Haviland- Chiller Plant Design Considerations

Share Embed Donate


Short Description

Download Haviland- Chiller Plant Design Considerations...

Description

Chiller Plant Design Considerations Jon R. Haviland, P.E., CEM Assistant Vice President Marx/Okubo Associates [email protected]

z Plant

design options z Equipment options z New plant design considerations z Retrofit design considerations z Retrofit project case study

Better Buildings by Design 2005

Chiller Plant Design

2

Plant Design Options

Better Buildings by Design 2005

Chiller Plant Design

3

Single Chiller System Tower TWP

Chiller

CWP Loads Better Buildings by Design 2005

Chiller Plant Design

4

Single Chiller System z Advantages – Lower first cost – Simple system for installation and control

z Disadvantages – Inefficient at low load conditions – Lack of back-up and redundancy

Better Buildings by Design 2005

Chiller Plant Design

5

Parallel Chiller System Tower TWP1 CWP1

Chiller 1

TWP2 CWP2

Chiller 2

Loads Better Buildings by Design 2005

Chiller Plant Design

6

Parallel Chiller System z

Advantages – More efficient at low load conditions – Provides back-up and/or redundancy

z

Disadvantages – Increased first cost – More difficult to control effectively, especially with

different size chillers (should have computerized system) – More equipment to maintain Better Buildings by Design 2005

Chiller Plant Design

7

Series Chiller System Tower TWP

Chiller 1

Chiller 2

CWP Loads Better Buildings by Design 2005

Chiller Plant Design

8

Series Chiller System z

Advantages – Easier to control with simple control systems – Effective with different size chillers – Utilize one stand-by pump – Good for large temperature differential systems

z

Disadvantages – Increased pumping requirements for chilled water – Chillers may not be interchangeable

Better Buildings by Design 2005

Chiller Plant Design

9

Primary-Secondary Chilled Water Systems

Better Buildings by Design 2005

Chiller Plant Design

10

Primary-Secondary Chilled Water Systems z Advantages – Uncouples chillers and loads to allow variable flow in – – – – –

loads Can be used with large temperature differential systems Can be used with thermal storage systems Can be used with water-side economizer systems Improved control Reduced operating costs

Better Buildings by Design 2005

Chiller Plant Design

11

Primary-Secondary Chilled Water Systems z Disadvantages – Higher first costs – Requires more, sophisticated equipment – Requires sophisticated control system

Better Buildings by Design 2005

Chiller Plant Design

12

Variable Flow Primary z New

chillers can operate with variable flow z Simplifies system design z Bypass with modulating control valve required to maintain minimum flow z System can be parallel or series design

Better Buildings by Design 2005

Chiller Plant Design

13

Equipment Options

Better Buildings by Design 2005

Chiller Plant Design

14

Electric Chillers z Reciprocating

chillers z Rotary screw chillers z Centrifugal chillers z Air-cooled chillers

Better Buildings by Design 2005

Chiller Plant Design

15

Non-electric Chillers z Absorption chillers – Single-effect absorption chiller z z z

Low pressure steam Hot water Use in CHP applications

– Double-effect absorption chillers z Medium pressure steam z Direct-fired z Heat recovery Better Buildings by Design 2005

Chiller Plant Design

16

Non-electric Chillers z Centrifugal

or screw chiller without electric

motor – Natural gas engine – Steam turbine – Dual drive – engine and electric motor

Better Buildings by Design 2005

Chiller Plant Design

17

Other Cooling Sources z Air-side

economizer z Water-side economizer z Thermal energy storage

Better Buildings by Design 2005

Chiller Plant Design

18

New Plant Design Considerations z Determine

requirements z Design process z After construction considerations

Better Buildings by Design 2005

Chiller Plant Design

19

Determine Requirements z Capacity

required

– Current load – Potential future loads – Redundancy requirement – Provisions for special loads

Better Buildings by Design 2005

Chiller Plant Design

20

Determine Requirements z Operating

profile

– Hours per day – Days per week – Continuous loads – Load diversity

Better Buildings by Design 2005

Chiller Plant Design

21

Design Process z Schematic

design of possible options

– Chiller sizing – Chiller Performance – Cooling sources – Operating temperatures – Cooling tower selection – Basic plant layout Better Buildings by Design 2005

