Download Haviland- Chiller Plant Design Considerations...
Chiller Plant Design Considerations Jon R. Haviland, P.E., CEM Assistant Vice President Marx/Okubo Associates
[email protected]
z Plant
design options z Equipment options z New plant design considerations z Retrofit design considerations z Retrofit project case study
Better Buildings by Design 2005
Chiller Plant Design
2
Plant Design Options
Better Buildings by Design 2005
Chiller Plant Design
3
Single Chiller System Tower TWP
Chiller
CWP Loads Better Buildings by Design 2005
Chiller Plant Design
4
Single Chiller System z Advantages – Lower first cost – Simple system for installation and control
z Disadvantages – Inefficient at low load conditions – Lack of back-up and redundancy
Better Buildings by Design 2005
Chiller Plant Design
5
Parallel Chiller System Tower TWP1 CWP1
Chiller 1
TWP2 CWP2
Chiller 2
Loads Better Buildings by Design 2005
Chiller Plant Design
6
Parallel Chiller System z
Advantages – More efficient at low load conditions – Provides back-up and/or redundancy
z
Disadvantages – Increased first cost – More difficult to control effectively, especially with
different size chillers (should have computerized system) – More equipment to maintain Better Buildings by Design 2005
Chiller Plant Design
7
Series Chiller System Tower TWP
Chiller 1
Chiller 2
CWP Loads Better Buildings by Design 2005
Chiller Plant Design
8
Series Chiller System z
Advantages – Easier to control with simple control systems – Effective with different size chillers – Utilize one stand-by pump – Good for large temperature differential systems
z
Disadvantages – Increased pumping requirements for chilled water – Chillers may not be interchangeable
Better Buildings by Design 2005
Chiller Plant Design
9
Primary-Secondary Chilled Water Systems
Better Buildings by Design 2005
Chiller Plant Design
10
Primary-Secondary Chilled Water Systems z Advantages – Uncouples chillers and loads to allow variable flow in – – – – –
loads Can be used with large temperature differential systems Can be used with thermal storage systems Can be used with water-side economizer systems Improved control Reduced operating costs
Better Buildings by Design 2005
Chiller Plant Design
11
Primary-Secondary Chilled Water Systems z Disadvantages – Higher first costs – Requires more, sophisticated equipment – Requires sophisticated control system
Better Buildings by Design 2005
Chiller Plant Design
12
Variable Flow Primary z New
chillers can operate with variable flow z Simplifies system design z Bypass with modulating control valve required to maintain minimum flow z System can be parallel or series design
Better Buildings by Design 2005
Chiller Plant Design
13
Equipment Options
Better Buildings by Design 2005
Chiller Plant Design
14
Electric Chillers z Reciprocating
chillers z Rotary screw chillers z Centrifugal chillers z Air-cooled chillers
Better Buildings by Design 2005
Chiller Plant Design
15
Non-electric Chillers z Absorption chillers – Single-effect absorption chiller z z z
Low pressure steam Hot water Use in CHP applications
– Double-effect absorption chillers z Medium pressure steam z Direct-fired z Heat recovery Better Buildings by Design 2005
Chiller Plant Design
16
Non-electric Chillers z Centrifugal
or screw chiller without electric
motor – Natural gas engine – Steam turbine – Dual drive – engine and electric motor
Better Buildings by Design 2005
Chiller Plant Design
17
Other Cooling Sources z Air-side
economizer z Water-side economizer z Thermal energy storage
Better Buildings by Design 2005
Chiller Plant Design
18
New Plant Design Considerations z Determine
requirements z Design process z After construction considerations
Better Buildings by Design 2005
Chiller Plant Design
19
Determine Requirements z Capacity
required
– Current load – Potential future loads – Redundancy requirement – Provisions for special loads
Better Buildings by Design 2005
Chiller Plant Design
20
Determine Requirements z Operating
profile
– Hours per day – Days per week – Continuous loads – Load diversity
Better Buildings by Design 2005
Chiller Plant Design
21
Design Process z Schematic
design of possible options
