Hitra Procedure Kz01 Cg Pro 53 0113 a02
Short Description
hazard identification task risk assessment procedure...
Description
Khazzan Project Security Classification: Project Internal
Contract No. CO-BPXO-12-0376
Khazzan Commissioning Hazard Identification and Task Risk Assessment (HITRA) Procedure (CPF)
Khazzan Project
Commissioning Hazard Identification and Task Risk Assessment (CPF)
Revision History Amendment Date
Revision Number
Amender Initials
24/02/2016
A01
RT
Amendment
Related Documents Document Number
Document Name
Description of Content
Petrofac Golden Rules of Safety KZ01-CG-PRO-53-0107
Khazzan Commissioning Control of Work
KZ01-SA-PLN-53-0005
Emergency Response & Crisis Management Plan
KZ01-CG-PRO-53-0111
Energy Isolation Procedure
A02
24/02/2016
A01
Khazzan Project Commissioning Energy Isolation procedure
RE-ISSUED FOR REVIEW
05/02/2016
Rev.
Commissioning specific CoW process including PtW and Authorisations
ISSUED FOR REVIEW
Date
Reason for Issue
RT
CM
VK Author
EC Checked
CE ELIE LAHOUD Approved Rev.
KZ01-CG-PRO-53-0113
Holds Section Number
Short Description of Hold
Abbreviations AA
Area Authority
AAD
Area Authority Designate
ALARP
As Low as Reasonably Practicable
CoW
Control of Work
KZ01-CG-PRO-53-0113
Page 2 of 41
Rev: A02 Project Internal
A02
Khazzan Project
Commissioning Hazard Identification and Task Risk Assessment (CPF)
CSE
Confined Space Entry
GPO
BP Global Projects Organisation
GRoS
BP Golden Rules of Safety
HITRA
Hazard Identification and Task Risk Assessment
ISA
Isolating Authority
MOC
Management of Change
PA
Performing Authority
PTW
Permit to Work
PTWC
Permit to Work Coordinator
SA
Site Authority
TBT
Toolbox Talk
TRA
Task Risk Assessment
TRAT
Task Risk Assessment Table
KZ01-CG-PRO-53-0113
Page 3 of 41
Rev: A02 Project Internal
Khazzan Project
Commissioning Hazard Identification and Task Risk Assessment (CPF)
TABLE OF CONTENTS 1.0.
2.0.
INTRODUCTION.................................................................................................. 1.1.
PURPOSE......................................................................................................................................
1.2.
SCOPE...........................................................................................................................................
ROLES AND RESPONSIBILITIES............................................................................ 2.1.
SINGLE POINT OF ACCOUNTABILITY.........................................................................................
2.2.
SITE AUTHORITY..........................................................................................................................
2.3.
AREA AUTHORITY.........................................................................................................................
2.4.
AREA AUTHORITY DESIGNATE....................................................................................................
2.5.
PERFORMING AUTHORITY..........................................................................................................
2.6.
RESPONSIBILITIES OF HITRA FACILITATORS.......................................................................... 2.6.1.
HITRA LEVEL 1 FACILITATOR (TYPICALLY PA) 10
2.6.2. HITRA LEVEL 2 FACILITATOR (TYPICALLY AA OR REPRESENTATIVE FROM THE HSE SITE TEAM) 10 3.0.
4.0.
5.0.
6.0.
7.0.
HAZARD IDENTIFICATION AND TASK RISK ASSESSMENT PROCESS OVERVIEW ....................................................................................................................... 3.1.
TASK RISK ASSESSMENT LEVELS............................................................................................
3.2.
HITRA PROCESS STEPS............................................................................................................
3.3.
LEVEL 1 HITRA PROCESS..........................................................................................................
3.4.
LEVEL 2 HITRA PROCESS..........................................................................................................
ENERGY SOURCES, HAZARDS AND RISK............................................................. 4.1.
HAZARDS.....................................................................................................................................
4.2.
DETERMINING CONSEQUENCES.............................................................................................
4.3.
RISK ASSESSMENT AND RISK RANKING.................................................................................
4.4.
IDENTIFICATION OF CONTROLS...............................................................................................
PERFORM TASK................................................................................................ 5.1.
PERMIT TO WORK AND COMMUNICATION..............................................................................
5.2.
PERFORMING THE TASK............................................................................................................
5.3.
MONITOR FOR CONDITION CHANGE.......................................................................................
5.4.
LESSONS LEARNED...................................................................................................................
TRAINING AND COMPETENCY............................................................................ 6.1.
GENERAL.....................................................................................................................................
6.2.
LEVELS OF TRAINING................................................................................................................
TASK RISK ASSESSMENT TABLE (TRAT)..............................................................
APPENDIX A ENERGY SOURCE PROMPTS..................................................................... APPENDIX B HAZARD IDENTIFICATION PROMPTS......................................................... APPENDIX C IMPACT ASSESSMENT TABLE.................................................................... KZ01-CG-PRO-53-0113
Page 4 of 41
Rev: A02 Project Internal
Khazzan Project
Commissioning Hazard Identification and Task Risk Assessment (CPF)
APPENDIX D RISK ASSESSMENT MATRIX...................................................................... APPENDIX E APPROVAL MATRIX.................................................................................. APPENDIX F TASK RISK ASSESSMENT TABLE (TRAT)..................................................... APPENDIX G LEVEL 1 RISK ASSESSMENT PRO FORMA................................................... APPENDIX H HITRA FORM...........................................................................................