Chiller Plant Design

22

Chiller Sizing z Benefits

of different size chillers

– Fewer total operating hours – More operation above 50% load

z Depends

Better Buildings by Design 2005

on load profile

Chiller Plant Design

23

Even Chillers - 8,463 operating hours

Better Buildings by Design 2005

Chiller Plant Design

24

Uneven Chillers - 7,624 operating hours

Better Buildings by Design 2005

Chiller Plant Design

25

Chiller Sizing z Use

of different size chillers may eliminate need for pony chiller z Variable speed chillers provide improved part load performance and minimum capacity

Better Buildings by Design 2005

Chiller Plant Design

26

Chiller Performance Ratings z American

Refrigeration Institute Standard 550/590-98 z Standard conditions – Full load – Chilled water temperatures - 54 F to 44 F – Condenser water temperatures - 85 F to 95 F

z Efficiency Better Buildings by Design 2005

rating - kW/Ton Chiller Plant Design

27

Chiller Performance Ratings z Part

load efficiency

– Integrated Part Load Value (IPLV) z Standard temperature conditions z Weighted average of kW/ton at various loads – Non-standard Part Load Value (NPLV) z Specific application temperatures z Same weighting as IPLV

Better Buildings by Design 2005

Chiller Plant Design

28

Chiller Performance Ratings z IPLV/NPLV

rating scale

– A = kW/ton at 100% load – B = kW/ton at 75% load – C = kW/ton at 50% load – D = kW/ton at 25% load

z ARI

Standard 550-98

– IPLV = 1/(0.01/A + 0.42/B + 0.45/C + 0.12/D) Better Buildings by Design 2005

Chiller Plant Design

29

Cooling Sources z Use

of different fuel sources provides flexibility and reliability z Types to be considered depend on several factors – – – –

Utility rates and structure Load profile Air quality considerations Maintenance considerations

Better Buildings by Design 2005

Chiller Plant Design

30

Cooling Sources z Economizer

cycle

– Air-side generally most effective – Water-side use z Building configuration does not allow air-side z Cooling for special load requirements z Climatic considerations

Better Buildings by Design 2005

Chiller Plant Design

31

Operating Temperatures z Chilled

water supply temperature

– Lower supply temperature z Reduced air flow requirements z Improved dehumidification z Increased chiller operating cost versus reduced fan operating costs, especially with a VAV system

Better Buildings by Design 2005

Chiller Plant Design

32

Operating Temperatures z Chilled

water ∆T

– Higher ∆T means reduced pipe size and

pumping requirement, increased coil size, and reduced fan energy – Optimum temperature depends on amount of piping in system

Better Buildings by Design 2005

Chiller Plant Design

33

Chilled Water ∆T Comparison

Better Buildings by Design 2005

Chiller Plant Design

34

Operating Temperatures z Condenser

water supply temperature

– Lower supply temperature improves chiller

efficiency – Approach temperature can be 6 – 10 ºF above design wet bulb – Use 0.4% design temperature data

Better Buildings by Design 2005

Chiller Plant Design

35

Operating Temperatures z Condenser

water ∆T

– Normal 10ºF works well in most cases – Larger ∆T common with absorption chillers

due to higher load and should be considered for large systems or when the cooling tower is remote from the chiller plant – Reduced chiller efficiency versus smaller pipes and reduced pumping horsepower Better Buildings by Design 2005

Chiller Plant Design

36

Cooling Tower Selection z Selection

should be based on required water flow, optimum approach temperature and ∆T z Allowance for potential tenant equipment load z Selection should based on water-side economizer conditions if that is part of system Better Buildings by Design 2005

Chiller Plant Design

37

Cooling Tower Selection z Increasing

size of the cooling tower is generally the least expensive way to improve the efficiency and provide some safety margin in the system z Use of variable speed drive on the fan motor minimizes any operating cost penalty

