FR-EE-403-00003-L
Short Description
Relay coordination report...
Description
L
5-NOV-2014
Rev.
Date
Issued for COMPANY Review Description
TAT
NAS
MTH
Prep’d By
Chk’d By
Appr’d By
COMPANY
EPC CONTRACTOR
Abu Dhabi Polymers Company Limited (Borouge)
PROJECT
BOROUGE PO FLARE GAS RECOVERY PROJECT TITLE
RELAY SETTINGS & PROTECTION COORDINATION STUDY Contractor Project No.:6502
Contractor Doc No: 6502-10-100-M1380-005-01
Document Class: 1 BOROUGE Document Information: Project No.
Document Number
Page
Rev.
PE/000451
FR-EE-403-00003
1 OF 14
L
Abu Dhabi Polymers Company Limited (Borouge)
BOROUGE PO FLARE GAS RECOVERY PROJECT RELAY SETTINGS & PROTECTION COORDINATION STUDY Issued date
Project No.
Document Number
Page
Rev.
5-NOV-2014
PE/000451
FR-EE-403-00003
2 OF 14
L
Revision / Changes: Revision No.
Page No.
Section
Change(s)
Abu Dhabi Polymers Company Limited (Borouge)
BOROUGE PO FLARE GAS RECOVERY PROJECT RELAY SETTINGS & PROTECTION COORDINATION STUDY Issued date
Project No.
Document Number
Page
Rev.
5-NOV-2014
PE/000451
FR-EE-403-00003
3 OF 14
L
TABLE OF CONTENTS 1 I NT R O D U CTI O N . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4 2 S T U DY O BJ E C T I V E . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4 3 R EFE RE NC E DO CUME NTS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4 4 ET AP MO DEL . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5 5 B A SIS & AS S UMPTI O N S . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6 6 N ET W O R K DE S C RIPTI O N FO R ST U DY . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6 7 M O DEL SIM U L ATI O N CO N DI TION S . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6 8 F A U LT C UR RE NT LEV ELS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7 9 R EL AY TYP E . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9 10 H V P ROTE CTI O N REL AY SE T TIN GS D A T A . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9 11 TI ME CU RR E NT C URV ES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1 0 12 C O N C L USIO N A N D RE CO MME ND A TI O NS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1 4
Attachments: Attachment A: ETAP SLD Attachment B: ETAP Report
Abu Dhabi Polymers Company Limited (Borouge)
BOROUGE PO FLARE GAS RECOVERY PROJECT RELAY SETTINGS & PROTECTION COORDINATION STUDY Issued date
Project No.
Document Number
Page
Rev.
5-NOV-2014
PE/000451
FR-EE-403-00003
4 OF 14
L
1 INTRODUCTION The intent of this study report is to carry out electrical power system analysis by performing protection coordination study of the electrical network under the scope of Borouge PO Flare Gas Recovery project (B3). 2 STUDY OBJECTIVE The main objectives of protection coordination study are as follows:
To determine the characteristics, ratings, and settings of over current protective devices that minimizes plant outages and interrupts short circuits as rapidly as possible. To verify the existing protection device settings. To verify the proper margin between protective devices in series to enable a back-up protection system. That is, upstream devices are on a standby basis to act expeditiously in case the immediate device nearer to the fault location fails to operate.
