UEC-MSP-001 Rev.: 00 / 05-09-2013 Author: Ong-Art S. Factory AVP

1

Sample of Visual in excel

Author: Ong-Art S. Factory AVP

2

Guide line  This article is to explain Project Management Concept as a quick reference through step by step guidance using MS Project 2013  The targeted audience is a beginner to the project management and experienced with MS Project in early version, such 2007 or 2010

Author: Ong-Art S. Factory AVP

3

Table of Contents 1. 2. 3. 4. 5. 6. 7. 8. 9.

Start Project Plan the Tasks Assign resources Project Baseline set up Update progress Forecast Information Step by Step to S-Curve Step by Step Export Data to Excel (Visual Report) Close Project

Author: Ong-Art S. Factory AVP

4

Step-1: Start Project  Prior to start the project planning, Project manager should be identified, who can set up a project plan in MS project 2013 1. Create a new Project File

Author: Ong-Art S. Factory AVP

To create a new blank project in Project, click the file tab. Click new

5

Step-1: Start Project 2. Set project start date

Author: Ong-Art S. Factory AVP

Go to Project tab. Click Project information

6

Step-1: Start Project 3. Define Project Calendar

Author: Ong-Art S. Factory AVP

Go to Project tab. Click Change Working time

7

Step-1: Start Project 4. Save the Project file

Author: Ong-Art S. Factory AVP

Go to Tab file, select save as with Project Name or Job Order running number

8

Step-2: Plan the Tasks  In the planning stage, we need to achieved project’s goals. To do this, we have to identify the project’s milestone, deliverables and tasks.  This plan can be use work breakdown structure (WBS).

Author: Ong-Art S. Factory AVP

9

Step-2: Plan the Tasks 1. Enter Task

Author: Ong-Art S. Factory AVP

Click View tab. In the Task View groups, click Gantt Chart. In the Task Name fields, enter tasks.

10

Step-2: Plan the Tasks 2. Decide how you want to Schedule Task

Author: Ong-Art S. Factory AVP

In Project 2013, we can schedule tasks manually or automatically. Select schedule method after enter a new tasks by clicking in the Task Mode column:Note: New Tasks manually set by default in Option Tab

11

Step-2: Plan the Tasks 3. Outline Tasks

Author: Ong-Art S. Factory AVP

Create task hierarchy including tasks and milestones under summary task, which can be represent phase or other work divisions. Click the Task tab. In the Schedule group select Indent or Outdent button • Tip: if you created a summary task with duration, start or finish date, then the tasks that fall under the summary task will not be rolled up to this summary tasks.

12

Step-2: Plan the Tasks 4. Enter Durations Click the Duration field for a task and enter a Duration. Two way to entering a duration: Mutually Schedule task  A number or text like “Tomorrow” or “Next after roll shell” etc.  Auto Schedule task  Number only, 3d=3 Days, 0d=milestone, 6? is an estimate duration. Note: Both can selected in the Task Mode Author: Ong-Art S. Factory AVP

13

Step-2: Plan the Tasks 5. Link Tasks to show relationships

Author: Ong-Art S. Factory AVP

Click the Task tab, in the View Group click Gantt Chart. Select the tasks that you want to link then click the Link Tasks button in the Schedule group, or move a mouse to bar chart press and drack down to tasks that you want to link. To change the default Finish-to-Start (FS), double click the link line and change.

14

Step-3: Assign Resources  Assignments are the associations between specific tasks and the resources needed to completed them. We can assign more than one resources to a tasks.  We can assign work resources (People), material (pipe/shell etc.) and cost (THB) to tasks.

Author: Ong-Art S. Factory AVP

15

Step-3: Assign Resources 1. Add Resources Click the Task Tab, in the Views dropdown to Project list select Resources Sheet. In the Resources Name filed, type the name of resources that we’ll use in this project.

