HARMONIC PENETRATION ANALYSIS As per MOM KNOC UL-0004 DEV/S dated 27th April 05, it is concluded that detailed harmonic analysis calculation is not necessary for Electrical Power System of Rong Doi Gas Field Development Project. Accordingly this document is issued without change and shall be treated as final.
DISCIPLINE
ARCH
CONST
ELECT
INSTR
MAT’RL
MECH
PIPING
PIPELINE
PROCESS
SAFETY
STRUC
SIGN/DATE
-
-
-
-
-
-
-
-
-
-
-
D1
28-APR-05
APPROVED FOR CONSTRUCTION
YSN
JUB/MSH
BSK
C1
28-APR-05
APPROVED FOR DESIGN
YSN
JUB/MSH
BSK
B1
28-JAN-05
ISSUED FOR APPROVAL
HFS
BK
KCG
TM
A1
26-JAN-05
ISSUED FOR DIC / IDR
HFS
BK
-
-
-
Rev.
Date
Description
By
Checked
Approved
QA
Client
This document is the property of KECS – any unauthorized use of the same will be prosecuted. Total or partial reproduction and/or utilization of this document are forbidden without prior written authorization of the Owner Korea National Oil Corporation Vietnam Office
Category
Code Description
Facility
200
Common
Phase
30
Detailed Engineering
Discipline
E
Electrical Engineering
Type
CA
Calculation
Project Number
Facility
Phase
Discipline
Type
Sequence Number
Revision Code
VN01
200
30
E
CA
8007
D1
RONG DOI GAS FIELD DEVELOPMENT PROJECT HARMONIC PENETRATION ANALYSIS
TABLE OF CONTENTS SECTION
DESCRIPTION
PAGE
1.0
INTRODUCTION
1
2.0
OBJECTIVE
2
3.0
ACCEPTABLE HARMONIC DISTORTION LIMITS
2
4.0
STUDIES
3
4.1 4.2
3 3
CURRENT TOTAL HARMONIC DISTORTION (THDI) VOLTAGE TOTAL HARMONIC DISTORTION (THDU)
5.0
SYSTEM PARAMETERS
4
6.0
HARMONIC PARAMETERS
4
6.1 6.2 6.3 6.4
5 6 6 7
7.0
VSD FOR STARTING MOTOR UPS AND DC CHARGERS THYRISTER HEATER LIGHTING
INTRODUCTION The Kvaerner Engineering and Construction Singapore Pte Ltd (KECS) has been engaged by a HHI who have been awarded EPIC contract for the project to undertake certain design and engineering activities for a Rong Doi Gas Development Project operated by KNOC. The Rong Doi and Rong Doi Tay Fields are located in Block 11-2 in the Nam Con Son Basin offshore Vietnam. The Rong Doi and Rong Doi Tay Fields (RD and RDT) are located approximately 320km to the south-east of Vung Tau and were discovered in 1995 and 1996 respectively by KNOC, working as the Operator on behalf of a consortium of seven Korean companies. The Rong Doi Tay Field is located approximately 2.5km to the west of Rong Doi. The current development schedule will achieve a First Gas Date of 30 September 2006. The field and facilities are designed to deliver an average of 130MMscfd of sales gas but will have the capacity to produce up to 175MMscfd of sales gas for short periods. The objective of the Rong Doi and Rong Doi Tay development is to design, install, produce and deliver pipeline specification gas to the gas purchaser PetroVietnam, as per the terms of the Gas Sales and Purchase Agreement (GSPA). The facilities shall consist of a Wellhead Platform bridge connected (80m) to a Production Utilities Quarters Compression Platform (PUQC). An FSO will be installed to receive stabilized condensate stripped from the gas via a 2.5 Km long 6" line. The gas will be transported by a 58 Km 18” pipeline to a Wye in Namcon Son gas trunk line operated by BP. Drilling activities will be performed by a jack-up rig with all weather capability.
OBJECTIVE Harmonic analysis has been carried out to study the performance of the electrical system with harmonic loads. The purpose of harmonic analysis is to arrive at the total harmonic distortion at various locations due to harmonic producing loads in the network and to determine the corrective measures required to reduce the harmonic distortion to acceptable levels. Normally harmonic analysis is conducted when harmonic producing loads exceed 10% of total load. In Rong Doi Gas Field Development Project, the harmonic producing loads such as UPS, rectifiers, variable speed drives, thyrister control heaters and lighting constitutes more than 10% of total running loads. This has necessitated to conduct detail harmonic analysis for the complete Generation and Distribution System for Rong Doi Project. This study considered the impact of the harmonic producing equipment installed on Wellhead Platform (WHd) and Production Utilities Quarters Compression Platform (PUQC).
3.0
ACCEPTABLE HARMONIC DISTORTION LIMITS The total harmonic voltage distortion shall be limited to following values as indicated in Table 3.1 in compliance to IEC 61000. TABLE 3.1
indicated in Table 3.2 below. TABLE 3.2 - CURRENT DISTORTION LIMITS FOR GENERAL DISTRIBUTION SYSTEM (120V THROUGH 69,000V MAXIMUM HARMONIC CURRENT DISTORTION IN PERCENTAGE OF IL Individual Harmonic Order (Odd Harmonics) Isc/IL