Relay Coordination study is performed on the basis & recommendations of following international standards
IEEE Std 399-1997. (IEEE Recommended Practice for Industrial & Commercial Power System Analysis) IEEE Std 242-2001. (IEEE Recommended Practice for Protection and Coordination of Industrial and Commercial Power Systems)
3 REFERENCE DOCUMENTS The documents listed below have been considered as the basis/reference for the relay settings & protection coordination study: Document Name Electrical Cable Schedule Electrical Load Summary (B3) Electrical One Line Diagram B3 PE5 Process Substation Unit N-42(11KV, 3.3 KV, 0.415 KV) 11 KV SWITCHGEAR 42-ES-9001 Protection and Metering One Line Diagram Electrical One Line Diagram B3 PP4 Process Substation UNIT N-45 11 KV SWITCHGEAR 45-ES-9001 Protection and Metering One Line Diagram 3.3 KV SWITCHGEAR 45-ES-9002 Protection and Metering One Line Diagram 3.3 KV SWITCHGEAR 42-ES-9002 Protection and Metering One Line Diagram BOR 3 PO SUBSTATION Protection and Metering Diagram 0.415 KV Switchgear Electrical One Line Diagram PE5 Extrusion Substation Unit N-42(11KV, 3.3 KV, 0.415 KV) Electrical One Line Diagram PP4 Extrusion Substation Unit N-42(11KV, 3.3 KV, 0.415 KV)
Borouge Document No. FR-EE-403-00006 STU-EE-FR-003
Contractor Document No. 6502-10-100-D1-1382-001-01 6502-10-100-D1381-002-01
TEC-EE-FR-0044
----
TEC-EE-FR-0045
----
TEC-EE-FR-0046
----
TEC-EE-FR-0047
----
TEC-EE-FR-0048
----
TEC-EE-FR-0050
----
TEC-EE-FR-0049
----
42-EE-153-920001
----
45-EE-153-920001
----
Abu Dhabi Polymers Company Limited (Borouge)
BOROUGE PO FLARE GAS RECOVERY PROJECT RELAY SETTINGS & PROTECTION COORDINATION STUDY Issued date
Project No.
Document Number
Page
Rev.
5-NOV-2014
PE/000451
FR-EE-403-00003
5 OF 14
L
4 ETAP MODEL As per Descon / Contractor scope (DOC: Electrical System Description and Scope Definition for EPC Package) in Borouge 3 expansion project, Descon has to analyze the impact of newly added loads (which are in Descon scope, DOC: Electrical Load Summary B3) on the electrical network of B3 by performing the protection coordination study. The details of ETAP model provided by Company are as follows: Name: ETAP-3583-PO This contains the following switchgears with associated electrical equipment (Motors, Transformers, and Cables etc). 80-ES-1802 (33 KV) 41-ES-9203 (3.3 KV) 42-ES-9213 (0.415 KV) 42-ES-9201 (11 KV) 42-ES-9203 (3.3 KV) 42-ES-9212 (0.415 KV) 44-ES-9202 (3.3 KV) 44-ES-9212 (0.415 KV) 45-ES-9202 (3.3 KV)
41-ES-9001 (11 KV) 41-ES-9011 (0.415) 41-ES-9212 (0.415 KV) 42-ES-9001 (11 KV) 42-ES-9011 (0.415 KV) 44-ES-9001 (11 KV) 44-ES-9011 (0.415 KV) 45-ES-9001 (11 KV) 45-ES-9011 (0.415 KV)
41-ES-9002 (3.3 KV) 41-ES-9211 (0.415 KV) 41-ES-9201 (11 KV) 42-ES-9002 (11 KV) 42-ES-9211 (0.415 KV) 44-ES-9002 (3.3 KV) 44-ES-9211 (0.415 KV) 45-ES-9002 (3.3 KV) 45-ES-9211 (0.415 KV)
Loads in Contractor’s scope have been modeled along with associated cables.
Abu Dhabi Polymers Company Limited (Borouge)
BOROUGE PO FLARE GAS RECOVERY PROJECT RELAY SETTINGS & PROTECTION COORDINATION STUDY Issued date
Project No.
Document Number
Page
Rev.