Author: Ong-Art S. Factory AVP

16

Step-3: Assign Resources 2. Assign Resources to Tasks

Author: Ong-Art S. Factory AVP

In the Resources Tab, Click Assign Resources the click resources name then click assign

17

Step-3: Assign Resources 3. Enter the Work After assign a resources to the Tasks, work Hours spending hours automatically show in a Work. If PM on Tasks prefer control a Working hours, it can be change in in Work Field. Entering Work reflects real world scheduling. Go to Gantt Chart, right click on column then click Insert Columns type "WORK” to select the Work Columns

Author: Ong-Art S. Factory AVP

18

Step-3: Assign Resources 4. Know the Work After Assign a resources to Tasks, MS Tasks Type Project determine how to schedule the tasks based on the tasks type.(Manually tasks don’t use task type) durations may change as we assign resources to tasks. How tasks types work Work, duration and unit are determined by formula:Work =Duration x Units

Author: Ong-Art S. Factory AVP

19

Step-3: Assign Resources In a…

If we revised Work

If we revised Duration

If we revised units

Fixed units tasks

Duration changes

Work changes

Duration changes

Fixed work tasks

Duration changes

Units change

Duration changes

Fixed duration tasks

Units change

Work changes

Work changes

 To set a default task type for the entire project, click the options. Go to Schedule group, in the default task type box shown fixed units as a default, we can change to Fixed Duration or Fixed Work  To change the task type for an individual, go to tasks tab in properties group click information or to tasks name double click it will appear. Author: Ong-Art S. Factory AVP

20

Step-3: Assign Resources 5. Identify factors We can use MS Project 2013 to help for effecting task understanding how changes one task can schedules effect the rest of the project. Click the task tab then in the Schedule group click Inspect Task. A pane opens on the left showing the factors that affect the scheduling of selected task. Or double click in tasks name.

Author: Ong-Art S. Factory AVP

21

Step-4: Set the Project Baseline  Create a baseline or interim plan is to compare between plan and actual.  Saving baseline plan enables to identify and solve discrepancy and plan more accurately for similar future projects.

Author: Ong-Art S. Factory AVP

22

Step-4: Set the Project Base Line 1. Save the baseline plan

Author: Ong-Art S. Factory AVP

After the plan is solidly in place for the finish date, budget and scope, we can submit a plan for approval. Once it has been approved, save the baseline plan. Click the Project tab, in Schedule group click Set Baseline

23

Step-4: Set the Project Base Line 2.View baseline data in Gantt Chart views Name Base Plan (Custom)

In Gantt chart view, move a mouse to gantt area, right click and select Bar Style.

Appearance Select bar shave and color

Author: Ong-Art S. Factory AVP

Show for Task Select Normal

Row 2 or 3

From

To

Baseline Start

Baseline finish

24

Step-4: Set the Project Base Line 3. View Baseline in a Table

Author: Ong-Art S. Factory AVP

Go to View tab, in Data group click to Table and select Variance or insert columns with custom field.

25

Step-5: Update Progress  Updating the progress is the only way to ensure it stays on tracks as work is performed. The focus at this point is on managing changes, updating the schedule, tracking progress and communicating project information.  MS Project 2013 tracks 3 sets of date: Current, Baseline and Actual. When we set the baseline, current = baseline. when a task is 100% complete, current=actual. Author: Ong-Art S. Factory AVP

26

Step-5: Update Progress 1. Manage Change

Author: Ong-Art S. Factory AVP

Managing changes involves modifying duration, date, dependencies, resource assignment or tasks based on requested changes or new information. Keep the current fields up to date and compare to baseline.

27

Step-5: Update Progress 2. Track actual It’s the best to decide on a single method date and duration for tracking progress. We can enter percentage complete, actual start and finish dates, actual remaining durations or actual and remaining work. Click the Task tab, select the task that we want to enter actual progress. In the Schedule group select the amount of progress done on the tasks. Default: 0%, 25%, 50%, 75%, 100% Note: we can put a number direct to %Complete field Author: Ong-Art S. Factory AVP

28

Step-5: Update Progress 3. Track Actual Hours and Cost

Author: Ong-Art S. Factory AVP

If we want to enter actual and remaining work hours or costs, use tracking table. Click View tab, in Data group point Table and select Tracking. Enter progress data in the Act. Work or Act. Cost field for the task. Program is determine if we put the actual start and actual finish or % Complete.

29

Step-6: View Report Information  MS Project 2013 provide many ways of built in report, but for us we have to create a customize report by using S-Curve Reports.