KZ01-CG-PRO-53-0113
Page 5 of 41
Rev: A02 Project Internal
Khazzan Project
Commissioning Hazard Identification and Task Risk Assessment (CPF)
1.0. INTRODUCTION Hazard Identification and Task Risk Assessment (HITRA) is used during the planning and execution stages of Commissioning Control of Work (CoW) to identify hazards associated with performing tasks. It prescribes the control measures to implement during task execution to prevent or eliminate, isolate or minimize task risks so that work is executed in a safe, systematic and compliant manner. This document should be read in conjunction with Khazzan Commissioning Control of Work Procedure KZ01-CG-PRO-53-0107 and the Energy Isolation Process KZ01-CG-PRO-53-0111
1.1. Purpose The purpose of this procedure is to describe how to identify work-related hazards and assess risks associated with activities undertaken as part of the Khazzan Project Commissioning scope. It provides the necessary detail to illustrate ‘what good hazard identification and task risk assessment looks like’. The HITRA process forms an essential part of the Commissioning Control of Work (CoW) process. Before conducting HITRA, evaluate: 1. Is the job really necessary? 2. Is there an alternate way(s) to do the work that ‘eliminates’ inherent hazard(s) involved? It is a Khazzan Project principle that no unnecessary work will be done. Only work that provides business value will be undertaken.
1.2. Scope This procedure applies to work undertaken –inside the CPF boundary limits. See Figure 1 below illustrating the CPF Commissioning CoW document structure. An equivalent approach managed by BP for GWES Category 1 scope.
KZ01-CG-PRO-53-0113
Page 6 of 41
Rev: A02 Project Internal
Khazzan Project
Commissioning Hazard Identification and Task Risk Assessment (CPF)
Figure 1: Commissioning CoW Document Structure
KZ01-CG-PRO-53-0113
Page 7 of 41
Rev: A02 Project Internal
Khazzan Project
Commissioning Hazard Identification and Task Risk Assessment (CPF)
2.0. ROLES AND RESPONSIBILITIES
2.1. Single Point of Accountability Khazzan CPF HITRA Single Point of Accountability (SPA) is the Petrofac Commissioning Manager and is responsible for ensuring that:
All activities within their area of responsibility comply with this procedure
Delegation of any of the CoW role’s responsibility is documented
CoW audit, assurance and self-verification systems are in place, including lessons learned and continual improvement processes
Sufficient resources (time, people and budget) are allocated to implement this procedure
Personnel involved in facilitating HITRA are properly trained and competent
Periodic self-verification against the requirements in this procedure is undertaken
Responsibility can be delegated but not accountability. This delegation must be documented (Refer to CPF Commissioning CoW ProcedureKZ01-CG-PLN-53-0107.
2.2. Site Authority The Site Authority (SA) is responsible to:
Ensure that an adequate number of competent persons are appointed to manage the work and the associated risks, as defined in this procedure
Confirm that a process is in place to manage the appointment of competent persons as: o
Authorizing signatories for Level 1 and Level 2 HITRAs,
o
Level 1 HITRA completers,
o
Team Leaders to facilitate the Level 2 HITRA process.
Ensure that the HITRA process is in place and followed consistently
Review and self-verify the HITRA process to confirm that the quality of the HITRAs and areas of improvement have been identified and implemented
Ensure that the HITRA process is subject to regular monitoring and Self Verification , acting upon the results of Self Verification to maintain the integrity of the system and proposing any recommendations for system improvement
Ensure that formal records of all TRAs are maintained
Ensure that the training and competency standards, and formal authorization of personnel, as defined in this document and in Control of Work Procedure (KZ01-CG-PLN-53-0107) are followed
Manage the TRAT
Note: The SA is the Single Point of Accountability for CoW on their site. The responsibilities but not the accountabilities can be delegated to a competent person with proper documented approval from the SPA. Review and authorization of all Level 1 & 2 HITRA should be commensurate with the level of risk. It is incumbent on the SA to request a higher level of risk assessment should they consider that risks have not been fully addressed.
KZ01-CG-PRO-53-0113
Page 8 of 41
Rev: A02 Project Internal
Khazzan Project
Commissioning Hazard Identification and Task Risk Assessment (CPF)
2.3. Area Authority The Area Authority (AA) role is central to the site CoW process for the management and control of CoW tasks. AAs are accountable for task hazard identification and risk control measures associated with work performed in their area of responsibility. The number of areas can be depending on the complexity and the footprint of the work to be undertaken. Responsibility can be delegated but not accountability. This delegation should be through documented approval from the SA. The Area Authorities are responsible for ensuring that the requirements of this procedure are adhered to for all TRAs conducted within their area of responsibility. The AA or their competent delegate (AAD) shall be trained and competent to lead the team in performing a Level 2 HITRA. They shall be responsible to:
Ensure that everyone associated with the work activity is aware of the requirements of HITRA, permit to work conditions and any risks or hazards
Ensure that the appropriate level of risk assessment is conducted for the task
Organise and participate in the HITRA process
Ensure that the Performing Authority (PA. Refer to Section 2.5) participates in risk assessments and conducts Tool Box Talks associated with the work activity
Ensure that the HITRA is communicated to the workforce in commonly used language(s)
Ensure that the risk assessment requirement is included in the planning for each work activity
Ensure that a pre-job site visit is conducted with the PA to identify all hazards and appropriate controls that need to be included in the Work Permit or risk assessment
Ensure that the appropriate level of HITRA has been carried out for the task
Ensure that all the appropriate control measures have been put in place prior to a permit being issued, confirming that the PA fully understands the scope of work and tasks involved
Ensure that active permits and hazard control measures are effective at the work site and can continue simultaneously with other PTW tasks
Ensure that the PA is competent to perform the task and HITRA
Promote the culture to “STOP the Job” if anyone feels unsafe.