Better Buildings by Design 2005

Chiller Plant Design

38

Determine Basic Plant Layout z Select

system that will best fit needs of project z For simpler systems, parallel system with different size chillers is probably best choice

Better Buildings by Design 2005

Chiller Plant Design

39

Determine Basic Plant Layout z Systems

with different occupancy schedules or load requirements need more complex system – Primary-secondary plant offers most flexibility – Variable primary flow works with new electric

chillers with less complexity than a primarysecondary system

Better Buildings by Design 2005

Chiller Plant Design

40

Determine Basic Plant Layout z Large

chilled water ∆T

– Series plant – Primary-secondary with primary flow greater

than secondary flow

Better Buildings by Design 2005

Chiller Plant Design

41

Design Process z Analyze

options

– Opinion of probable costs – Operating cost estimates z Screening measures z Energy simulation – Life cycle costs

Better Buildings by Design 2005

Chiller Plant Design

42

Design Process z Complete

design of chosen option

– Peer review – Operator review – Determine sequence of operations

Better Buildings by Design 2005

Chiller Plant Design

43

New Plant Design Considerations z After

construction activities

– Commissioning – Training

Better Buildings by Design 2005

Chiller Plant Design

44

Chiller Plant Retrofit Considerations

Better Buildings by Design 2005

Chiller Plant Design

45

Don’t Simply Replace; Re-engineer

Chiller Plant Retrofit Considerations z Basic

process should follow same steps as outlined above z Additional considerations – Engineer and contractor should have experience

with this type of project

Better Buildings by Design 2005

Chiller Plant Design

47

Chiller Plant Retrofit Considerations z Additional

considerations

– Engineer needs to familiarize himself with

existing plant z z z

Record drawings Operator interview Observation of plant

Better Buildings by Design 2005

Chiller Plant Design

48

Chiller Plant Retrofit Considerations – Constructability should be considered during

design phase z z

Operator review Contractor review

– Coordination critical during construction phase

Better Buildings by Design 2005

Chiller Plant Design

49

Retrofit Project Case Study

Background z Vacated

single tenant building z 26 years old z Adjacent buildings under same ownership with sale of one or all unlikely z Building to be taken to shell condition and renovated for multi-tenant use z Due diligence based on these assumptions Better Buildings by Design 2005

Chiller Plant Design

51

Site Plan

Better Buildings by Design 2005

Chiller Plant Design

52

Participants z Owner z Project

manager z Property managers (2 firms) – Contract maintenance staff

z Construction

manager

z Consultants – Architect – Engineer Better Buildings by Design 2005

Chiller Plant Design

53

Existing Central Plant z z z

Located in penthouse Two 360-ton single effect absorption chillers Two low pressure steam boilers – Modified to meet AQMD requirements – Also provides heating and domestic hot water

z

Two cell cooling tower – Replaced three years earlier – Capacity for single effect absorption chillers

Better Buildings by Design 2005

Chiller Plant Design

54

Possible Options z Electric

chillers z Absorption chillers z Engine-driven chillers z Thermal storage z Independent or with adjacent building

Better Buildings by Design 2005

Chiller Plant Design

55

Alternatives Considered z Stand-alone

alternatives

– Two 350-ton electric chillers – Two 350-ton absorption chillers – Two 350-ton engine-driven chillers – Electric chillers with 4500 ton-hour thermal

storage

Better Buildings by Design 2005

Chiller Plant Design

56

Alternatives Considered z Integrated

alternatives

– Provide piping between two buildings – Utilize one of the four options above for the

stand-alone plant

Better Buildings by Design 2005

Chiller Plant Design

57

Alternatives Considered z Single

plant alternatives

– Abandon plant in Building 2 and expand plant

in Building 3 with piping between the buildings – Existing Plant in Building 3 z

z

Three 250-ton electric chillers in plant on parking level P-2 Cooling tower on roof

Better Buildings by Design 2005

Chiller Plant Design

58

Alternatives Considered z Single

plant alternatives

– New Equipment possibilities z 600-ton electric chiller z Two 350-ton engine-driven chillers z Two low temperature chillers plus 4500 ton-hour thermal storage