– Chiller sizing – Chiller Performance – Cooling sources – Operating temperatures – Cooling tower selection – Basic plant layout Better Buildings by Design 2005
Chiller Plant Design
22
Chiller Sizing z Benefits
of different size chillers
– Fewer total operating hours – More operation above 50% load
z Depends
Better Buildings by Design 2005
on load profile
Chiller Plant Design
23
Even Chillers - 8,463 operating hours
Better Buildings by Design 2005
Chiller Plant Design
24
Uneven Chillers - 7,624 operating hours
Better Buildings by Design 2005
Chiller Plant Design
25
Chiller Sizing z Use
of different size chillers may eliminate need for pony chiller z Variable speed chillers provide improved part load performance and minimum capacity
Better Buildings by Design 2005
Chiller Plant Design
26
Chiller Performance Ratings z American
Refrigeration Institute Standard 550/590-98 z Standard conditions – Full load – Chilled water temperatures - 54 F to 44 F – Condenser water temperatures - 85 F to 95 F
z Efficiency Better Buildings by Design 2005
rating - kW/Ton Chiller Plant Design
27
Chiller Performance Ratings z Part
load efficiency
– Integrated Part Load Value (IPLV) z Standard temperature conditions z Weighted average of kW/ton at various loads – Non-standard Part Load Value (NPLV) z Specific application temperatures z Same weighting as IPLV
Better Buildings by Design 2005
Chiller Plant Design
28
Chiller Performance Ratings z IPLV/NPLV
rating scale
– A = kW/ton at 100% load – B = kW/ton at 75% load – C = kW/ton at 50% load – D = kW/ton at 25% load
z ARI
Standard 550-98
– IPLV = 1/(0.01/A + 0.42/B + 0.45/C + 0.12/D) Better Buildings by Design 2005
Chiller Plant Design
29
Cooling Sources z Use
of different fuel sources provides flexibility and reliability z Types to be considered depend on several factors – – – –
Utility rates and structure Load profile Air quality considerations Maintenance considerations
Better Buildings by Design 2005
Chiller Plant Design
30
Cooling Sources z Economizer
cycle
– Air-side generally most effective – Water-side use z Building configuration does not allow air-side z Cooling for special load requirements z Climatic considerations
Better Buildings by Design 2005
Chiller Plant Design
31
Operating Temperatures z Chilled
water supply temperature
– Lower supply temperature z Reduced air flow requirements z Improved dehumidification z Increased chiller operating cost versus reduced fan operating costs, especially with a VAV system
Better Buildings by Design 2005
Chiller Plant Design
32
Operating Temperatures z Chilled
water ∆T
– Higher ∆T means reduced pipe size and
pumping requirement, increased coil size, and reduced fan energy – Optimum temperature depends on amount of piping in system
Better Buildings by Design 2005
Chiller Plant Design
33
Chilled Water ∆T Comparison
Better Buildings by Design 2005
Chiller Plant Design
34
Operating Temperatures z Condenser
water supply temperature
– Lower supply temperature improves chiller
efficiency – Approach temperature can be 6 – 10 ºF above design wet bulb – Use 0.4% design temperature data
Better Buildings by Design 2005
Chiller Plant Design
35
Operating Temperatures z Condenser
water ∆T
– Normal 10ºF works well in most cases – Larger ∆T common with absorption chillers
due to higher load and should be considered for large systems or when the cooling tower is remote from the chiller plant – Reduced chiller efficiency versus smaller pipes and reduced pumping horsepower Better Buildings by Design 2005
Chiller Plant Design
36
Cooling Tower Selection z Selection
should be based on required water flow, optimum approach temperature and ∆T z Allowance for potential tenant equipment load z Selection should based on water-side economizer conditions if that is part of system Better Buildings by Design 2005
Chiller Plant Design
37
Cooling Tower Selection z Increasing
size of the cooling tower is generally the least expensive way to improve the efficiency and provide some safety margin in the system z Use of variable speed drive on the fan motor minimizes any operating cost penalty
Better Buildings by Design 2005
Chiller Plant Design
38
Determine Basic Plant Layout z Select