2.4. Area Authority Designate The AAD serves as a delegate for the AA, can facilitate L1 HITRA, participate in L2 HITRA and perform site visit for low residual risks tasks. Only certain elements of the AA role can be delegated by the AA to the AAD. The accountability for ensuring hazards are identified and the associated risks are controlled cannot be delegated. The AA cannot delegate worksite visit for high residual risk tasks or approval of Level 2 HITRA that requires AA approval as per the Approval Matrix (Appendix E)
2.5. Performing Authority The Performing Authority (PA) is the person responsible for the activity being carried out under the Permit to Work. For permit-related work, the PA should perform the Level 1 HITRA assessment. The PA may also participate in Level 2 HITRAs. The PA shall be competent to supervise performance of the task and be very familiar with the equipment and tools being used. The PA may be the person carrying out the task or supervising a group of people carrying it out. KZ01-CG-PRO-53-0113
Page 9 of 41
Rev: A02 Project Internal
Khazzan Project
Commissioning Hazard Identification and Task Risk Assessment (CPF)
The PA can be responsible for more than one task at a time providing they can safely manage the tasks simultaneously. This should be discussed and agreed with the Area Authority The PA shall ensure that:
All personnel under their supervision comply with this procedure when involved in risk-assessed activities
Level 1 HITRA is completed where required and that adequate consultation has taken place, typically with AA and the line supervisor
The necessity of Level 2 HITRA is identified and participate in Level 2 HITRA
Risk assessment has been performed and a toolbox talk conducted
Where other persons are involved in the task, they fully understand the scope of the work and the hazards and controls for the job by holding a toolbox talk meeting. This includes ensuring that all of those involved in the specific work activity sign the worksite hard copy of the Work Permit
The controls identified in the HITRA are effectively in place and that the activity is executed in accordance with this procedure
Work activity is STOPPED if an unsafe situation occurs
Work activities have been reviewed and pertinent information exchanged with all other affected parties
Appropriate authorisation is obtained prior to the commencement of work
The proposed controls reduce the risks associated with the task; consider the controls specified by any relevant local procedure and the capability of the person in charge.
Work is stopped immediately when there is any change to the Work Permit conditions, including an emergency, and that hazards and risks are reassessed before the work is resumed
A culture prevails to “STOP the Job” if anyone feels unsafe.
2.6. Responsibilities of HITRA Facilitators 1.1.1.
HITRA Level 1 Facilitator (Typically PA)
The Level 1 HITRA Facilitator should:
Complete Level 1 HITRAs
Confirm that adequate consultation has taken place, typically with the AA and / or line supervisor
Confirm appropriate authorisation is obtained prior to the commencement of work
1.1.2. HITRA Level 2 Facilitator (Typically AA or representative from the HSE site team) The main responsibilities are to:
Lead the assigned team in performing a Level 2 HITRA as described in this procedure
Ensure the team understands the assessment process and its objectives
Take responsibility for maintaining the quality of the HITRA
Ensure that the assessment team includes personnel with the necessary experience, knowledge and competence for the task involved
Ensure that the HITRA includes a worksite visit prior to issuing PTW
KZ01-CG-PRO-53-0113
Page 10 of 41
Rev: A02 Project Internal
Khazzan Project
Commissioning Hazard Identification and Task Risk Assessment (CPF)
Ensure that all members of the HITRA team have full opportunity to contribute and that the details of the assessment are agreed by all team members
Ensure that the details of the assessment are accurately recorded and correspond with the agreed level of risk
Take appropriate guidance on health, safety and environmental legislation and consequent limits on operation
3.0. HAZARD IDENTIFICATION AND TASK RISK ASSESSMENT PROCESS OVERVIEW This section outlines the HITRA process for systematically examining a task to identify the hazards, evaluate the risks and specify appropriate controls.
3.1. Task Risk Assessment Levels There are two levels of Task Risk Assessment (TRA). Level 1 TRA includes a detailed overview of the task to identify the hazards involved and required controls. It is conducted by one or more competent persons, typically the Performing Authority (PA) and / or the Area Authority (AA). Level 2 TRA includes a structured semi-quantitative assessment, conducted when the Site Authority (SA) or AA determines that there are greater hazards or complexities associated with the task, necessitating a more rigorous assessment. Level 2 TRA is performed by a TRA team. The reasons for a Level 2 HITRA include, for example:
The task is new and unfamiliar
It is not possible to comply fully with the standards in a relevant local procedure or other recognized source of guidance
Previously used controls may not be reasonably practicable in this case
The task is complex and/or has potential impact on other activities.
Energy of significant magnitude will be introduced into the system/process
The following activities require a Level 2 TRA:
Confined space entry
Excavation of a trench or pit more than 4 feet or 1.2 metres deep or other ground disturbance, such as piling
Working at heights, where a fall could result in serious injury
Work on energised systems
Complex (Category 2) or critical (Category 3) lifting operations
Activities that could involve exposure to substances for which there are defined exposure limits, including:
o
hydrogen sulphide (H2S)
o
products that contain benzene
o
inert gases
Work that could result in performance or availability of safety critical equipment or systems falling below expected standards, for example: o
Removal or inhibition of protective devices
KZ01-CG-PRO-53-0113
Page 11 of 41
Rev: A02 Project Internal
Khazzan Project
Commissioning Hazard Identification and Task Risk Assessment (CPF)
o
Blocking of escape routes
o
Taking a fire pump or emergency generator offline
Note, safety critical performance shall be considered with respect to the hazards present in a Commissioning, pre hydrocarbon environment.
Online connections to process equipment tanks or pipelines, including hot tapping.
Planned deviation from an existing policy, procedure or practice.
More examples of activities, and whether they warrant Level 1 or Level 2 assessment, are included in the TRAT, Appendix F.
3.2. HITRA Process Steps
Identify the site and process hazards that could result in harm such as injury, illness, damage to the environment, plant or process
Identify risk; determine the credible consequences and their probabilities to assess the level of risk(consequence x probability = risk) including who or what could be affected
Reduce risk by eliminating or substituting the hazards AND controlling and / or mitigating the risks
Evaluate residual risk that remains with all the planned controls in effect. Confirm that residual risk has been considered and no additional controls are needed for the task(s) to be conducted safely
Document in a standard format the hazards, controls and residual risk
Record approvals of the HITRA document
Communicate the hazards and controls to all personnel involved in performing the task. Confirm that the controls are effective throughout the task.
Monitor the on-going work to identify any new hazard that may be introduced during or because of the activities.