Better Buildings by Design 2005

Chiller Plant Design

59

Constructibility Issues z Building

2 options

– Electric capacity – Cooling tower and structure – Existing chilled water riser size – Noise considerations

Better Buildings by Design 2005

Chiller Plant Design

60

Constructibility Issues z Building

3 options

– Cooling tower capacity – Condenser water riser size – Thermal storage space requirements – Engine exhaust routing – Electrical capacity

Better Buildings by Design 2005

Chiller Plant Design

61

Analysis z Opinion

of probable costs z Schedule z Operating costs – DOE-2 simulations – Nine options considered

Better Buildings by Design 2005

Chiller Plant Design

62

Analysis z Other

considerations

– Electricity riser problem in Building 2 – Impact of utility deregulation

Better Buildings by Design 2005

Chiller Plant Design

63

Economic Analysis z Based

on estimated impact of deregulation z Final options – Integrated system with new chillers in Building

2 connected to Building 3 plant z z

700-tons electric 700-tons absorption

Better Buildings by Design 2005

Chiller Plant Design

64

Economic Analysis z First

Cost

– 700 ton electric z $929,223 z $1,109,273 with potential bus duct repair – 700 ton absorption z $1,395,247

Better Buildings by Design 2005

Chiller Plant Design

65

Economic Analysis z Annual

energy cost

– 700 ton electric - $778,160 – 700 ton absorption - $680,769

z Simple

Payback

– Without bus riser repair – 4.5 years – With bus riser repair – 1.9 years

Better Buildings by Design 2005

Chiller Plant Design

66

Final Choice z Absorption

chillers in Building 2 with connection to Building 3 – Proactive ownership with long term outlook – Support from local natural gas utility – Optimum conditions for new plant in Building

2 – Significant problems with expanding plant in Building 3 Better Buildings by Design 2005

Chiller Plant Design

67

Chiller Purchase z Chiller

pre-purchased by owner

– Maintain control over final selection and

options – Delivery critical z

z

Potential full building tenant wanted early availability City rigging restrictions – Saturday night only

Better Buildings by Design 2005

Chiller Plant Design

68

Chiller Purchase z Bid

to major manufacturers z Bid specified conditions of capacity, giving cost, efficiency, delivery and willingness to accept penalty clause z Allow manufacturers to suggest alternatives of capacity and/or efficiency and additional cost for this Better Buildings by Design 2005

Chiller Plant Design

69

New Central Plant z Two

360-ton direct fired absorption chillers with lower supply temperature z One 120-ton rotary screw chiller for off hours use (minimum effective absorption chiller capacity) z Primary-secondary piping system z Piping between the two buildings with transfer pumps and metering Better Buildings by Design 2005

Chiller Plant Design

70

Single Line Diagram

Better Buildings by Design 2005

Chiller Plant Design

71

Sequence of Operations z Seven

modes of operation identified with written sequence z Independent versus integrated operation z Electric or gas chiller base load z Occupied versus unoccupied

Better Buildings by Design 2005

Chiller Plant Design

72

Phase II z Building

1 central plant

– Originally absorption chillers and boilers – Reciprocating chillers installed in 1987 z Noise complaints z Reliability issues – Small chiller in Building 3 plant for Fitness

Center after hours use with piping to lower level air handling unit Better Buildings by Design 2005

Chiller Plant Design

73

New Building 1 Plant z Two

centrifugal chillers and new cooling tower – Tower selected for maximum capacity for space

available – Chillers selected to match cooling tower capacity – Use existing connection (increase size to maximize transfer capacity) with new riser Better Buildings by Design 2005

Chiller Plant Design

74

New Single Line Diagram

Better Buildings by Design 2005

Chiller Plant Design

75

Summary z Project

illustrates choices available and retrofit process discussed z Ownership with long term outlook z Cooperation by all participants z Life is easier with a vacant building

Better Buildings by Design 2005

Chiller Plant Design

76

View more...

Comments

Copyright ©2017 KUPDF Inc.
SUPPORT KUPDF