5-NOV-2014
PE/000451
FR-EE-403-00003
6 OF 14
L
5 BASIS & ASSUMPTIONS The basis and assumptions are listed below
The protection data for motors i.e starting time, thermal withstand limits, thermal time constants etc are based on technical data provided by vendor and assumptions are made where vendor data is pending. Thermal overload settings of motors shall be performed at site during commissioning stage. For simulation purposes, exact Relay/ETU model is used as available in standard ETAP device library. In case of unavailability of particular model, nearest match having similar characteristics is used. In this report, following switchgears of Unit 42 (PE5) and Unit 45 (PP4) are under observation as most of the loads under contractor’s scope are being fed from theses switchgears. However attached ETAP report will reflect the results of other switchgears as well. 42-ES-9001 (11 KV)
45-ES-9001 (11 KV)
42-ES-9011 (0.415 KV)
45-ES-9011 (0.415 KV)
6 NETWORK DESCRIPTION FOR STUDY For the simulation, ETAP models have been updated as per the reference documents mentioned in section 3 of this report. The Network Description for the study is as follows:
The main power sources for 11 KV switchgear 42-ES-9001 are 2 Nos. 33 KV feeders supplied by switchgear 80-EE-1802 through 31.5 MVA, 33/11.5 KV transformers (42-EP-9011, 42-EP-9012). 2 Nos. 11 KV feeders (from switchgear 42-ES-9001) are stepped down by 2 Nos. 3.15 MVA, 11/0.433 KV transformers (42-EP-9031, 42-EP-9032) to feed 0.415 KV switchgear 42-ES-9011. The main power sources for 11 KV switchgear 45-ES-9001 are 2 Nos. 33 KV feeders supplied by switchgear 80-EE-1803 through 31.5 MVA, 33/11.5 KV transformers (45-EP-9011, 45-EP-9012). 2 Nos. 11 KV feeders (from switchgear 45-ES-9001) are stepped down by 2 Nos. 2.5 MVA, 11/0.433 KV transformers (45-EP-9031, 45-EP-9032) to feed 0.415 KV switchgear 45-ES-9011. Following Generators are operating in Standby mode and considered OFF in the analysis. 42-EG-9201
42-EG-9001
45-EG-9001
45-EG-9201
7 MODEL SIMULATION CONDITIONS Following are the basis of model simulation conditions.
Loads are categorized into Continuous, Intermittent and Stand by 100%, 50% & 0% loading respectively. All Lump Loads are considered as “Continuous” and operating at 80% loading. Loading Category is selected as Normal. Primary tap positions are set at +2.5% of nominal voltage, for all transformers (for Unit 42 & 45). 33kV Grid bus is considered as slack/swing bus. The by-pass switches for VFDs are closed to get maximum short circuit contribution from motors. Maximum short circuit power from utility to switchgears of unit 42 and 45 is considered 1257 MVA (3-phase) as per etap model/etap report submitted by Company described in section 5 of this report. Minimum short circuit power from utility to switchgears of unit 42 and 45 is considered 850 MVA (3-phase) as per etap model/etap report submitted by Company described in section 5 of this report.
Abu Dhabi Polymers Company Limited (Borouge)
BOROUGE PO FLARE GAS RECOVERY PROJECT RELAY SETTINGS & PROTECTION COORDINATION STUDY Issued date
Project No.
Document Number
Page
Rev.