3.3. Level 1 HITRA Process A Level 1 HITRA involves a review of the task by the PA in consultation with the AA to identify the hazards associated with the task and appropriate control measures required to manage these hazards. The PA uses their technical knowledge and task information to select job hazards from the prompt list on the permit (see Figure 2 below). The PA should not be constrained by the list and must use their judgement to identify any other hazards and record on the space provided on the permit. The PA then uses the controls listed to show how the hazards will be managed. Once again, the PA should not be constrained by the list and must use their judgement to identify any other control measures and record on the space provided on the permit. The AA with the PA will review task details, hazards and control measures described on the permit along with any documentation. Prior to the commencement of the job, they will visit the worksite to confirm all hazards have been identified and adequately controlled. During Commissioning, where there will be repetitive low risk tasks carried out such as instrument loop checks, or uncoupled motor runs; a Level 1 risk assessment may be carried out and recorded on a specific L1 risk assessment pro forma, included in Appendix G These risk assessments shall be held in the PtW office and given a unique reference number. The assessment shall be reviewed, copied and attached to subsequent equivalent permits as required. This will ensure a level of consistency in low risk activities. Additional site specific hazards can be added directly to the permit as required.
KZ01-CG-PRO-53-0113
Page 12 of 41
Rev: A02 Project Internal
Khazzan Project
Commissioning Hazard Identification and Task Risk Assessment (CPF)
This approach shall also be followed when considering Risk Assessed Procedures and the existing HITRA shall be reviewed for applicability and any lessons learned from previous application of the procedure.
Figure 2: Example from Cold Work Permit - Hazards and Controls Checkboxes
Figure 3: Level 1 HITRA Flowchart If the proposed controls are adequate for the identified risks of the task, and the task can be conducted safely, the task risk assessment is approved. If, considering any residual risks, the authorised signatory doubts that the risks are adequately controlled by the proposed means, they will request a Level 2 HITRA. Those who conducted the Level 1 HITRA may also participate in the Level 2 HITRA.
KZ01-CG-PRO-53-0113
Page 13 of 41
Rev: A02 Project Internal
Khazzan Project
Commissioning Hazard Identification and Task Risk Assessment (CPF)
3.4. Level 2 HITRA Process A Level 2 HITRA is a structured examination of all hazards associated with a task to devise a set of control measures that reduce the level of risk sufficiently to allow a task to proceed safely. If the risk cannot be sufficiently reduced, alternative methods must be found before the task can proceed. The Level 2 method uses a risk assessment proforma sheet and a suite of matrices to help to determine the consequences and likelihood of hazardous conditions in a consistent and repeatable manner. To complete a Level 2 risk assessment, a team is formed with a minimum of 3 persons with suitable experience, led by a competent Level 2 HITRA facilitator appointed by the AA. The objective of forming a team is to bring together understanding and experience of the task to examine all the hazards and devise a set of controls that will ensure that the level of risk is reasonable. Where larger tasks, series of tasks or significant introduction of energy is planned the potential to require Level 2 HITRAs should be identified early, to allocate time in the plan to complete the HITRAs. A Level 2 HITRA can be carried out at any stage in the work process if the PA, AA, a member of management or any other personnel believes that significant risks exist which will not be adequately controlled without a more rigorous assessment and the application of additional controls. The AA is responsible for deciding whether a L2 HITRA is required. The decision about when Level 2 Risk Assessment is required is somewhat subjective, depending on the people involved, but the following rules should be applied to ensure a consistent level of assessment is being carried out across the organization.
Figure 4: Level 2 HITRA Flowchart
4.0. ENERGY SOURCES, HAZARDS AND RISK This section provides guidance on the use of an energy source approach to identify hazards and clarifies the differences between hazards and risks.
4.1. Hazards Hazards are anything with the potential to result in harm such as injury, illness or damage.
KZ01-CG-PRO-53-0113
Page 14 of 41
Rev: A02 Project Internal
Khazzan Project
Commissioning Hazard Identification and Task Risk Assessment (CPF)
NOTE: Through Commissioning, the absence of hydrocarbons and associated SIMOPs makes the process of hazards identification and risk assessment less complex than Operational facilities. To identify all the hazards, consider the aspects below:
Affected Hazards: The energy sources affected by the work, e.g. commissioning fluids and the system in which they are transported and contained (e.g. operations equipment).
Applied Hazards: Uncontrolled or unwanted contact with an energy source that may occur while setting up tools and equipment at the job site.
Ambient Hazards: The site conditions that may cause uncontrolled or unwanted contact with an energy source (e.g. weather conditions or concurrent work).
Other considerations may include;
Characteristics of the plant and / or systems involved:
Access
Type of service (e.g., water, diesel, inert gas)
Likelihood of foam, sand, and sludge, types of scale
Sensitivity of the location within the premises, including proximity to Health, Safety, Security and Environment (HSSE) critical plant or systems such as:
o
Heating, Ventilating and Air Conditioning (HVAC) intakes
o
Flare header
o
Emergency Shut Down Valves (ESDVs)
o
Escape routes, fire pumps, large inventories (pipelines, vessels or tanks)
Possible interactions between simultaneous activities within the task, or with another task taking place nearby, that call for close coordination or controls.
Energy Sources and Hazard Identification prompts are found in Appendices A and B. Also, consider what would occur in the event of an emergency.
4.2. Determining Consequences After identifying the hazards, the potential credible consequences should also be identified, taking into consideration any impact on personnel or plant. The worst reasonably credible consequences should be identified and recorded for each hazard. There may be more than one consequence per hazard. Refer to Appendix C: Impact Assessment Table for guidance on determining the level of impact for each of: Health and Safety, Environment or Financial consequences.
4.3. Risk Assessment and Risk Ranking Risk assessment assigns semi-quantitative values for each consequence and probability. The product of these values lies inside or outside the allowed limits. The risk created by each hazard on the list should be evaluated according to: The worst reasonably credible impact, should anything go wrong (taken from Appendix C) AND the probability of such an impact being realized (from Appendix D) The result is a numerical risk ranking which must be recorded and approved according to the requirements found in Appendix E.
KZ01-CG-PRO-53-0113
Page 15 of 41
Rev: A02 Project Internal
Khazzan Project
Commissioning Hazard Identification and Task Risk Assessment (CPF)
For example, impact level F and probability level 4 gives a ranking of 6, which falls in Risk Area II, requiring approval by Site Authority.