system that will best fit needs of project z For simpler systems, parallel system with different size chillers is probably best choice
Better Buildings by Design 2005
Chiller Plant Design
39
Determine Basic Plant Layout z Systems
with different occupancy schedules or load requirements need more complex system – Primary-secondary plant offers most flexibility – Variable primary flow works with new electric
chillers with less complexity than a primarysecondary system
Better Buildings by Design 2005
Chiller Plant Design
40
Determine Basic Plant Layout z Large
chilled water ∆T
– Series plant – Primary-secondary with primary flow greater
than secondary flow
Better Buildings by Design 2005
Chiller Plant Design
41
Design Process z Analyze
options
– Opinion of probable costs – Operating cost estimates z Screening measures z Energy simulation – Life cycle costs
Better Buildings by Design 2005
Chiller Plant Design
42
Design Process z Complete
design of chosen option
– Peer review – Operator review – Determine sequence of operations
Better Buildings by Design 2005
Chiller Plant Design
43
New Plant Design Considerations z After
construction activities
– Commissioning – Training
Better Buildings by Design 2005
Chiller Plant Design
44
Chiller Plant Retrofit Considerations
Better Buildings by Design 2005
Chiller Plant Design
45
Don’t Simply Replace; Re-engineer
Chiller Plant Retrofit Considerations z Basic
process should follow same steps as outlined above z Additional considerations – Engineer and contractor should have experience
with this type of project
Better Buildings by Design 2005
Chiller Plant Design
47
Chiller Plant Retrofit Considerations z Additional
considerations
– Engineer needs to familiarize himself with
existing plant z z z
Record drawings Operator interview Observation of plant
Better Buildings by Design 2005
Chiller Plant Design
48
Chiller Plant Retrofit Considerations – Constructability should be considered during
design phase z z
Operator review Contractor review
– Coordination critical during construction phase
Better Buildings by Design 2005
Chiller Plant Design
49
Retrofit Project Case Study
Background z Vacated
single tenant building z 26 years old z Adjacent buildings under same ownership with sale of one or all unlikely z Building to be taken to shell condition and renovated for multi-tenant use z Due diligence based on these assumptions Better Buildings by Design 2005
Chiller Plant Design
51
Site Plan
Better Buildings by Design 2005
Chiller Plant Design
52
Participants z Owner z Project
manager z Property managers (2 firms) – Contract maintenance staff
z Construction
manager
z Consultants – Architect – Engineer Better Buildings by Design 2005
Chiller Plant Design
53
Existing Central Plant z z z
Located in penthouse Two 360-ton single effect absorption chillers Two low pressure steam boilers – Modified to meet AQMD requirements – Also provides heating and domestic hot water
z
Two cell cooling tower – Replaced three years earlier – Capacity for single effect absorption chillers
Better Buildings by Design 2005
Chiller Plant Design
54
Possible Options z Electric
chillers z Absorption chillers z Engine-driven chillers z Thermal storage z Independent or with adjacent building
Better Buildings by Design 2005
Chiller Plant Design
55
Alternatives Considered z Stand-alone
alternatives
– Two 350-ton electric chillers – Two 350-ton absorption chillers – Two 350-ton engine-driven chillers – Electric chillers with 4500 ton-hour thermal
storage
Better Buildings by Design 2005
Chiller Plant Design
56
Alternatives Considered z Integrated
alternatives
– Provide piping between two buildings – Utilize one of the four options above for the
stand-alone plant
Better Buildings by Design 2005
Chiller Plant Design
57
Alternatives Considered z Single
plant alternatives
– Abandon plant in Building 2 and expand plant
in Building 3 with piping between the buildings – Existing Plant in Building 3 z
z
Three 250-ton electric chillers in plant on parking level P-2 Cooling tower on roof
Better Buildings by Design 2005
Chiller Plant Design
58
Alternatives Considered z Single
plant alternatives
– New Equipment possibilities z 600-ton electric chiller z Two 350-ton engine-driven chillers z Two low temperature chillers plus 4500 ton-hour thermal storage