5-NOV-2014
PE/000451
FR-EE-403-00003
7 OF 14
L
8 FAULT CURRENT LEVELS Initial Symmetrical Short Circuit Current (maximum):
Bus
Nominal Voltage (kV)
Rated Short Circuit (kA)
42-ES-9001 A 42-ES-9001 B 42-ES-9011 A 42-ES-9011 B 45-ES-9001 A 45-ES-9001 B 45-ES-9011 A 45-ES-9011 B
11 11 0.415 0.415 11 11 0.415 0.415
31.5 31.5 80 80 31.5 31.5 80 80
Initial Symmetrical RMS Current kA (Ik”) Double Line to Three Phase Line to Ground Line to Line Ground 26.3 0.4 23.1 23.2 26.3 0.4 23.1 23.2 54.2 47.3 46.8 52.8 54.2 47.3 46.8 52.8 25.1 0.4 21.8 21.9 25.1 0.4 21.8 21.9 47.7 42.8 41.2 46.8 47.7 42.8 41.2 46.8
Peak Short Circuit Current (maximum): Bus 42-ES-9001 A 42-ES-9001 B 42-ES-9011 A 42-ES-9011 B 45-ES-9001 A 45-ES-9001 B 45-ES-9011 A 45-ES-9011 B
Nominal Voltage (kV)
Rated Short Circuit (kA)
11 11 0.415 0.415 11 11 0.415 0.415
31.5 31.5 80 80 31.5 31.5 80 80
Peak Short Circuit Current kA (ip) Double Line to Three Phase Line to Ground Line to Line Ground 67.7 1.08 59.4 59.7 67.7 1.08 59.4 59.7 124.3 108.6 107.3 121.3 124.3 108.6 107.3 121.3 64.9 1.08 56.4 56.7 64.9 1.08 56.4 56.7 110.4 99.1 95.3 108.2 110.4 99.1 95.3 108.2
Symmetrical Short Circuit Breaking Current (maximum): Symmetrical Short Circuit Breaking Current kA (Ib) Nominal Rated Short Bus Voltage (kV) Circuit (kA) Line to Ground Line to Line Double Line to Ground 42-ES-9001 A 11 31.5 0.4 23.1 23.2 42-ES-9001 B 11 31.5 0.4 23.1 23.2 42-ES-9011 A 0.415 80 47.3 46.8 52.8 42-ES-9011 B 0.415 80 47.3 46.8 52.8 45-ES-9001 A 11 31.5 0.4 21.8 21.9 45-ES-9001 B 11 31.5 0.4 21.8 21.9 45-ES-9011 A 0.415 80 42.8 41.2 46.8 45-ES-9011 B 0.415 80 42.8 41.2 46.8
Abu Dhabi Polymers Company Limited (Borouge)
BOROUGE PO FLARE GAS RECOVERY PROJECT RELAY SETTINGS & PROTECTION COORDINATION STUDY Issued date
Project No.
Document Number
Page
Rev.
5-NOV-2014
PE/000451
FR-EE-403-00003
8 OF 14
L
Initial Symmetrical Short Circuit Current (minimum): Bus
Nominal Voltage (kV)
Rated Short Circuit (kA)
42-ES-9001 A 42-ES-9001 B 42-ES-9011 A 42-ES-9011 B 45-ES-9001 A 45-ES-9001 B 45-ES-9011 A 45-ES-9011 B
11 11 0.415 0.415 11 11 0.415 0.415
31.5 31.5 80 80 31.5 31.5 80 80
Initial Symmetrical RMS Current kA (I”k) Three Phase Line to Ground Line to Line 14.1 14.1 29.7 29.7 14.1 14.1 28.1 28.1
0.3 0.3 30.6 30.6 0.3 0.3 28.9 28.9
12.2 12.2 25.7 25.7 12.2 12.2 24.3 24.3
Double Line to Ground 12.3 12.3 30.2 30.2 12.3 12.3 28.5 28.5
Peak Short Circuit Current (minimum): Bus
Nominal Voltage (kV)
Rated Short Circuit (kA)
42-ES-9001 A 42-ES-9001 B 42-ES-9011 A 42-ES-9011 B 45-ES-9001 A 45-ES-9001 B 45-ES-9011 A 45-ES-9011 B
11 11 0.415 0.415 11 11 0.415 0.415
31.5 31.5 80 80 31.5 31.5 80 80
Peak Short Circuit Current kA (ip) Double Line to Three Phase Line to Ground Line to Line Ground 36.7 0.9 31.8 32 36.7 0.9 31.8 32 74.7 77.1 64.7 76 74.7 77.1 64.7 76 36.7 0.9 31.8 32 36.7 0.9 31.8 32 70.2 72.3 60.8 71.4 70.2 72.3 60.8 71.4
Symmetrical Short Circuit Breaking Current (minimum): Bus 42-ES-9001 A 42-ES-9001 B 42-ES-9011 A 42-ES-9011 B 45-ES-9001 A 45-ES-9001 B 45-ES-9011 A 45-ES-9011 B
Nominal Voltage (kV) 11 11 0.415 0.415 11 11 0.415 0.415
Rated Short Circuit (kA) 31.5 31.5 80 80 31.5 31.5 80 80
Symmetrical Short Circuit Breaking Current kA (Ib) Line to Ground Line to Line Double Line to Ground 0.3 12.2 12.3 0.3 12.2 12.3 30.6 25.7 30.2 30.6 25.7 30.2 0.3 12.2 12.3 0.3 12.2 12.3 28.9 24.3 28.5 28.9 24.3 28.5
Abu Dhabi Polymers Company Limited (Borouge)
BOROUGE PO FLARE GAS RECOVERY PROJECT RELAY SETTINGS & PROTECTION COORDINATION STUDY Issued date
Project No.