4.4. Identification of Controls For each risk, control measures shall be identified. The HITRA Facilitator works systematically through the list of hazards to specify all the methods necessary to control each of the associated risks. Existing controls are recorded along with any additional controls that the team considers necessary to achieve a sufficient level of overall control. The hierarchy of controls shown below should be used as a guide to confirm that a full range of options is considered. Note: As consequences are deemed reasonably credible, then control measures should be reasonably practicable. They should be chosen to adequately reduce the identified risk.
Figure 5: Hierarchy of Controls Two types of control measures should be identified from a Level 1 or Level 2 HITRA process:
Prerequisite controls that should be in effect prior to job execution. These may or may not include a PTW.
Supplementary controls that should be applied during the job. Consideration should be given whether supplementary controls introduce another hazard, while in effect.
Before the task is authorised to start, the person controlling the work activity should confirm that:
All the prerequisite controls are in effect
The persons allocated to perform the task are competent to initiate and manage the supplementary controls
The output from the risk assessment (with Work Permit where applicable) has been “communicated in writing and signed off by all involved in the task”
Monitoring activities are arranged e.g. controls are still effective, no new hazard is introduced
Actions in the event of an emergency are understood by all involved in the task.
Controls Check KZ01-CG-PRO-53-0113
Page 16 of 41
Rev: A02 Project Internal
Khazzan Project
Commissioning Hazard Identification and Task Risk Assessment (CPF)
Consideration should be given to the following questions:
Have all the necessary control measures been fully identified?
Is an engineering change necessary for eliminating or reducing the risk?
Are any additional capabilities needed to complete the task?
Should the plant or process be shut down?
Is the residual risk at a level to allow the task to be safely completed?
KZ01-CG-PRO-53-0113
Page 17 of 41
Rev: A02 Project Internal
Khazzan Project
Commissioning Hazard Identification and Task Risk Assessment (CPF)
Residual Risk Check A. If the residual risk is not at a level to allow the task to be completed safely, the hierarchy of controls should be used again with emphasis on the most effective or prevention categories.
If any control measures are practicable to implement and would reduce the residual risk, they should be recorded.
If further control measures cannot reduce the risk to a level that allows the task to be completed safely, the HITRA team cannot authorize the task and should refer back to the work requester.
B. The HITRA team will document:
The assessment including all the identified control measures that should be in effect for the defined task.
The residual risk level for each identified hazard, with the highest residual risk defining the level of approval. (Appendix E)
C. Agreement on risks and controls
Approval to proceed is sought when the HITRA team unanimously agrees that the hazards and risks are controlled to the point that the task(s) can be conducted safely
D. Documentation and records
The HITRA team shall record the findings in the HITRA format included as Appendix G
E. Approval levels are explained in Appendix E.
5.0. PERFORM TASK
5.1. Permit to Work and Communication This section discusses the approval to proceed and the importance of communication to the success of HITRA. Before work commences, the risk assessment shall have been approved based on the residual risk and according to the approval matrix Appendix E. The success of a HITRA depends on the effective communication of its results, so that people who execute the job are fully aware of and thoroughly understand the hazards and the controls in effect. The HITRA document is used as the basis for workforce communications so that all personnel concerned have an understanding of the following:
The steps involved in carrying out the job
The hazards they may encounter at each step
Control measures in effect or planned and how they relate to the hazards
Individual actions and responsibilities at various steps in the work
All involved in the task have the opportunity to identify further hazards and control measures that may have been overlooked in the HITRA. The HITRA Facilitator should be notified if such improvements are identified.
5.2. Performing the Task Each person involved in actually performing the task should:
Be satisfied that all the defined controls are actually in place and effective (even though the task has been duly authorised)
KZ01-CG-PRO-53-0113
Page 18 of 41
Rev: A02 Project Internal
Khazzan Project
Commissioning Hazard Identification and Task Risk Assessment (CPF)
Feel empowered (and obliged) to voice any concerns to their supervisor and not start the job if they do not think it can be completed safely
5.3. Monitor for Condition Change The HITRA includes a monitoring frequency for the work. However, personnel who execute the task should monitor their activities on an on-going basis and be alert to:
Any new or unauthorised personnel
Conditions at the work site (e.g. isolations, weather, SIMOPS)
Hazards generated by the activity
Hazards not originally covered by the HITRA
Whether controls are still effective
If necessary, personnel should stop the job so that the hazards and risk can be re-assessed.
5.4. Lessons Learned It is important to capture lessons learned upon completion of work and incorporate the lessons into the process. This may be in the form of changes or revisions to:
Links between a procedure and the underpinning HITRA.
HITRA records.
The HITRA process, including team composition.
Lessons learned should be communicated to all concerned through existing methods such as meetings, circulars, training and toolbox talks.
6.0. TRAINING AND COMPETENCY
6.1. General All personnel involved in the HITRA process are trained on HITRA process & procedure and competent. The competency of all relevant personnel shall be established during the planning process for a particular risk assessment. The AA shall ensure that the personnel involved in the activity have the correct competencies through training records or requesting individuals to produce relevant certification. While it is simple, successful application of the HITRA method depends upon participants having industry experience, different perspectives and understanding of relevant hazards, realistic consequences and a hierarchy of risk reduction measures (hierarchy of controls is shown in Section 4.5 above). All personnel involved in the HITRA process should complete the fundamental training module (Refer to Section 6.2 below for links) which covers:
Definitions of hazard, consequence, probability, risk, control, hierarchy of controls and risk matrix
The principles and process of HITRA
When to conduct Level 1 and 2 HITRAs
HITRA tools (checklists, prompts)
Expectations of team members: the need to contribute personal experience, reach agreement and record divergent views
Responsibility after the completion of the HITRA (communication, responding to changes at the task location)
KZ01-CG-PRO-53-0113
Page 19 of 41
Rev: A02 Project Internal
Khazzan Project
Commissioning Hazard Identification and Task Risk Assessment (CPF)
Before selection for training, Level 2 HITRA Facilitators should be able to demonstrate an extensive knowledge of the work environment. They should be able to apply informed judgment when using checklists and other available tools.
