLCC systems A 24V dc system for the 11kV OD CBs
Unit Auxiliary Transformers The
name plate details
of
Maker: National Electrical - 630kVA, 11000/433V, 53.1/840A
the
UATs
Industries
- 3Ø
- S/N: RY2692/1(UAT 2), RY2692/3(Standby)
1),
RY2692/2(UAT
- Type
of
Cooling:
SN,
Frequency:
- Impedance:
4.86%, Vector Group:DYn11
- Tap
Changing:
Off
Load
Core and
Winding:
of
596kg, Total Weight:
- Weight:
1270kg
- Weight
Oil:
2578kg,
Year: 1980, Tmax: 45°C
50Hz
Unit
Auxiliary
Transformers
The
name
plate
details
- Maker:
National
Electrical
Industries
- 630kVA,
11000/433V,
53.1/840A
of
the
- 3Ø
- S/N:
RY2692/1(UAT
1),
RY2692/2(UAT
2), RY2692/3(Standby)
- Type
of
Cooling:
SN,
Frequency:
50Hz
- Impedance:
4.86%,
Vector
Group:
DYn11
- Tap
Changing:
Off
Load
- Weight:
Core
and
Winding:
1270kg
- Weight
of
Oil:
596kg,
Total
2578kg,
Year:
1980,
Tmax:
45°C
Weight:
UATs
LA-SC Cubicle
-Station Arrestor & Surge Capacitor
Generator Breakers
- Closing Time - Opening Time - Dead Time
Generator Breakers
- Closing Time - Opening Time - Dead Time
Generator Breakers
- Closing Time - Opening Time - Dead Time
Generator CTs
- Duct CTs - No of Cores and Spec.
Generator PTs
Generator PTs
IMMA Line PTs
IMMA Line CTs
IMMA Line Breakers
IMMA Line Breakers
Lighting Arrestors for GTs
- LA Gradings - Insulation Coordination of Equipments at a
power station - Necessity
Lighting Arrestors for GTs
- LA Gradings - Insulation Coordination of Equipments at a
power station - Necessity
•
Lightning Arrestors for IMMA
Generator Isolators
- Isolators in General - Current Carrying Capacity
Generator Isolators
- Isolators in General - Current Carrying Capacity
•
Line Isolators Bus Coupler Isolator
- No CB here
for Coupling/ Decoupling operations - This results in generation loss that could ve been
avoided. Bus Coupler Isolator
110/66kV Transformer
110/66kV Transformer
110/66kV Transformer
Breakers for HT Side of 110kV Side
Breakers for LT Side of 66kV Side
•
Bus PTs for 66kV Bus
•
Bus PTs for 11kV Bus
Incomer 1 Transformer 66/11kV
Incomer 2 Transformer 66/11kV
Open fuses on the HT side of the Incomers
Dam/Colony and Chakkimedu 11kV Feeders
Dam/Colony and Chakkimedu 11kV Feeders
EOT Crane in Service Bay
Earth
Mat in
the
Yard
EOT Crane in Main Store
EOT Crane in Valve House
Protections:
-
Of
the
Machine
-
Of
the
Feeders
-
Of
the
Transformers
-
Start/Stop
Sequence
-
Relays
for
Fire
Protection
Systems
-
CO2
-
the
Start/Stop
sequencing
Flooding
System
for
Generator
Stator
Water
Deluge
system
for
the
GTs
-
CO2
portable
cylinders
-
AFFF
portable
cylinders
-
DCP
portable
cylinders
-
Cooling
Systems
in
place:
-
Oil TGB
Heat
Exchangers
at
UGB,
LGB,
TB
-
Surface
Air
Coolers
for
the
Generator
Stator
-
Uses the reservoir which pumping
Penstock is results method.
bleeding large in
than the and the an affordable loss
pumping head compared
method is to
Lubrication: units Servomotors, Guide vane Pump:
serves bushings
lubrication etc.
needs
of
the
Works
with from
the the
Ventury
principle,
clears
the
water
TGB's
shaft
seal
side
Shaft
Sealing:
Why
not
Pelton
for
medium
and
high
heads?
and
since small, the
CGLU
Ejector
leakage
Filtering
Units
pumps
-
redundancy
HP/LP
Air
Compressor
Systems
-
Redundancy
Drainage
Pit Leakage
Water
Pump Leakage
Oil
Pump
Leakage
Oil
Collector
under
bearings
Pumps
for
removing
the
leakage
Measurement
/
Instrumentation
System:
-
Condition
Monitoring
-
RTDs/TSDs
for
temp
-
Rotor
temp
measurement
-
Permit
to
Work
on
-
AVR
-
Thyristor
Panels
-
Redundancy
-
Regulation
Cubicle
Oil
OPUs
OPU
AOT
oil
from
these
measurement
-
Machines/Feeders/Other
Equipments
collectors
CBs Operation SF6
Air
Blast
Vacuum
Air
Spirng/Air
for
Close
/
Open
Thrust
bearing Beaing
pads
Russian
design
-
Pin
type
(Kingsbury
Pins)
Semi
Umbrella
advantage
-
Minimization
of
Iron
cost
Mattress
type
pads
HPOP
system
Jacking
Up
of
Rotor
-
Necessity
-
Min
Continous
Operating
Speed
Thrust
Braking
Brake
Pads up
while stopping
position
below
rotor,
lifts
the
rotor
Saves
the increased friction
babbitting during
from the
getting slow
damaged speeds
due
to
the
Power
Transformer & Transformer
Distribution
Tests Meggering PI IR PD CT Secondary
for
a
Open situation while
Capacitor Banks -
Functions
Turbine
Mode/Condenser mode
-
no
issue
Startup
Normal Spin Generator Generator
Spinning Reserve?
Shutdown
Modes:
Controlled Action
Shutdown
-
Initiated turbine
under
non
urgent
mechanical/electrical
faults
of
&
generator
-
Once initiated vanes/jets
this which results to
signal in the
is the no
received, closing load
governer of values
stop the
is guide
-
GCB control) If trip failed.
is Guide in Goes
opened vanes preset to Emergency
(Nothing is dont close/GCB time, Controlled Action SHutdown
mentioned and Shutdown
abt FB is
Excitation dont considered
-
Initiated
when
the
controlled
action
shutdown
fails
-
Initiated
usually
under
electrical
&
mechanical
faults
-
Operates simultaneously
the
Emergency
Closing
Valve
&
GCB
-
Guidevanes/Jets
are
closed
very
fast
-
FB opened.
tripping
is
done
once
the
GCB
is
-
If trip
Guide in
vanes preset
dont close/GCB time, Catastrophic Shutdown
and is
FB initiated
dont
listed happen
Catastrophic
Shutdown
-
Initiated when a condition arises
catastrophic
-
Or Controlled Action/Emergency SHutdown program fails
-
Commands given to simulataneously close MIV, to Open Emergency
View more...
Comments