Document Number
Page
Rev.
5-NOV-2014
PE/000451
FR-EE-403-00003
9 OF 14
L
9 RELAY TYPE The relays used for HV motor feeder protection are ABB make REF630 with following protection functions. 50P 51P 50N 51N 87M 74 42R 86 46 38 49 49T 48 66
Motor Feeder REF 630
Phase definite time OC Phase inverse OC Earth definite time OC Earth inverse OC Differential protection Alarm Running CB Lockout Phase balance current relay Bearing protection Thermal protection Temperature protection Incomplete Sequence Relay
Jogging device
10 HV PROTECTION RELAY SETTINGS DATA Only over current protection function settings (50P, 50G, 51P, 51G) are proposed in this document. All other settings shall be performed at site during commissioning stage. Motor TAG Description Relay CT Ratio Pickup Value TMS Characteristic Curve Pickup Value Time Pickup Value Time
47-XK-921-KM-921 47-XK-931-KM-931 Motor feeder Motor feeder REF 630 REF 630 250-1 200-1 OVERCURRENT STAGE I> (51) Settings 0.9 0.9 3.5 2.11 IECIECExtremely Inverse Extremely Inverse OVERCURRENT INSTANTANEOUS I>> (50) Settings 6.71 6.41 0.05 0.05 RESIDUAL CURRENT INSTANTANEOUS I02 > (50N) Settings 0.21 0.18 0.05 0.05
Abu Dhabi Polymers Company Limited (Borouge)
BOROUGE PO FLARE GAS RECOVERY PROJECT RELAY SETTINGS & PROTECTION COORDINATION STUDY Issued date
Project No.
Document Number
Page
Rev.
5-NOV-2014
PE/000451
FR-EE-403-00003
10 OF 14
L
11 TIME CURRENT CURVES Time current curves (TCC) are plotted to verify the present state of coordination. a. 47-XK-921-KM-921 PE compressor motor relay phase TCC.
Figure 1
Abu Dhabi Polymers Company Limited (Borouge)
BOROUGE PO FLARE GAS RECOVERY PROJECT RELAY SETTINGS & PROTECTION COORDINATION STUDY Issued date
Project No.
Document Number
Page
Rev.
5-NOV-2014
PE/000451
FR-EE-403-00003
11 OF 14
L
b. 47-XK-921-KM-921 PE compressor motor relay earth time current curves
Figure 2
Abu Dhabi Polymers Company Limited (Borouge)
BOROUGE PO FLARE GAS RECOVERY PROJECT RELAY SETTINGS & PROTECTION COORDINATION STUDY Issued date
Project No.
Document Number
Page
Rev.