6.2. Levels of Training All members defined in the Control of Work team (PA, AA, , AAD, PTWC, SA, ISA, AGT) are required to carry out HITRA awareness training. This will capture HITRA level 1 and a summary of what level 2 risk assessment includes and awareness of why and when it should be used. Personnel identified to be Level 2 facilitators, shall carry out further training to HITRA Level 2 facilitator level. Personnel shall only take on the roles of authorised signatory or HITRA Facilitator after successfully completing the supplementary training and competency assessment. Training and Competency Matrix: Role SA
Experience 1. Has led and facilitated Level 1 and 2 HITRAs using the HITRA process.
Training 1.
2. Practical demonstration in leading a level 2 HITRA 2.
AA
1.
2.
PA
Has led and facilitated Level 1 and 2 HITRAs using the HITRA process. Practical demonstration in leading a level 2 HITRA.
Explain the PA’s role in worksite visits and Level 1 HITRA or equivalent.
KZ01-CG-PRO-53-0113
1.
Completed training for both HITRA participation and facilitation modules. Satisfactorily passed the HITRA knowledge assessment criteria.
Complete the HITRA participation and facilitation training course.
2
HITRA Awareness (participation)
Page 20 of 41
Assessment Criteria Practical field assessment shall include: 1.
Can lead a Level 2 TRA.
2.
Can articulate the difference between a hazard and a risk.
3.
Can state the difference between Level 1 and 2 HITRAs.
4.
Understands how residual risk is determined and the approval process.
5.
Leads a field CoW verification/audit, including HITRA.
6.
Can articulate the HITRA hierarchy of controls.
Field assessment shall include/verify the following: 1.
He or she has led a Level 2 HITRA.
2.
Demonstrate that they understand the HITRA and approval process.
3.
Explain the difference between Level 1 and Level 2 HITRAs.
4.
Demonstrate ability to lead a L2 HITRA.
5.
Apply the HITRA tools and approval process.
6.
Explain the HITRA hierarchy of Controls and residual risk.
Assessment shall include: 1.
What is a Level 1 HITRA, and what are the key principles
2.
Name the energy sources and identify hazards.
3.
What hazards to look for during a worksite visit
4.
When to escalate to Level 2 TRA
Rev: A02 Project Internal
Assessor SPA with support from Technical Discipline Engineers (if needed)
SA
AA
Khazzan Project
Commissioning Hazard Identification and Task Risk Assessment (CPF)
7.0. TASK RISK ASSESSMENT TABLE (TRAT) TRAT lists typical Commissioning activities, prescribing Level 1 or 2 HITRA, recommended participants and approver. The TRAT table included in Appendix F is based on BP Upstream guidance The purpose of the TRAT is to:
Categorise a number of standard tasks according to their residual risk level
List the appropriate permit to work types (including procedures and routine)
Define the required Level (1 or 2) of TRA and the approval/authorization level
The Site Authority is accountable for the management of the TRAT. When a task is not covered in the TRAT, the Site Authority will determine the level of TRA required by applying the HITRA process.
KZ01-CG-PRO-53-0113
Page 21 of 41
Rev: A02 Project Internal
Khazzan Project
Commissioning Hazard Identification and Task Risk Assessment (CPF)
APPENDIX A ENERGY SOURCE PROMPTS Energy sources
Description / guidance
Biological - including wildlife and viruses or bacteria, e.g., as found in sewage systems, drain lines, cooling towers Biological
Body Mechanics - human strength and agility applied to a task involving lifting, pushing, pulling, climbing or positioning Body Mechanics
Chemical - in the form of reactive or life-threatening gases, liquids, solids, e.g., water, methane, nitrogen, process chemicals, etc. Chemical Electrical - includes all types and voltages of electricity: high voltage power systems ( (AC), battery systems (DC) and static.
Electrical
Consider whether the task: Requires equipment related to the task or in the area of the task to be isolated. Involves electricity powered equipment. Is in an area where there is vulnerable electrical equipment such as insulated cabling, un-insulated overhead power lines, etc. Involves transfer of fluids, powers, etc. or friction between nonconducting materials which could generate static electrical charges. Are systems and equipment where this could occur adequately grounded and / or bonded.
Gravity - causes tools, equipment or people to fall or move. This affects lifting task, work at height and potential dropped objects Gravity Mechanical - includes mobile equipment as well as moving parts on stationary equipment and rotating equipment. Even though items are non-powered, their momentum as they are moved may crush or cut people or vulnerable equipment. Also includes sharp edges of tools and / or equipment. Mechanical
KZ01-CG-PRO-53-0113
Page 22 of 41
Rev: A02 Project Internal
Khazzan Project
Commissioning Hazard Identification and Task Risk Assessment (CPF)
Energy sources
Description / guidance Noise - A form of pressure energy. Consideration should be given to whether: The task is in a high noise area. Noisy tools / equipment will be used. Noise could cause communication problems, including in any emergency.
Noise
Pressure - air, water, pneumatics, springs, gases are all possible sources of significant pressure.
Pressure
Consideration should be given to: Non-Return Valves (NRVs) where system contents may be trapped between the NRV and an isolation point. Section of equipment in which trapped or undrained contents may remain. General equipment / line condition, e.g., area of corrosion, where a pressure leak is foreseeable. Reaction forces from a pressure leak, which may move an unrestrained item, such as a hose, cylinder or pipe segment.