Better Buildings by Design 2005
Chiller Plant Design
59
Constructibility Issues z Building
2 options
– Electric capacity – Cooling tower and structure – Existing chilled water riser size – Noise considerations
Better Buildings by Design 2005
Chiller Plant Design
60
Constructibility Issues z Building
3 options
– Cooling tower capacity – Condenser water riser size – Thermal storage space requirements – Engine exhaust routing – Electrical capacity
Better Buildings by Design 2005
Chiller Plant Design
61
Analysis z Opinion
of probable costs z Schedule z Operating costs – DOE-2 simulations – Nine options considered
Better Buildings by Design 2005
Chiller Plant Design
62
Analysis z Other
considerations
– Electricity riser problem in Building 2 – Impact of utility deregulation
Better Buildings by Design 2005
Chiller Plant Design
63
Economic Analysis z Based
on estimated impact of deregulation z Final options – Integrated system with new chillers in Building
2 connected to Building 3 plant z z
700-tons electric 700-tons absorption
Better Buildings by Design 2005
Chiller Plant Design
64
Economic Analysis z First
Cost
– 700 ton electric z $929,223 z $1,109,273 with potential bus duct repair – 700 ton absorption z $1,395,247
Better Buildings by Design 2005
Chiller Plant Design
65
Economic Analysis z Annual
energy cost
– 700 ton electric - $778,160 – 700 ton absorption - $680,769
z Simple
Payback
– Without bus riser repair – 4.5 years – With bus riser repair – 1.9 years
Better Buildings by Design 2005
Chiller Plant Design
66
Final Choice z Absorption
chillers in Building 2 with connection to Building 3 – Proactive ownership with long term outlook – Support from local natural gas utility – Optimum conditions for new plant in Building
2 – Significant problems with expanding plant in Building 3 Better Buildings by Design 2005
Chiller Plant Design
67
Chiller Purchase z Chiller
pre-purchased by owner
– Maintain control over final selection and
options – Delivery critical z
z
Potential full building tenant wanted early availability City rigging restrictions – Saturday night only
Better Buildings by Design 2005
Chiller Plant Design
68
Chiller Purchase z Bid
to major manufacturers z Bid specified conditions of capacity, giving cost, efficiency, delivery and willingness to accept penalty clause z Allow manufacturers to suggest alternatives of capacity and/or efficiency and additional cost for this Better Buildings by Design 2005
Chiller Plant Design
69
New Central Plant z Two
360-ton direct fired absorption chillers with lower supply temperature z One 120-ton rotary screw chiller for off hours use (minimum effective absorption chiller capacity) z Primary-secondary piping system z Piping between the two buildings with transfer pumps and metering Better Buildings by Design 2005
Chiller Plant Design
70
Single Line Diagram
Better Buildings by Design 2005
Chiller Plant Design
71
Sequence of Operations z Seven
modes of operation identified with written sequence z Independent versus integrated operation z Electric or gas chiller base load z Occupied versus unoccupied
Better Buildings by Design 2005
Chiller Plant Design
72
Phase II z Building
1 central plant
– Originally absorption chillers and boilers – Reciprocating chillers installed in 1987 z Noise complaints z Reliability issues – Small chiller in Building 3 plant for Fitness
Center after hours use with piping to lower level air handling unit Better Buildings by Design 2005
Chiller Plant Design
73
New Building 1 Plant z Two
centrifugal chillers and new cooling tower – Tower selected for maximum capacity for space
available – Chillers selected to match cooling tower capacity – Use existing connection (increase size to maximize transfer capacity) with new riser Better Buildings by Design 2005
Chiller Plant Design
74
New Single Line Diagram
Better Buildings by Design 2005
Chiller Plant Design
75
Summary z Project
illustrates choices available and retrofit process discussed z Ownership with long term outlook z Cooperation by all participants z Life is easier with a vacant building
Better Buildings by Design 2005
Chiller Plant Design
76