5-NOV-2014
PE/000451
FR-EE-403-00003
12 OF 14
L
c. 47-XK-931-KM-931 PP compressor motor relay phase time current curves
Figure 3
Abu Dhabi Polymers Company Limited (Borouge)
BOROUGE PO FLARE GAS RECOVERY PROJECT RELAY SETTINGS & PROTECTION COORDINATION STUDY Issued date
Project No.
Document Number
Page
Rev.
5-NOV-2014
PE/000451
FR-EE-403-00003
13 OF 14
L
d. 47-XK-931-KM-931 PP compressor motor relay earth time current curves
Figure 4
Abu Dhabi Polymers Company Limited (Borouge)
BOROUGE PO FLARE GAS RECOVERY PROJECT RELAY SETTINGS & PROTECTION COORDINATION STUDY Issued date
Project No.
Document Number
Page
Rev.
5-NOV-2014
PE/000451
FR-EE-403-00003
14 OF 14
L
12 CONCLUSION AND RECOMMENDATIONS Relay coordination study has been performed after incorporating protection settings of existing system and proposed protection settings of newly added loads. The study reflects that both HV & LV electrical systems are adequate and properly coordinated after the Borouge project load additions and no modification/update in protection settings of existing system is required at this stage.
^,KZd/Zh/d^dhz PROTECTION COORDINATION STUDY ETAP SLD ATTACHMENT A
ATTACHMENT A
One-Line Diagram - SCMAX (Star Sequence-of-Operation) 80-ES-1802 A
80-ES-1802 B ±
±
I> I>
42-EP-9011 31.5 MVA
42-EP-9012 31.5 MVA
±
±
R
R
CB336
CB339
± ±
R
42-ES-9001 A
R
±
±
CB331 ±
R
R
±
CB337 ±
R ±
CB332 ±
R
CB334 ±
R
R
R
47 1- EC 3/ CC 50 18 00 5 1
12:05:32
Oct 31, 2014
CB340
CB328
CB329
0 A
CB7 ±
R ±
1750 kVA Cable7 0 A
42-EP-9032 42-EP-9232 42-EP-9234 2-3/C 185
42-XE-705-EC-701A 42-XE-705-EC-701B
Project File: ETAP-3583-PO
4450 kW
C/42-ES-9001 B 42-XK-401-KM-401
1400 kW
C/42-ES-9001 A 42-XE-705-NM-701A
42-XK-402-KM-402 2300 kW
47-XK-921-KM-921 3300 kW
page 1
XC/42-ES-001A
±
42-EP-9233 42-EP-9231 42-XE-705-EP-701A 1750 kVA
CB327
±
CB338 Open
± ±
42-EP-9031
CB341
R
±
±
±
CB326
CB335
1400 kW
R ±
CB330
42-XE-705-NM-701B
±
CB17
XC/42-ES-001B
CB40
42 -X E70 5EP -7 01 B
42-ES-9001 B
ATTACHMENT A
One-Line Diagram - SCMAX (Star Sequence-of-Operation) 80-ES-1803 A
80-ES-1803 B
±
±
I>
I>
45-EP-9011 31.5 MVA
45-EP-9012 31.5 MVA ±
±
R
R
CB581
CB584
± ±
R
R
45-ES-9001 B
R
R
R
R
R
±
± ± ±
12:03:46
Oct 31, 2014
±
R ±
0 A
±
45-EP-9032
0 A
45-EP-9232
45-XE-705-NM-701
Project File: ETAP-3583-PO
±
R
±
R
±
R ±
7.85 MVA
2.6 MVA
C/45-ES-9001 A
45-EP-9031
3150 kW
45-XK-401-KM-401
47-XK-931-KM-931 2650 kW
45-EP-9231
XC/45-ES-9001A