Radiation - in the form of sunlight, radio waves or ionizing radiation (radioactivity) Radiation
Thermal - energy associated with hot or cold surfaces and fluids, undesired chemical reactions and / or ambient temperatures. Thermal
KZ01-CG-PRO-53-0113
Page 23 of 41
Rev: A02 Project Internal
Khazzan Project
Commissioning Hazard Identification and Task Risk Assessment (CPF)
APPENDIX B HAZARD IDENTIFICATION PROMPTS Category Mechanical
Type of harm Trapping (crushing, pressing, drawing in and shearing injuries)
Examples Two moving parts, or one moving part and a fixed surface Conveyor belt and drive V belt and pulley Power press Using hammer Hoist, crane
Impact (includes puncture) / mobile equipment
Something that may strike or stab someone or may be struck against Moving vehicle, machine, aircraft Drill, lathe Crane hook or load
Contact (cutting, friction or abrasion)
Something sharp or with a rough surface Knife, chisel, saw Fan blade Circular saw blade Sanding belt Abrasive wheel
Entanglement (rotating parts)
Power take-off shaft Pipe threading machine Abrasive wheel
Ejection (of work piece or part of tool)
Cartridge tool Hammer and chisel Abrasive wheel Abrasive blasting
Electrical
Shock / burn / fire /
Electricity > 240v, 240v, 110v…
Explosion
DC electricity, especially batteries (hydrogen gas) when charging
Ignition sources
Static Batteries Pressure
Release of energy
Compressed air
(explosion / injection /
Compressed gas
implosion)
Process fluid Steam Vacuum Hydraulic system
KZ01-CG-PRO-53-0113
Page 24 of 41
Rev: A02 Project Internal
Khazzan Project
Commissioning Hazard Identification and Task Risk Assessment (CPF)
Category
Type of harm
Examples Hydro-blasting
Stored energy
Flying objects,
Springs under tension
Electrical / hydraulic / pneumatic systems
Springs under compression Turbine variable inlet guide vanes Conveyor tension weight Counterweight Accumulators/ pulsation dampers
Gravity
Struck by falling objects
Overhead work areas / platforms Items mounted or stored on ceilings or on walls High rack storage areas (warehouse) Hoist platform cage Load carried by crane Raised tipper lorry body
Thermal
Burns / fires / scalds / frostbite
Hot surface Welding flame / arc Refrigerant Steam Process fluid, heat transfer medium
Radiation Ionizing radiation
Burns, cancer, sunburn, melanoma, skin cancer
X Rays or radiation Ultra violet
Non ionizing radiation
Burns
Micro wave Radio frequency Laser Infrared
Noise
Hearing loss, tinnitus
Noise > 85 dB(A) continuous Noise >? dB impact
Vibration
Vibration white finger, whole body effects
Pneumatic drill Driving mobile plant Using jackhammer
Stability
Crushing
Inadequate crane base Fork lift truck on slope Machine not bolted down Mobile scaffold too high Scaffold not tied
Overload or defect due to KZ01-CG-PRO-53-0113
Crushing Page 25 of 41
Crane overload Rev: A02 Project Internal
Khazzan Project
Commissioning Hazard Identification and Task Risk Assessment (CPF)
Category
Type of harm
mechanical failure
Examples Chain sling Scaffold overload Structure overload, especially extreme weather
Fire / explosion
Burns
Combustion
Paper store Grease Plastic foam
Flammable substances (highly and extremely flammable)
Burns
Petrol, diesel, avgas Liquefied Petroleum Gas (LPG) Hydrogen
See also explosive below Oxidizing substance
Burns
Organic peroxide, other oxidising agents Nitric acid
Gas explosions
Burns, structural failure
Flammable gas or liquid above its flash point in a confined space
Dust explosions
Burns, structural failure
Wood dust
Health hazards
Skin, eyes and respiratory track effects; noise
Sulphuric acid, other acids – especially hydrofluoric
Corrosive / irritating materials
Caustic soda, other alkalis Ammonia, chlorine
Sensitising materials and particulates
Sensitisation, fibrosis and cancers of the lungs irritation / injury to eyes
Silica dust Wood dust Iron dust
Vapours
Acute and chronic effects on health
Benzene Toluene Acetone
Fumes
Acute and chronic effects on health (local and systemic effects)
Lead fume Rubber fume Asphalt fume
Gases
Acute and chronic effects on health and death
Carbon monoxide Hydrogen sulphide Sulphur dioxide
Mists
Acute and chronic effects on health
Oil mist, cutting fluids Printing ink mist Detergents Aerosols
Asphyxiates
Acute and chronic effects on health and death
Nitrogen Carbon monoxide Smoke Argon
Health hazard by ingestion KZ01-CG-PRO-53-0113
Burns to upper alimentary tract Page 26 of 41
Corrosive liquids Rev: A02 Project Internal
Khazzan Project
Commissioning Hazard Identification and Task Risk Assessment (CPF)
Category
Type of harm
Examples
Poisoning
Toxins All harmful aerosols Polluted water Contaminated food and drink
Hazards by contact
Cuts, abrasions
Metal swarf Concrete blocks
Environmental Hazards Biological / hazardous waste storage and disposal
Burns, frostbite;
Molten metal
also structural failure
Cryogenic gases
Sewage systems / groundwater / soil pollution / biohazardous waste and sharps / influenza / malaria
Crude / condensate transportation and storage Storage of hazardous sludge / material in pits Infectious and non-infectious diseases, parasites
Human factors / fatigue
Injuries, illness
Shift work Work patterns Driving Poor ergonomic design of plant Control / alarm systems Procedures
KZ01-CG-PRO-53-0113
Page 27 of 41
Rev: A02 Project Internal
Khazzan Project
Commissioning Hazard Identification and Task Risk Assessment
APPENDIX C IMPACT ASSESSMENT TABLE Severity
A
B
Health and Safety Levels A-C maintain the visibility of risks with the potential for catastrophic impact even if their probability of occurrence is extremely low. The upper level of this framework is defined by the most severe level of impact ever seen in industry.
Comparable to the most catastrophic health/safety incidents ever seen in industry. The potential for 100 or more fatalities (or onset of life threatening health effects) shall always be classified at this level.
Catastrophic health/safety incident causing very widespread fatalities within or outside a facility. The potential for 50 or more fatalities (or onset of life threatening health effects) shall always be classified at this level.
Catastrophic health/safety incident causing widespread fatalities within or outside a facility. The potential for 10 or more fatalities (or onset of life threatening health effects) shall always be classified at this level.
Environmental
Future impact, e.g., unintended release, with widespread damage to any environment and which remains in an "unsatisfactory" state for a period > 5 years.
Future impact with extensive damage to a sensitive environment and which remains in an "unsatisfactory" state for a period > 5 years.