Author: Ong-Art S. Factory AVP

30

Step-6: View Report Information 1. Select a View

Author: Ong-Art S. Factory AVP

MS Project 2013 has old and new views to help you to see project information and report it to others. Click the View Tab, in either the Task Views group or Resources Views group, select the view you want to use. There’re many view but most usful ones include:• Team planner View • Timeline View • Gantt Chart View • Calendar View 31

Step-6: View Report Information 2. Customize a View

Author: Ong-Art S. Factory AVP

Select the view you want to customize and then on the Format tab click the type of view element you want to change, such as the bar style on the Gantt Chart or gridlines and time scales of any views. Tips & Tricks, if you want to filter, sort or group tasks prior to printing, click the View tab and then in the Data group, click sort, Filter or Group options.

32

Step-6: View Report Information 3. Print a View or Set up the current view that we want it to Report look when printed. Click the File Tab and then click Print. A preview part of the view to see the actual size of the view as it will be printed.

Author: Ong-Art S. Factory AVP

33

Step-6: View Report Information 4. Generate a Report

Author: Ong-Art S. Factory AVP

In Report tab has many report to view information of project but we’re intent to create the S-Curve by using MS Project as a tools, we’ll focus on how to do it. Click the Report tab, go to View reports group, select Customer

34

Step-7: Step by Step to S-Curve  In the field list (right hand) Select Category to Time.

Author: Ong-Art S. Factory AVP

35

Step-7: Step by Step to S-Curve  Then Select Field go to Work, click Actual Work and Cumulative Actual Work only.

Author: Ong-Art S. Factory AVP

36

Step-7: Step by Step to S-Curve  The Click on Baseline, click Baseline Cumulative Work, just only one.

Author: Ong-Art S. Factory AVP

37

Step-7: Step by Step to S-Curve  In chart area Right click to change chart type.  Select Chart type to Combo.

Author: Ong-Art S. Factory AVP

38

Step-7: Step by Step to S-Curve  In the Change Chart Type dialog in Series Name choose All Cumulative (Actual & Baseline) Chart type to Line Type.  Actual Work chart type to Clustered Column and Click Secondary Axis

Author: Ong-Art S. Factory AVP

39

Step-7: Step by Step to S-Curve  In Field List, in Tasks Tab look at Select Category, click Edit customize time from Days to Weeks and change format as you like.

Author: Ong-Art S. Factory AVP

40

Step-7: Step by Step to S-Curve  In design Tab, choose format color as you like.  In Chart Layout select Layout No 5 to show Data

Author: Ong-Art S. Factory AVP

41

Step-7: Step by Step to S-Curve  Final as just Fonts size and others

Author: Ong-Art S. Factory AVP

42

Step-8: Export Data to Excel 1. Visual Report

Author: Ong-Art S. Factory AVP

Go to Report tab, select on Visual reports Export. Select template dialog show, go to Task Usage tab, move a mouse on Cash Flow Report template, then click Edit Template. In Visual Report-Field Picker is pop up, in Available Field, select Base line Cumulative Work and Cumulative Actual Work add to selected Fields.

43

Step-8: Export Data to Excel 2. Analyze Data in In PivotTable Fields, select only Actual Pivot Table Work, Baseline Cumulative work and Cumulative Actual Work.

Author: Ong-Art S. Factory AVP

44

Step-8: Export Data to Excel 3. Custom Charts In Pivot Tab Fields, select only Baseline in Excel Cumulative Work, Cumulative Actual Work and Actual Work. In Chart Area Right Click mouse select Combo chart, then All cumulative change type to Line only Actual Work to Clustter Column.

Author: Ong-Art S. Factory AVP

45

Step-8: Export Data to Excel

Author: Ong-Art S. Factory AVP

46

Step-9: Close the Project  Just because your project is almost finished doesn’t mean that your work is done.  We still need to solve any final project detail and customer acceptance for final deliverables.  Conduct a “Lessons Learned” session, recording information abount areas for improvement and best practices.  Make any final update to project plan.  Finally archive the project plan according to our organization’s guideline. Author: Ong-Art S. Factory AVP

47

Step-9: Close the Project 1. Create a Final Report

Author: Ong-Art S. Factory AVP

Click the Report tab, click Visual Reports to see project data as a Pivot Table report in Excel 2013 or Pivot Diagram view in Visio professional 2013 We can also view basic reports that don’t require Excel or Visio. Click Report Tab many report category available to view depend on how we want to views.

48

Step-9: Close the Project 2. Save a Project as a Template

Author: Ong-Art S. Factory AVP

After completing a project, we have to leverage what we’ve learned in the project by making it as a template for future projects. Click the File tab and Save As and then in the Save As Type box click Template.

49

Thanks you

End