47 -E C 1- C3/ 50 C 00 18 2 5
±
C/45-ES-9001 B
page 1
CB583 Open
±
±
±
2130 kW
R
45-XK-503-KM-503
±
CB35
CB72
45 -X E70 5EC -7 54
±
CB574
6350 kW
±
CB585
45-XE-705-NM-754
±
±
CB572
45 -X E70 5EP -7 54
R ±
CB586
CB571
CB580
45 -X E70 5EC -7 01
CB579
CB577
2100 kW
CB582
XC/45-ES-9001B
CB28
CB38
45 -X E70 5EP -7 01
45-ES-9001 A
^,KZd/Zh/d^dhz
PROTECTION COORDINATION STUDY ETAP REPORT ATTACHMENT B
Project:
BOROUGE #3
Location: LHR PAK
ETAP
Page:
1
12.5.0C
Date:
29-10-2014
Contract: 6502
Revision: Base
Engineer: DIPL
Overcurrent Relay Settings
Filename: ETAP-3583-PO
OCR: R_42-ES-9001-A1 MFR:
ABB
Model:
RE_630
Tag #:
CT
Base kV
If (kA)
Phase:
2500/1
24.70 3 ph, (User-Defined)
GND:
2500/1
0.40 LG, (User-Defined)
Phase:
250/1
24.70 3 ph, (User-Defined)
GND:
100/1
0.40 LG, (User-Defined)
OC Level: OC1 Range
Setting
Phase TOC IEC - Normal Inverse Pickup (Tap)
0.3 - 5 xCT Sec
Time Dial Phase INST Pickup Time Delay Ground INST Pickup Time Delay
0.790 0.150
0.01 - 35 xCT Sec
6.300
0.04 - 30 Sec
0.400
0.01 - 400 xCT Sec
0.100
0.01 - 300 Sec
0.600
OCR: R_42-ES-9001-KM-921 MFR:
ABB
Model:
RE_630
Tag #:
CT
Base kV
If (kA)
OC Level: OC1 Range
Setting
Phase TOC IEC - Extremely Inverse Pickup (Tap)
0.3 - 5 xCT Sec
Time Dial Phase INST Pickup Time Delay Ground INST Pickup Time Delay
0.900 3.500
0.01 - 35 xCT Sec
6.710
0.04 - 30 Sec
0.050
0.01 - 400 xCT Sec
0.210
0.01 - 300 Sec
0.050
ATTACHMENT B
Project:
BOROUGE #3
Location: LHR PAK
ETAP
Page:
2
12.5.0C
Date:
29-10-2014
Contract: 6502
Revision: Base
Engineer: DIPL
Overcurrent Relay Settings
Filename: ETAP-3583-PO
OCR: R_45-ES-9001-A1 MFR:
ABB
Model:
RE_630
Tag #:
CT
Base kV
If (kA)
Phase:
2500/1
23.90 3 ph, (User-Defined)
GND:
2500/1
0.40 LG, (User-Defined)
Phase:
200/1
23.90 3 ph, (User-Defined)
GND:
100/1
0.40 LG, (User-Defined)
OC Level: OC1 Range
Setting
Phase TOC IEC - Normal Inverse Pickup (Tap)
0.3 - 5 xCT Sec
Time Dial Phase INST Pickup Time Delay Ground INST Pickup Time Delay
0.790 0.150
0.01 - 35 xCT Sec
6.300
0.04 - 30 Sec
0.400
0.01 - 400 xCT Sec
0.100
0.01 - 300 Sec
0.600
OCR: R_45-ES-9001-KM-931 MFR:
ABB
Model:
RE_630
Tag #:
CT
Base kV
If (kA)
OC Level: OC1 Range
Setting
Phase TOC IEC - Extremely Inverse Pickup (Tap)
0.3 - 5 xCT Sec
Time Dial Phase INST Pickup Time Delay Ground INST Pickup Time Delay
0.900 2.110
0.01 - 35 xCT Sec
6.410
0.04 - 30 Sec
0.050
0.01 - 400 xCT Sec
0.180
0.01 - 300 Sec
0.050
ATTACHMENT B