Future impact with widespread damage to a sensitive environment and which can only be restored to a "satisfactory"/agreed state in a period of more than 1 and up to 5 years.
Future impact with extensive damage to a non-sensitive environment and which remains in an "unsatisfactory" state for a period > 5 years.
Future impact with extensive damage to a sensitive environment and which can only be restored to a "satisfactory"/agreed state in a period of more than 1 and up to 5 years.
Future impact with widespread damage to a non-sensitive environment and which can only be restored to a "satisfactory"/agreed state in a period of more than 1 and up to 5 years.
Future impact with widespread damage to a sensitive environment and which can be restored to an equivalent capability in a period of around 1 year.
Future impact with extensive damage to a non-sensitive environment and which can only be restored to a "satisfactory"/agreed state in a period of more than 1 and up to 5 years.
Future impact with widespread damage to a non-sensitive environment and which can be restored to an equivalent capability in a period of around 1 year.
Future impact with extensive damage to a sensitive environment and which can be restored to an equivalent capability in a period of around 1 year.
Future impact with widespread damage to a sensitive environment and which can be restored to an equivalent capability in a period of months.
C
Every employee associate with this project has the ultimate responsibility for Health, Safety, Security & Environmental performance. This will be achieved through a positive HSSE culture at all the levels and by implementing a robust HSSE Management system. Petrofac and its Sub-Contractor management will continually strive towards reducing HSSE risks to As Low As Reasonably Practical (ALARP) in all its operations to achieve the Project HSSE goals. KZ01-CG-PRO-53-0113
Page 28 of 41
Rev: A02 Project Internal
Khazzan Project
Severity
D
Commissioning Hazard Identification and Task Risk Assessment
Health and Safety Very major health/safety incident The potential for 3 or more fatalities (or onset of life threatening health effects) shall always be classified at this level. 30 or more injuries or health effects, either permanent or requiring hospital treatment for more than 24 hours.
Major health/safety incident 1 or 2 fatalities, acute or chronic, actual or alleged. 10 or more injuries or health effects, either permanent or requiring hospital treatment for more than 24 hours.
E
F
High impact health/safety incident Permanent partial disability(ies) Several non-permanent injuries or health impacts. Days Away From Work Case (DAFWC)
Medium impact health/safety incident Single or multiple recordable injury or health effects from common source/event.
G
H
Low impact health/safety incident
KZ01-CG-PRO-53-0113
Page 29 of 41
Environmental
Future impact with extensive damage to a non-sensitive environment and which can be restored to an equivalent capability in a period of around 1 year.
Future impact with localized damage to a sensitive environment and which can be restored to an equivalent capability in a period of around 1 year.
Future impact with widespread damage to a non-sensitive environment and which can be restored to an equivalent capability in a period of months.
Future impact with extensive damage to a sensitive environment and which can be restored to an equivalent capability in a period of months.
Future impact with localized damage to a non-sensitive environment and which can be restored to an equivalent capability in a period of around 1 year.
Future impact with extensive damage to a non-sensitive environment and which can be restored to an equivalent capability in a period of months.
Future impact with localized damage to a sensitive environment and which can be restored to an equivalent capability in a period of months.
Future impact with extensive damage to a sensitive environment and which can be restored to an equivalent capability in a period of days or weeks.
Future impact with localized damage to a non-sensitive environment and which can be restored to an equivalent capability in a period of months.
Future impact with immediate area damage to a sensitive environment and which can be restored to an equivalent capability in a period of months.
Future impact with extensive damage to a non-sensitive environment and which can be restored to an equivalent capability in a period of days or weeks.
Future impact with localized damage to a sensitive environment and which can be restored to an equivalent capability in a period of days or weeks.
Future impact with immediate area damage to a non-sensitive environment and which can be restored to an equivalent capability in a period of months.
Future impact with localized damage to a non-sensitive environment and which can be restored to an equivalent capability in a period of days or weeks.
Future impact with immediate area damage to a sensitive environment and which can be restored to an equivalent capability in a period of days or weeks.
Future impact with immediate area damage to a non-sensitive environment Rev: A02 Project Internal
Khazzan Project
Severity
Commissioning Hazard Identification and Task Risk Assessment
Health and Safety First aid Single or multiple over-exposures causing noticeable irritation but no actual health effects
KZ01-CG-PRO-53-0113
Page 30 of 41
Environmental and which can be restored to an equivalent capability in a period of days or weeks.
Rev: A02 Project Internal
Khazzan Project
Commissioning Hazard Identification and Task Risk Assessment
Financial Impact Severity
Non-financial Business Impact
(equipment damage, business value lost)
A
Public or investor outrage on a global scale. Threat of global loss of license to operate.
>$20 billion
B
Loss of license to operate a major asset in a major market – US, EU, Russia. Intervention from major Government – US, UK, EU, Russia. Public or investor outrage in major western markets – US, EU. Damage to relationships with key stakeholders of benefit to the Group.
$5 billion - $20 billion
C
Loss of license to operate other material asset, or severe enforcement action against a major asset in a major market. Intervention from other major Government. Public or investor outrage in other material market where we have presence or aspiration.
$1 billion - $5 billion
D
Severe enforcement action against a material asset in a non-major market, or against other assets in a major market. Interventions from non-major Governments. Public or investor outrage in a non-major market, or localised or limited “interest-group” outrage in a major market. Prolonged adverse national or international media attention. Widespread adverse social impact. Damage to relationships with key stakeholders of benefit to the Segment.
$100 m to $1 billion
E
Other adverse enforcement action by regulators. Limited “interest-group” outrage in non-major market. Short term adverse national or international media coverage. Damage to relationships with key stakeholders of benefit to the SPU.
$5m -$100m
F
Regulatory compliance issue which does not lead to regulatory or other higher severity level consequence Prolonged local media coverage. Local adverse social impact. Damage to relationships with key stakeholders of benefit to the Performance Unit (PU).
$500k-$5m
G
Short term local media coverage. Some disruption to local operations (e.g., loss of single road access less than 24 hours).
$50k -$500k
H
Isolated and short term complaints from neighbours (e.g., complaints about specific noise episode).
View more...
Comments